23
Information Technology Services DESIGN AND INSTALLATION STANDARDS Requirements and Guidelines for: New Construction, Renovations, Upgrades, and Retrofits. Revised: June 5, 2015 – VIU ITS Network Services

Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Requirements and Guidelines for:

New Construction, Renovations, Upgrades, and Retrofits.

Revised: June 5, 2015 – VIU ITS Network Services

Page 2: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

2

Page 3: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

3

TABLE OF CONTENTS

0 GENERAL ............................................................................................................................................... 5

1 FIBER OPTIC CABLING ........................................................................................................................... 5

1.1 GENERAL ....................................................................................................................................... 5

1.2 BUILDING CONNECTIONS .............................................................................................................. 5

1.3 INTERNAL (FLOOR) CONNECTIONS ............................................................................................... 5

2 DATA/VOICE CABLING ........................................................................................................................... 6

3 HORIZONTAL (FLOOR / FIELD) CABLING ............................................................................................... 7

4 LEGACY CABLING ................................................................................................................................... 8

5 DECOMMISSIONED CABLING ................................................................................................................ 8

6 COMMUNICATION ROOMS ................................................................................................................... 9

6.1 GENERAL ....................................................................................................................................... 9

6.2 ROOM SIZE .................................................................................................................................... 9

6.3 ARCHITECTURAL .......................................................................................................................... 10

6.4 ELECTRICAL .................................................................................................................................. 10

6.5 MECHANICAL ............................................................................................................................... 10

6.6 COMMUNICATIONS/SERVER ROOM SAMPLE LAYOUTS ............................................................. 11

6.6.1 COMMUNICATIONS ROOM, TYPE A .................................................................................... 11

6.6.2 COMMUNICATIONS ROOM, TYPE B .................................................................................... 12

6.6.3 COMMUNICATIONS/SERVER ROOM, TYPE C ...................................................................... 14

7 COMMUNICATION RACKS ................................................................................................................... 16

7.1 GENERAL ..................................................................................................................................... 16

7.2 COMMUNICATION RACK SAMPLE LAYOUT ................................................................................. 17

8 LABELING ............................................................................................................................................. 18

8.1 GENERAL ..................................................................................................................................... 18

8.2 SAMPLE FIBER PATCH PANEL LABEL ........................................................................................... 19

9 WIRELESS COMMUNICATION ............................................................................................................. 19

10 MECHANICAL / ELECTRICAL ROOMS ............................................................................................... 20

Page 4: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

4

11 OFFICES ........................................................................................................................................... 20

12 CLASSROOMS .................................................................................................................................. 20

12.1 GENERAL ..................................................................................................................................... 20

12.2 POWER and DATA/VOICE ............................................................................................................ 20

12.3 AUDIO/VISUAL PROVISIONS ....................................................................................................... 21

12.4 SOUND REINFORCEMENT ........................................................................................................... 22

12.5 ACOUSTICS .................................................................................................................................. 22

12.6 LIGHTING ..................................................................................................................................... 22

13 COMPUTER LABS ............................................................................................................................. 22

13.1 GENERAL ..................................................................................................................................... 22

13.2 ARCHITECTURAL .......................................................................................................................... 23

13.2.1 LOCATIONS WITHIN A BUILDING ........................................................................................ 23

13.2.2 ROOM SHAPE ...................................................................................................................... 23

13.2.3 DOORS ................................................................................................................................. 23

13.2.4 FURNITURE .......................................................................................................................... 23

Page 5: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

5

0 GENERAL 0.1 Any proposed deviation from this standard must be approved in advance by Vancouver Island

University (VIU) Information Technology Services.

0.2 It will be at the contractor’s expense to remedy any and all installations that do not meet the

requirements of this specification.

0.3 If unclear about any item in this document, please contact VIU IT Services at 250.740.6300 or

[email protected]

1 FIBER OPTIC CABLING 1.1 GENERAL

1.1.1 Fiber runs, terminations and patch panels should be installed as per industry

standards, grouped together by type and in sequence, top-down and/or left to right.

1.1.2 Fibers are to be fully tested and results given to VIU IT Services, in electronic (PDF)

format, this is a requirement before payment for services provided.

1.2 BUILDING CONNECTIONS 1.2.1 Building interconnect fiber will be 24 strands of single mode fiber rated for outdoors.

1.2.2 Building entry fiber will terminate in the at the top of the entry communications

room on a rack, as specified in Section 7.2 below and corresponding diagram.

1.2.3 Fiber strands will be terminated with LC terminations in properly labeled front-

serviceable fiber patch panels that include integrated cable management as specified

in Section 7 and Section 8. As space behind the rack may be tight, it is important that

panels are front-serviceable so that future changes can be done easily.

1.2.4 All new fiber run for building connection are to terminate in the building where the

fiber is to be connected, and terminated in either Building 305 Room 219 or Building

120 Room 244, depending on geographical proximity to the nearest network core

room. Do not terminate fiber to connect a building, to another building.

1.3 INTERNAL (FLOOR) CONNECTIONS 1.3.1 Any multimode fiber required must be 50/125μm OM3 rated.

1.3.2 All internal cabling between communications rooms will consist of 12 strands single

mode fiber and 6 strands multimode fiber.

1.3.3 All communication rooms must have fibers that run back to the buildings fiber entry

communications room, which has fiber terminations to a network core.

1.3.4 Cabling between communications rooms internally will require fiber to terminate at

the top of the rack (except in the building entry closet where it will terminate just

below the building entry fiber) using LC terminations in properly labeled front-

serviceable fiber patch panels that include integrated cable management. As space

Page 6: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

6

behind the rack may be tight, it is important that panels are front-serviceable so that

future changes can be done easily.

2 DATA/VOICE CABLING 2.1 Provide all materials, labour and expertise to provide data/voice/CATV cabling and terminations

to the building entry communications room. All wiring should suit usage as per industry and

vendor standards.

2.2 All telecommunications cabling at Vancouver Island University must come with a manufacturer’s

warranty of at least 20 years. Cable installers must hold all certifications required by the

manufacturer and comply with any other manufacturer’s requirements to ensure that the

warranty is validated. Manufacturers that will be considered for the supply of structured wiring

products in alphabetical order are: Amp, Hubbell, Lucent and Nordx.

2.3 Under no circumstances will a mix of vendor products in any one building be acceptable.

2.4 In order to provide maximum flexibility all horizontal (floor) cabling must be capable of carrying

voice and/or data traffic. All cable runs must be certified capable of handling data to Enhanced

Category 6 specifications and terminated in accordance with EIA/TIA 568 A standard.

2.5 All data/voice wiring shall be installed in conduit or in cable tray and transitions to be properly

supported with J-hooks.

2.5.1 Where a cable tray is used, it shall be minimum 300mm wide with 150mm rung

spacing class D type ladder tray.

2.5.2 Where conduits are used into and between communications rooms,

2.5.2.1 Standard conduit fill rates must not be exceeded.

2.5.2.2 Conduits entering a communication room from the ceiling are to be extended

down to 3048mm (10ft) off the floor, for easier access and organization.

2.5.2.3 Leave pull strings for future use.

2.5.3 Fiber and copper runs must not share the same conduit.

2.6 Patch cables to be used in the rack are to be provided and installed by the Contractor. Use 4’

blue patch cables. Ensure that the jacket and boot used in the patch cables is not the stiff kind.

The Contractor is responsible for neatly installing the patch cables on the rack, connecting patch

panel ports to the switch ports, in coordination with VIU IT Services staff.

Page 7: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

7

3 HORIZONTAL (FLOOR / FIELD) CABLING 3.1 Horizontal cabling shall be 24 AWG solid, 4-pair UTP. Cable jacketing shall be blue in colour and

shall be lead-free. Cable shall exceed all TIA/EIA and ISO Enhanced Category 6 (Cat 6)

requirements and be characterized to a minimum of 250MHz.

3.2 Cable runs will not exceed 90m in length, from field punch down to patch panel punch down.

3.3 Cable performance shall be verified and test results for each run delivered to VIU—in electronic

(PDF) format.

3.4 A printed map and electronic (PDF) copy of labeled drop locations will also be delivered to the

Owner. Simply leaving the hand marked blueprints used during installation is not acceptable.

3.5 Data/voice cabling will terminate in the field in a blue coloured RJ45 wall jack.

3.6 Floor box and surface mounted outlets are not to be used, unless specified.

3.7 All horizontal cabling will be supported on cable tray from the communications room to within

15m of the destination drop where it may branch to the destination drop, supported according

to standards. Destination wall jacks will be fed from 12 mm conduit stubbed-up above ceiling

level.

3.8 Cable shall be installed in accordance with manufacturer’s recommendations and best industry

practices.

3.9 Cable raceways shall not be filled greater than the NEC maximum fill for the particular raceway

type.

3.10 Cables shall be installed in continuous lengths from origin to destination (no splices) unless

specifically addressed in this document.

3.11 Where cable splices are allowed, they shall be in accessible locations and housed in an

enclosure intended and suitable for the purpose.

3.12 The cable’s minimum bend radius and maximum pulling tension shall not be exceeded.

3.13 If a J-hook or trapeze system is used to support cable bundles all horizontal cables shall be

supported at a maximum of four-foot intervals - at no point shall cable(s) rest on acoustic ceiling

grids or panels.

3.14 Horizontal distribution cables shall be bundled in groups of not greater than 40 cables (cable

bundle quantities in excess of 40 cables may cause deformation of the bottom cables within the

bundle)

3.15 Cable shall be installed above fire-sprinkler systems and shall not be attached to or come in

contact with any ancillary equipment or hardware.

3.16 The cabling system and support hardware shall be installed so that it does not obscure any

valves, fire alarm conduit, boxes, or other control devices.

3.17 Cables shall not be attached to ceiling grid or lighting support wires. Use J-hooks for support if

necessary.

3.18 Where light support for drop cable legs is required, the Contractor shall install clips to support

the cabling.

Page 8: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

8

3.19 Any cable damaged or exceeding recommended installation parameters during installation

shall be replaced by the Contractor prior to final acceptance at no cost to VIU.

3.20 Unshielded twisted pair cable shall be installed so that there are no bends less than four times

the cables outside diameter (4 X cable O.D.) at any point in the run.

3.21 Pulling tension on 4-pair UTP cables shall not exceed 25-pounds for a single cable or cable

bundle.

4 LEGACY CABLING 4.1 All Legacy Cabling installations must be approved by VIU IT Network Services or VIU Facilities

Services in-house Electrician with approval from a member of VIU IT Services Management.

4.2 To allow for emergency phones, fax machines and possibly alarm systems, CAT5e cabling will be

required into each building and between each communication room and the entrance closet.

4.3 A 100-pair CAT5e cable (4 x 25-pair) is to be available from the main campus telephone room to

the building entrance communication room.

4.4 A 25-pair CAT5e is then to be pulled from the building entrance into every communication room

in the building.

4.5 These will be terminated in BIX blocks on the wall adjacent to the communication rack as

specified in the drawings.

4.6 Provide wiring for emergency phones located at the exterior building entrances.

5 DECOMMISSIONED CABLING 5.1 The term “Decommissioned” in use when referring to cabling in this document, means that the

cable is no longer terminated on the field or in the communications room.

5.2 All decommissioned copper CAT3/CAT5/CAT5e/CAT6 cabling that was used for data is to be

removed from the Building in which the construction / renovation is being done.

5.3 Phone wiring can only be removed with approval of the VIU Facilities Services in-house

Electrician, or a member of VIU IT Network Services.

5.4 All decommissioned fiber should be left in place.

5.4.1 Unless the building is being demolished, in which the fiber run used for the entry

communications room will be pulled back to the connecting network core room and

coiled neatly, waiting for deployment to another building or scheduled for removal

from the network core.

5.5 In cases where cabling cannot be easily removed, contact VIU IT Staff for guidance.

Page 9: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

9

6 COMMUNICATION ROOMS

6.1 GENERAL 6.1.1 Each building must have at least one communications room per floor designed as

detailed in the requirements of this section.

6.1.2 Any deviation from this section requires the approval of Vancouver Island University

Information Technology Services department.

6.1.3 Each room shall be located within the building such that Category 6 cables do not

extend any longer than 90 meters in cable length, from field punch down to patch

panel punch down.

6.1.4 All data/voice runs will terminate in a communication room, unless otherwise

specified.

6.1.5 Floor standing racks are required unless communications room cannot contain one.

Wall mounted cabinets are acceptable only upon approval from VIU IT Network

Services.

6.1.6 All communication rooms will be dedicated to data/voice communications only. If

equipment other than those for data/voice communications are to be added in these

rooms, including but not limited to energy management, security and audiovisual

equipment, VIU IT Services is to be consulted regarding room size and compatibility.

6.1.7 Heat-generating equipment not related to these specific functions will NOT be

housed in communication room spaces.

6.2 ROOM SIZE 6.2.1 For communication rooms with capacity up to 200 data/voice ports:

6.2.1.1 A minimum room size of 2m x 1m (2 sq m / 18 sq ft), see Communications

Room, Type A

6.2.1.2 No wall to be less than 1 m (3’) wide

6.2.1.3 A 2285mm (7’ 6”) minimum clear height; 2440mm (8’) preferred

6.2.1.4 Room entrance to be a lockable double door with a total 1524mm (5’) minimum

width, 2035mm (6’ 8”) minimum height is to be installed on one of the 2m side.

6.2.2 For communication rooms with capacity up to 400 data/voice ports:

6.2.2.1 A minimum room size of 2m x 2.15m (4.2 sq m / 45.5 sq ft), see

Communications Room, Type B

6.2.2.2 No wall to be less than 2 m (6.5’) wide

6.2.2.3 A 2285mm (7’ 6”) minimum clear height; 2440mm (8’) preferred

6.2.2.4 Room entrance to be a lockable double door with a total 1524mm (5’) minimum

width, 2035mm (6’ 8”) minimum height is to be installed on one of the 2.15m

side.

6.2.3 Alternate configurations may be considered in agreement with IT Services.

Page 10: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

10

6.3 ARCHITECTURAL 6.3.1 Doors must open out unless prohibited by BC Building Code requirements for exit

access passage width. If the doors open in, then allow for additional space.

6.3.2 Door access must be from exterior or a common corridor. Access through one room

to the next is not acceptable.

6.3.3 No suspended or false ceiling unless required by BC Building Code construction

requirements.

6.3.4 Fire treated furred plywood panels will be required on the wall adjacent to the front

of the communication rack. Dimensions are to be 20.5mm (3/4”) in depth, a height

of 1219mm (4’) and is to be located 760mm (2’-6”) above finished floor.

6.3.5 Rooms should be stacked vertically where possible and be interconnected by bushed

sleeve floor penetrations extending 100mm above the floor. On the room below, it

will stubbed out at 2438mm (8’) above the finished floor.

6.3.6 In communication rooms, racks must be bolted to the floor and located in such a

manner as to allow access of not less than 762mm (2.5’) to both the front and back

of the rack(s).

6.3.7 In a server/communication room, all racks must be bolted to the floor and located in

such a manner as to allow access of not less than 914mm (3’) to both the front and

back of the rack(s). Servers and communication equipment are to be in housed in

separate racks.

6.4 ELECTRICAL 6.4.1 50 foot candles illumination level at 915mm above floor, mounted 2285mm

minimum clear above floor (no wall mounted light fixtures).

6.4.2 Power requirements vary per communication room type. Refer to Power

Requirements under each communication room type below.

6.4.3 Provide oversized cable opening/conduits through walls/floors/ceiling to all

communication rooms to allow addition of cabling. Ensure openings are fire-stopped.

Fire-stopping preferred to be reused and re-penetrated.

6.5 MECHANICAL 6.5.1 HVAC capacity to maintain ambient room temperature over the range 50 to 85

degrees F, 30-75% relative humidity, positive pressure with air exchange sufficient to

dissipate heat generated by equipment (typically not less than 2500 watts) and plan

HVAC for future capacity by over-compensating for the heat produced.

6.5.1.1 Equipment added to the communications room which produce heat, shall have

their specifications and BTU output forwarded to VIU IT Services and VIU

Facilities Services.

Page 11: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

11

6.6 COMMUNICATIONS/SERVER ROOM SAMPLE LAYOUTS

6.6.1 COMMUNICATIONS ROOM, TYPE A Capacity for 200 data/voice ports

3’ x 6’ (1m x 2m)

Plywood for BIX termination2x20amp

Power requirements:

Emergency power: o Comm rack: 2 x 20 Amp circuits

1 outlet per circuit Anchored to the top of the rack (facing back) or on the wall

beside the rack

Standard power o Comm rack: 2 x 20 Amp circuits

1 outlet per circuit Anchored to the top of the rack (facing back) or on the wall

beside the rack o Back wall: 1 x 15 Amp circuit

1 duplex

Page 12: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

12

6.6.2 COMMUNICATIONS ROOM, TYPE B Capacity for 400 data/voice ports

6’ 6” x 7” (2m x 2.15m)

Plywood for BIX termination

15amp shared

2x20amp

2x20amp

Page 13: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

13

Power requirements:

Emergency power: o 2 x 20 Amp circuits per rack (4 total)

1 outlet per circuit Anchored to the top of the racks (facing back) or on the wall

beside the rack

Standard power o Comm racks: 2 x 20 Amp circuits per rack (4 total)

1 outlet per circuit Anchored to the top of the racks (facing back) or on the wall

beside the rack o Walls: 1 x 15 Amp circuit

1 duplex on side wall in front of racks 1 duplex on back wall behind racks

Page 14: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

14

6.6.3 COMMUNICATIONS/SERVER ROOM, TYPE C 6.6.3.1 A cable tray just above the racks is required, going from the communications

rack to the server racks.

2 server cabinets and capacity for 200 data/telephone drops

10’ x 12’ (3m x 3.7m)

Ply

wo

od

fo

r B

IX te

rmin

atio

n

15amp shared

15amp shared

4x20amp4x20amp

2x20amp

Page 15: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

15

Power requirements:

Emergency power: o Server cabinets: 4 x 20 Amp circuits per server cabinet (8 circuits

total) 1 outlet per circuit Anchored to the top of the cabinets (facing back)

o Comm rack: 2 x 20 Amp circuits 1 outlet per circuit Anchored to the top of the rack or on the wall beside the

rack

Standard power o Server cabinets: 4 x 20 Amp circuits per server cabinet (8 circuits

total) 1 outlet per circuit Anchored to the top of the cabinets (facing back)

o Comm rack: 2 x 20 Amp circuits 1 outlet per circuit Anchored to the top of the rack (facing back) or on the wall

beside the rack o Front/Side walls: 2 x 15 Amp circuits

2 duplex per circuit

Page 16: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

16

7 COMMUNICATION RACKS

7.1 GENERAL 7.1.1 Communications racks will be Electron Metal model RK7FR2-194400-BK (Legacy

Model EM-19-77/700RR2-BK), tapped on both sides; complete with vertical wire

management model CMRSTD-054406-BK (Legacy Model EM-05-06/77CT-BK), on both

sides.

7.1.2 All communications racks are to be arranged as per sample layout below. New racks

will leave 30% of the rack or 13 rack units, whichever is greater, available for future

expansion. This 30% or 13u will not include 5u from the bottom of each rack which

are reserved for a UPS and a battery pack.

7.1.3 Data/voice cabling will be built down in 5u repeatable modules as shown in below.

The first module will begin after 1u of blank space below the last fiber patch panel.

7.1.4 Each module will consist of the following and in this order, top-down:

7.1.4.1 2u 48-port RJ45 front-serviceable/hinged patch panel to terminate horizontal

field runs

7.1.4.2 1u cable management

7.1.4.3 1u blank to accommodate customer provided 48-port Power Over Ethernet

(POE) switch

7.1.4.4 1u cable management

7.1.5 Data/voice modules will repeat down the rack immediately below the preceding

module leaving no vacant space between modules.

Page 17: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

17

7.2 COMMUNICATION RACK SAMPLE LAYOUT

Page 18: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

18

8 LABELING

8.1 GENERAL 8.1.1 Communications rooms will be labeled by floor number and by ascending alphabetic

character per floor (e.g. 1A, 2A, 2B). Coordinate with VIU IT Services for

communication room designations.

8.1.2 Horizontal Distribution patch panels will be designated D1 for Patch Panel 1, D2 for Patch Panel 2, etc. Each port on the patch panel will be left with the manufacturer's label of 1 to 48.

8.1.3 Wall jack faceplates will be labeled with the communications room designation

followed by the appropriate patch panel number and the port number (e.g. 1AD101,

1AD148). Note that single digit port numbers will have a preceding 0.

1A D1 01

| | +------ Port number

| +----------- Patch Panel Designation

+------------------ Communication Room Designation

8.1.4 All strands of fiber optic cabling must be clearly identified by source building and

actual room number (e.g. 355-110); mode type (e.g. MM, SM); and numbered

sequentially for a given type. Please see fiber optic labeling sample below.

8.1.5 Power receptacles are to be labeled properly to indicate amperage, circuit panel

location/sequence and whether it goes to a standard/emergency power source.

Page 19: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

19

8.2 SAMPLE FIBER PATCH PANEL LABEL

9 WIRELESS COMMUNICATION 9.1 All new buildings at Vancouver Island University will have access to the campus wireless

network from all areas of the building.

9.2 All new construction will allow for 1 wireless access point for every 90 sq. m. (969 sq. ft.) of floor

area.

9.3 As the location of wireless access points (WAP) within a building is dependent upon building

layout, construction materials and the amount of wireless bandwidth required it is not possible

to specify in advance the number of wireless access points needed to meet these requirements

when construction is based upon design/build.

9.4 Wireless access points require a data drop and will be powered over the Ethernet cable. (A

nearby AC power outlet is not required). There may be cases where an access point will have to

be relocated within an area. Allow for at least 3028mm (10ft) of cable slack coiled neatly

towards the access point end.

Page 20: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

20

9.5 Vancouver Island University Network Services staff will locate these data drops at the 25%

drawing stage.

9.6 Data jacks are to be properly terminated, enclosed and labeled. Enclosure may be similar to a

surface-mount type, securely fastened to a J-hook.

9.7 Access points are to be installed by the contractor as per vendor specifications, in coordination

with VIU IT Services staff.

10 MECHANICAL / ELECTRICAL ROOMS 10.1 Mechanical/Electrical equipment rooms shall be provided with a data/voice jack located

in proximity to Building Management Systems Control units.

11 OFFICES 11.1 All outlets are to be fed from above for ease of future relocation. Slab feeds are not

permitted.

11.2 Single-Occupancy Office

11.2.1 Provide two (2) x dual network jacks (4 in total), and two (2) power duplex per office,

located on opposite walls at the end of the room opposite the door. These locations

are to be confirmed by VIU IT Services before final drawings are issued for

construction.

11.3 Double-Occupancy Office

11.3.1 Provide three (3) x dual network jacks (6 in total), and three (3) power duplex per

office. Refer to drawings for actual locations.

12 CLASSROOMS 12.1 GENERAL

12.1.1 All classrooms, large or small, should be designed for the use of multimedia video

and audio presentation.

12.1.2 Rooms should be designed for student laptop connectivity via the wireless network.

12.1.3 Where wired access is required, data drop locations will be specified in the drawings.

12.2 POWER and DATA/VOICE 12.2.1 Provide a network jack for one wall mounted phone inside each classroom and lab

adjacent to the main door.

12.2.2 Provide one network jack to the data projector location that goes back to a

communication room.

Page 21: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

21

12.2.3 Provide three network jacks from the instructor’s desk or podium, to the

communication room. These are to be run in a 20mm (3/4”) conduit stubbed out

within the ceiling structure. Add one network jack centered on the front wall.

12.2.4 One quad electrical receptacle, on a dedicated circuit, should be provided in the

instructor’s desk, affixed to the interior of the desk or equipment cabinet.

12.2.5 One duplex electrical receptacle should be centered on the front wall.

12.2.6 A classroom designed for laptops must include power outlets for student

connections. Review quantity and locations with VIU IT Services.

12.2.6.1 Two duplex electrical receptacles should be evenly spaced on the back wall.

12.2.6.2 Three duplex electrical receptacles should be evenly spaced on each of the

sidewalls.

12.2.7 Provide one duplex receptacle in the ceiling for the fixed data projector. To be

powered via a key switch located in the room to enable power reset of the data

projector.

12.3 AUDIO/VISUAL PROVISIONS 12.3.1 Provide one 25.4mm (1”) conduit from podium in lecture theatre or instructor

stations in general classrooms to the data projector location. No tight bends

permitted. This will be used to accommodate any required AV cables.

12.3.2 All audio, video and control electrical circuits should be fed from “clean” legs of the

transformer, free of high inductive loads. There shall be no elevator motors,

compressor motors, blower motors, etc. on the side of the power transformer that

feeds the media equipment.

12.3.3 Data projectors should be ceiling mounted. Exact location to be coordinated with

the VIU Audiovisual Services Group. Typical lens to screen distances 11’ and 16’

depending on room size and data projector model.

12.3.4 For small to medium classrooms the projection screen will be suspended from

earthquake-proofed ceiling or wall mounts.

12.3.5 Designers must consult with the VIU Audiovisual Services Group when selecting and

sizing projection screens.

12.3.6 Any screen 10’ or wider should be motorized.

12.3.7 When screens are installed in ceiling recesses, it is important that the recess be large

enough to permit maintenance of the screen, motor and fabric.

12.3.8 To facilitate screen motor maintenance, a quick disconnection should be used.

12.3.9 The switch for electrically operated screens must be the type that returns to neutral

when released and be located close to the instructor’s station.

12.3.10 Ceiling mounted fixtures must not interfere with the physical mounting of the data

projector or the projected image path.

Page 22: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

22

12.4 SOUND REINFORCEMENT 12.4.1 For classrooms or lecture theatres over 50 seats, voice amplification/sound

reinforcement/infrared transmitter is required. This assists with the hearing

impaired and ease of instruction. The design of these systems must be determined

in consultation with the VIU Audiovisual Services Group.

12.4.2 Provision for fixed and wireless microphone capability must be included in all

permanent sound reinforcement systems.

12.4.3 Amplifiers to be "low-impedance".

12.4.4 System must have the capability of playback and recording. Balanced lines to be

provided.

12.4.5 Speaker lines must never be included in conduit carrying electric power.

12.5 ACOUSTICS 12.5.1 Amplification equipment should be specified when reinforcement is needed,

particularly when music reproduction and film projection is undertaken. A simple

portable amplification system should be available when needed. Controls should be

convenient, simple and all in one place. As many controls as possible should be “pre-

set” to optimum levels for the respective media to be used.

12.5.2 Microphone inputs should be provided at front of rooms (presenter’s position) and

side and/or rear wall locations.

12.6 LIGHTING 12.6.1 Combination direct/indirect lighting is preferred. Zone lighting control required for

instructor vs. student spaces. Exact configuration to be determined in consultation

with VIU Audiovisual Services Group.

13 COMPUTER LABS 13.1 GENERAL

13.1.1 Computer labs have many of the same characteristics and requirements as standard

classrooms. Refer to Classrooms guidelines for applicable information. This section

will highlight any requirements over and above classroom design.

13.1.2 Instructor and student workstation locations are to be fixed and hard wired.

Page 23: Information Technology Services DESIGN AND INSTALLATION ... · 6/5/2015  · 2.5.2.1 Standard conduit fill rates must not be exceeded. 2.5.2.2 Conduits entering a communication room

Information Technology Services DESIGN AND INSTALLATION STANDARDS

Vancouver Island University

REVISION DATE: June 11, 2015

23

13.2 ARCHITECTURAL 13.2.1 LOCATIONS WITHIN A BUILDING

13.2.1.1 When multiple labs are located within a building, their proximity to each other

should be considered with ease of computer lab supervision and support in

mind. One person can supervise three or four labs if they are located adjacent

to each other.

13.2.2 ROOM SHAPE

13.2.2.1 The furniture style and layouts must be designed in coordination with the room

shape and usage. Layouts must provide for optimal sight lines for viewing visual

presentations. Exact configuration to be determined in consultation with the

VIU Audiovisual Services Group.

13.2.3 DOORS

13.2.3.1 Computer lab doors must have electronic card access control. Where multiple

doors enter the room, one door must be the access (card reader) door and the

remaining doors must be auto lock doors.

13.2.4 FURNITURE

13.2.4.1 Computer lab furniture requires data and power services to each station. It is

important that the furniture style and layout are confirmed before the room

design is complete.

13.2.4.2 Allow space for a print release station either in the room (preferred) or in close

proximity. Ideal location is at the back of the room.

13.2.4.3 Allow for secure storage. Typically an 18” deep, 36” wide, 70” high cabinet will

be sufficient.

13.2.4.4 Adjustability of instructor desk height is preferred.

13.2.4.5 At least one student station must be designed for wheelchair use with a hand

crank operation to adjust desk height.