Information Technology Department Bond Program Implementation Plan January 8, 2013 1 West Contra Costa Unified School District

Information Technology Department Bond Program Implementation Plan January 8, 2013

  • Upload
    radley

  • View
    29

  • Download
    0

Embed Size (px)

DESCRIPTION

West Contra Costa Unified School District. Information Technology Department Bond Program Implementation Plan January 8, 2013. Agenda. Project Selection Drivers Fund Allocation and Schedule Determinants Funding Need Schedule Budget for 2013 Project Implementation Schedule. - PowerPoint PPT Presentation

Citation preview

Page 1: Information Technology Department Bond Program Implementation Plan January 8, 2013

Information Technology Department

Bond Program Implementation Plan

January 8, 2013

1

West Contra Costa Unified School District

Page 2: Information Technology Department Bond Program Implementation Plan January 8, 2013

Agenda

• Project Selection Drivers• Fund Allocation and Schedule Determinants• Funding Need Schedule• Budget for 2013• Project Implementation Schedule

2

Page 3: Information Technology Department Bond Program Implementation Plan January 8, 2013

Project Selection Drivers

• Compliance• Instructional Technology• Infrastructure

3

Page 4: Information Technology Department Bond Program Implementation Plan January 8, 2013

Fund Allocation and Schedule Determinants

• Online Assessment compliance by 2014• Common Core requirements• Curriculum & Technology Integration• Digital Equity

4

Page 5: Information Technology Department Bond Program Implementation Plan January 8, 2013

Funding Need Schedule

5

Year Amount ($M) Cumulative ($M)

2013 20 20

2015 8 28

2017 5 33

2019 2 35

Page 6: Information Technology Department Bond Program Implementation Plan January 8, 2013

Budget for 2013

6

Scheduled Technology Projects for the First Two (2) Years

Project Sites Projected Budget

Wireless All $ 6,775,000.00

Refresh of Student Desktop Computers All $ 800,000.00

Virtual Desktop Infrastructure (VDI) All $ 5,300,000.00

Cloud Initiative All $ 1,150,000.00

Professional Development * All $ 1,000,000.00

Educational Software All $ 900,000.00

Help Desk Management All $ 600,000.00

Single- Sign -On (Completion) All $ 250,000.00

Website Enhancements All $ 100,000.00

Resource Augmentation * All $ 270,000.00

Document SOP All $ 540,000.00

Relocate Data Center All $ 1,000,000.00

Upgrade Wiring to Fire Code Standards All $ 300,000.00

Project Management $ 1,015,000.00 Projected Total: $20,000,000.00

* Requires legal vetting

Page 7: Information Technology Department Bond Program Implementation Plan January 8, 2013

Budget for 2013 (Cont’d)

7

Supporting Facilities Projects

Project Sites Cost

Security Cameras 10 $ 3,250,000.00

Card Access 10 $ 2,250,000.00

Project Management $ 612,500.00

Total: $6,112,500.00

Page 8: Information Technology Department Bond Program Implementation Plan January 8, 2013

Project Implementation Schedule

8

No. Project Start End Duration

Days

1 Wireless 1/1/2013 7/31/2015 720.00

3 Refresh of Student Desktop Computers 1/1/2013 12/29/2013 150.00

2 Single Sign-On 1/1/2013 8/1/2013 212.00

4 Help Desk Management 1/1/2013 7/31/2014 941.00

5 Upgrade All Wiring to Fire Code Standards 8/1/2013 12/31/2013 152.00

6 Professional Development 8/1/2013 7/31/2015 729.00

7 Website Enhancements 8/1/2013 7/31/2015 729.00

8 Resource Augmentation 8/1/2013 7/31/2015 729.00

9 Document SOP 8/1/2013 7/31/2014 364.00

10 Relocate Data Center 8/1/2013 7/31/2015 729.00

11 Educational Software 9/1/2013 12/31/2014 486.00

12 Virtual Desktop Infrastructure (VDI) 1/1/2014 12/31/2014 360.00

13 Cloud Initiative 8/1/2014 7/31/2015 364.00

Page 9: Information Technology Department Bond Program Implementation Plan January 8, 2013

Thank You