Industry DayEast County Advanced Water Purification Project August 15, 2019
Welcome
1
2
8/14/2019
2
Presentation Overview
Introduction of Agency Members
Project Background
Progressive Design‐Build Construction Packages
Minimum Qualifications
Procurement Schedule
Questions and Answers
Introduction of Agency Members
Allen Carlisle Karen JassoyMark Niemiec Seval Sen Kyle Swanson
Graham MitchellDirk Epperson Yazmin Arellano
Richard Crompton Bill MorganDan Brogadir Susan Spotts
Carlos Lugo Brian OlneyMichelle Berens Jennifer Bryant
3
4
8/14/2019
3
Project BackgroundEast County Advanced Water Purification (ECAWP)
ECAWP Project Purpose
Create a new, local, sustainable, and drought proof drinking water supply for East County
Produce up to 30 percent of East County’s drinking water supply
Reduce future financial liabilities related to imported water supply cost and wastewater treatment and disposal
Reduce discharge to the Pacific Ocean
5
6
8/14/2019
4
Project Description
A water supply project implementingSurface Water Augmentation (SWA)
Treating 15 MGD of wastewater
● Padre Dam
● City of El Cajon
● County of San Diego
Producing 11.5 MGD of advancedtreated water for SWA at Lake Jennings
● Supply to R. M. Levy WTP
ECAWP Project Delivery
ECAWP JPABoard
Technical Advisory
Committee
Padre Dam(Administrator)
Progressive DB
Contractors
Program Manager/
Owner’s Advisor
El Cajon
County
Padre Dam
Helix
JPA formation anticipated in October 2019 PDB Contracts will be with the JPA
7
8
8/14/2019
5
ECAWP Project Financing
Cash
Revenue BondsState and Federal Grants
SRF Loan WIFIA Loan
LRP
Progressive Design‐Build Construction Packages & Minimum Qualifications
9
10
8/14/2019
6
Procurement Packages
Package #2 Advanced Water Purification Pipeline/ Dechlorination Facility (~$30M)
Package #3 East Mission Gorge Force Main/ Residuals Bypass System (~$20M)
Package #4 Influent Pump Station/East Mission Gorge Pump Station Retrofits (~$10M)
Package #1 Water Recycling Facility/Advanced Water Purification Facility/Solids Handling (~$260M)
Package #1 – WRF/AWP Facility/Solids Handling
New 16 MGD WRF Headworks, odor control, primary clarifiers,
EQ basin, bioreactors, secondary clarifiers,tertiary filters, and chlorine contact basin
WRF
11
12
8/14/2019
7
Package #1 – WRF/AWP Facility/Solids Handling
New 11.5 MGD AWP Facility MF, RO, UV/AOP, Free Chlorination, Post
Treatment Stabilization, and Product WaterPump Station, Administration Building, andVisitor’s Center
AWPF
Package #1 – WRF/AWP Facility/Solids Handling
New Solids Handling Thickeners, digesters, dewatering, and
considerations for future energy recovery
Solids Handling
13
14
8/14/2019
8
Package #1 (WRF/AWP Facility/Solids) PDB Minimum Qualifications
Within the past 15 years, DB entity’s Engineer completed:● Design of at least two (2) Wastewater Treatment Facility
projects, each over 10 MGD in design flow
● Design of at least one (1) Water Treatment or Advanced Water Treatment project (inclusive of membrane filtration), over 10 MGD in design flow
Within the past 15 years, DB entity’s Contractor completed:● Construction of at least two (2) Wastewater Treatment
Facility projects, each over 10 MGD in design flow
● Construction of at least one (1) Water Treatment or Wastewater Treatment Facility project with construction cost over $100M
Package #2 – AWP Pipeline/Dechlorination Facility
AWP Pipeline
New 24 inch AWP Pipeline Approximately 54,000 ft long ~49,000 ft of open‐cut ~2,600 ft of above‐grade ~2,300 ft of trenchless Rock excavation Welded Steel Pipe
15
16
8/14/2019
9
Package #2 – AWP Pipeline/Dechlorination Facility
DechlorinationFacility
Cl
New Dechlorination Facility Located at El Monte Pump Station site
Package #2 – AWP Pipeline/Dechlorination Facility
New Lake Jennings Inlet Rock water feature
Lake Jennings Inlet
17
18
8/14/2019
10
Package #2 (AWP Pipeline/Dechlorination Facility) PDB Minimum Qualifications
Within the past 10 years, DB entity’s Engineer completed:● Design of at least three (3) conveyance projects, each 24‐inch
or larger diameter pressure pipeline and minimum 10,000 feet in length, one of which being welded steel pipe
● Design of at least one (1) conveyance project using trenchless construction methods of at least 500 feet in length
Within the past 10 years, DB entity’s Contractor completed:● Construction of at least three (3) conveyance projects, each
24‐inch or larger diameter pressure pipeline and minimum 10,000 feet in length, one of which being welded steel pipe
● Construction of at least one (1) conveyance project using trenchless construction methods of at least 500 feet in length
Package #3 – EMG Force Main/Residuals Bypass System
EMG Force Main
New 30 inch EMG Force Main Approximately 18,200 ft long ~14,700 ft of open‐cut ~3,500 ft of trenchless under San Diego River
19
20
8/14/2019
11
Package #3 – EMG Force Main/Residuals Bypass System
Residuals Bypass Lift Station
Residuals Bypass Pipeline
New Residuals Bypass System Slipline existing 24 inch, ~8,800 ft long pipeline New 16‐inch, ~3,100 ft long gravity pipeline
(open‐cut) New 12‐inch, ~3,500 ft long force main
(trenchless) under San Diego River New 1.7 MGD lift station
Package #3 (EMG FM/Residuals Bypass System) PDB Minimum Qualifications
Within the past 10 years, DB entity’s Engineer completed:● Design of at least three (3) conveyance projects, each
24‐inch or larger diameter pipeline and minimum 1 mile in length
● Design of at least one (1) conveyance project using trenchless construction methods of at least 500 feet in length
Within the past 10 years, DB entity’s Contractor completed:● Construction of at least three (3) conveyance projects,
each 24‐inch or larger diameter pipeline and minimum 1 mile in length
● Construction of at least one (1) conveyance project using trenchless construction methods of at least 500 feet in length
21
22
8/14/2019
12
Package #4 – Influent Pump Station/EMG Pump Station Retrofits
Influent Pump Station
Influent Pump Station Increase capacity from 2 mgd to 6 mgd Replace four existing 50‐hp pumps with
three new 200‐hp (estimated) pumps Replace existing electrical and mechanical
systems
Package #4 – Influent Pump Station/EMG Pump Station Retrofits
EMG Pump Station
EMG Pump Station Replace four existing 500‐hp pumps with
four new 600‐hp (estimated) pumps Replace existing electrical and mechanical
systems
23
24
8/14/2019
13
Package #4 (EMGPS/IPS Retrofits) PDB Minimum Qualifications
Within the past 10 years, DB entity’s Engineer completed:
● Design of at least three (3) Sewer Lift Station projects, each 5 MGD or more in design flow
Within the past 10 years, DB entity’s Contractor completed:
● Construction of at least three (3) Sewer Lift Station projects, each 5 MGD or more in design flow
Not Eligible Parties
In accordance with Section V of the As‐Need Technical Engineering and Environmental Professional Services RFP (Project No. 215011) with Padre Dam, the following entities that were selected under the As‐Needed Contract are precluded from participating on a PDB team for the ECAWP Project:
Kennedy Jenks Trussell Technologies Brown and Caldwell Helix Environmental Clear Controls Services Michael R. Welch Consulting Clean Energy Capital
NV5 Flow Science National Water Research Institute Geocon Paul Revers Brown, Inc. Public Financial Management Scripps Institute of Oceanography
25
26
8/14/2019
14
Procurement Schedule
PossibleInterviews
SOQs ReceivedRFIs
Two Step Progressive Design‐Build Procurement
Pre‐SOQ MeetingRFQ IssuedIndustry Day
Step 1
Shortlist
InterviewsProposals ReceivedRFIsProprietary
MeetingsPre‐Proposal MeetingRFP Issued
Step 2
Selection
27
28
8/14/2019
1
Schedule Overview
Package 1: WRF-AWP-Solids (~$260M)
RFQ/RFP
Design
Const.
Package 2: AWP Pipeline-Dechlorination(~$30M)
RFQ/RFP
Design
Const.
Package 3: EMG FM-Bypass (~$20M)
RFQ/RFP
Design
Const.
Package 4:IPS-EMGPS (~$1OM)
RFQ/RFP
Design
Const.
2019 2020 2021 2022 2023 2024 2025 2026
Questions and Answers