18
QUANTUM-2009 1 R.I.T. RAJARAMNAGAR.

Innovative Planning & Design Concepts in Civil Engg._rit

Embed Size (px)

DESCRIPTION

Innovative Planning & Design Concepts in Civil Engg._rit

Citation preview

GREEN BUILDING:-

QUANTUM-2009

INDEX

Sr. No.ContentsPage No.

01.ABSTRACT3

02.INTRODUCTION4

03.THEORY5-11

04.PLANNING PART5

05.DESIGN PART9

06.CONCLUSION12

07.REFERNCES12

Abstract Now a days, big cities are facing with lots of problems related with unavailability of land, transportation, traffic etc. These problems are directly related to human health, economical condition & development of nation. To overcome these problems INNOVATIVE PLANNING & DESIGN CONCEPTS are essential . innovative & planning & desing concepts deals with economy, strength,stability & confort of structure.the best example of these type of concepts is CHEK LAP KOKinternational airport of hong kong.planning part of this structure is done by considering ecological impact & by using scientific tests such as standard penetration test,cone penetration test,seismic geophysical test,bearing estimation test,elastic modull test etc.the planning & design concepts are used for construction of rotating floor , suspention bridges, under water tunnel & movable roof structures which gives strength,stability,confort & reduces cost of construction.designing is done by considering functional planning,architectural concept & natural sources.INTRODUCTIONAs explained in abstract due to unavailability of land & bad airport facilities ,hong kong airport authority decided to plan new airport i.e. chek lap kok airport .this airport required 7 years to completion. The authority decided built this new airport in between two islands named as Land chanu & chek-lap-kok. To create airport platform the authority used reclamanition process. They converted area under sea water into leveled ground as airport platform. This is worlds biggest land moving exercise project in the history of world. For the completion of this project the engineer faced lots of challenges such as construction of tunnel at the depth of 15 m below bottom of river which has length of 2km, 2.5km long suspension bridge, 35km long super highway. The great constributers of this projects are Douglas Oakervee (Airport Authority Project Director), Alistair Thomson (Airport Authority, Head of construction), Andrew Beard (Bridge Engineer), etc. THEORY:Planning part:

Ecological ImpactsIf it is not properly controlled, a large scale project can have significant effects on the local ecology. The following points discuss the reduction of the impact of the construction of the New Airport on local marine and terrestrial ecology.

1)Site InvestigationThe large scale site investigation (SI) conducted at the New Airport site involved a great number and variety of field and laboratory tests.

A) Land-Based SI:

SI was carried out to aid reclamation design. SI of the 'as placed' reclamation fill was required for the design of buildings, tunnels and runways.

B) Marine-Based SI:

Marine SI was conducted to gain information for design of temporary ferry piers, a sea channel between Chek Lap Kok and Tung Chung, airfield approach lighting and temporary sewage outfalls. 2)Desk Study

Desk Studies provide an opportunity to gather valuable information for negligible cost. They are carried out at the start of the Site Investigation, and involve reading existing information about the site. This existing information could include; topographical maps, geological maps aerial photographs, existing SI records, geotechnical journals

Information obtained during the Desk Study will be taken into account when planning the SI 3)Site Reconnaissance Following the Desk Study, further information can be gained through site reconnaissance, this involves a visit to the site for inspection. Information can also be obtained by talking to local inhabitants during the visit .Site reconnaissance can provide information on the following; slopes and mounds, site geology, surface water (ponds and streams) and erosion features ,groundwater, site access, condition of existing structures,existence of grave sites or archaeological features.

4) FieldworkSite Investigation fieldwork is undertaken to gain information on groundwater levels, geological strata, bedrock depth etc. Samples, which are later sent to laboratories for testing, can also be obtained.

A)Ground water Level Analysis:Ground water level analysis consist of:Pumping Test ,Falling Head Test ,Falling Head Test, Standpipe Piezometer, Dipmeter

Knowledge of the minimum and maximum groundwater levels was required for platform and foundation design and for assessing pumping requirements.

B)Trial Pits:The use of trial pits enables a visual inspection of the in-situ soils conditions and strata boundaries can be determined accurately. It is also relatively easy to obtain samples, blocks can be cut by hand from the bottom or sides of the pit and tube samples can also be obtained from below the bottom of the pit.

C)Boreholes:The most common method used to obtain soil and rock details directly is to drill a borehole. To estimate the engineering properties, plasticity etc. mazier and U76 samples can be taken from the borehole and sent to a laboratory for testing.

The core samples are carefully stored in coreboxes for further study and geological description. Details on strata type, levels, colour, stiffness, weathering grade, jointing, infilling, cavities etc. can be obtained visually.

D)Standard Penetration Tests:

The Standard Penetration Tests aims to determine the SPT N value, which gives an indication of the soil stiffness and can be empirically related to many engineering properties.

The test is conducted inside a borehole. A 'split spoon' sampler is attached to the bottom of a core barrel and lowered into position at the bottom of the borehole. The sampler is driven into the ground by a drop hammer weighing 68 kg falling through a height of 76 cm. The number of hammer blows is counted. The number required to drive the sampler three successive 150mm increments is recorded. The first increment

(0-150mm) is not included in the N value as it is assumed that the top of the test area has been disturbed by the drilling process. The SPT N is the number of blows required to achieve penetration from 150-450mm.

After the test, the sample remaining inside the split spoon is preserved in an airtight container for inspection and description.

E)Cone Penetration Test:Cone Penetration Tests are conducted to obtain the cone resistance, the side friction and,

if there is a piezocone , the pore pressure. The soil type can be determined by analysing

these results, the values can also be used in the design of shallow foundations through the

estimation of stiffness and shear strength of cohesive soils.

F)In-Situ Vane Shear Test:This test is used to estimate the undrained shear strength of a soil, and is particularly appropriate for assessing very soft and sensitive clays, which can not be tested accurately in a laboratory as it is difficult to obtain an undisturbed sample.

The test can be done at the b ase of a drillhole or trial pit, or at ground level. If the test is being conducted at the bottom of a drillhole it is important that the test area has not been disturbed by boring, generally the test is conducted five borehole diameters below the borehole base. G)Plate Loading Test:

This test is used to estimate the compressibility and bearing capacity of soils which are not easily sampled. H)Elastic Moduli Estimation:The load is applied to the plate in increments of one fifth of the design load. The next increment is not applied until the settlement rate has reduced to 0.1 inch/min for a period of 60 mins. The increments are applied until shear failure or until the loading is 2 to 3 times the design load.

I)Bearing Capacity Estimation:In this case the load is applied such that the rate of penetration remains constant. A load-settlement curve is produced. Equations have been developed to obtain undrained shear strength from ultimate bearing capacity, thickness of soil above test strata and a bearing capacity factor that depends on the shape of the loaded area. If bearing capacity failure is not apparent from the load-settlement curve, it is assumed to be the load at which settlement equals 15% of plate diameter.

J)Seismic Geophysical Testing:Seismic surveys make use of the fact that seismic waves travel at different speeds through different strata. Generally the waves travel faster through denser materials. This method can be used to estimate engineering properties and strata boundaries.

Generally an elastic wave is generated by striking a hammer on a steel plate at or near the ground surface. The wave travels though the ground until it hits a harder surface from which it rebounds. Geophones on the surface measure the time taken by the rebounded signal and, by comparing this with the time interval for the surface wave, the depth to the harder layer can be estimated. The strata type can also be inferred from the wave speeds. Seismic analysis may also be conducted on the

seabed.Advantages:

1)relatively cheap compared to borehole and in-situ testing option

2)results are often inconclusive or unreliableDisadvantages:

1)non-destructive (no holes/excavations are required)

2)not yet fully accepted by the industry.Laboratory Testing:

Soil Classification Tests:Soil classification tests are conducted in order to ascertain the soil type, e.g. clay, silty

sand etc., and to provide some preliminary information on the soil properties & gives idea about settlement

Particle Size Distribution Test:One of the most commonly used tests is the Particle Size Distribution test (PSD), this test

gives an indication of the proportion of different particle sizes within the soil sample.

The PSD test is only appropriate for coarse particles, for very fine particles (0.1mm to 1

mm) the sedimentation test can be used.Engineering Properties:

The following tests were conducted to determine engineering properties required for design. A)Vane Shear TestThis test is conducted to determine the shear strength of the sample

B) Direct Shear Test

This test is conducted to determine shear strength parameters. The sample is placed in a horizontally split box and a normal force is applied.

Triaxial Test

This test can be used to determine the undrained shear strength, the drained effective

shear strength parameters and the undrained and drained Young's Moduli.

Permeability Tests

Permeability tests are conducted to estimate the coefficient of permeability (k). This will

be used in pumping and dewatering design.

Types :

Constant Head Permeability Test

Falling Head Permeability Test

Airport Platform Site Formation

Site formation work for the Airport Platform constituted one of the largest scale

formation works ever conducted. Approximately 3/4 of the 1248 ha proposed site was to be produced through reclamation from the sea. The remaining area was produced by flattening the existing headlands of Chek Lap Kok and Lam Chau Islands by blasting and

earthworks. Marine-Side Operations

carried out. To provide the enormous dredging capacity and meet the time-scale imposed

Before reclamation started, removal of marine muds within the airport footprint was

by the works programme, a large fleet of trailing suction hopper dredgers, cutter suction

dredgers and grab and bucket dredgers was used.

Seawall Construction

Seawalls stabilise the land behind the wall and protect it from future erosion by the sea.

They also provide berthing facilities for marine vessels. In order to contain the sediment

dispersed, the southern seawall was constructed prior to marine dredging activity. New techniques:

A new transportation corridor stretches 34km from Hong Kong Island to the site of the airport, incorporating a high-speed rail system, two tunnels, two bridges and a six-lane expressway.

Designed for the rapid movement of millions of passengers

Rotating floor information

ALTO is a company that specialises in airportROTATING HANGAR FLOORS:

One of our specialities is the integration of rotating floors of any dimension. In many situations, this system is the best solution in terms of hangar space efficiency and overall construction costs.

ALTO JET decks rotating hangar floors are latest invention. They can rotate large size, circular hangar floor space, providing hangar positions for at least four medium-sized business jets, and can be integrated within existing or planned hangars. Any aircraft parked on a JET deck is relocated automatically into door position within a maximum of 90s.

FUTURE DEVELOPMENTS WITH PLANNING:

with the construction of a new development adjacent to the passenger terminal called Sky City. This consists of Sky Plaza an office, retail and business complex integrated with the passenger terminal (terminal two), which then links to the rest of Sky City.

The airport is one of the most accessible in operation today. Despite its size, the passenger terminal is designed for maximum convenience. A simple layout and effective signage, moving walkways and the automated people mover allow quick and easy movement throughout the building. The airport also features the HKIA Automated People Mover, a driverless people mover system consisting of 3 stations to provide fast transportation from the check-in area to the gates (and vice versa). These trains travel at 62km/h and the service is provided for free to all passengers and crew

Design part:Design Consideration:Detailed Design of the Terminal Building. An impressive architectural structure was expected.Design Objectives:The building design had to achieve the following objectives

Large roof span

Allocation of a large space for Processing Terminal

Sophisticated aesthetic and architectural requirements

Provision of an impressive and attractive gateway to Hong Kong for local and foreign travellers

Change in size of space in different locations and the shape of the building give a sense of direction to travellers. In the existing roof design, the plan area and roof height gradually decrease from Processing Terminal (landside) to Central Concourse (airside).

Maximum use of sunlight:The utilization of natural light is highly recommended in modern design of passenger terminal buildings. This greatly reduces power consumption and is more environmentally friendly.

Structural design should stress fewer columns and greater headroom. High transparent glass panels are useful for providing relaxing panoramic views.

Use of modularization:

Modular roof design not only reduces the general and detail design work, but also provides some flexibility for the Client for revision of parts of the roof structure during the life of the building. The erection time is accelerated and the site management process is simplified.

Changing Roof Height:

The roof is designed to change in height to accommodate the differing requirements of the activities beneath; hence it is at its highest above the Processing Terminal to give a large and dramatic space, and then gently decreases in height above the East Hall and along the Central Concourse before rising again above the West Hall.

The roof is designed to change in height to accommodate the differing requirements of the activities beneath; hence it is at its highest above the Processing Terminal to give a large and dramatic space, and then gently decreases in height above the East Hall and along the Central Concourse before rising again above the West Hall. Shape of Roof Vaults:

The 'wavy' shape of the roof has the following advantages:

It increases transmission of sunlight to lobby areas

It increases stiffness and bending moment resistanceIt enhances smooth air circulation inside the building and extraction of smoke in case of fire.Perimeter Glass Wall (Side Wall):

It is desirable to reduce the roof height to minimize the costs of perimeter wall and of air-conditioning at the Terminal Building. The perimeter wall consists of cladding mullions,transoms, back chords and glazing materials. The glazing materials are selected to maximize transparency while controlling solar radiation, heat gain and glare.

Joint Between Roof Vault and Perimeter Wall:

It was not practical to have a fixed joint between the roof and the perimeter (side) wall. Roof movement is caused by the accumulative effect of numerous vaults under vertical, lateral and thermal loads.

The concept of a "Floating Roof" was introduced. It consists of:

An armature system consisting of slotted brackets and spigot details

A pin-ended arm allows the roof to move in a vertical plane

A lower end of the armature that slides along a high strength duplex stainless steel rod for horizontal movement

A rotation that is accommodated by a spherical bearing on the armature fork around the sliding surface

Maximum allowable movements of 175mm vertically and 120mm horizontally

Construction Methods:

In roof erection the modularization concept and advanced construction techniques are used.On the basis of Supermodule principle they developed an effective construction strategy.

Below is the construction sequence of the roof structure:

Individual steel elements manufactured in England and Singapore

Shop-fabricated elements transported to assembly yard at Chek Lap Kok and welded to form roof sub-assemblies, 18m long and either 3m or 6m wide

Sub-assemblies further welded together to form a large roof module on module building jigs (typical module of 36m span and 33m long)

Large modules transported from assembly yard to site by multi-wheeled transporters

Modules lifted up and placed in final position using high capacity crawler cranes

Modules zipped up via a trestle rail system to form a giant continuous roof structure

Roof Modularization:In constructing the modules, several important points were considered:

Variation in design details, e.g. size of modules.

Accuracy of construction and defects when fixing to columns

Module Transportation: Multi-Wheeled Transporter

After producing the large standard roof modules on jigs, the next step was to transport them to the Terminal Building site (at a distance of about 1 km) for erection. A similar technique to heavy load transportation in off-shore and petrochemical industries was adopted.

Used four "Mammoet" self-propelled, multi-wheeled transportersGround Treatment:Most of the Airport Platform was constructed by end-tipping of rockfill and bottom dumping or hydraulic placement of marine sand. These materials were in a very loosely compacted condition, especially as most of the fill was placed under sea water. Ground treatment techniques were employed in order to prevent the occurrence of excessive settlement and to reduce differential settlement. Surcharge:This was the quickest and cheapest form of ground treatment used at the Airport Site. Large stockpiles of

Material , usually sand and rock obtained from dredging and excavation works, were placed at specific

locations . Under the increased loading, excess pore water pressure were dissipated more quickly, thus increasing the rate of settlement. Surcharging reduced the residual settlement after the platform construction was complete.

Vibrocompaction of Marine Sands:of which was marine sand. As this marine sand was dumped into the sea it was in a

The reclamation of the Airport platform required 197 mill m3 of Fill material, 76 mill m3

material to reduce adverse effects from excessive and differential settlement.The areas

relatively loose state, vibrocompaction (or vibro-floatation) was used to densify this

which would require vibrocompaction were identified using a pre-compaction cone penetration test results.

Prediction and Monitoring of Airport Platform Settlement:

A reliable estimation of the magnitude and rate of platform settlement was required in order to;

ensure that sufficient quantities of fill were available to fill the island to the desired formation evel

evaluate the performance of the reclamation at all stages of constructionlocate critical areas where ground treatment would be required

ensure that all Airport facilities would operate properly following settlement completion

estimate differential settlement and decide which pavement type to use for runways and roads

Settlement Considerations:

in settlement consideration the following elements are analysed

Marine Mud

Alluvial (River Deposits) Clays

Fill Material

Roof Structures for Passenger Terminal Building:The roof over the main Passenger Terminal Building takes the form of a multi-bay barrel

thus helpful for orientation within the building.

vault structure. The vaults are aligned parallel to the direction of passenger flow and are

Below are some interesting facts and figures about the Passenger Terminal Building and

its roof structures:

From the East Hall and Processing Terminal (check-in desks), the concourses extend in

three directions to provide 37 bridge-served gates for boarding

The overall width is 700m and the length is 1,270m

The whole roof structure is divided into 129 barrel vaults

Typical size of a single barrel vault is 36m span and 33m long

Each barrel vault weighs from 65 tonnes to 150 tonnes

The structural steelwork is mainly of Grade 50C

CONCLUSION:-

Though new planning & designing processes are continued, it is required to innovative & follow the planning & designing concepts. These are the biggest sources to overcome the difficult problem such as unavailability of constructional land, transportation problems, traffic, etc. By using such innovative planning & designing concepts we can improve our nation, economical conditions.

REFERANCES:-

1) www.google.com

2) Discovery channel

3) Book name:

New construction techniques in Civil World by Alistreve Oakervee

4) Magazine name:

Bridge and Tunnel construction

PRESENTED BY

Mr. ABHIJEET A. JADHAV. Mr. HEMANT A.PANDIT.

(S.E.CIVIL) (S.E.CIVIL)

(jadhav.abhijeet2021HYPERLINK "mailto:[email protected]"@gmail.com) ( hmnt.pndtHYPERLINK "mailto:[email protected]"@gmail.com)

DEPARTMENT OF CIVIL ENGINEERING

RAJARAMBAPU INSTITUTE OF TECHNOLOGY

RAJARAMNAGAR

TAL:-WALWA DIST:-SANGLI

MAHARASHTRA

APAPER ONINNOVATIVE PLANNING & DESIGN CONCEPTS IN CIVIL ENGINEERING

2 R.I.T. RAJARAMNAGAR.