4
Punch List Items F-1013 Boiler 1 of 4 Item # Description Status 1 Complete 2 Grout all supports Complete 3 Complete 4 Send Valves to Western to Get Tested Complete 5 Adjust all Spring Cans Complete 6 Insulation In Progress 7 Missing Anchor Bolts Complete 8 Hydro Boiler Trim Pipe and NDE Complete 9 10 Complete 11 Pull all Blinds from the Boiler. Complete 12 In Progress 13 Complete 14 Install Silencer 15 Missing Supports on Utility Air Lines Complete 16 Pull out shims underneath BFW393 Complete 17 Anchor down and grout support on BFW393 Complete 18 Complete 19 Complete 20 Power Piping Paper Work In Progress 21 Install TI on SH379 Iso 138 Complete 22 Install TI on BFW391 Iso 57 Complete 23 Install TI on SH455 Iso 163 Complete 24 Install TI on SH379 Iso 145 Complete 25 26 Complete 27 Complete 28 Complete 29 Complete 30 31 Complete 32 Complete Fix rip on expantion joint on Eastn side of Economizer. Pull the slip blind from the Fuel Gas Tie-in Fix hole in wall where drain pipe comes out Fix 1 1/2" Flanged tie from blow-down pipe to boiler. (Mis-Alignment) Missing bolts on Ladders. And missing Safety Gates on Ladders as well. Missing U-Bolt on Cooling Water Line on the west side of the boiler. Anchor down support on Ladder on North side of Boiler Turn Check Valve on Blow Down Piping on North East Side of Boiler Missing 300# RF Ball Valve Tag# FV-165A on Blow Down By Pass Iso # 044 Ping The Bolts on the East side of the Economizer Blind Flanges Install Inserta seal on drain on North Side of Boiler Mud Drum Install Unions on drains on North Side of Boiler Install Teflon pads undernesth all Stainless Pipe and structure steel Blow a hole in the Fuel Gas Skid so that it can drain. Install U-Bolt on stainless pipe at loading rack. Ping The Bolts on the on all stainless piping

Inspection Punch List

  • Upload
    jrod915

  • View
    36

  • Download
    5

Embed Size (px)

DESCRIPTION

pipe punchlist

Citation preview

Page 1: Inspection Punch List

Punch List Items F-1013 Boiler

1 of 2

Item # Description Status Comments/Remarks

1 Complete

2 Grout all supports Complete3 Pull the slip blind from the Fuel Gas Tie-in Complete4 Send Valves to Western to Get Tested Complete5 Adjust all Spring Cans Complete6 Insulation In Progress7 Missing Anchor Bolts Complete8 Hydro Boiler Trim Pipe and NDE Complete9 Fix hole in wall where drain pipe comes out Civil Crew Has been informed

10 Complete

11 Pull all Blinds from the Boiler. Complete

12 In Progress Ladder has been bolted down

13 Complete

14 Install Silencer Need Crane15 Missing Supports on Utility Air Lines Complete16 Pull out shims underneath BFW393 Complete17 Anchor down and grout support on BFW393 Complete

18 Complete

19 Complete

20 Power Piping Paper Work In Progress21 Install TI on SH379 Iso 138 Complete22 Install TI on BFW391 Iso 57 Complete23 Install TI on SH455 Iso 163 Complete24 Install TI on SH379 Iso 145 Complete

25 We have not received item yet

26 Complete

27 Complete

28 Install Unions on drains on North Side of Boiler Complete

29 Complete

30

31 Install U-Bolt on stainless pipe at loading rack. Complete32 Ping The Bolts on the on all stainless piping Complete

Fix rip on expantion joint on Eastn side of Economizer.

Fix 1 1/2" Flanged tie from blow-down pipe to boiler. (Mis-Alignment)

Missing bolts on Ladders. And missing Safety Gates on Ladders as well.

Missing U-Bolt on Cooling Water Line on the west side of the boiler.

Anchor down support on Ladder on North side of Boiler

Turn Check Valve on Blow Down Piping on North East Side of Boiler

Missing 300# RF Ball Valve Tag# FV-165A on Blow Down By Pass Iso # 044

Ping The Bolts on the East side of the Economizer Blind Flanges

Install Inserta seal on drain on North Side of Boiler Mud Drum

Install Teflon pads undernesth all Stainless Pipe and structure steel

Blow a hole in the Fuel Gas Skid so that it can drain.

Waiting on instructions as what we are going to do their.

Page 2: Inspection Punch List

Punch List Items F-1013 Boiler

2 of 2

Item # Description Status Comments/Remarks

33 Complete

34 Fix support on Iso 143 Complete

35 Complete Leave as is.

36 Complete

37 Ping all bolts on Boiler Flanges Complete38 Weatherproof top of boiler at penetrations. Complete39 F-001 Missing Contriol valve Repeat Same as Item 2540 F-019 Missing TI Repeat Same as Item 2341 F-003 Two anchor bolts missing Repeat Same as Item 1742 F-003 grout base plate Repeat Same as Item 17

43 F-003 TI missing Iso #065 ?

44 Complete

45 Check tightness on flanges of the round ducts Complete46 BFW Missing supports Complete47 Install missing covers on each end of mud drum48 Complete all insulation Repeat Same as Item 6

49 Complete

50 Finish with the Concrete Probably Friday or Monday

Run Pipe down from the high point vents from the BFW piping all the way to the ground.

Cut anchors/stops off of 110# Steam Piping Iso 177 item 14

Install Missing Guides and Supports on Stainless Pipe

Iso # 65 does not require a TI per the Drawing

Ammonia piping- Need mechanical completion sign off

Ping/check manway covers on economizer &ducts. Found loose fasteners.