Industry Governance Group
29/04/2020
Rmdservice.com2rmdservice.com
Minutes from Previous IGG Meeting 13:30 – 13:35
Review of Action Items 13:35 – 13:55
CRU Update 13:55 – 14:15
De-harmonisation Update 14:15 – 14:25
Retail Market Design Service Update 14:25 – 14:45
MRSO Update 14:45 – 14:55
ESBN Networks Update 14:55 – 15:15
Gemserv Update 15:15 – 15:20
AOB 15:20 – 15:25
Next Steps 15:25 – 15:30
IGG Agenda
Rmdservice.com3rmdservice.com
Minutes from previous IGG
For Approval Today:
• Minutes (v1.0) from Conference Call on 01.04.2020
Rmdservice.com4rmdservice.com
IGG Actions
Updated IGG Action List issued in advance of meeting
• 1 Action closed since last IGG meeting
• 3 IGG Actions carried forward
Rmdservice.com5rmdservice.com
IGG Actions - Closed
AP No. Title
Org.
Assigned to Date Closed Date Raised
1139
CoS Registration Date Issue – MRSO to issue to MPs via RMDS details of the
CoS Registration Date issue MRSO 04/03/2020 05/02/2020
Rmdservice.com6rmdservice.com
IGG Actions – Open
AP No. Title
Org.
Assigned to Date Due Date Raised
1122
Data Sharing Agreement - ESBN to revert with a position on a proposed Data
Sharing Agreement (Action 1118). ESBN 29/04/2020 05/12/2018
1129
Low Call Phone Numbers - CRU to contact Com Reg with regard to the
changes to the low call numbers (1890 etc.) which come into effect in 2022 CRU 29/04/2020 06/03/2019
1137
Revenue Protection Workshop – RMDS to organise a Revenue Protection
Workshop for early 2020 on behalf of ESBN. RMDS 29/04/2020 04/12/2019
Industry Governance Group Meeting
7
29 April 2020
CRU Update
Rmdservice.com8rmdservice.com
Lisa Fahy, CRU
De-harmonisation Update
Retail Market Design UpdateLindsay Sharpe, RMDS
Rmdservice.com10rmdservice.com
Facilitate energy efficiencies in Local Authority Public Lighting
• The following Market Changes will be implemented in a single release, schema and non-
schema
v13.00.00 Release – Status
MCR Version Description Completed Milestones Status
MCR1157 V5.0*Data Aggregation and Data
ProcessingDraft 1 Sample Market Messages
MCR1158 V5.0* Customer Data Draft 1 Sample Market Messages
MCR1159 V5.0* Change of Supplier
Draft 1 Sample Market Messages,
Downloadable Files & Extranet
Screenshots
MCR1160 V5.0* Meter Works Draft 1 Sample Market Messages
MCR1161 V3.0* New Connection Draft 1 Sample Market Messages
MCR1135 V7.0* MPRN Enquiry web service None
MCR0176 V5.0* E-Mail Validation None
<NI MCRs> <N/A> <No NI MCRs in agreed scope> N/A <N/A>
Other (ROI Only) Comment Status
Smart Enablement • Technical Upgrades
* IGG approval of latest re-versioning pending
Rmdservice.com11rmdservice.com
v13.00.00 Release – Plan
2019
Q1 Q2 Q3 Q4
IGG
Engagement
2020
Q1 Q2 Q3 Q4
Design/Build/Test
April
2020
Go Live
(TBC)
Smart Enablement
Market Engagement
Other (ROI Only)
29th
May
26th
Jun
Market
AssuranceROI Assurance
Approach
Published
ROI Approach
Approved By
IGG ROI Participant
Questionnaire
Phase 2 Issued
IPT
Prep
IPT
Exec
IPT Window
(NI & ROI)
Go Live
(TBC)
Key
IGG (Meetings & Calls)
Key Milestone (Confirmed & Draft)
Go live
13th
Sep
24th
Jul
02nd
Oct
06th
Nov
04th
Dec
ROI Participant
Questionnaire
Phase 1 Issued
Publish Draft
Schema Sharing
Approach
Schema
Draft 1
Schema
Draft 2
Schema
Draft 3 (Not
issued, as no
change)
Schema
Draft 5
v.13.00.00
Schema
Final
Schema
Release
16th
Jan 5th
Feb4th
Mar1st
Apr
29th
Apr
27th
May24th
Jun
22nd
Jul
2nd
Sep
30th
Sep4th
Nov
2nd
Dec
Draft 1 Release
Sample Market
Msgs, Files &
Screenshots
Draft 2 Release
Sample Market
Msgs, Files &
Screenshots
Schema
Draft 3 (Not
issued, as no
change)
Rmdservice.com12rmdservice.com
Facilitate energy efficiencies in Local Authority Public Lighting
• Approval is sought for the re-versioned MCRS:
• Please note that the market documentation associated with each MCR is linked
in each of the pdf’s that were issued via the ReMCoDS emails.
• Once approved they will all be posted on the RMDS website.
MCR Re-Versioning Approval
MCR # Title
1157 Smart Metering Data Processing and Data Aggregation
1158 Smart Metering Customer Data Changes
1159 Smart Metering Change of Supplier
1160 Smart Metering Meter Works
1161 Smart Metering New Connections
1135 MPRN Enquiry web service
0176 Email Address Validation
Rmdservice.com13rmdservice.com
Facilitate energy efficiencies in Local Authority Public Lighting
v13.00.00 Cutover Approach Update
• ESBN estimates that cutover for the v13.00.00 Market Release will require 10-11 days
• The cutover is made up of two parts:
1. A system outage of 3-4 days on the Retail Market Systems to deploy v13.00.00
Schema
2. Syncing the Smart Meter data between the Retail Market and AMI Systems,
estimated to require 6-7 days
• Smart Meter data sync (part 2), which is specific to the ROI jurisdiction only, can be
carried out while the Retail Market Systems are operational, with the following caveat:
• Smart Data Services (SDS) should not be requested before:
• the 4th Jan 2021 (in line with agreed Industry Positions), and
• until after the Smart Meter data sync is complete
• From the time that v13.00.00 Schema is deployed until the Smart Meter data sync has
completed, there are a number of Market Messages that will be rejected if they are
submitted with SDS populated (see appendix for details).
• As part of v13.00.00 testing and dress rehearsals, ESBN is in the process of validating
these scenarios and timings.
Rmdservice.com14rmdservice.com
Facilitate energy efficiencies in Local Authority Public Lighting
v13.00.00 Proposed cutover window options
• ESBN have looked at two options:
1. System outage commences COB Friday 18th December 2020
• System outage expected to finish at latest on Monday 21st December
• v13.00.00 operational post system outage as per v13.00.00 Cutover Approach
• Smart Meter data sync expected to finish by 31st December
2. System outage commences Saturday 26th December 2020
• System outage expected to finish at latest on Tuesday 29th December
• v13.00.00 operational post system outage as per v13.00.00 Cutover Approach
• Smart Meter data sync expected to finish by w/e 8th January 2021
• ESBN are minded towards option 1: System outage commences COB Friday 18th
December 2020.
• ESBN will also consult with other stakeholders such as MRSO & NIE Networks.
• ESBN are seeking feedback from Market Participants on the above options to
ReMCoDS by COB Friday 7th May 2020.
Rmdservice.com15rmdservice.com
Facilitate energy efficiencies in Local Authority Public Lighting
Appendix
• Within the ROI jurisdiction, Smart Data Services can be requested on the Market
Messages below. These Market Messages will be accepted between Go-Live of
v13.00.00 Schema and completion of the Smart Meter data sync, once they are not
submitted with a request for Smart Data Services.
• Example:
• 016 – Change of Legal Entity
• A valid 016 without SDS populated will be accepted
• An 016 submitted with SDS populated e.g. request for CoLE and 01 Interval Smart
Data Services / MCC12 will be rejected in its entirety
Message No. Message Description
010 Registration Request
013 Customer Details Change
016 Change Of Legal Entity
017 Meter Point Status Change Request
(Note: SDS can be requested for Re-Energisation only)
Rmdservice.com16rmdservice.com
Access Agreement Approach
• The existing Extranet Access Agreement requires updating to ensure GDPR
compliance.
• A similar Access Agreement is required for the existing Secure File Transfer Service
(SFTS), and for the new MPRN Enquiry Web Service.
• To meet the above requirements, ESB Networks will draft a general Access
Agreement containing three Schedules to cover the access mechanisms:
• RMP Extranet
• Secure File Transfer Service (SFTS).
• MPRN Enquiry Web Service
• This general Access Agreement will supersede the existing Extranet Access
Agreement.
• The Access Agreement will need to be approved and signed by Market Participants in
advance of the v13.00.00 Market Release.
• The Access Agreement document will be communicated and shared with Market
Participants as per the timeline outlined on the next slide.
Rmdservice.com17rmdservice.com
Access Agreement Timeline
• The Access Agreement document will be communicated as per the timeline below
(please note the dates refer to the week commencing):
Draft 1 Access
Agreement circulated
to Market Participants
Market
Participant Feedback
returned on Draft 1
Access Agreement
Draft 2 Access
Agreement circulated
to Market Participants
Market
Participant Feedback
returned on Draft 2
Access Agreement
25/05/20 22/06/20 20/07/20 03/08/20
Final Access
Agreement circulated
to Market Participants
Final Access
Agreement Approved
at September IGG
Final Access
Agreement circulated
to Market Participants
for Sign Off
21/08/20 31/08/20 07/09/20
1
765
432
Signed Access
Agreement returned
to ESB Networks by
Market Participants
8
02/11/20
Rmdservice.com18rmdservice.com
Re-Energise with CoLE for v13.00.00
• Proposed v13.00.00 market design states that for Non-Interval sites:
• When a site is re-energised, MM307 billing message is issued to the registered Supplier
(MPD10)
• When a CoLE is processed, MM300 billing message is issued to the registered Supplier
(MPD25)
• BAU operation is that where a Re-Energisation with CoLE takes place, both are
processed separately and MM307 and MM300 billing messages are issued to the
registered Supplier. This is not specifically called out in either MPD10 or MPD25.
• This will continue to be the case from Go-Live of v13.00.00 for Non-Smart sites.
• For Smart sites post v13.00.00 release, where a Re-Energisation with CoLE is
requested, as per proposed design the CoLE will be processed once the Re-
Energisation is complete. MM307 billing message only will issue to the registered
Supplier; MM300 will not issue.
Rmdservice.com19rmdservice.com
DR1205 Details
Date Raised 20/2/2020 Date last Approved
Requesting
Organisation
ESBN Jurisdictional
Implementation
ROI
Schema Impacting N Jurisdictional Applicability ROI
Latest Version V2.0
Change Summary This MCR sets out ESB Networks process for invoicing and collecting PSO money relating to
Commercial Storage units. ESB Networks proposed this manual solution to the CRU in response
to CRU/19/034 on the basis that the number of customers involved are relatively low and that it is
limited in scope i.e. to commercial storage sites only.
ESB Networks will update it owns Embedded Generator application process to include details on
how a commercial storage unit applies for and agrees a house load MIC with ESB Networks.
ESB Networks will contact commercial storage customers who have already made a connection
application and will discuss MIC requirements with those customers.
Classification • For Approval as an MCR
MCR1205 - Application of the PSO to
Commercial Storage
Facilitate energy efficiencies in Local Authority Public Lighting
Rmdservice.com20rmdservice.com
• SoLR Review Exercise
• Continuing to progress.
Updates
Rmdservice.com21rmdservice.com
http://rmdservice.com/outages-2020/
Upcoming Outages for ROI
There are no outages scheduled for May
Thank You
MRSO Update James Long
29th April 2020
Gerry Halligan
esbnetworks.ie
Debt Flagging
Jan-20 Feb-20 Mar-20
Total Debt Notifications received (012) 186 (32) 178 (31) 158 (20)
Total Debt Notifications not forwarded for
reason implied or explicit CoLE, timeout, etc.43 (5) 44 (5) 33 (3)
Total Debt Notifications sent to gaining
supplier (112)143 (27) 134 (26) 125 (17)
Total not cancelled 104 (22) 93 (23) 93 (14)
Total cancelled 39 (5) 41 (3) 32 (3)
Total Debt Notifications sent to gaining
supplier as % of total COS0.4% 0.4% 0.4%
Figures in brackets represent situations where an ESB Networks PAYG meter
is installed.
esbnetworks.ie
Debt Flagging
Nov-18
Dec-18
Jan-19Feb-19
Mar-19
Apr-19
May-19
Jun-19 Jul-19Aug-19
Sep-19
Oct-19Nov-
19Dec-19
Jan-20Feb-20
Mar-20
Total Debt Notifications received 221 162 180 184 268 311 379 355 252 307 320 375 268 125 186 178 158
Total Debt Notifications sent to gaining supplier 145 124 139 156 141 192 200 252 183 172 193 218 133 102 143 134 125
Total Cancelled 47 48 42 58 50 46 78 74 49 51 44 39 22 25 39 41 32
PAYG Debt Notifications sent to gaining supplier 23 23 29 31 26 37 36 32 36 28 42 42 39 22 27 26 17
0
50
100
150
200
250
300
350
400
Total Debt Notificationsreceived
Total Debt Notificationssent to gaining supplier
Total Cancelled
PAYG Debt Notificationssent to gaining supplier
esbnetworks.ie
Objections – Erroneous Transfer
Jan-20 Feb-20
No. of Objections 131 162
Cancellations from Objections 39 41
Objection emails to MRSO 9 11
Reasons:
Uncontactable by phone 4 1
Written communication
COS confirmed 5 10
Other
Escalation emails 9 4
Mar-20
139
32
7
1
6
11
esbnetworks.ie
Objections – Erroneous Transfer
7367
7873
63
80 80
6266
94
72
8792 92
82
57
72
59
73
51
58
68
59
95
86
79
131
162
139
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
0
20
40
60
80
100
120
140
160
180
No
. o
f C
oS
Co
mp
leti
on
s
No
. o
f O
bje
cti
on
s
No. of Objections
CoS Completions
Industry Governance Group (IGG) PresentationWednesday 29 April 2020
esbnetworks.ie
Q3 Q4 Q1 Q2 Q3 Q4
V.13 Schema Release Hypercare
System Separation (30 Weeks)
Early May 2021
Markets
Separated in
Dublin
ESBN SMART
Phase 1
System
Separation
Phase
Dublin Build
Supplier Project 8 Weeks
Dual Jurisdiction Supplier
• Webforms Replacement on Emma
• New Emma Required to Service
ROI Market.
• Existing Emma Remains in Situ for
NI Market unchanged.
• Participation in IPT
• No back end system work required
initially due to both jurisdiction
been on v.13 at go-live
Scope of Supplier Project
Single Jurisdiction Supplier
• Webforms Replacement on Emma
• ROI Participant Point Emma at New
ROI Hub at cutover
• No Change for Single Jurisdiction NI
Market Participant
Webforms Replacement
Back End System Work (if required)
Option 4 - Separate Post V13 @ end of Q2 2021
De-harmonisation
2020 2021
esbnetworks.ie
Detail Definition
Design
Build
Test
IPT
Cutover
RA Approval to proceed
Go
live
RA Engagement
Market Participant Engagement
Market Plan Published
Hypercare
De-harmonisation
esbnetworks.ie
De-harmonisation
Status update:
• ESBN working through project definition with Procurement and Legal.
• Intend to meet RAs within the week.
• Early project milestones slightly delayed due to the current work
programme and the impacts of Covid 19
Retail Market Assurance Services for the Irish Electricity Market
Sarah Fuller
Industry Governance Group (IGG)
Teleconference
29 April 2020
New Entrants
▪ 1 Large Supplier▪ In ITA stage
▪ 1 Large Supplier entering new Market Segment▪ In planning stage
Gemserv 33
15
9
47
86
Large Supplier
Small Supplier
Self-Supplier
Demand Side Unit
Export Only Supplier
V13 Release
▪ Self Assessment Phase 2▪ PQs have been sent to all Market Participants▪ Deadline is 29 May 2020▪ Please be reminded there is no contingency in the
project plan to facilitate late responses
Gemserv 34
Forward Work Plan
Gemserv 35
May 20 Jun 20 Jul 20
New Large
Supplier
New Segment
Suppliers
BSA ongoing, IPT Scheduled
BSA Assurance Phase
V13 Release
Planning
StageAssurance Activities
Assurance Activities
Formal Assessment Phase Self
Assessment Phase 2 PQ
PQ response analysis &
reporting
Questions
Gemserv 36
Sarah Fuller
Assurance Contract Manager
+353 (0)1 669 4630
Elizabeth Montgomerie
Assurance Consultant
+44 (0)7703 740 282
Simon Fox-Mella
Assurance Consultant
+44 (0)20 7090 7744
Thank you
Rmdservice.com38rmdservice.com
AOB
IGG Meeting
Rmdservice.com39rmdservice.com
Next Steps
Diary dates for next meetings:
• IGG Conference Call – Wednesday 27th May 2020
• IGG Meeting – Wednesday 24th June 2020 Belfast (subject to change)
Dates for 2020 are on Calendar of Events on RMDS website www.rmdservice.com
Thank You