Punch List Items F-1013 Boiler
1 of 2
Item # Description Status Comments/Remarks
1 Complete
2 Grout all supports Complete3 Pull the slip blind from the Fuel Gas Tie-in Complete4 Send Valves to Western to Get Tested Complete5 Adjust all Spring Cans Complete6 Insulation In Progress7 Missing Anchor Bolts Complete8 Hydro Boiler Trim Pipe and NDE Complete9 Fix hole in wall where drain pipe comes out Civil Crew Has been informed
10 Complete
11 Pull all Blinds from the Boiler. Complete
12 In Progress Ladder has been bolted down
13 Complete
14 Install Silencer Need Crane15 Missing Supports on Utility Air Lines Complete16 Pull out shims underneath BFW393 Complete17 Anchor down and grout support on BFW393 Complete
18 Complete
19 Complete
20 Power Piping Paper Work In Progress21 Install TI on SH379 Iso 138 Complete22 Install TI on BFW391 Iso 57 Complete23 Install TI on SH455 Iso 163 Complete24 Install TI on SH379 Iso 145 Complete
25 We have not received item yet
26 Complete
27 Complete
28 Install Unions on drains on North Side of Boiler Complete
29 Complete
30
31 Install U-Bolt on stainless pipe at loading rack. Complete32 Ping The Bolts on the on all stainless piping Complete
Fix rip on expantion joint on Eastn side of Economizer.
Fix 1 1/2" Flanged tie from blow-down pipe to boiler. (Mis-Alignment)
Missing bolts on Ladders. And missing Safety Gates on Ladders as well.
Missing U-Bolt on Cooling Water Line on the west side of the boiler.
Anchor down support on Ladder on North side of Boiler
Turn Check Valve on Blow Down Piping on North East Side of Boiler
Missing 300# RF Ball Valve Tag# FV-165A on Blow Down By Pass Iso # 044
Ping The Bolts on the East side of the Economizer Blind Flanges
Install Inserta seal on drain on North Side of Boiler Mud Drum
Install Teflon pads undernesth all Stainless Pipe and structure steel
Blow a hole in the Fuel Gas Skid so that it can drain.
Waiting on instructions as what we are going to do their.
Punch List Items F-1013 Boiler
2 of 2
Item # Description Status Comments/Remarks
33 Complete
34 Fix support on Iso 143 Complete
35 Complete Leave as is.
36 Complete
37 Ping all bolts on Boiler Flanges Complete38 Weatherproof top of boiler at penetrations. Complete39 F-001 Missing Contriol valve Repeat Same as Item 2540 F-019 Missing TI Repeat Same as Item 2341 F-003 Two anchor bolts missing Repeat Same as Item 1742 F-003 grout base plate Repeat Same as Item 17
43 F-003 TI missing Iso #065 ?
44 Complete
45 Check tightness on flanges of the round ducts Complete46 BFW Missing supports Complete47 Install missing covers on each end of mud drum48 Complete all insulation Repeat Same as Item 6
49 Complete
50 Finish with the Concrete Probably Friday or Monday
Run Pipe down from the high point vents from the BFW piping all the way to the ground.
Cut anchors/stops off of 110# Steam Piping Iso 177 item 14
Install Missing Guides and Supports on Stainless Pipe
Iso # 65 does not require a TI per the Drawing
Ammonia piping- Need mechanical completion sign off
Ping/check manway covers on economizer &ducts. Found loose fasteners.