Upload
millicent-goulas
View
31
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Input Development for SPSG Scenarios. November 13, 2014. Arne Olson, Partner Nick Schlag, Sr. Consultant. Topics for Discussion. Carbon capture & sequestration technologies Enhanced geothermal Load modifications. IGCC with CCS. Cost Reductions – IGCC w/ CCS. - PowerPoint PPT Presentation
Citation preview
Input Development for SPSG Scenarios
November 13, 2014
Arne Olson, Partner
Nick Schlag, Sr. Consultant
2
Topics for Discussion
Carbon capture & sequestration technologies
Enhanced geothermal
Load modifications
IGCC WITH CCS
3
Cost Reductions – IGCC w/ CCS
Reference Case cost: $8,200/kW
• Consistent with expected cost of Kemper County plant
• Does not reflect significant technological progress/learning
As in prior study cycle, E3 recommends using the Reference assumptions in all scenarios except Scenario 2
• Scenario 2 narrative allows for a breakthrough in CCS technology
4
$8,200 $4,800
$8,200 $8,200
$8,200
IGCC w/ CCS Capital Cost by Scenario ($/kW)
No change from Reference Case
Technology breakthrough
Cost Reduction Recommendations from 2032
In 2012, E3 chose a 40% reduction for IGCC with CCS technology to represent a “breakthrough” based on the lowest available cost estimates for the technology
This level of cost reduction would also render IGCC w/ CCS technology competitive with traditional gas CCGT in a high carbon price future ($100/ton)
5
Slide from E3 presentation to MDTF, October 2, 2012
Origin of E3’s Original Recommendation
Pre- vs. Post-Combustion CCS
Availability of cost estimates for both technologies are limited:
• Kemper: $5.6 billion for 580 MW unit ($9,600/kW)
• Boundary Dam: $1.24 billion for 110 MW unit ($11,200/kW)
• WA Parish: $1 billion for 250 MW unit ($4,000/kW)
Other public sources do not suggest substantial differences between current costs for pre- and post-combustion CCS:
6
Source PC w/ CCS IGCC w/ CCS
Pacificorp IRP$5,611 $5,434
$6355 $6,152
Lazard $8,568 $7,650
EIA $6,821 $8,612
NETL $5,160 $4,819
All costs have been adjusted
to reflect AFUDC costs
and are expressed in
2014 $
ENHANCED GEOTHERMAL
7
8
Enhanced Geothermal Costs
Cost estimates for enhanced geothermal systems vary widely and are highly site-specific:
Reference Case
$0
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
$16,000
$18,000
Low Med Hi Low Med Hi
Binary Flash
Capi
tal C
ost (
$/kW
)
NREL Base Case
“NREL Base Case” costs reflect EGS systems and
are obtained from Updated US Geothermal Supply Characterization and Representation for
Market Penetration Model Input (Oct 2011)
9
Enhanced Geothermal Costs
Based on NREL study, a 30% capital cost reduction in EGS technology is plausible
Cost reduction could be applied to EGS technologies in Scenarios 2 & 4
Reference Case
$0
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
$16,000
$18,000
Low Med Hi Low Med Hi
Binary Flash
Capi
tal C
ost (
$/kW
)
NREL Base Case
Plausible Reduction
$0
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
$16,000
$18,000
Low Med Hi Low Med Hi
Binary FlashCa
pita
l Cos
t ($/
kW)
NREL Target
LOAD FORECASTS
10
11
Components of Load Forecast
Three independent parameters may drive differences in load between scenarios:
1. How much to increment/decrement Reference Case load forecasts to capture impacts of differences in economic conditions on underlying load growth?
2. How much incremental energy efficiency (beyond that embedded in Reference Case) to include?
3. How much policy-driven electrification load to include?
Assumptions used in 2032 scenarios provide a useful starting point for a framework to develop updates
GOAL: Review assumptions used in 2032 load forecasts to inform development of 2034 load forecasts
12
Changes in Underlying Load Growth (2032 Study)
In 2032 study, WECC-wide growth rates were adjusted by ±0.4%/yr between 2022-2032 to reflect differences in underlying economic growth:
• Scenarios 1 & 2: +0.4%
• Scenarios 3 & 4: -0.4%
1.9% 1.9%
1.1% 1.1%
1.5%
WECC-Wide CAGR Assumptions, 2022-2032
Slide summarizes assumptions from 2032 study
13
Changes in Incremental Energy Efficiency (2032 Study)
LBNL’s 2032 High DSM load forecast served as the basis for assumptions related to incremental energy efficiency
• Assumes average efficiency of residential/ commercial end uses in 2032 equals that of today’s best available technology
Savings reflected in the High DSM forecast scaled to reflect scenario narratives:
• Scenarios 1 & 3: no additional EE
• Scenario 2: very aggressive EE
• Scenario 4: moderate incremental EE
100% of LBNL 2032 High DSM forecast savings
(~21% load reduction)
n/a
WECC-Wide Incremental Efficency(2032 Study)
n/a
n/a
50% of LBNL 2032 High DSM forecast savings
(~11% load reduction)
Slide summarizes assumptions from 2032 study
14
Changes in Electrification (2032 Study)
Additional load in Scenario 2 driven by electrification of end uses across all sectors, motivated by trend towards deep decarbonization pathways
Additional load in Scenario 4 assumed to result from growing penetrations of plug-in electric vehicles
+160 TWh(~13% load
increase)
n/a
WECC-Wide Electrification Load(2032 Study)
n/a
n/a+50 TWh(~5% load increase )
Slide summarizes assumptions from 2032 study
15
Parameter 2010Reference
CaseScenario 1 Scenario 2 Scenario 3 Scenario 4
Load Energy 854,036 1,163,526 1,210,159 1,210,159 1,118,518 1,118,518 (Growth Rate, 2010-2032) (+1.42%) (+1.60%) (+1.60%) (+1.23%) (+1.23%)
+ Policy Driven Energy Effi ciency - - (250,165) - (125,082) + Incremental Electrification - - 160,000 - 50,000 = Net Load 854,036 1,163,526 1,210,159 1,119,994 1,118,518 1,043,436
(Growth Rate, 2010-2032) (+1.42%) (+1.60%) (+1.24%) (+1.23%) (+0.91%)
2032 Load Forecast – Building Blocks
Scenario-specific load adjustments yield a range of load assumptions for studies:
Implied growth rates vary from 0.62%/yr (Scenario 4) to 1.75%/yr (Scenario 2)
Slide summarizes assumptions from 2032 study
16
2032 Load Forecast - Results
Load levels vary widely across scenarios:
Slide summarizes assumptions from 2032 study
854
1,164 1,210
1,120 1,119 1,043
0
200
400
600
800
1,000
1,200
1,400
2010 Reference Case Scenario 1 Scenario 2 Scenario 3 Scenario 4
WEC
C-W
ide
Load
by
Scen
ario
(GW
h)
Thank You!Energy and Environmental Economics, Inc. (E3)
101 Montgomery Street, Suite 1600
San Francisco, CA 94104
Tel 415-391-5100
Web http://www.ethree.com
18
Scenario 2 Electrification: Review of Long-Term GHG Reduction Studies
Assume incremental electrification increases (post-DSM) demand by 20% in 2032 due to electrification across all sectors
Studies demonstrate what would be needed to achieve long-term GHG reductions (rather than a forecast of what’s likely given current policies & trends):
• U.K. Department of Energy and Climate Change, “2050 Pathways Analysis,” July 2010.
• California Council on Science and Technology, “California’s Energy Future: The View to 2050,” May 2011.
• Williams, et al. “The Technology Path to Deep Greenhouse Gas Emissions Cuts by 2050: The Pivotal Role of Electricity,” Science (2012) (written by E3 colleagues and LBNL staff).
Comparison of electrification as a share of that year’s total electricity demand
18
19
Scenario 4 Electrification : National Academies Press Study Scaled to the WECC
19
0
10
20
30
40
50
60
70
2015 2017 2019 2021 2023 2025 2027 2029 2031
Elec
tric
and
Plu
g-in
Hyb
rid E
lect
ric V
ehic
les i
n W
ECC
(mill
ions
of l
ight
dut
y ve
hicl
es)
Year
National Academies-HIGH
Total Light Duty Vehicles in WECC
Nat’l Academies Study = 11.4 million light-duty vehicles (LDVs) by 2032 in WECC
17% of fleet
Equal to ~ 46 TWh of incremental electricity load in WECC in 2032 assuming fully-electric vehicles use ~4,000 kWh/yr
National Academies Press report, “Transitions to Alternative Transportation Technologies – Plug-in Hybrid Electric Vehicles,” (PHEVs), (2012).