    "Inflow Performance"

    - Home work -

    Hawar Abdul-khaliq

    4th stage

  • 7/30/2019 inflow performance "IPR"

    2/5

    H.W.

    construct the IPR of a vertical well in an oil reservoir considers:

    1.Transient flow at 1 month .2.Steady state flow.

    3.Pseudo steady state flow.

    The following data are given:

    K=8.2 md. , =19% ,h=53 ft , Pe=5651 psi , Pb=50 psi , Bo=1.1

    =1.7 cp. , A=640 acre. , re=2980 ft , rw= 0.328 ft , S=0

    Ct=1.29*10

    -5

    psi

    -1

    Solution:

    time = 30 day = 720 hr.

    1.q= ( )

    = 1161.98 bbl/day

    J= = 0.20745 bbl/day/psi

    2.q= * + = 1011.46 bbl/day

    J=

    = 0.1806 bbl/day/psi

    3.q= = 1102.2 bbl/day

    J=

    = 0.19678 bbl/day/psi

  • 7/30/2019 inflow performance "IPR"

    3/5

    pwf (psi) q)1 q)2 q)3

    0 1466.051 1020.492 1111.995200 1414.164 984.3749 1072.639

    400 1362.278 948.2577 1033.284600 1310.391 912.1405 993.928800 1258.505 876.0233 954.57231000 1206.619 839.906 915.21671200 1154.732 803.7888 875.8611400 1102.846 767.6716 836.50531600 1050.959 731.5544 797.14961800 999.0729 695.4372 757.79392000 947.1865 659.3199 718.43822200 895.3 623.2027 679.08252400 843.4136 587.0855 639.72682600 791.5272 550.9683 600.37112800 739.6408 514.851 561.01543000 687.7544 478.7338 521.65973200 635.868 442.6166 482.3043400 583.9816 406.4994 442.94833600 532.0952 370.3821 403.59263800 480.2087 334.2649 364.23694000 428.3223 298.1477 324.88124200 376.4359 262.0305 285.52564400 324.5495 225.9132 246.16994600 272.6631 189.796 206.81424800 220.7767 153.6788 167.4585

    5000168.8903 117.5616 128.1028

    5200 117.0039 81.44434 88.747095400 65.11745 45.32712 49.39145600 13.23104 9.209892 10.03575651 0 0 0

  • 7/30/2019 inflow performance "IPR"

    4/5

    Transient flow

    Steady state flow

    0

    1000

    2000

    3000

    4000

    5000

    6000

    0500100015002000

    q

    q

    0

    1000

    2000

    3000

    4000

    5000

    6000

    020040060080010001200

    q

    q

  • 7/30/2019 inflow performance "IPR"

    5/5

    Pseudo steady state flow

    * according the productivity index J and IPR , the best flow in

    this reservoir is transient flow after this flow the pseudo-steady

    state is the best , and steady-state flow .

    * the formula of the eq. of the transient flow depends on time (as

    time increases J decreases ).

    * when the pressure pwf below bubble point pb, the IPR appearas a curve and J constant because the reservoirat the pressure

    below pb is two-phase flow .

    0

    1000

    2000

    3000

    4000

    5000

    6000

    020040060080010001200

    q

    q