Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
© 2016 Electric Power Research Institute, Inc. All rights reserved.
Glenn A. White, Kyle P. Schmitt, Kevin J. Fuhr, Markus Burkardt, and Jeffrey A. Gorman
Dominion Engineering, Inc.
Paul CrookerElectric Power Research Institute
William SimsEntergy Nuclear Inc.
EPRI International Light Water Reactor Materials Reliability Conference and Exhibition 2016
Chicago, IL, August 1-4, 2016
Inspection Credit for PWSCC
Mitigation via Peening Surface
Stress Improvement
2© 2016 Electric Power Research Institute, Inc. All rights reserved.
Outline
Introduction
Process for Acceptance of Inspection Relief
MRP-335R3 Technical Basis for Inspection Relief
– Inspection Objectives
– Performance Criteria
– Inspection Requirements
– Deterministic Approach
– Probabilistic Approach
Conclusions
3© 2016 Electric Power Research Institute, Inc. All rights reserved.
IntroductionBackground on Peening Surface Stress Improvement Methods for PWRs
Peening surface stress improvement (SSI) mitigates PWSCC by inducing compressive residual stress at the surface exposed to reactor coolant
– Initiation of PWSCC flaws requires tensile stress at the surface above a threshold
– Any existing flaws that are fully within the surface compressive normal plus operating stress zone cannot grow via PWSCC
Peening provides an option to mitigate reactor vessel closure head penetration nozzles instead of replacing the entire head
Peening provides an option to mitigate components that are not easily replaced or mitigated from outer surface using weld overlay or mechanical stress improvement (e.g., some reactor vessel inlet/outlet nozzles)
4© 2016 Electric Power Research Institute, Inc. All rights reserved.
IntroductionExperience with Peening in the Nuclear Power Industry
Peening has been previously applied at numerous components in Japanese PWRs and BWRs
Japanese PWRs (starting in 2001)
– At least 23 out of 24 PWR units have applied water jet peening (WJP) or laser peening (LP) to bottom-mounted nozzles (BMNs) and/or reactor vessel inlet/outlet nozzle dissimilar metal welds (DMWs)
– WJP and LP have also been applied to reactor vessel safety injection nozzles
– Ultrasonic Shot Peening (USP) has been applied to
Steam generator inlet or outlet nozzles at more than 10 PWRs
Pre-service peening of 9 replacement reactor vessel heads with Alloy 690 nozzles
Japanese BWRs (starting in 1999)
– WJP and LP have extensively been applied to core shrouds and bottom head penetrations (i.e., CRD stud tubes)
– Applying to new ABWR units during the fabrication and construction phases
The abrasive water jet (AWJ) conditioning process has been widely used in the U.S. for more than a decade in PWR nozzle repair applications
Several hundred thousand steam generator tubes have been shot peened over the past 30 years, extending their useful life
Successful application of shot peening on Alloy 600 pressurizer heater sheaths installed in 1990 at one PWR
First WJP or LP application in the U.S. successfully completed in spring 2016
Peening applications at several additional PWR units are scheduled through 2017
5© 2016 Electric Power Research Institute, Inc. All rights reserved.
Process for Acceptance of Inspection ReliefASME and Regulatory Requirements in U.S.
Inspection requirements for Alloy 600/82/182 PWR primary system
pressure boundary components are specified in ASME Boiler &
Pressure Vessel Code Cases that are made mandatory with
conditions by U.S. NRC regulations (10 CFR 50.55a):
– N-770-1: Alloy 82/182 piping dissimilar metal butt welds (DMWs)
– N-729-1: Reactor pressure vessel head penetration nozzles (RPVHPNs)
– N-722-1: Reactor vessel bottom-mounted instrumentation nozzles (BMNs)
Inspection requirements identify
– Nondestructive exam (NDE) inspection methods
– Inspection frequency
– Inspection coverage
– Flaw acceptance standards
6© 2016 Electric Power Research Institute, Inc. All rights reserved.
Process for Acceptance of Inspection ReliefRegulatory Process in U.S.
Asset Management
(10 CFR 50.59 Process)
Licensees may make changes to the facility
and procedures and conduct tests and
experiments without prior NRC approval
– If change requires no license or technical
specifications modifications
– If change does not meet one or more of the
eight criteria specified in 10 CFR 50.59(c)(2)
No license amendment request required
This process does not grant inspection
relief
NRC has confirmed that ASME Code
requirements do not prohibit peening for
purpose of surface stress improvement
Alternative Inspection Intervals
(10 CFR 50.55a Process)
For NRC approved and regulation-
mandated programs (e.g. in-service
inspection programs) separate from the
license
10 CFR 50.55a specifies the processes for
requesting alternatives to, or relief from, the
in-service inspection and testing
requirements of the ASME Code
Licensees may submit “relief requests” to
the NRC
NRC reviews and approves relief requests
by Safety Evaluations (SE)
7© 2016 Electric Power Research Institute, Inc. All rights reserved.
Process for Acceptance of Inspection ReliefDevelopment of ASME Code Requirements and U.S. NRC Review of Topical Report
Parallel paths were taken for acceptance of inspection relief
1. ASME Section XI Code Cases for peening inspection credit
2. NRC Safety Evaluation (SE) based on NRC review of peening topical report
Revised ASME Section XI Code Cases include performance criteria and inspection intervals for components mitigated by peening:
– DMWs per Code Case N-770-4, approved by ASME May 7, 2014
– RPVHPNs per Code Case N-729-5, approved by ASME October 7, 2015
– These revised code cases have not yet been approved by U.S. NRC and incorporated by reference in 10 CFR 50.55a
– See ASME Paper PVP2016-64008 (D. Weakland, et al.)
The industry’s topical report (MRP-335R3) was submitted to NRC for review
– Specifies program of pre-peening, follow-up, and long-term inservice inspection (ISI) exams
– Submitted to NRC February 19, 2016
– Upon NRC approval, the topical report (with SE) will be cited in relief requests submitted by individual licensees as the basis for inspection credit for peening processes demonstrated to meet a set of performance criteria
– The topical report (with SE) does not automatically grant inspection relief for individual plants
8© 2016 Electric Power Research Institute, Inc. All rights reserved.
EPRI Materials Reliability Program Technical Documentation
EPRI MRP has prepared multiple documents in support of PWSCC mitigation by surface stress improvement (peening)
MRP-267R1Technical Basis for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement
– Provides background on peening methods and the technical basis for effectiveness of peening as a mitigation method
– Includes extensive data generated by peening vendors as well as confirmatory testing sponsored by EPRI
– Freely downloadable at www.epri.com, Product ID # 1025839
MRP-335R3Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement
– Supports acceptance of peening as a mitigation method, including appropriate extension of the required inspection intervals following mitigation if performance criteria are met
– Freely downloadable at www.epri.com, Product ID # 3002007392
MRP-336R1Specification Guideline for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement
– Provides guidance to utilities regarding items that should be addressed in detail by the utility and vendor
9© 2016 Electric Power Research Institute, Inc. All rights reserved.
Inspection Objectives for Peened Components
Inspection requirements for unmitigated Alloy 600/82/182 components were
developed to maintain an acceptably low effect on nuclear safety of PWSCC:
– MRP-110, MRP-117, MRP-105, MRP-113, MRP-139R1, and MRP-206
These inspection requirements also result in low probability of through-wall
cracking and leakage, ensuring defense in depth
The goal of MRP-335R3 was to develop inspection requirements and
performance criteria for peened components that maintain this acceptably low
effect on nuclear safety
– As shown by probabilistic analyses, the requirements of MRP-335R3 actually result in an
increased nuclear safety margin, plus a large reduction in the probability of leakage occurring
– The leakage prevention benefit of peening performed in accordance with MRP-335R3 is further
demonstrated through a matrix of deterministic crack growth cases
Peening mitigation implemented in accordance with the requirements of MRP-335R3
provides a substantial risk benefit for a risk that is already low
10© 2016 Electric Power Research Institute, Inc. All rights reserved.
MRP-335R3 Performance Criteria
MRP-335R3 (Section 4.2 – DMWs, Section 4.3 – RPVHPNs) defines the following peening
performance criteria:
– Peening coverage
– Surface stress magnitude including operating stress
– Compressive residual stress depth
– Sustainability
– Inspectability
– Lack of adverse effects
– NDE Qualification
Peening vendors are required to establish essential variables and associated ranges of
acceptable application-specific values
– Part of the controlled special process procedures submitted for licensee pre-implementation approval
– Vendor qualification tests demonstrate that the MRP performance criteria are met
– Acceptable ranges of essential variables will ensure that specified performance criteria are met
Essential variables are documented in process qualification and post-implementation reports
11© 2016 Electric Power Research Institute, Inc. All rights reserved.
MPR-335R3 Inspection Requirementsfor Peened DMWs and RPVHPNs (Tables 4-1 and 4-3)
12© 2016 Electric Power Research Institute, Inc. All rights reserved.
Matrix of Deterministic Crack Growth CasesApproach
A matrix of deterministic crack growth cases that model growth to through-wall penetration and leakage is included in MRP-335R3
Cases model growth for range of initial flaw depths up to the NDE detectability limit at time of peening– Flaws at least as deep as the NDE detectability limit are detectable
during the follow-up and ISI exams
– Vary initiating location, orientation, operating temperature, crack growth rate material variability factor, initial crack aspect ratio, weld residual stress profile, and effective bending moment (DMWs)
Matrix consists of 72 cases for mitigated components and 72 cases for unmitigated components, each for DMWs and RPVHPNs
13© 2016 Electric Power Research Institute, Inc. All rights reserved.
Matrix of Deterministic Crack Growth CasesInspection Schedule
Hot Head Cold Head
Pre-Peening
1st Follow Up 2 3
2nd Follow Up 4 N/A
1st ISI 14 13
2nd ISI 24 23
3rd ISI 34 33
4th ISI 44 43
5th ISI 54 53
6th ISI 64 63
7th ISI 74 73
Never Leaks 80 80
Inspection
Inspection Time (yr)
min(RIY=2.25, 8yr)
Hot-Leg DMW Cold-Leg DMW
Pre-Peening every 5 every 7
1st Follow Up 5 10
2nd Follow Up 10 N/A
1st ISI 20 20
2nd ISI 30 30
3rd ISI 40 40
4th ISI 50 50
5th ISI 60 60
6th ISI 70 70
Never Leaks 80 80
Inspection Time (yr)
Inspection
The inspection schedules shown below are applied to determine
during which inspection a crack is predicted to be detected, or if the
crack is predicted to lead to a leak
14© 2016 Electric Power Research Institute, Inc. All rights reserved.
Matrix of Deterministic Crack Growth CasesExample DMW Cases
Example Mitigated DMW Cases (Table 5-5 through 5-7)
Crack Weld MRP-115 Initial Growth Growth Time Aspect Total Total
Orient. Detect. Residual A182 Initial Initial Aspect Time to from Detect Ratio at Length at Length at
Case Axial/ Limit Stress CGR Temp. Depth Depth Ratio Bending Detect Limit Limit to Leak Detection Detect Limit Detect Limit Detect Limit
Number Circ (%TW) Profile %ile (°F) (in.) (mm) (2c 0/a 0) Moment (yr) (yr) Time (2c /a ) (in.) (mm)
2 Axial 1.4% Median 50% 605.5 0.010 0.25 8.0 N/A 15.8 7.7 1st ISI 2.4 0.093 2.37
12 Circ 1.4% High 95% 618 0.010 0.25 10.0 High 3.1 1.7 Leaks before extension of interval 2.5 0.100 2.54
13 Axial 1.4% Low 5% 538 0.010 0.25 6.0 N/A 274.5 174.9 Never Leaks 1.9 0.076 1.94
29 Circ 1.4% Median 50% 605.5 0.020 0.50 8.0 Base Case 4.1 11.1 1st Follow Up 4.1 0.160 4.06
63 Axial 1.4% High 95% 559 0.039 1.00 10.0 N/A 0.0 6.4 Leaks 10.0 0.394 10.00
Crack Weld MRP-115 Initial Growth Growth Time Aspect Total Total
Orient. Detect. Residual A182 Initial Initial Aspect Time to from Detect Ratio at Length at Length at
Case Axial/ Limit Stress CGR Temp. Depth Depth Ratio Bending Detect Limit Limit to Leak Detected/ Detect LimitDetect LimitDetect Limit
Number Circ (%TW) Profile %ile (°F) (in.) (mm) (2c 0/a 0) Moment (yr) (yr) Leaks (2c /a ) (in.) (mm)
49 - NP Axial 1.4% Low 5% 593 0.039 1.00 6.0 N/A 0.0 26.1 Detected 6.00 0.236 6.00
50 - NP Axial 1.4% Median 50% 605.5 0.039 1.00 8.0 N/A 0.0 4.5 Leaks 8.00 0.315 8.00
51 - NP Axial 1.4% High 95% 618 0.039 1.00 10.0 N/A 0.0 0.9 Leaks 10.00 0.394 10.00
52 - NP Circ 1.4% Low 5% 593 0.039 1.00 6.0 Base Case 0.0 28.8 Detected 6.00 0.236 6.00
53 - NP Circ 1.4% Median 50% 605.5 0.039 1.00 8.0 Base Case 0.0 6.4 Detected 8.00 0.315 8.00
54 - NP Circ 1.4% High 95% 618 0.039 1.00 10.0 Base Case 0.0 1.5 Leaks 10.00 0.394 10.00
Example Unmitigated DMW Cases (Table 5-8 through 5-10)
15© 2016 Electric Power Research Institute, Inc. All rights reserved.
Matrix of Deterministic Crack Growth Cases Overall Results
DMW –
Peened
DMW –
No Peening
RPVHPN –
Peened
RPVHPN –
No Peening
Never Leaks, Never
Detected10 of 72 0 of 72 28 of 72 10 of 72
Detected in Follow-
Up Exam31 of 72 N/A 30 of 72 N/A
Detected in ISI Exam20 of 72 48 of 72 12 of 72 52 of 72
Leaks Before
Extension of Intervals8 of 72
24 of 72
0 of 72
10 of 72Leaks After Extension
of Intervals3 of 72 2 of 72
All but one of the peened cases that result in leakage assume the combination of a high tensile weld residual stress profile, the highest operating temperature for their category, and 95th percentile crack growth rate behavior
There is a very low probability of cases like this occurring in practice
16© 2016 Electric Power Research Institute, Inc. All rights reserved.
Matrix of Deterministic Crack Growth CasesConclusions
Frequency of cases with leakage is much reduced compared to unpeened components inspected per current requirements
Large fraction of cases with peening show no leakage subsequent to extension of inspection intervals
The long-term ISI exams address the residual risk of slow-growing pre-existing flaws
The MRP inspection requirements are effective to prevent leakage
Deterministic matrix results are consistent with and complement the probabilistic results
As for unmitigated heads, any J-groove weld cracking is addressed by the visual exams for leakage
17© 2016 Electric Power Research Institute, Inc. All rights reserved.
Probabilistic AnalysesApproach
The DMW and RPVHPN probabilistic models applied inMRP-335R3 are similar to models that have been applied for more than 12 years to assess PWSCC:– Inspection requirements to address PWSCC of Alloy 600 and Alloy 690
RPVHPNs (MRP-105, MRP-375, and MRP-395)
– Inspection requirements to address PWSCC of Alloy 600 BMNs (MRP-206)
– Assessment of depth-sizing uncertainty of flaws in large-diameter piping welds (MRP-373)
Probabilistic analyses assess the benefit of peening on the probability of pressure boundary leakage or rupture assuming reduced frequency of inspection– Component loading including effect of peening on residual stress field
– PWSCC crack initiation and growth
– Probability of PWSCC detection
– Various inspection options
18© 2016 Electric Power Research Institute, Inc. All rights reserved.
Probabilistic AnalysesConclusions
Follow-up and ISI exams address the possibility of growth of pre-existing PWSCC flaws that were not detected in the pre-peening exam
– Flaws tend to become more easily detectable as they grow in size
The probabilistic analysis results are compared to acceptance criteria:
– Alloy 82/182 piping butt welds: Peening mitigation with the recommended inspection intervals results in a large reduction in the probability of leakage compared to no mitigation and standard intervals
– RPVHPNs: Peening mitigation with the recommended inspection intervals results in:
an acceptably low nozzle ejection frequency
a nozzle ejection frequency that is below that calculated for no mitigation and standard intervals
a large reduction in the probability of leakage compared to no mitigation and standard intervals
19© 2016 Electric Power Research Institute, Inc. All rights reserved.
Conclusions
Advanced laser peening and water jet peening technologies have
been successfully adapted for use in the nuclear power industry
Peening has been demonstrated as a long-term mitigation method
for PWSCC, without adverse effects
Technical basis documents have been developed to support
appropriate inspection relief for peened components
This technical basis is now under regulatory review in the U.S.
Peening for asset management has successfully been performed in
the U.S.
20© 2016 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity