120
Indra Airports STUDY OF CAPACITY SESAR CH Annexes Author: MERITXELL VIÑAS T Tutor: Rubén Martínez Sevi Barcelona / 22 nd January 201 AIRPORT Y VS. EFFICIENCY HALLENGES TIÓ illano 10 Y

Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

Indra Airports

STUDY OF AIRPORT

CAPACITY VS

SESAR CHALLENGESAnnexes

Author: MERITXELL VIÑAS TIÓ

Tutor: Rubén Martínez Sevillano

Barcelona / 22nd January 2010

STUDY OF AIRPORT

CAPACITY VS. EFFICIENCY

SESAR CHALLENGES

Author: MERITXELL VIÑAS TIÓ

Tutor: Rubén Martínez Sevillano

January 2010

EFFICIENCY

Page 2: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

1

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

ANNEX INDEX

1 ACRONYMS ............................................................................................................................... 8

2 NOMENCLATURE (EQUATIONS) ............................................................................................... 11

3 DEFINITIONS ............................................................................................................................ 14

3.1 AIRSIDE AIRPORT COMPONENTS .................................................................................................... 15

3.1.1 Clear zone ......................................................................................................................... 15

3.1.2 Movement area ................................................................................................................ 15

3.1.3 Runway ............................................................................................................................. 15

3.1.4 Taxiway ............................................................................................................................. 15

3.2 LANDSIDE AIRPORT COMPONENTS ................................................................................................. 15

3.2.1 Apron ................................................................................................................................ 16

3.2.2 Baggage services .............................................................................................................. 16

3.2.3 Check-in ............................................................................................................................ 16

3.2.4 Functional component ...................................................................................................... 16

3.2.5 Gate .................................................................................................................................. 17

3.2.5.1 Gate type ................................................................................................................................ 17

3.2.5.2 Gate mix ................................................................................................................................. 17

3.2.5.3 Gate occupancy time .............................................................................................................. 17

3.2.6 Ground access ................................................................................................................... 17

3.2.7 Hardstand ......................................................................................................................... 17

3.2.8 Hold room ......................................................................................................................... 17

3.2.9 Passenger circulation area................................................................................................ 18

3.2.10 Ramp ............................................................................................................................ 18

3.2.11 Stand ............................................................................................................................ 18

3.2.12 Terminal ....................................................................................................................... 18

3.2.13 Terminal curb ............................................................................................................... 19

3.2.14 Wait areas .................................................................................................................... 19

3.3 CAPACITY TERMS ........................................................................................................................ 20

3.3.1 Aircraft mix ....................................................................................................................... 20

3.3.2 Annual service volume (ASV) ............................................................................................ 20

3.3.3 Capacity (airside) .............................................................................................................. 20

3.3.4 Capacity (landside) ........................................................................................................... 20

3.3.5 Crowding ........................................................................................................................... 20

3.3.6 Delay ................................................................................................................................. 20

3.3.7 Demand ............................................................................................................................ 21

3.3.8 Declared capacity ............................................................................................................. 21

3.3.9 Dynamic capacity .............................................................................................................. 21

3.3.10 Gate occupancy ratio ................................................................................................... 21

3.3.11 Level of service ............................................................................................................. 21

Page 3: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

2

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.3.12 Maximum capacity or Maximum throughput .............................................................. 21

3.3.13 Mix index ...................................................................................................................... 22

3.3.14 Peak load factor ........................................................................................................... 22

3.3.15 Peak period ................................................................................................................... 22

3.3.16 Percent arrivals............................................................................................................. 22

3.3.17 Percent touch and go’s ................................................................................................. 22

3.3.18 Runway-use configuration ........................................................................................... 23

3.3.19 Saturated time periods ................................................................................................. 23

3.3.20 Static capacity .............................................................................................................. 23

3.3.21 Sustained Capacity ....................................................................................................... 23

3.3.22 Runway capacity .......................................................................................................... 23

3.4 PARALLEL RUNWAY OPERATION MODES .......................................................................................... 23

3.4.1 Minimum distance between parallel runways .................................................................. 24

3.4.2 Departing aircraft ............................................................................................................. 24

3.4.2.1 Mixed mode ........................................................................................................................... 24

3.4.2.2 Parallel independent mode .................................................................................................... 24

3.4.3 Arriving aircraft ................................................................................................................ 25

3.4.3.1 Segregated mode ................................................................................................................... 25

3.4.3.2 Parallel dependent mode ....................................................................................................... 25

3.4.3.3 Parallel independent mode .................................................................................................... 25

3.5 OTHER ..................................................................................................................................... 26

3.5.1 Instrument flight rules ...................................................................................................... 26

3.5.2 Long haul .......................................................................................................................... 26

3.5.3 Narrow body ..................................................................................................................... 26

3.5.4 Poor visibility and ceiling (PVC) ......................................................................................... 26

3.5.5 Range ................................................................................................................................ 26

3.5.6 Short haul ......................................................................................................................... 26

3.5.7 Visual flight rules .............................................................................................................. 27

3.5.8 Wide body ......................................................................................................................... 27

4 AIRSIDE CAPACITY ASSESSMENT METHODS ............................................................................ 28

4.1 CAPACITY ASSUMPTIONS (FOR FAA METHOD) ................................................................................. 28

4.1.1.1 Runway configuration ............................................................................................................ 28

4.1.1.2 Percent arrivals ...................................................................................................................... 33

4.1.1.3 Percent touch and go’s ........................................................................................................... 33

4.1.1.4 Taxiways ................................................................................................................................. 33

4.1.1.5 Airspace limitations ................................................................................................................ 33

4.1.1.6 Runway instrumentation ........................................................................................................ 33

4.1.1.7 Annual service volume assumptions ...................................................................................... 33

4.2 APRON CAPACITY ....................................................................................................................... 34

4.2.1 Parsons apron area capacity estimate ............................................................................. 34

4.2.2 Aggregate apron utilization efficiency .............................................................................. 34

4.2.3 Apron and stands .............................................................................................................. 34

4.3 RUNWAY CAPACITY..................................................................................................................... 36

4.3.1 FAA method ...................................................................................................................... 36

Page 4: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

3

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.3.2 Methodology from Ministerio de Obras Públicas, Transporte y Medio Ambiente ........... 42

4.3.2.1 Minimum separation between aircraft .................................................................................. 42

4.3.2.2 Runway capacity assessment ................................................................................................. 43

4.4 TAXIWAY CAPACITY [FAA METHOD] .............................................................................................. 43

4.5 GATE CAPACITY.......................................................................................................................... 46

4.5.1 Gate capacity using FAA method ...................................................................................... 46

4.5.2 Gate capacity direct calculation ....................................................................................... 47

4.5.3 Gate capacity using Parsons gate-enplanement curve..................................................... 48

4.5.4 Average-to-peak utilization correction ............................................................................. 49

4.5.5 Gate capacity graphic analysis ......................................................................................... 49

4.5.6 Ramp chart hourly utilization analysis .............................................................................. 49

4.5.7 Movement area capacity [Separation analysis method] .................................................. 50

4.5.8 Description of the method ................................................................................................ 50

4.6 AIRSIDE CAPACITY AND ANNUAL SERVICE VOLUME [FAA METHOD] ..................................................... 52

4.6.1 Airside hourly capacity (short term) ................................................................................. 52

4.6.2 Annual service volume (short term) .................................................................................. 53

4.6.3 Airside capacity and annual service volume (long term; general) .................................... 54

4.7 DELAY ...................................................................................................................................... 55

4.7.1 Hourly delay to aircraft on the runway component.......................................................... 55

4.7.2 Daily delay to aircraft on the runway component when the d/c ratio is 1.0 or less for each

hour 56

4.7.3 Daily delay to aircraft on the runway component when the d/c ratio is greater than 1.0

for one or more hours .................................................................................................................... 57

4.7.4 Hourly demand corresponding to a specified level of average hourly delay .................... 58

4.7.5 Aircraft delay (annual) ...................................................................................................... 58

4.7.6 Annual delay to aircraft on the runway component ......................................................... 59

5 LANDSIDE CAPACITY ASSESSMENT METHODS ......................................................................... 61

5.1 GROUND ACCESS CAPACITY .......................................................................................................... 61

5.1.1 Estimation method ........................................................................................................... 61

5.1.2 Access capacity-to-demand index..................................................................................... 62

5.2 PASSENGER TERMINAL CAPACITY ................................................................................................... 62

5.2.1 Arrival hall capacity .......................................................................................................... 62

5.2.2 Baggage area capacity ..................................................................................................... 63

5.2.2.1 Baggage area space required ................................................................................................. 63

5.2.2.2 Number of baggage claim units.............................................................................................. 63

5.2.3 Security check ................................................................................................................... 64

5.2.4 Check-in area capacity ...................................................................................................... 65

5.2.4.1 Check-in queue ....................................................................................................................... 65

5.2.4.2 Number of check-in counters ................................................................................................. 65

5.2.5 Connecting passenger transfer ......................................................................................... 68

5.2.6 Customs and immigration ................................................................................................ 69

5.2.7 Gate hold room capacity .................................................................................................. 69

5.2.8 Passport control capacity ................................................................................................. 69

5.2.8.1 Estimation method ................................................................................................................. 69

Page 5: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

4

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

5.2.8.2 Passport control arrivals capacity .......................................................................................... 70

5.2.8.3 Passport control departures capacity .................................................................................... 72

5.2.9 Parking capacity (vehicles) ............................................................................................... 73

5.2.9.1 Parking requirement planning curve ...................................................................................... 73

5.2.10 Terminal curb capacity ................................................................................................. 73

5.2.11 Waiting areas capacity ................................................................................................. 73

5.2.12 Terminal circulation capacity ....................................................................................... 74

5.3 LANDSIDE SYSTEM AS A WHOLE ..................................................................................................... 74

6 AIRPORT SURVEY AND DESCRIPTION ....................................................................................... 76

6.1 BARCELONA–EL PRAT AIRPORT ..................................................................................................... 76

6.1.1 Runways............................................................................................................................ 78

6.1.2 T1 Terminal building ......................................................................................................... 79

6.1.3 T2 Terminal building ......................................................................................................... 84

6.1.4 Corporate Aviation Terminal building ............................................................................... 88

6.1.5 Accesses ............................................................................................................................ 90

6.1.5.1 Car / Bus / Taxi ....................................................................................................................... 90

6.1.5.2 Train ....................................................................................................................................... 91

6.1.6 Airport numbers ................................................................................................................ 91

6.2 GIRONA–COSTA BRAVA AIRPORT .................................................................................................. 92

6.2.1 Runways............................................................................................................................ 94

6.2.2 Terminal building .............................................................................................................. 95

6.2.3 Accesses ............................................................................................................................ 97

6.2.4 Airport numbers ................................................................................................................ 97

6.3 LLEIDA–ALGUAIRE AIRPORT ......................................................................................................... 98

6.3.1 Runways.......................................................................................................................... 100

6.3.2 Terminal building ............................................................................................................ 100

6.3.3 Accesses .......................................................................................................................... 103

6.3.4 Airport numbers .............................................................................................................. 103

7 RUNWAY CAPACITY ASSESSMENT (INDEPENDENT) ............................................................... 104

8 AIRCRAFT APPEARING IN THIS REPORT ................................................................................. 107

8.1 A-300 ................................................................................................................................... 107

8.2 B-727 ................................................................................................................................... 108

8.3 B-747 ................................................................................................................................... 109

8.4 B-767 ................................................................................................................................... 110

8.5 DC-9..................................................................................................................................... 111

8.6 DC-10 .................................................................................................................................. 112

8.7 GULFSTREAM II ....................................................................................................................... 113

8.8 L-1011 ................................................................................................................................. 114

9 REFERENCES .......................................................................................................................... 115

9.1 BIBLIOGRAPHY ......................................................................................................................... 115

9.2 WEB ..................................................................................................................................... 117

9.3 SOFTWARE ............................................................................................................................. 118

Page 6: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

5

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

FIGURE INDEX

FIGURE 3.1. THE AIRFIELD AND ITS COMPONENTS .............................................................................................. 14

FIGURE 3.2. AIRPORT LANDSIDE TERMINAL CONFIGURATIONS .............................................................................. 19

FIGURE 4.1. CAPACITY AND ASV FOR LONG RANGE PLANNING (A) ........................................................................ 29

FIGURE 4.2. CAPACITY AND ASV FOR LONG RANGE PLANNING (B) ........................................................................ 30

FIGURE 4.3. CAPACITY AND ASV FOR LONG RANGE PLANNING (C) ........................................................................ 31

FIGURE 4.4. CAPACITY AND ASV FOR LONG RANGE PLANNING (D) ........................................................................ 32

FIGURE 4.5. RUNWAY USE DIAGRAM (A) .......................................................................................................... 37

FIGURE 4.6. RUNWAY USE DIAGRAM (A) .......................................................................................................... 38

FIGURE 4.7. RUNWAY USE DIAGRAM (B) .......................................................................................................... 39

FIGURE 4.8. RUNWAY USE DIAGRAM (C) .......................................................................................................... 39

FIGURE 4.9. RUNWAY USE DIAGRAM (D) ......................................................................................................... 39

FIGURE 4.10. RUNWAY USE DIAGRAM (E) ........................................................................................................ 40

FIGURE 4.11. RUNWAY USE DIAGRAM (F) ........................................................................................................ 41

FIGURE 4.12. TIME SEPARATION BETWEEN AIRCRAFT WHEN LANDING AND TAKING-OFF ............................................ 42

FIGURE 4.13. HOURLY CAPACITY OF A TAXIWAY CROSSING AN ACTIVE RUNWAY W/ ARRIVALS ..................................... 44

FIGURE 4.14. HOURLY CAPACITY OF A TAXIWAY CROSSING AN ACTIVE RUNWAY W/O ARRIVALS................................... 45

FIGURE 4.15. HOURLY CAPACITY OF GATES ...................................................................................................... 46

FIGURE 4.16. CAPACITY ASPECTS OF TERMINAL CONCEPTS .................................................................................. 48

FIGURE 4.17. AVERAGE AIRCRAFT DELAY IN AN HOUR ......................................................................................... 56

FIGURE 4.18. AVERAGE AIRCRAFT DELAY DURING SATURATED CONDITIONS ............................................................ 57

FIGURE 4.19. AVERAGE AIRCRAFT DELAY FOR LONG RANGE PLANNING ................................................................... 59

FIGURE 5.1. INTERMEDIATE RESULTS CHART 1................................................................................................... 67

FIGURE 5.2. INTERMEDIATE RESULTS CHART 2................................................................................................... 67

FIGURE 5.3. INTERMEDIATE RESULTS CHART 1................................................................................................... 71

FIGURE 5.4. INTERMEDIATE RESULTS CHART 2................................................................................................... 71

FIGURE 5.5. ESTIMATED REQUIREMENTS FOR PUBLIC PARKING AT US AIRPORTS ...................................................... 73

FIGURE 6.1. LOCATION AND AREAS OF INFLUENCE OF AIRPORTS OPERATING IN CATALUNYA [B1] ................................ 76

FIGURE 6.2. BARCELONA–EL PRAT AIRPORT [W13] .......................................................................................... 76

FIGURE 6.3. BARCELONA–EL PRAT AIRPORT [W8] ............................................................................................ 77

FIGURE 6.4. BARCELONA–EL PRAT NEW CONTROL TOWER [W8] ........................................................................ 78

FIGURE 6.5. BARCELONA–EL PRAT AIRPORT T1 TERMINAL [W15] ....................................................................... 79

FIGURE 6.6. BARCELONA-EL PRAT AIRPORT FUTURE VIEW [W7] .......................................................................... 80

FIGURE 6.7. BARCELONA-EL PRAT AIRPORT FUTURE SATELLITE. ARTIST’S IMPRESSION .............................................. 80

FIGURE 6.8. BARCELONA–EL PRAT T1 FLOOR PLAN [W8] ................................................................................... 81

FIGURE 6.9. CHECK-IN FIGURE 6.10. SKY CENTRE .................................................................................. 82

FIGURE 6.11. INTERMODAL HALL FIGURE 6.12. BAGGAGE CLAIM ................................................................ 82

FIGURE 6.13. DEPARTURES FIGURE 6.14. LA PLAÇA .............................................................................. 82

FIGURE 6.15. ARRIVALS ............................................................................................................................... 82

FIGURE 6.16. BARCELONA–EL PRAT T1 BOARDING / DEBOARDING AREAS [W8] ..................................................... 83

FIGURE 6.17. BARCELONA–EL PRAT T1 TERMINAL 3RD

FLOOR PLAN ...................................................................... 83

FIGURE 6.18. BARCELONA–EL PRAT T2 TERMINAL BREAKDOWN [W7] ................................................................. 84

FIGURE 6.19. BARCELONA–EL PRAT T2 TERMINAL PLAN [W8] ........................................................................... 84

Page 7: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

6

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

FIGURE 6.20. BARCELONA–EL PRAT T2A TERMINAL PLAN [W8] ........................................................................ 85

FIGURE 6.21. BARCELONA–EL PRAT T2B TERMINAL PLAN [W8] ......................................................................... 85

FIGURE 6.22. BARCELONA–EL PRAT T2C TERMINAL PLAN [W8] ......................................................................... 86

FIGURE 6.23. BARCELONA–EL PRAT AIRPORT T2 TERMINAL [W8] ....................................................................... 87

FIGURE 6.24. BARCELONA–EL PRAT AIRPORT T2A TERMINAL [W8]..................................................................... 87

FIGURE 6.25. BARCELONA–EL PRAT AIRPORT T2B TERMINAL [W8] ..................................................................... 87

FIGURE 6.26. BARCELONA–EL PRAT AIRPORT T2C TERMINAL [W8] ..................................................................... 88

FIGURE 6.27. BARCELONA–EL PRAT CORPORATE AVIATION TERMINAL PLAN [W8] .................................................. 88

FIGURE 6.28. BARCELONA–EL PRAT AIRPORT CORPORATIVE AVIATION TERMINAL [W8] .......................................... 89

FIGURE 6.29. T2 PARKING AREAS [W8] .......................................................................................................... 90

FIGURE 6.30. GIRONA–COSTA BRAVA AIRPORT [W6] ....................................................................................... 92

FIGURE 6.31. GIRONA–COSTA BRAVA AIRPORT [W6] ....................................................................................... 92

FIGURE 6.32. GIRONA–COSTA BRAVA AIRPORT MAIN DESTINATIONS [W8] ........................................................... 93

FIGURE 6.33. GIRONA–COSTA BRAVA CONTROL TOWER [W8] ........................................................................... 94

FIGURE 6.34. GIRONA–COSTA BRAVA AIRFIELD [W8] ....................................................................................... 94

FIGURE 6.35. GIRONA–COSTA BRAVA AIRPORT TERMINAL [W8] ......................................................................... 95

FIGURE 6.36. GIRONA–COSTA BRAVA AIRPORT 0TH

FLOOR TERMINAL PLAN [W8] ................................................... 96

FIGURE 6.37. GIRONA–COSTA BRAVA AIRPORT 1ST

FLOOR TERMINAL PLAN [W8].................................................... 96

FIGURE 6.38. LLEIDA–ALGUAIRE AIRPORT [W14] ............................................................................................. 98

FIGURE 6.39. LLEIDA–ALGUAIRE AIRPORT [W11] ............................................................................................. 98

FIGURE 6.40. LLEIDA–ALGUAIRE CONTROL TOWER [W11] ................................................................................ 99

FIGURE 6.41. LLEIDA–ALGUAIRE AIRPORT TERMINAL OUTSIDE VIEW (VIRTUAL RECREATION) [W11] ......................... 100

FIGURE 6.42. LLEIDA–ALGUAIRE AIRPORT TERMINAL INSIDE VIEW (VIRTUAL RECREATION) [W12] ............................ 101

FIGURE 6.43. LLEIDA–ALGUAIRE AIRPORT TERMINAL BUILDING 1ST

FLOOR TERMINAL PLAN [B16] ............................. 102

FIGURE 6.44. LLEIDA–ALGUAIRE AIRPORT TERMINAL BUILDING 2ND

FLOOR TERMINAL PLAN [B16] ............................ 102

FIGURE 6.45. LLEIDA–ALGUAIRE AIRPORT ACCESSES [W14] ............................................................................. 103

FIGURE 8.1. AIRBUS A-300 ........................................................................................................................ 107

FIGURE 8.2. AIRBUS A-300 ........................................................................................................................ 108

FIGURE 8.3. AIRBUS A-300 ........................................................................................................................ 109

FIGURE 8.4. B767 .................................................................................................................................... 110

FIGURE 8.5. DC-9-30 ............................................................................................................................... 111

FIGURE 8.6. DC-10 ................................................................................................................................... 112

FIGURE 8.7. GULFSTREAM II ....................................................................................................................... 113

FIGURE 8.8. DELTA AIRLINES L-1011 ........................................................................................................... 114

Page 8: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

7

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

TABLE INDEX

TABLE 3.1. RANGE CLASSIFICATION ................................................................................................................. 26

TABLE 4.1. DEMAND RATIOS ......................................................................................................................... 33

TABLE 4.2. MINIMUM SEPARATION TIMES BETWEEN CONSECUTIVE TAKE-OFFS (TDD) ............................................... 42

TABLE 4.3. MINIMUM SEPARATION TIMES BETWEEN CONSECUTIVE LANDINGS (TAA) ................................................ 42

TABLE 4.4. ICAO AIRPORT DESIGN GROUP CLASSIFICATION ................................................................................. 51

TABLE 4.5. ATC APPROACH SPEED CLASSIFICATION ............................................................................................ 51

TABLE 4.6. MINIMUM SEPARATION MATRIX MODEL ........................................................................................... 52

TABLE 4.7. MINIMUM SEPARATION CAPACITY TABLE .......................................................................................... 52

TABLE 4.8. ASV WEIGHTING FACTORS ............................................................................................................. 53

TABLE 4.9. TYPICAL DEMAND RATIOS .............................................................................................................. 54

TABLE 5.1. TYPICAL SPACE STANDARDS USED IN PLANNING AND DESIGN ................................................................. 61

TABLE 5.2. LEVEL OF SERVICE FOR BAGGAGE CLAIM UNIT (RETRIEVAL AND PERIPHERAL AREA) ..................................... 63

TABLE 5.3. LEVEL OF SERVICE SPACE STANDARDS (M2/OCCUPANT) AT CHECK-IN FOR SINGLE QUEUE ............................ 65

TABLE 5.4. PEAK 30-MINUTE AT CHECK-IN AS A PERCENTAGE OF THE PEAK HOUR PERIOD .......................................... 66

TABLE 5.5. ADDITIONAL DEMAND GENERATED BY THE FLIGHTS DEPARTING BEFORE AND AFTER THE PEAK HOUR PERIOD ... 66

TABLE 5.6. LEVEL OF SERVICE A TO E IN HOLD ROOMS ........................................................................................ 69

TABLE 5.7. TYPICAL SPACE STANDARDS USED IN PLANNING AND DESIGN ................................................................. 69

TABLE 5.8. LEVEL OF SERVICE FOR A SINGLE (BANK) QUEUE AT PASSPORT CONTROL .................................................. 70

TABLE 5.9. SPACE AND SPEED FOR LEVEL OF SERVICE C ....................................................................................... 74

TABLE 5.10. SPEED FOR LEVEL OF SERVICE C ..................................................................................................... 74

TABLE 6.1. BARCELONA-EL PRAT AIRPORT RUNWAY DESCRIPTION ........................................................................ 78

TABLE 6.2. BARCELONA-EL PRAT AIRPORT T1 TERMINAL IN NUMBERS ................................................................... 81

TABLE 6.3. BARCELONA-EL PRAT AIRPORT T2 TERMINAL IN NUMBERS [W8] .......................................................... 86

TABLE 6.4. BARCELONA-EL PRAT AIRPORT CORPORATE AVIATION TERMINAL IN NUMBERS ......................................... 89

TABLE 6.5. TRAFFIC OF PASSENGERS IN BARCELONA-EL PRAT AIRPORT [W9] .......................................................... 91

TABLE 6.6. FREIGHT IN BARCELONA-EL PRAT AIRPORT [W9] ............................................................................... 91

TABLE 6.7. AIRCRAFT MOVEMENTS IN BARCELONA-EL PRAT AIRPORT [W9] ........................................................... 91

TABLE 6.8. GIRONA-COSTA BRAVA AIRPORT RUNWAY DESCRIPTION ...................................................................... 94

TABLE 6.9. GIRONA–COSTA BRAVA AIRPORT TERMINAL IN NUMBERS .................................................................... 96

TABLE 6.10. TRAFFIC OF PASSENGERS IN GIRONA-COSTA BRAVA AIRPORT [W9] ..................................................... 97

TABLE 6.11. FREIGHT IN GIRONA-COSTA BRAVA AIRPORT [W9] .......................................................................... 97

TABLE 6.12. AIRCRAFT MOVEMENTS IN GIRONA-COSTA BRAVA AIRPORT [W9] ...................................................... 97

TABLE 6.13. LLEIDA–ALGUAIRE AIRPORT RUNWAY DESCRIPTION ........................................................................ 100

TABLE 6.14. LLEIDA-ALGUAIRE AIRPORT TERMINAL IN NUMBERS [B16] ............................................................... 101

TABLE 8.1. A-300-600R SPECIFICATIONS [W3] ............................................................................................. 107

TABLE 8.2. B727-200 SPECIFICATIONS [W3] ................................................................................................ 108

TABLE 8.3. B747-400 SPECIFICATIONS [W3] ................................................................................................ 109

TABLE 8.4. B767-300 SPECIFICATIONS [W3] ................................................................................................ 110

TABLE 8.5. DC-9-30 SPECIFICATIONS [W3] ................................................................................................... 111

TABLE 8.6. DC-10-30 SPECIFICATIONS [W3] ................................................................................................. 112

TABLE 8.7. GULFSTREAM II SPECIFICATIONS [W3] ........................................................................................... 113

TABLE 8.8. L-1011-200 SPECIFICATIONS [W3] ............................................................................................. 114

Page 9: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

8

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

1 ACRONYMS

ABAS Aircraft Based Augmentation System

A-CDA Advanced Continuous Descent Approach

ACL ATM Capability Levels

ADS-B/-C Automatic Dependent Surveillance -Broadcast / -Contract

AENA Aeropuertos Españoles y Navegación Aérea

AIS Aeronautical Information Service

AMAN Arrival Manager

AMHS ATS Message Handling System

ANSP Air Navigation Service Provider

AO Airport Operators

AOC Airline Operational Control / Airlines Operations Centre

ASAS Airborne Separation Assistance Systems

ASL ATM Service Levels

ASPA Airborne Spacing

ATC Air Traffic Control

ATFCM Air Traffic Flow and Capacity Management

ATFM Air Traffic Flow Management

ATM Air Traffic Management

ATS Air Traffic Service

ATSA Airborne Traffic Situation Awareness

BIC Best In Class

BTV Brake to Vacate

CDA Continuous Descent Approach

CDM Collaborative Decision Making

CNS Communications, Navigation and Surveillance

ConOps Concept of Operations

DMAN Departure Management

DOD Detailed Operational Description

DTG Distance To Go

FAA Federal Aviation Agency

FCM Flow and Capacity Management

FDP Flight Data Processing

FMS Flight Management System

FUA Flexible Use of Airspace

Page 10: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

9

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

GBAS Ground Based Augmentation System

GNSS Global Navigation Satellite System

HUD Head up Display

IATA International Air Transport Association

ICAO International Civil Aviation Organization

IFR Instrumental Flight Rules

ILS Instrumental Landing System

IMC Instrumental Meteorological Conditions

IOC Initial Operational Capability

IP Implementation Packages

KPA Key Performance Area

KPI Key Performance Indicators

LoC Line of Changes

LVC Low Visibility Conditions

MLS Microwave Landing System

NOP Network Operation Plan

OAT Operational Air Traffic

OI Operational Improvements

P2P Peer-to-peer

PENS Pan European Network Service

P-RNAV Precision Area Navigation

PSR Primary Surveillance Radar

PTC Precision Trajectory Clearances

QoS Quality of Service

R&D Research & Development

RBT Reference Business/Mission Trajectory

RET Rapid Exit Taxiways

RNP Required Navigation Performance

ROT Runway Occupancy Time

RWY Runway

SBT Shared Business Trajectory

Page 11: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

10

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

SES Single European Sky

SESAR Single European Sky ATM Research

SJU SESAR Joint Undertaking

SMAN Surface Manager

SSR Secondary Surveillance Radar

STAR Standard Terminal Arrival Routes

SVS Synthetic Vision System

SWIM System Wide Information Management

TGT Target Operational Concept

TMA Terminal Control Area

TTA Target Time of Arrival

UDPP User Driven Prioritisation Process

VDL VHF Data-Link

VNAV Vertical Navigation

VSA Visual Separation on Approach

WAM Wide Area Multi-lateration

WBS Work Breakdown Structure

WP Work Programme

Page 12: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

11

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

2 NOMENCLATURE (EQUATIONS)

A Number of arriving aircraft in an hour

ADF Arrival delay factor

ADI Arrival delay index

AOP Average occupancy time per passenger

AOV Average occupancy time per visitor

C Capacity for runway-use configuration

Number of class C aircrafts

Cw Weighted hourly capacity of the runway component

C* Hourly capacity base

CDN Average claim device occupancy time per narrow-body aircraft

CDW Average claim device occupancy time per wide-body aircraft

CI Number of check-in servers including business class counters assuming

common use

CIY Number of economy class check-in servers assuming common use

CIJ Number of business class check-in servers

D Ratio of annual demand to average daily demand during the peak month

Number of class D aircrafts

d Minimum separation between two different classes of aircraft

DA Number of departing aircraft in an hour

DAHA Average delay for arriving aircraft

DAHD Average delay for departing aircraft

DASA Average delay per arrival

DASD Average delay per departure

DDF Departure delay factor

DDI Departure delay index

DPF Demand profile factor

DTH Hourly delay

DTS Delay in the saturated period

D/C Ratio of hourly demand to hourly capacity

E Exit factor

F1 % of the PHP in the peak 30-minute

F2 additional demand generated by the flights departing before and after the

peak hour period

Page 13: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

12

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

H Ratio of average daily demand to average peak hour demand during the

peak month

HD Hourly demand

J Percentage of business class passengers

MI Mix Index

MQT Mean Queuing Time

NNB Number of passengers per narrow-body aircraft at 80% load factor

NWB Number of passengers per wide-body aircraft at 80% load factor

P Percent of time each runway-use configuration is in use

PA Percent arrivals

PAS Percent of arrivals

PCD Number of passport control desks

PHP Peak Hour Passengers

Pij Amount of times that a type j aircraft is preceded by another aircraft, type i

PTci Average processing time at check-in

PTpca Average processing time at passport control arrival

PTpcd Average processing time at passport control

PTsc Average processing time at security check

PNB Proportion of passengers arriving by narrow-body aircraft

PWB Proportion of passengers arriving by wide-body aircraft

Q Peak 15 minute demand

R Gate occupancy ratio

S Intermediate result

SC Number of security servers

SPP Space required per person

T Touch and go factor

Tad Time between landing and take-off Taa Minimum time separation between consecutive landings

Tda Time between take-off and landing

Tdd Minimum time separation between consecutive take-offs

Tij Time (in minutes) between two events (landing or take-off) in a ij series

T&G Number of touch and go's in an hour

VPP Number of visitors per passenger

Page 14: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

13

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

X Peak-30 minute at check-in

W ASV weighting factor

Page 15: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

14

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3 DEFINITIONS

Figure 3.1. The airfield and its components1

1 Extracted from [B19]

Page 16: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

15

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.1 Airside airport components

Airside refers to airport facilities associated with aircraft movement to transport

passengers and cargo, used primarily for landing and take-off, for example, runways,

taxiways, and ATC facilities. The airside may overlap the airspace at ends of

runways.

3.1.1 Clear zone

Area at ends of runways and other areas surrounding airport in which height and land

use limitations are imposed to ensure that no obstructions to safe aircraft operations

occur.

3.1.2 Movement area

The maneuvering area, maneuvering area, or movement area is the part of the

airport used by aircraft for landing and takeoff that does not include the airport ramp

(or apron). In the US, the rest of the airport is considered the non-movement area.

3.1.3 Runway

The term runway includes the landing surface, plus those portions of the approach

and departure paths used in common by all aircraft

3.1.4 Taxiway

A taxiway is a path on an airport connecting runways with ramps, hangars, terminals

and other facilities. They mostly have hard surface such as asphalt or concrete,

although smaller airports sometimes use gravel or grass.

Busy airports typically construct high-speed or rapid-exit taxiways in order to allow

aircraft to leave the runway at higher speeds. This allows the aircraft to vacate the

runway quicker, permitting another to land in a shorter space of time

The term taxiway includes the parallel taxiways, entrance-exit taxiways, and crossing

taxiways, recognizing that a capacity limiting condition may exist where an arriving or

departing stream of aircraft must cross an active runway.

3.2 Landside airport components

Landside refers to facilities and services associated with air passengers or cargo

movement between aircraft and trip origin or destination. The landside includes

aprons, gates, terminals, cargo storage areas, parking and ground access

Page 17: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

16

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.2.1 Apron

When a commercial service aircraft arrives at the airport, it maneuvers from the

runway system to the taxiway system and to the ramp area adjacent to the terminal

building.

This ramp or apron area contains the aircraft parking positions – the designated

locations where these aircraft unload and load passengers and baggage and are

serviced – and the gates through which passengers pass to board or leave the

aircraft.

Moreover, it includes the aircraft circulation area, because in being routed to its

assigned parking position and gate, the aircraft may encounter other taxiing aircraft

and ground traffic, may have to wait for its assigned gate to be vacated by another

departing flight, and in congested or geometrically constrained apron areas may have

to be towed into the parking position.

Apron is the interface between landside and airside of the airport, and depends on

the bibliography whether if it’s part of the airside ([B19]) or landside ([B38]), even if

physically speaking it is located on the airside of the airport.

3.2.2 Baggage services

Processing of passengers checked baggage. Included are destination tagging,

movement to baggage room, sorting, movement to and from aircraft, loading and

unloading, and delivery to baggage claim display device. Interline transfer, storage,

and delivery may be included

3.2.3 Check-in

Initial step in passenger processing, involving passenger contact with the airline

immediately before flight departure. It may include ticket inspection, issuance of

boarding pass and seat assignment, baggage checking, ticketing, and preliminary

inspection of immigration documents and may occur at ticket counter or gate area.

3.2.4 Functional component

Element of the landside such as a gate or ticket counter that provides specific service

to air passengers or cargo. Functional components unable to meet demand

characteristics and maintain adequate service levels may become limits to capacity.

Page 18: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

17

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.2.5 Gate

A gate is a terminal portal for passengers to enter and exit aircraft. The term is

commonly used to mean a loading bridge-equipped entry adjacent to a hold room,

but may include entry to a transporter or directly onto an apron. It sometimes

includes the hardstand. It can also be referred to the parking position used by a

single aircraft loading or unloading passengers, mail, cargo, etc.

3.2.5.1 Gate type

The gate type refers to the size of the gate.

• Type 1: is capable of accommodating all aircraft, including widebodies such

as the A-300, B-747, B-767, DC-10, L-1011

• Type 2: accommodates only non-wide-bodied aircraft

3.2.5.2 Gate mix

Gate mix is the percent of non-wide-bodied aircraft accommodated by the gate group

3.2.5.3 Gate occupancy time

Gate occupancy time is the length of time required to cycle an aircraft through the

gate.

3.2.6 Ground access

Highways, local streets, fixed guide way systems, and public and privately operated

transit services linking an airport to the area that it serves.

3.2.7 Hardstand

Aircraft apron parking position equipped with fixed facilities for ground handling (this

is, made relatively permanent by installation of ground power and sometimes fueling

facilities) but not directly linked to a terminal. It may be considered as a gate.

3.2.8 Hold room

Passenger waiting area adjacent to gate where international passengers and their

goods remain in a controlled environment pending processing by the CIS2, or until

their departure.

The term is also used to refer to other passenger waiting areas such as that for

immigration or baggage claim devices.

2 See Annex 1

Page 19: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

18

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.2.9 Passenger circulation area

Corridor, stairway, escalator, or moving walkway connecting processing components,

generally only in a terminal.

3.2.10 Ramp

Aircraft parking position often used to refer to gate parking positions. It can be

situated adjacently to the terminal building or remotely from the terminal building. On

the first case passengers are boarded / de-boarded through the gate component

whereas when remotely passengers may have to walk some distance on the ramp to

reach the terminal or may be carried by transporter vehicles.

Aircraft parking positions are designed to accommodate the particular dimensions of

specific types of aircraft and may thus be unavailable to other aircraft with

significantly different dimensions.

3.2.11 Stand

An aircraft stand is a designated area intended for parking an aircraft where

passengers can be loaded / unloaded with a bridge or by bus. The aircraft stand

system is effectively an interface between passenger and aircraft flow.

3.2.12 Terminal

Building with facilities for passenger processing and boarding of aircraft or groups of

such buildings (unit terminals, often used by a single airline) within a terminal area.

Terminals are often classified into four configurations by the system used for

horizontal movement of passengers: linear, pier, satellite and transporter.

Page 20: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

19

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 3.2. Airport landside terminal configuration s3

3.2.13 Terminal curb

Passenger interface between ground access and terminal. Passengers arrive or

depart in private automobiles, hotel and rental-car vans, limousines and buses, and

transit vehicles. The curb system may include direct rapid transit and rail system links

to the airport, although stations are typically located elsewhere and linked by bus or

pedestrian paths to terminal buildings.

3.2.14 Wait areas

Waiting areas are these parts of the airport where people are allowed to shop, eat

and relax before or after their journeys; this would include all the shops, restaurants,

bars, cafes, areas where circulation takes place after check-in, some of these areas

are opened to the general public not only the travelling passenger, so that a

passenger can speed some time with their love ones before proceeding on a trip.

3 Adapted from [B23]

Page 21: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

20

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.3 Capacity terms

Capacity (throughput capacity) is a measure of the maximum number of aircraft

operations which can be accommodated on the airport or airport component in an

hour. Since the capacity of an airport component is independent of the capacity of

other airport components, it can be calculated separately.

3.3.1 Aircraft mix

Aircraft mix is the relative percentage or operations conducted by each of the four

classes of aircraft (A, B, C, D).

3.3.2 Annual service volume (ASV)

ASV is an estimate of an airport’s annual capacity. It accounts for differences in

runway use, aircraft mix, weather conditions, etc., that would be encountered over a

year’s time. It corresponds to the number of annual operations which the aircraft

mean delay value it’s within one and four minutes.

3.3.3 Capacity (airside)

As defined by [B11], the maximum number of aircraft operations that can take place

in an hour. This is a maximum throughput rate.

3.3.4 Capacity (landside)

As defined by [B23], capability of the landside or its functional components to

accommodate passengers, cargo, ground transport vehicles, and aircraft. Service

volume is the principal indicator of landside capacity in this report.

3.3.5 Crowding

Density of people in airport waiting areas, or number of people per unit area. Those

accompanying departing passengers or greeting arrivals may be included as ell as

passengers themselves.

3.3.6 Delay

Delay is the difference between constrained and unconstrained operating time.

For the airside, it refers to the added time spent in accomplishing an aircraft

operation because of airport congestion, or the difference between time required

under constrained conditions caused by simultaneous demands on the facility and

time required under unconstrained conditions.

Page 22: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

21

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Landside delay is the added time required for a passenger to complete processing at

a functional component because of limits to capacity. Wait time and processing time

are included. Acceptable delay depends on type of service being delivered, demand

characteristics, and local conditions at an airport.

3.3.7 Demand

Demand is the magnitude of aircraft operations to be accommodated in a specified

time period.

3.3.8 Declared capacity

Site specific limiting capacities, in numeric terms, of individual facilities and

resources. These capacities are forwarded to the appropriate bodies to be used in

the preparation of flight schedules.

3.3.9 Dynamic capacity

Maximum processing or flow rate of persons (i.e. occupants) through a subsystem

per unit time. The actual time unit selected as the measurement index (minutes,

hours, etc.)

3.3.10 Gate occupancy ratio

When wide-bodied aircraft are served, the gate occupancy ratio is:

= Average gate occupancy time for widebodied aircraftAverage gate occupancy time for non-widebodied aircraft

R (4.1)

When wide-bodied aircraft are not served, R equals 1.00

3.3.11 Level of service

Defined by IATA, it defines the quality and conditions of service of a functional

component or group of components as experienced by passengers. Such factors as

delay, crowding, and availability of passenger amenities for comfort and convenience

measure service level.

3.3.12 Maximum capacity or Maximum throughput

Maximum rate (or traffic flow) at which passengers (or aircraft, ground transport

vehicles, pieces of baggage, tons of cargo, etc.) can be processed (or achieved) by a

functional component or group of components for a chosen time unit only, but not

Page 23: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

22

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

sustained for a longer period, in accordance with safety requirements and regardless

of delay or level of service.

In practice this rate is observed only when demand equals or exceeds a component’s

processing capability, and is typically sustained only for brief periods, because

excess demand usually produces significant delays and crowding.

3.3.13 Mix index

Mix index is a mathematical expression. It is the percent of class C aircraft plus 3

times the percent of Class D aircraft

= +%( 3 )MI C D (4.2)

3.3.14 Peak load factor

The ratio of demand during the peak period (for example, a peak hour) to average

demand during a reference period (for example, the daily average hour). Generally

expressed as a number or percentage.

3.3.15 Peak period

Time period, which may be one hour, several hours, or one day, representative of

busy conditions within a functional component. It is typically defined from historical

records by frequency of occurrence.

3.3.16 Percent arrivals

The percent of arrivals is the ratio of arrivals to total operations:

+

=+ +

12 &

·100&

A T GPA

A DA T G (4.3)

where

A is the number of arriving aircraft in the hour

DA is the number of departing aircraft in the hour

T&G is the number of touch and go's in the hour

3.3.17 Percent touch and go’s

The percent of arrivals is the ratio of landings with an immediate takeoff to total

operations, and is captured as follows:

=+ +

&·100

&T G

PAA DA T G (4.4)

Page 24: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

23

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Touch and go operations are normally associated with flight training. The number of

these operations usually decreases as the number of air carrier operations increase,

as demand for service approaches runway capacity, or as weather conditions

deteriorate.

3.3.18 Runway-use configuration

Runway-use configuration is the number, location, and orientation of the active

runway(s), the type and direction of operations, and the flight rules in effect at a

particular time.

3.3.19 Saturated time periods

A saturated period consist of the consecutive hours when demand exceeds capacity

(termed the overload phase) plus the subsequent hour(s) required to accommodate

the residual demand (termed the recovery phase).

3.3.20 Static capacity

Storage potential of a facility or area, and is usually expressed as the number of

occupants that a given area will accommodate at any one moment. It is a function of

the total useable space available and the level of service to be provided; i.e. the

amount of space each occupant may occupy. Static capacity standards are stated as

square meters per occupant (m2/occ.) for each level of service.

3.3.21 Sustained Capacity

Sustained capacity is the overall capacity of a subsystem to accommodate traffic

demand, over a sustained period within the space and time standards of a particular

level of service. IATA recommends using level of service C to determine the

sustainable capacity.

3.3.22 Runway capacity

Runway capacity is defined as the hourly rate of aircraft operations (departures,

arrivals or both), to be accommodated by a runway of combination of runways, under

specified local conditions.

3.4 Parallel runway operation modes

All information attached here is described in deeper detail in ICAO’s doc 444 and

Annex 14 volume 1.

Page 25: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

24

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.4.1 Minimum distance between parallel runways

Where parallel non-instrument runways are intended for simultaneous use, the

minimum distance between their centre lines should be:

• 210 m where the higher code number is 3 or 4;

• 150 m where the higher code number is 2; and

• 120 m where the higher code number is 1.

Where parallel instrument runways are intended for simultaneous use the minimum

distance between their centre lines should be:

• 1035 m for independent parallel approaches;

• 915 m for dependent parallel approaches;

• 760 m for independent parallel departures;

• 760 m for segregated parallel operations;

except that for segregated parallel operations the specified minimum distance:

1) may be decreased by 30m for each 150m that the arrival runway is

segregated toward the arriving aircraft, to a minimum of 300m; and

2) should be increased 30m for each 150m that the arrival runway is

staggered away from the arriving aircraft;

3.4.2 Departing aircraft

3.4.2.1 Mixed mode

In a two-parallel runway configuration, provided runways are at sufficient distance

apart, in mixed mode both runways can be operated fully independent of each other

allowing:

• one runway is used exclusively for departures while the other runway is used

for a mixture of arrivals and departures (semi-mixed operation); and

• both runways are used for mixed arrivals and departures (mixed operation) on

each

3.4.2.2 Parallel independent mode

In a two-parallel runway configuration, provided runways are at sufficient distance

apart, in parallel independent mode both runways are used exclusively for departures

(independent departures) and suitable surveillance radar capable of identification of

the aircraft within 2 km (1.0 NM) from the end of the runway is available.

Page 26: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

25

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.4.3 Arriving aircraft

3.4.3.1 Segregated mode

In a two-parallel runway configuration, provided runways are a sufficient distance

apart, in segregated mode one of the runways is used for take offs whilst the other is

used only for landings. These can be alternated.

ILS and/or MLS precision approach, surveillance radar approach (SRA) or precision

approach radar (PAR) approach and visual approach may be conducted in

segregated parallel operations provided suitable surveillance radar and the

appropriate ground facilities conform to the standard necessary for the specific type

of approach.

3.4.3.2 Parallel dependent mode

In a two-parallel runway configuration, provided runways are a sufficient distance

apart, in parallel dependent mode simultaneous landings are operated in IFR and/or

MLS conditions on both runways, when minimums of radar separation are prescribed

(minimum azimuth accuracy of 0.3 degrees (one sigma)) between aircraft situated on

the extensions of the axes of the adjacent runways.

3.4.3.3 Parallel independent mode

In a two-parallel runway configuration, provided runways are at sufficient distance

apart, in parallel independent mode simultaneous landings are operated in IFR

and/or MLS conditions on both runways, when:

• where runway centre lines are spaced by less than 1310 m but not less than

1035 m, suitable secondary surveillance radar (SSR) equipment, with a

minimum azimuth accuracy of 0.06 degrees (one sigma);

• where runway centre lines are spaced by less than 1525 m but not less than

1310 m, SSR equipment with performance specifications other than the

foregoing may be applied;

• where runway centre lines are spaced by 1525 m or more, suitable

surveillance radar with a minimum azimuth accuracy of 0.3 degrees (one

sigma) is available

Note: Precision Runway Monitor (PRM) is a high-speed, high-precision radar system

that can be used to allow simultaneous approaches on parallel runways that are

spaced less than 1525 m to each other.

Page 27: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

26

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.5 Other

3.5.1 Instrument flight rules

Instrument flight rule conditions occur whenever the reported cloud ceiling is at least

500 feet but less than 1,000 feet and/or visibility is at least one statute mile but less

than three statue miles.

3.5.2 Long haul

Flights longer than 1500 miles. Such flights normally require more preparatory

ground time before departure than short-haul flights ((those less than 500 mi long)

and are often flown by larger aircraft.

3.5.3 Narrow body

A narrow-body aircraft is an airliner with a fuselage aircraft cabin diameter typically of

3 to 4 meters, and airline seat arranged 2 to 6 abreast along a single aisle. Narrow-

body aircraft seating less than 100 passengers are commonly known as regional

airliners.

3.5.4 Poor visibility and ceiling (PVC)

Poor visibility and ceiling conditions exist whenever the cloud ceiling is less than 500

feet and/or the visibility is less than one statute mile.

3.5.5 Range

The maximal total range is the distance an aircraft can fly between take-off and

landing, as limited by fuel capacity in powered aircraft, or cross-country speed and

environmental conditions in unpowered aircraft.

Ferry range means the maximum range the aircraft can fly. This usually means

maximum fuel load, optionally with extra fuel tanks and minimum equipment. It refers

to transport of aircraft for use on remote location.

Short range Mid range Long range

< 1900 NM 1900 – 4000 NM > 4000 NM

Table 3.1. Range classification

3.5.6 Short haul

Flights less than 500 miles long. Aircraft on short-haul routes may be able to operate

with very short turnaround times compared with those on long haul routes.

Page 28: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

27

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

3.5.7 Visual flight rules

Visual flight rule conditions occur whenever the cloud ceiling is at least 1,000 feet

above ground level and the visibility is at least three statute miles.

3.5.8 Wide body

A wide-body aircraft is a high-passenger-capacity airliner such as the Airbus, Boeing

747, McDonell-Douglas DC-10, and Lockheed L-10114, and is usually configured

with multiple travel classes with a fuselage diameter of 5 to 6 meters and twin aisles.

Passengers are usually seated 7 to 10 abreast. Typical wide-body aircraft can

accommodate between 200 and 600 passengers, while the largest narrow-body

aircraft currently in widespread service (the Boeing 757-300) carries a maximum of

about 250. Physical dimensions of such aircraft, also termed jumbo jets, may be

incompatible with airport gate and apron areas designed for smaller narrowbody

aircraft.

4 See Annex 8

Page 29: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

28

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4 AIRSIDE CAPACITY ASSESSMENT METHODS

The material contained in [B10] report is primarily intended for airport planning. The

values of capacity and delay obtained from the report cannot and should not be

construed as precise values for a particular airport. Rather, the capacity and delay

values, the method itself and the figures are representative for US airports. The

applicability to other countries’ airports is questionable and the results obtained are,

in general, optimistic outside the US.

4.1 Capacity assumptions (for FAA method)

All the capacity assumptions listed below are those assumed in [B10].

4.1.1.1 Runway configuration

The most widely used method for the mathematical calculation of runway capacity is

the one detailed in [B10]. Marcos García Cruzado, in [B15], re-edited the text

appearing in the capacity and ASV for long range planning figures converting the

units into the international system. An abstract of those is attached in Figure 4.1,

Figure 4.2, Figure 4.3 and Figure 4.4:

Page 30: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

29

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.1. Capacity and ASV for long range plannin g (a)

Page 31: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

30

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.2. Capacity and ASV for long range plannin g (b)

Page 32: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

31

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.3. Capacity and ASV for long range plannin g (c)

Page 33: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

32

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.4. Capacity and ASV for long range plannin g (d)

Notes:

• Hourly VFR and IFR values are based on runway utilizations which produce

the highest sustainable capacity consistent with current ATC ties and

practises

• Configurations 9 to 19 show by means of arrows the predominant direction of

runway operations

• Runway-use configurations 14 through 19 indicate by dashed lines the limit of

the range of runway orientation.

Page 34: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

33

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.1.1.2 Percent arrivals

Arrivals equal departures5

4.1.1.3 Percent touch and go’s

The percent of touch and go’s is within the ranges specified in table 2.1 from [B10],

repeated here as Table 4.1:

Mix

index

Percent

arrivals

Percent

Touch &

Go

Demand ratios 6

Annual Demand

Av. Daily Demand

Av. Daily Demand

Av. Peak Hour Demand

0-20 50 0-50 290 9

21-20 50 0-40 300 10

51-80 50 0-20 310 11

81-120 50 0 320 12

121-180 50 0 350 14

Table 4.1. Demand ratios

4.1.1.4 Taxiways

A full-length parallel taxiway, ample runway entrance/exit taxiways and no taxiway

crossing problems are considered.

4.1.1.5 Airspace limitations

No space limitations which would adversely impact flight operations or restrict aircraft

from operating at the airport are considered. Missed approach protection is assured

for all converging operations in IFR weather conditions.

4.1.1.6 Runway instrumentation

The airport has at least one runway equipped with an ILS and has the necessary

ATC facilities and services to carry but operations in a radar environment.

4.1.1.7 Annual service volume assumptions

The ASV values in Figure 4.1, Figure 4.2, Figure 4.3 and Figure 4.4 are based on the

assumptions of section 4.1, Table 4.1 and the following:

• Weather conditions occur roughly 10 percent of the time

• Roughly 80 percent of the time the airport is operated with the runway-use

configuration which produces the greatest hourly capacity

5 See Annex 3 section 3.3.14 6 In the peak month

Page 35: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

34

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.2 Apron capacity

4.2.1 Parsons apron area capacity estimate

Extracted from [B38]. According to [B28] and [B13], the total space required for

parking an aircraft, projected at 1,41 acres/aircraft, ranges from 1.0 acre for a DC-9

to 3.7 acres for a B-747. This assumption considers also an inferred typical “all

aircraft parking envelope” at 232 ft x 260 ft. This approach uses straightforward

computation and yields seemingly valid results but may seldom be relevant to

capacity.

4.2.2 Aggregate apron utilization efficiency

Extracted from [B38]. In this procedure, a calculation is made of the plan area of a

circle with diameter equal to the length of wingspan of the aircraft, whichever is

greater. Then, calculate the average use efficiency parameter, equal to the ratio of

aircraft seat load to area of this circle, for the fleet currently operating at the airport.

This method may be a useful and quick test of impending space constraints.

4.2.3 Apron and stands

Extracted from [B38]. For apron, two types of capacity are considered: absolute and

user capacity.

Absolute capacity is the total number of stands available for each type of aircraft;

some of them admit more than one aircraft type.

User capacity, sometimes called "rotation capacity" is the number of aircraft that can

use a stand either per hours or per day, and is the really useful one for planning

purposes as the absolute capacity is not indicative.

If an airport is reported to have n parking positions or stands, nothing can be

deducted because it may happen that many of them are occupied permanently or for

long periods.

To perform this calculation is essential to know the average time of occupancy for

each aircraft class of aircraft and each type of stand.

• Manufacturer’s manuals usually include the times of operation and

stewardship of the aircraft, which tend to be optimistic;

• what is more practical, is to refer to airport statistics and complement them by

direct measurements. Data to be determined:

Page 36: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

35

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

o Aircraft class and operating airline. For the same aircraft, the time

required often varies from one to another company

o Flight type (initial, terminal, passenger stopover, technical stopover

and required services; refueling of fuel, food supply, cleaning, etc…) .

For flights with stopover, there can be significant differences in service

provision and stewardship as companies.

o Number of passengers boarding / de-boarding

o Load boarded / de-boarded

o Airport aids and efficiency in their use: bridges, buses, staircases,

containers, etc…

o Tank trucks or hydrants for fuel

o 400 Hz and compressed air supplies

o ect.

With these data the average time of occupancy can be calculated.

For the previous assessment should be noted that an aircraft in stopover flight is

equivalent to two operations and the mix of aircraft, as usual when not all positions

are interchangeable, therefore reduces the total capacity for class.

On large platforms, capacity must be estimated by areas because when considering

the apron as a whole it can lead to significant errors. The capacity C (and by

extension the number of stands required parking) is determined by the expression:

( )( ) ( ) , ( )f j N j T i j C j⋅ = ⋅ (5.1)

( )C C j=∑ (5.2)

Where

F (j) is the utilization factor (as a % of one hour) of j type stands by an i type of

aircraft

N (ji) is the number of type j stands that can be used by a type i aircraft

T (ij) is the occupation time required for a type j stand by a type i aircraft

C (j) is the capacity of type j stands

T(ij) times can be derived from the aircraft manufacturers’ manuals by multiplying

them by a 1.1 to 1.4 factor according to the constraints of the airport, the type of flight

and class of transit or by making direct measurements "in situ" on already existing

airports.

Page 37: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

36

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.3 Runway capacity

4.3.1 FAA method

Except for situations:

• involving PVC conditions

• absence of radar coverage or ILS

• airports with parallel runways when one runway is limited to use by small

aircraft

hourly capacity can be calculated as follows:

1. Select the runway-use configuration in Figure 4.5, Figure 4.7 and Figure 4.8

(extracted from [B10]) which best represents the use of the airport during the

hour of interest. To adjust for staggered thresholds, see [B10], chapter 4.

2. Select the Figure number for capacity

3. Determine the percentage of Class C and D aircraft operating on the runway

component and calculate the mix index7

4. Determine percent arrivals (PA)8

5. Determine hourly capacity base from graph (C*)

6. Determine the percentage of touch and go operations during VFR9 operations

and determine the touch and go factor (T).

7. Determine the location of exit taxiways (measured from the threshold at the

approach end of the runway) and determine the exit factor (E)

8. Calculate the hourly capacity of the runway component with:

= ⋅ ⋅*C C T E (5.3)

7 See ANNEX 3 section 3.3.13 8 See ANNEX 3 section 3.3.16 9 See ANNEX 3 section 3.3.17

Page 38: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

37

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.5. Runway use diagram (a)

Page 39: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

38

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.6. Runway use diagram (a)

Page 40: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

39

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.7. Runway use diagram (b)

Figure 4.8. Runway use diagram (c)

Figure 4.9. Runway use diagram (d)

Page 41: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

40

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.10. Runway use diagram (e)

Page 42: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

41

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.11. Runway use diagram (f)

Page 43: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

42

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.3.2 Methodology from Ministerio de Obras Públicas , Transporte y

Medio Ambiente

4.3.2.1 Minimum separation between aircraft

In landing or take off consecutive operations, separation constraints in time and

space (distance) are fixed. In section 9.2.5.1, minimums of spatial separation

prescribed due to wake turbulence effects were described Table 9.6. According to

the type of aircraft10, minimum time separation between aircrafts in consecutive take-

offs (Tdd) and consecutive landings (Taa) must be:

Preceding aircraft

Succeeding

aircraft

(seconds) Heavy Medium Small

Heavy 90 60 60

Medium 120 60 60

Small 120 60 60

Table 4.2. Minimum separation times between consecu tive take-offs (Tdd)

Preceding aircraft

Succeeding

aircraft

(seconds) Heavy Medium Small

Heavy 102 77 77

Medium 150 90 90

Small 210 144 108

Table 4.3. Minimum separation times between consecu tive landings (Taa)

Moreover,

• Time between landing and take-off is Tad=50sec (take-off begins once the

preceding landed aircraft has abandoned the runway)

• Time between take-off and landing is Tda=130sec

Figure 4.12. Time separation between aircraft when landing and taking-off

10 See ¡Error! No se encuentra el origen de la referencia.

Page 44: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

43

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.3.2.2 Runway capacity assessment

To carry on with this procedure, two parameters need to be defined:

• Pij is the amount of times that a type j aircraft (S,M,H) is preceded by another

aircraft, type i. For example, if an aircraft type (S) is preceded a 30% of times

by an aircraft type (M), Pij = 0,3.

• Tij is the time (in minutes) between two events (landing or take-off) in a ij

series. For example, the time between two consecutive take-offs of (H) type

aircraft is, according to Table 4.2 is Tpp = 1,5min.

From this two parameters, capacity (in operations/hour) of a runway is determined

as:

60

ij ijij

CPT

=∑

(5.4)

With Tij expressed in minutes.

Note:

The probability of a j aircraft to be preceded by an i aircraft does not depend on i, this

means that Pi and Pj are statistically independent, so:

Pij Pi x Pj= (5.5)

4.4 Taxiway capacity [FAA method]

Hourly capacity of a taxiway component crossing a runway can be calculated as:

1. Determine the distance from the runway end (start of takeoff roll) to the

taxiway crossing

2. Determine the runway operations rate, i.e, the demand being accommodated

on the runway being crossed (arrival, departure, and touch and go operations

per hour). The operations rate cannot exceed the hourly capacity of the

runway

3. Calculate the mix index11 of the runway being crossed

4. Determine the hourly capacity of the taxiway crossing by using the following

figures extracted from [B10]:

5. Use Figure 4.13 when the crossed runway accommodates arrivals or mixed

operations

6. Use Figure 4.14 when the crossed runway accommodates only departures

and touch and go’s

11 See ANNEX 3 section 3.3.13

Page 45: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

44

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.13. Hourly capacity of a taxiway crossing an active runway w/ arrivals

Page 46: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

45

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.14. Hourly capacity of a taxiway crossing an active runway w/o

arrivals

Page 47: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

46

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.5 Gate capacity

4.5.1 Gate capacity using FAA method

Hourly capacity of a gate group component can be calculated as follows:

Figure 4.15. Hourly capacity of gates12

12 Extracted from [B10]

Page 48: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

47

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

1. Determine the number of gate groups and the number of gates in each gate

group

2. Determine the gate mix, i.e. the percent of non-widebodied aircraft using each

gate group (programmed demand)

3. Determine the percentage of gates in each gate group that can accommodate

widebodied aircraft (available stands)

4. Determine for each gate group the average gate occupancy time for wide-

bodied and non widebodied aircraft

5. Calculate the gate occupancy ratio (R) using the formula above (see Figure

4.15)

6. Calculate the hourly capacity of each gate group by using Figure 4.15.

4.5.2 Gate capacity direct calculation

According to [B4], to assess gate needs, this procedure should be followed:

1. List and categorize the peak-day aircraft fleet mix by expected gate

occupancy time

2. Calculate the weighted average service time from Table 8.4 in the Report.

3. Calculate the single-gate-capacity index, in aircraft per minute per gate, as

the inverse of the weighted average service time

= ⋅

1weighted service time min

aircraftC

gate (5.6)

4. Overall capacity, in number of aircraft, is the product of this index and the

total number of gates at the terminal:

= × ×

( ) 60minops

Capacity C gatesh

(5.7)

5. For exclusive gate use, the previous step is repeated for each group of gates

under exclusive use. Total terminal capacity is then the sum of individual

group capacities

The use of this method implies 100 percent utilization and perfect schedule mesh. A

slightly longer average occupancy time would allow for uncertainties and schedule

mismatch. Although the calculation is simple and fast, the method yields indicative

results only and application is limited to assessments.

Page 49: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

48

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.5.3 Gate capacity using Parsons gate-enplanement curve

This method described in [B28] can be summarized in the following steps:

1. Plot annual enplanements versus estimated gate positions. If this information

is not available, a broad idea about the number of annual enplanements that

the airport might serve according the terminal geometry and configuration can

be obtained from Figure 4.16

Figure 4.16. Capacity aspects of terminal concepts

2. Invert the curve to read capacity for a given number of gates, and it can be

read that:

3. Above approximately 4 million annual enplanements � a linear relationship

describes the capacity

300,000 ( )

annual enplanementsCapacity gates

gate= × (5.8)

4. Below 4 million annual enplanements � approximately parabolic behavior of

the capacity

212,000 ( )Capacity annual emplanements gates= × (5.9)

5. Translation to peak-hour capacity would presumably be made with standard

peak-to-annual relationships, ideally specific to the airport in question.

The Parsons manual as a whole, although frequently criticized as very general and

probably out of date, is nevertheless widely used.

Page 50: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

49

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.5.4 Average-to-peak utilization correction

According to [B5], easy correction factors can be obtained by using data for specific

airports. Finding the average gate utilization measured in terms of time occupied on a

basis of 6-min intervals, it can be determined as a percentage of peak utilization.

Such a factor could be used in conjunction with other procedures that yield annual

enplanement capacities.

4.5.5 Gate capacity graphic analysis

According to [B11], the capacity of gates can be read graphically as follows:

1. Given an average gate occupancy time for non-widebody flights and percent

of non-widebodies in peak-hour flight schedule, hourly gate capacity

operations base is read from graph

2. Gate size factor is read from graph, based on percentage of widebody aircraft

in peak-hour flight and percentage of available gates able to handle

widebodies

3. Gate capacity, in operations per hour, is computed as

( ) ( ) ( )Capacity operations base size factor number of gates= × × (5.10)

In this method full gate utilization is assumed. It would be applied separately to each

group of exclusive-use gates. Relatively easy to use, technically adequate, and

officially sanctioned, this method may often be a good starting point for preliminary

assessment of gate utilization problems.

4.5.6 Ramp chart hourly utilization analysis

[B23] proposes the following procedure:

1. Create a ramp chart for the average day and peak month, showing scheduled

flights on arrival and departure times by assigned gate

2. Gate occupancy in each hour can be immediately read from the ramp chart,

or calculated as the number of aircraft on the ground in the previous hour less

the number of departures in the previous hour plus the number of arrivals in

the current hour divided by the number of gates

If occupancy is computed to be 100 percent during the governing time period, then

effective capacity has been reached for that time period. If capacity is to be

determined on an hourly basis only, this procedure may be unnecessary. Gate

capacity is simply 100 percent occupancy with the airport’s current fleet mix.

Page 51: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

50

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Under exclusive gate use, an airline might have flights scheduled such that there is a

gate available for a full (peak) hour, so that apparent occupancy would not be 100

percent, even though no other flights could be accommodated.

This method requires assumptions about turnaround times to compute slot

availability.

4.5.7 Movement area capacity [Separation analysis m ethod]

Extracted from [B15]. As it is already known, landings have preference upon take-

offs, so as, in a hypothetical extreme case, it could be considered that if landing

demand was continuous, no take-offs would occur.

Anyway, this doesn’t happen because the distance between landing aircraft is bigger

than the one between take-off and landing, and operations can, most part of the time,

be interspersed.

If runways operate in parallel segregated mode, a queuing theory could be applied

for each one of them, assuming that demand follows a Poisson distribution pattern. In

already existing airports, on-site measures could be taken, so the analysis is done

with real data.

4.5.8 Description of the method

This is an easy-doing assessment method, valid for any airport around the world.

Two different cases can arise: the preceding aircraft lands at a higher speed than the

subsequent aircraft, or the reverse.

Variables used in this method are:

• Aircraft landing speed, V1, V2, … Vi (in knots)

• Minimum separation between two different classes of aircraft (in sec)

• Longitude of the final approximation path between initial landing point and the

threshold L (in miles) considering the previous one on the runway threshold

• Minimum separation between aircraft D (in miles)

The method develops as follows:

• Gather aircrafts in different classes, depending on their landing speed.

• ICAO classifies the aircraft according to airports’ design:

Page 52: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

51

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Design group Wingspan (m) Gear width (m)

A < 15 < 4,5

B 15 to 24 4,5 to 6

C 24 to 36 6 to 9

D 36 to 52 9 to 14

E 52 to 65 9 to 14

Table 4.4. ICAO airport design group classification

If landing speed values are not available, the following values can be adopted:

Group Approach speed (knots) 13

A <91

B 91-120

C 212-140

D 141-165

E >166

Table 4.5. ATC approach speed classification

Calculate every class as a fraction of unity with respect to the total ip according to

the following table model:

Aircraft Approach speed ip

A VA (in numbers)

B VB (in numbers)

C VC (in numbers)

D VD (in numbers)

E VE (in numbers)

Calculate the minimum separation distance between two different classes of aircraft

jid according to:

12 2 2 1 / = ≥d D V if V V (6.1)

12 2 2 1 2 1 / ·(1/ 1/ ) = + − <d D V L V V if V V (6.2)

where D and L are values already known. The value of D will be obtained from Table

8.2 in the Report, considering small planes those of classes A and B, medium those

from class C and heavy those of class D.

13 1 knot = 1.85200 km/h

Page 53: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

52

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Complete the minimum separation matrix:

Precedent Aircraft Following Aircraft VA VB VC VD

Approach speed Group A B C D VA A VB B VC C VD D

Table 4.6. Minimum separation matrix model

Calculate the average distance d . The fraction of unity of each class is the

probability ( ip ) of the considered aircraft to belong to a certain class, so the weighted

average minimum distance is:

( )i ji jji

d p d p=∑ (6.3)

Finally, calculate the maximum hourly capacity (in ops/h) for each class:

1mC

d=

(6.4)

Group Capacity [ops/h]

A

B

C

D

E

Table 4.7. Minimum separation capacity table

As said before, this is a theoretical method that uses a simple approach; taking into

account different error sources, capacity can be reduced by a 20%, and in some

cases this will have to be considered.

4.6 Airside capacity and Annual Service Volume [FAA method]

4.6.1 Airside hourly capacity (short term)

Airport hourly capacity can be calculated as follows:

1. Calculate the hourly capacities of the runway, taxiway, and gate groups

components and determine the hourly demands on each

Page 54: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

53

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

2. Calculate the demand ratio for each component by dividing the component

demand by the runway component demand

3. Calculate the component quotients by dividing each component’s capacity by

its demand ratio

4. Identify the airport hourly capacity, i.e., the lowest quotient of those calculated

above

4.6.2 Annual service volume (short term)

ASV can be calculated as follows:

1. Calculate the weighted hourly capacity Cw for the runway component as

follows:

2. Identify the different runway-use configurations used over the course of a

year

3. Determine the percent of time each runway-use configuration is in use (P1

through Pn).

4. Include those times when the hourly capacity is zero, i.e., the weather

conditions are below airport minimums or the airport is closed for other

reasons.

5. If a runway-use configuration is used less than 2 % of the time, that time may

be credited to another runway-use configuration.

6. Calculate the hourly capacity for each runway-use configuration (C1 through

Cn)

7. Identify the runway-use configuration that provides the maximum capacity.

Generally, this configuration is also the configuration most frequently used.

8. Divide the hourly capacity of each runway-use configuration by the hourly

capacity of the runway-use configuration that provides the maximum capacity

9. Determine the ASV weighting factor (W) (W1 through Wn) for each runway-

use configuration from Table 4.8, adapted from Table 3-1 of [B10]]

Percent of

maximum

capacity

Weighting factors

VFR IFR

Mix index (0 -

20)

Mix index (21 -

50)

Mix index (51 -

180)

91+ 1 1 1 1

81-90 5 1 3 5

66-80 15 2 8 15

51-65 20 3 12 20

0-50 25 4 16 25

Table 4.8. ASV weighting factors

10. Calculate the weighted hourly capacity of the runway component Cw of the

runway component by the following equation:

Page 55: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

54

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

( )

( )

⋅ ⋅=

n

i i ii

w n

i ii

P C WC

P W (6.5)

11. Calculate the ratio of annual demand to average daily demand during the

peak month (D). If this information is not available, values from Table 4.9 can

be used

12. Calculate the ratio of average daily demand to average peak hour demand

during the peak month (H). If this information is not available, values from

Table 4.9 can be used

Mix index Daily index (D) Hourly index (H)

0 -20 280 – 310 7 – 11

21 – 50 300 – 320 10 – 13

51 - 180 310 – 350 11 – 15

Table 4.9. Typical demand ratios

13. Calculate ASV by using the following equation:

= ⋅ ⋅WASV C D H (6.6)

4.6.3 Airside capacity and annual service volume (l ong term; general)

In order to calculate a long term approximate airport capacity and the annual service

volume (let’s say, for one year), the following procedure should be applied:

1. Determine the percentage of aircraft classes C and D using, or expected to

use, the airport

2. Select the runway-use configuration from Figure 4.1, Figure 4.2, Figure 4.3

and Figure 4.4 that most represents the airport.

3. When no direction of runway operations is specified, the direction of operation

is not critical

4. For airports having three or more runway orientations (consider parallel

runways as one runway orientation), identify the two-runway orientation that is

operated most frequently

5. Calculate the mix index (see 3.3.1)

6. Read the approximate VFR and IFR hourly capacities and the ASV directly

from Figure 4.1, Figure 4.2, Figure 4.3 and Figure 4.4.

Page 56: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

55

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.7 Delay

4.7.1 Hourly delay to aircraft on the runway compon ent

Hourly delay calculations described in this paragraph apply to those hours when the

hourly demand does not exceed the hourly capacity of the runway component. For

those hours when the hourly demand exceeds the hourly capacity of the runway

component, section 4.7.3 applies.

Hourly delay can be calculated as follows:

1. Calculate the hourly capacity of the runway component for the specific hour of

interest

2. Identify from Figure 4.5, Figure 4.7 and Figure 4.8 the figure number for delay

3. Identify the hourly demand (HD) and the peak 15 minute demand (Q) on the

runway component

4. Calculate the ratio of hourly demand to hourly capacity (D/C)

5. Calculate the arrival delay index (ADI) and the departure delay index (DDI)

from the figure numbers for delay in (3.)

6. Calculate the arrival delay factor (ADF) and departure delay factor (DDF) by

the following equations:

( )= ⋅ADF ADI D C (6.7)

( )= ⋅DDF DDI D C (6.8)

7. Calculate the demand profile factor (DPF) by the following equation:

= 100QDPF

HD (6.9)

o Airports with a high percentage of air carrier activity normally have a

DPF of 50 percent .

o Airports with a high percentage of general aviation activity normally

have a DPF in the 30 to 35 percent range.

8. Calculate the average delay for arriving aircraft (DAHA) and departing aircraft

(DAHD) from Figure 4.17, extracted from [B10]] by introducing ADF and DDF:

Page 57: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

56

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.17. Average aircraft delay in an hour

9. Calculate hourly delay (DTH) by the following equation:

( )( )⋅ + −=

100

100

HD PA DAHA PA DAHDDTH

(6.10)

4.7.2 Daily delay to aircraft on the runway compone nt when the d/c

ratio is 1.0 or less for each hour

Daily delay can be calculated as follows:

1. For each hour, calculate the hourly delay to aircraft on the runway component

2. Calculate the delay for the time period in question by summing the delay for

each the hours.

Page 58: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

57

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4.7.3 Daily delay to aircraft on the runway compone nt when the d/c

ratio is greater than 1.0 for one or more hours

Daily delay can be calculated as follows:

1. Identify the saturated time periods14.

2. For each saturated period (overload plus recovery phase), calculate the delay

to aircraft as follows:

3. Determine the duration of the overload phase

4. Calculate the hourly AD/C ratio during the overload phase, i.e., the sum of the

hourly demands during the overload phase divided by the sum of the hourly

capacities during the overload phase

5. Determine the percent of arrivals (PAS) for the saturated (overload plus

recovery) period

6. Determine the ADI and the DDI for the saturated (overload plus recovery)

period

7. Calculate the ADF and DDF using the following equations:

( )= ⋅ADF ADI AD C (6.11)

( )= ⋅DDF DDI AD C (6.12)

8. Determine the average delay per arrival (DASA) and per departure (DASD)

during the saturated (overload plus recovery) period from Figure 4.18,

adapted from [B10]]:

Figure 4.18. Average aircraft delay during saturat ed conditions

14 See ANNEX 3 section 3.3.19

Page 59: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

58

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

9. Calculate the delay in the saturated period (DTS) by the following equation:

( ) ( )( )+ + + ⋅ + −= 1 2 ... 100

100nHD HD HD PAS DASA PAS DASD

DTS (6.13)

where

HD is the hourly demand in the saturated period

10. Determine for each unsaturated hour the delay in accordance with the

procedures in section 4.7.2

11. Calculate the total daily delay by summing the saturated and unsaturated

delay

4.7.4 Hourly demand corresponding to a specified le vel of average

hourly delay

Determine the hourly demand which corresponds to a stipulated average level of

delay by trial and error, i.e., using a graphical plotting of delay versus demand.

4.7.5 Aircraft delay (annual)

In order to calculate the aircraft delay, the following procedure should be applied:

1. Estimate annual demand using current or historical information or projections

of future traffic

2. Calculate the ratio of annual demand to ASV

3. Obtain average delay per aircraft according to the following Figure 4.19,

extracted from [B12]

4. Calculate total annual aircraft delay as the average delay multiplied by the

annual demand

Page 60: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

59

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 4.19. Average aircraft delay for long range planning

The upper portion of the band applies to airports where air carrier operations

dominate. The full width of the band applies to airports where general aviation

operations dominate. Delays 5 to 10 times average could be perfectly experienced by

individual aircraft

4.7.6 Annual delay to aircraft on the runway compon ent

The following procedure uses 24 representative days, one VFR and one IFR for each

calendar month. Other increments of time may be selected. If the airport has

considerable fluctuation in operations during the week, or if a more precise delay

determination is needed, one representative VFR and one representative IFR day

should be used for each day of the week. Variation in seasonal traffic will require

repetition of these computations for each season. Airports which have consistent

patterns of operations throughout the week and year require fewer computations.

1. Convert annual demand to average day demand for each month

2. Distribute the annual demand to the 12 calendar months to account for

seasonal variations in traffic

3. Develop average day demand by dividing the monthly demands by the

number of days in the respective month

Page 61: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

60

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

4. Adjust the average day demand to account for differences in VFR and IFR

demand

5. Determine from weather records the percent of the time that IFR and PVC

operating conditions prevail (%IFR)

6. Determine from traffic records the percent IFR (and PVC) demand to VFR

demand (%IFR demand)

7. Calculate the representative VFR day demand (VFR demand) and

representative IFR day demand (IFR demand) by the following equations:

( )=− −

Average day demand1 % 1 % /100 100

VFRdemandIFR IFR demand

(6.14)

= ⋅% / 100IFR demand VFR demand IFR demand (6.15)

8. From historical data, develop a breakdown of hourly demand for the

representative day(s)

9. Determine monthly delay by multiplying the representative daily delays by the

number of days it represents and summing these quotients

10. Add monthly delays

Page 62: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

61

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

5 LANDSIDE CAPACITY ASSESSMENT METHODS

A brief review is given for a range of tools and procedures that may be useful in

assessments of airport landside capacity. A variety of rules of thumb and

mathematical relationships are available. Much of the research and many of the

resulting analysis tools for terminal buildings and curb use the mathematical

framework of queuing theory. Problems of motor vehicle access and parking are

sometimes addressed by using techniques of highway transportation and traffic

engineering.

Any airport’s landside system is complex. There is some flexibility for the airport user

to accommodate to current or anticipated conditions at the airport and to travel

through the system even when queues are growing. Given the difficulty of

representing such a situation, simple rules of thumb based on observation at airports

in operation may often be as useful as more complex mathematical analyses for

assessing capacity. Such rules of thumb are invariably easier to apply. Nevertheless

the framework of queuing theory gives a useful structure to the analysis process.

In order to obtain a quick idea of the capacity of an existing facility or the size that a

facility needs to be in order to handle a given throughput, a variety of simplified

formulae that meet the equilibrium between supply, demand and level of service are

recompiled in this section. However, such formulae employ many simplifications and

approximations that cannot be used as a substitute for a detailed evaluation.

Moreover, not all formulae will be applicable to all airports since not all local factors

are included.

5.1 Ground access capacity

5.1.1 Estimation method

Extracted from [B22]. A rough approximation to have an idea of the ground access

capacity is given in the following table:

Design situation Space standard (ft 2/person)

Design loading of urban transit vehicles 3 - 4

Table 5.1. Typical space standards used in planning and design

Page 63: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

62

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

5.1.2 Access capacity-to-demand index

Extracted from [B41]. It defines two indexes:

• Passenger demand index is calculated as:

( )( )

[1.5 min int

2 . ] / 1000

PDI daily passengers us erline transfers

no of airport employees

=

+ (7.1)

This index is meant to approximate the number of trips per day made to the airport.

• Access supply index is calculated as

( )3.1 / /1000PCI effective lane capacity vehicles hr = (7.2)

This calculation implies an assumed average vehicle occupancy rate of 3.1

persons/vehicle.

If the ratio PDI/PCI is greater than 1.0, there is a potential capacity problem.

Such indexes reflect the underlying principles for access capacity analysis. The

multipliers used could be changed to suit conditions at an individual airport. However,

such indexes can only be first approximations, useful for initial screening for

problems.

5.2 Passenger terminal capacity

5.2.1 Arrival hall capacity

Extracted from [B19]. To determine the arrival hall space requirement for greeters

and passengers, excluding concessions, follow the procedure below:

× × × = × + ×

2 SPP SPP [ ]60 60

AOP PHP AOV PHP VPPA m (7.3)

Where

PHP is the peak hour number of terminating passengers

AOP is the average occupancy time per passenger (minutes) or assume 5

minutes

AOV is the average occupancy time per visitor (minutes) or assume 30

minutes

SPP is the space required per person (m2) for level of service C or assume

2.0 m2

VPP is the number of visitors per passenger

Page 64: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

63

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

5.2.2 Baggage area capacity

5.2.2.1 Baggage area space required

Extracted from [B19]. Capacity of baggage claim areas is judged by considering the

average time passengers must wait to retrieve their checked baggage and by

comparing number of people in the claim area with the size of that area. Simple

queuing analysis is often used to estimate the average time passengers will have to

wait for bags and the number waiting. Planning and design standards are then

selected, generally on the basis of square feet of floor area and linear feet of

baggage display device per person.

The retrieval and peripheral area is a roughly 3.5 meter wide band around the unit.

This area is used to measure the level of service for the passengers waiting around

the carrousel and the static capacity of the unit.

A B C D E

Space standard (m 2/occupant) 2.6 2.0 1.7 1.3 1.0

Table 5.2. Level of service for baggage claim unit (retrieval and peripheral area)

Note 1: Sustainable capacity is at level of service C.

Note 2: Assuming 40% use of trolleys.

5.2.2.2 Number of baggage claim units

Wide-body aircraft

( )

60

PHP PWB CDWBC

NWB

× ×=

× (7.4)

Narrow-body aircraft

( )

60

PHP PNB CDNBC

NNB

× ×=

× (7.5)

Where

PHP is the peak hour number of terminating passengers, international /

domestic transfer passengers, where applicable

PWB is the proportion of passengers arriving by wide-body aircraft in the

peak hour

PNB is the proportion of passengers arriving by narrow-body aircraft in the

peak hour

Page 65: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

64

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

CDW average claim device occupancy time per wide-body aircraft (minutes)

or assume 45 minutes

CDN average claim device occupancy time per narrow-body aircraft

(minutes) or assume 20 minutes

NWB is the number of passengers per wide-body aircraft at 80% load factor

or assume 320 passengers

NNB is the number of passengers per narrow-body aircraft at 80% load

factor or assume 100 passengers

5.2.3 Security check

Extracted from [B19]. The centralized security check system is also designed to

process the check-in maximum throughput to ensure overall capacity balance.

A. Calculate the peak 10-minute check-in counters throughput

600 10 - min demand #CIY (%J)Peak ute

PTci = × ×

(7.6)

Where

#CIY is the number of economy class check-in servers assuming common

use15

PTci is the average processing time at check-in in seconds

%J is the percentage of business class passengers

B. Calculate the number of security check servers

# 10 - min 600

PTscSC Peak ute demand from A = ×

(7.7)

Where

#SC is the number of security servers

PTsc is the average processing time at security check in seconds

C. Calculate the maximum number of passenger queuing assuming a single

queue

# 60#

MQT SCMax Q

PTsc× × =

(7.8)

Where

MQT is the maximum queuing time in minutes

#SC is the number of security servers

PTsc is the average processing time at security check in seconds 15 See section 5.2.4, subpart C

Page 66: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

65

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

5.2.4 Check-in area capacity

5.2.4.1 Check-in queue

Capacity of the ticket counter and baggage check component is judged by

considering the average time required for processing passengers and by comparing

number of passengers in the terminal lobby queuing area with the size of that area.

Direct observation or simple queuing analysis is often used to estimate both the

average wait time and the number of people waiting.

To set up the check-in queue area, IATA [B19] recommends using four different sets

of space standards, as described in Table 5.316:

A B C D E

Few carts and few passengers with check-in

luggage (row width 1.2m)

1,7 1,4 1,2 1,1 0,9

Few carts and 1 or 2 pieces of luggage per

passenger (row width 1.2 m)

1,8 1,5 1,3 1,2 1,1

High percentage of passengers using carts (row

width 1.4m)

2,3 1,9 1,7 1,6 1,5

‘Heavy’ flights with 2 or more items per passenger

and a high percentage of passengers using carts

(row width 1.4 m)

2,6 2,3 2,0 1,9 1,8

Table 5.3. Level of service space standards (m 2/occupant) at check-in for single

queue

5.2.4.2 Number of check-in counters

Extracted from [B19]. The procedure to determine the required number of check-in

counters is as follows:

A. Calculate the peak 30 minute demand at check-in

The peak 30-minute demand is a good predictor of the performance and

requirements at check-in. The following procedure is recommended if the site-

specific demand/capacity characteristics required to determine the peak 30-minute

load are not available:

30 - min - 1 2Peak ute at check in PHP economy class F F= × × (7.9)

where

PHP is the peak hour originating passengers – economy class at check-in

F1 is the % of the PHP in the peak 30-minute from Table 5.417

16 adapted from [B19]

Page 67: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

66

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

F2 is the additional demand generated by the flights departing before and

after the peak hour period from Table 5.518

Number of flights during

the peak hour period

Domestic / Schengen /

Short-haul international

Long -haul

international

1 39 % 29 %

2 36 % 28 %

3 33 % 26 %

4 or more 30 % 25 %

Table 5.4. Peak 30-minute at check-in as a percenta ge of the peak hour period

Average passenger load in the

hour before and after the peak hour

period in % of the PHP

Domestic

Shengen /

Short-haul

international

Long-haul

international

90% 1.37 1.43 1.62

80% 1.31 1.40 1.54

70% 1.26 1.35 1.47

60% 1.22 1.30 1.40

50% 1.18 1.25 1.33

40% 1.14 1.20 1.26

30% 1.11 1.15 1.19

20% 1.07 1.10 1.12

10% 1.03 1.06 1.06

Table 5.5. Additional demand generated by the fligh ts departing before and

after the peak hour period

B. Determine the intermediate result S, which takes into account the MQT

using the following charts

Where

X is the peak-30 minute at check-in

S is the intermediate result

MQT is the maximum queuing time

17 adapted from [B19] 18 adapted from [B19]

Page 68: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

67

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 5.1. Intermediate results chart 1

Figure 5.2. Intermediate results chart 2

Page 69: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

68

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

C. Calculate the number of economy class (common use) check-in counters

#120PTci

CIY S = ×

(7.10)

Where

#CIY is the number of economy class check-in servers assuming common

use

PTci is the average processing time at check-in in seconds

D. Calculate the total number of check-in counters (including business class)

# # 20%CIJ CIY= × (7.11)

= +# # #CI CIY CIJ (7.12)

Where

#CI is the number of check-in servers including business class counters

assuming common use

#CIY is the number of economy class check-in servers assuming common

use

#CIJ is the number of business class check-in servers

E. Make adjustment for dedicated facilities

Due to the widely varying applications of dedicated facilities from airport to airport, it

is difficult to develop a general rule to account for the impact of dedicated facilities on

supply. Experience shows the total number of check-in positions should be increased

by 30 to 40% for dedicated facilities.

5.2.5 Connecting passenger transfer

Extracted from [B38]. There are virtually no analytical techniques intended to deal

specifically with passenger transfers. Assessment of this component of the landside

typically requires a direct estimation of transfer times by using assumptions about

passenger walking speeds, measured distances at the airport, and obstacles or aids

to movement. At some airports, the assessment may be appropriately conducted in

conjunction with the assessment of access or general circulation conditions.

The average time required for interline transfers at large hub airports (approximately

45 min for domestic and 75 min for international connections).

Page 70: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

69

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

5.2.6 Customs and immigration

Extracted from [B38]. The wait for immigration and customs inspections and the

crowding to which passengers may be subjected during these waits are the bases for

determining service levels and capacity. A peak period of 1 to 1.30 hours is usually

appropriate to observe the impact of multiple flight arrivals at most international

airports.

The number, size and load factor of arriving aircraft can be used to estimate

passenger loads at customs and immigration facilities.

Very little information on actual performance has been assembled, and the average

processing rate of 50 passengers per hour per agent suggested by FAA guidance

manual is cited in many publications. However, average inspection rates can

increase when conditions are crowded (in U.S. airports). Queues may grow very long

at some airports.

5.2.7 Gate hold room capacity

Extracted from [B19]. Space required for people seated or standing is different:

• Seated passengers: 1,7 m2

• Standing passengers: 1,2 m2

The occupancy rate is used to measure the level of service:

A B C D E

Maximum occupancy rate 40% 50% 65 % 80 % 95 %

Table 5.6. Level of service A to E in hold rooms

Note: 100% = maximum capacity

Design situation Space standard (ft 2/person)

IATA suggested breakdown level of service in hold

rooms [B19]

> 6,5 for more than 15 min

Table 5.7. Typical space standards used in planning and design

5.2.8 Passport control capacity

5.2.8.1 Estimation method

Extracted from [B19]. Passport control systems are similar to check-in systems. The

main criterion for determining the queue length for multiple queue systems is the

average distance between two individuals waiting in the same line (inter-person

Page 71: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

70

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

spacing). The comfort distance varies from person to person and from culture to

culture. IATA recommends using 0.8 to 0.9 meters . Less than 0.8 meters is possible,

but could conflict with other passengers or carry-on luggage.

Space requirements for a single queue at passport control are based on the space

standards shown in Table 5.8.

A B C D E

Passport control (m 2) 1,4 1,2 1,0 0,8 0,6

Table 5.8. Level of service for a single (bank) que ue at passport control

5.2.8.2 Passport control arrivals capacity

Arrival flights generate flows of terminating passengers and transfer passengers. The

demand of terminating passengers is concentrated over a short period of time,

whereas transfer passengers are processed at transfer desks or go directly to a

lounge or their connecting flights.

The number of terminating passengers and the sum of the number of exit doors from

all the flights during the peak hour are the key demand inputs. According to [B19], the

methodology to determine the number of passport control desks is:

A. Determine the intermediate result S, using the following charts

( )#

100

PHP doors used to exit the aircraftsX

×= (7.13)

Where

PHP is the terminating peak hour passengers

S is the intermediate result

MQT is the maximum queuing time

Page 72: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

71

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 5.3. Intermediate results chart 1

Figure 5.4. Intermediate results chart 2

B. Calculate the number of passport control desks required

#20

PTpcaPCD S = ×

(7.14)

Where

#PCD is the number of passport control desks

PTpca is the average processing time at passport control arrival in seconds

Page 73: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

72

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

C. Calculate the maximum of passenger queuing assuming a single queue

# 60#

MQT PCDMax Q

PTpca × ×=

(7.15)

Where

MQT is the maximum queuing time in minutes

#PCD is the number of passport control desks

PTpca is the average processing time at passport control arrival in seconds

5.2.8.3 Passport control departures capacity

Extracted from [B19]. The peak 10-minute number of passengers exiting check-in is

used to estimate the peak inbound demand at passport control departure.

The following procedure should be applied in order to determine the number of

passport control desks required for departing passengers:

A. Calculate the peak 10-minute check-in throughput

600 10 - min demand #CIY (1+%J)Peak ute

PTci = × ×

(7.16)

Where

#CIY is the number of economy class check-in servers assuming common

use

PTci is the average processing time at check-in in seconds

%J is the percentage of business class passengers

B. Calculate the number of passport control desks

# 10 - min 600

PTpcdPCD Peak ute demand from A = ×

(7.17)

Where

#PCD is the number of passport control desks

PTpcd is the average processing time at passport control in seconds

C. Calculate the maximum number of passenger queuing assuming a single

queue

# 60#

MQT PCDMax Q

PTpcd × ×=

(7.18)

Page 74: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

73

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Where

MQT is the maximum queuing time in minutes

#PCD is the number of passport control desks

PTpcd is the average processing time at passport control in seconds

5.2.9 Parking capacity (vehicles)

5.2.9.1 Parking requirement planning curve

The following picture extracted from [B25], reflects the relationship between

passengers and parking places, and might be helpful to estimate capacity.

Figure 5.5. Estimated requirements for public parki ng at US airports

Given a number of available parking spaces, the implied range of acceptable

passenger loads may be estimated. Such relationships may be useful first indicators

of problems, but may not fit the specific conditions at a particular airport.

5.2.10 Terminal curb capacity

Extracted from [B38]. Analyses of the terminal curb sometimes use procedures

adapted from traffic engineering.

5.2.11 Waiting areas capacity

Extracted from [B38]. In analyzing the capacity of passenger waiting areas, service

levels are usually indicated by the ratio of the number of people in the area and the

size of that area. Targets for this ratio may vary with the time passengers wait for

boarding, but in many cases, only a space standard is stated.

Page 75: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

74

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

In most applications, estimation of passenger demand over time is necessary.

Observation and sample passenger counts are often used to make these estimates.

Mathematical queuing and simulation models to predict the arrival on enplaning

passengers at waiting areas before scheduled departure may also be used. But, as

said before, this will not be covered in this study.

IATA’s recommendations referred to the dimensions of this area are specified in the

following table:

Space (m 2/pax) Speed (m/s)

Airside – no carts 1,5 1,3

Public area after check-in – few carts 1,8 1,1

Departure before check-in – carts 2,3 0,9

Table 5.9. Space and speed for level of service C

5.2.12 Terminal circulation capacity

In general, the terminal circulation component may be considered a pedestrian

circulation problem and analyzed by using procedures and standards such as those

suggested in [B39]. The length of the passenger’s pathway, the passenger’s walking

speed, number of level changes, and the degree of interference the passenger

encounters along the way are key variables in the assessment.

The time spent traveling between curb and gate is the principal measure of service

level and a determinant of capacity. Number of level changes and how complicated

the pathway appears to the passenger may also affect service levels.

IATA’ recommends in the following table velocity that pedestrians should be able to

walk at with a satisfactory comfort:

Speed (m/s)

Airside – no carts 1,3

Public area after check-in – few carts 1,1

Departure before check-in – carts 0,9

Table 5.10. Speed for level of service C

5.3 Landside system as a whole

The components discussed in the preceding chapters are linked together is an airport

terminal into a total system through which passengers move to and from aircraft.

Small queues and short delays in each component, although individually well within

Page 76: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

75

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

tolerable ranges of performance, may still combine to produce a landside capacity

problem. The capacity of the landside system of a particular airport taken as a whole

is more difficult to assess than that of an individual component, but nevertheless it

can be done.

Individual components are linked together in parallel and in series defining the paths

passengers may take through the system. If all components are operating at their

maximum throughput rates, throughput of the terminal as a whole is determined by

the most constrained component in each independent parallel path.

Analyses of individual component capacity may fail to recognize important functional

linkages within the system. Analysts have tried to overcome this problem by

constructing simulations of the terminal as a whole. These models are typically

complex computer simulations, reflecting the complexity of the terminal landside

system. Similar results can in principle be achieved by linking separate component

models together, but interaction among components may then be poorly represented.

Anyway, the analysis done in this report will end at this point; no further simulation

modeling will be done.

Page 77: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

76

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6 AIRPORT SURVEY AND DESCRIPTION

In this chapter, data research of three Catalan airports is presented, specifically,

Barcelona, Girona and Lleida airports are briefly described in their most

representative aspects.

Figure 6.1. Location and areas of influence of airp orts operating in Catalunya

[B1]

6.1 Barcelona–El Prat airport

Figure 6.2. Barcelona–El Prat airport [W13]

Perpignan

Isòcrones 120’

Lleida

Reus

Girona

Page 78: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

77

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Barcelona Airport, also known as El Prat, is the main airport serving Barcelona,

Catalonia, Spain. The airport is the largest in Catalonia, Spain's second largest

behind Madrid Barajas Airport and a major European hub airport.

It is located 10 km southwest from the city centre of Barcelona, between the city

limits of El Prat de Llobregat, Viladecans and Sant Boi. It is just 3 km from the Port of

Barcelona, one of the most important ports in the Mediterranean for container traffic

and the leader in the cruise market.

Figure 6.3. Barcelona–El Prat airport [W8]

It is run by Aeropuertos Españoles y Navegación Aérea (AENA) – Spanish airports

and air traffic agency), a publicly owned body which manages 60 other major airports

in Spain and Latin America and which is responsible to the Spanish government via

the Ministry of Development.

The Barcelona-Madrid air shuttle service, known as the "Pont Aeri" (in Catalan),

literally "Air Bridge", is the world's busiest route. The schedule has been reduced

since February 2008, when a Madrid-Barcelona high-speed rail line was opened,

covering the distance in 2½ hours, and quickly became popular.

The airport has links to 50 European Union cities, 40 in other countries as well as 30

domestic destinations, and operates over 1,000 daily flights.

Coordinates 41° 17' 49" N; 2° 04' 02" E

Elevation (amsl 19) 3,8 m (12 ft)

IATA code BCN

ICAO code LEBL

19 See Annex 1

Page 79: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

78

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Type of Operations Civil

Types of Traffic Domestic, International

Number of Airlines 78

Figure 6.4. Barcelona–El Prat New Control Tower [W8 ]

6.1.1 Runways

Barcelona airport has 3 takeoff and landing runways, two in parallel named 07L/25R

and 07R/25L (this last opened on 2004), and one crossed, the 02/20. Parallel runway

configuration allows independent instrumental operations, a key feature for hub

airports because represents a substantial increment on the number of operations.

The third runway is about 1.350 meters from 07L/25R runway, between La Ricarda

and El Remolar lagoons. This new runway respects both natural reserves.

07L-25R runway has been lengthened from 3.108 meters to 3.743 meters and

widened up to 60 meters, which now allows big airplanes to operate not only in

7R/25L runway, but also in this other one.

Runways

Name Length(m) Width(m) Approach Aids Surface PCN

07L/25R 3743 60 ILS Cat I concrete 086FAWT

7R/25L 2660 60 ILS Cat I asphalt 076FCWT

02/20 2745 45 PAPI asphalt 086FAWT

Table 6.1. Barcelona-El Prat airport runway descrip tion

Page 80: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

79

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.1.2 T1 Terminal building

In response to the projected increase in Spanish air traffic, the airport of Barcelona

started a major expansion program (called Plan Barcelona), the major upgrade since

a new terminal was built for 1992 when Barcelona hosted the Olympic Games.

The work undertaken for the expansion included several major construction projects.

The first of these was a six-gate extension to the airport's existing North Terminal,

followed by the construction of a new midfield terminal (T1 South terminal) designed

by Ricardo Bofill and a new air traffic control tower.

Figure 6.5. Barcelona–El Prat airport T1 Terminal [ W15]

The aircraft handling facilities were also upgraded, starting in with the construction of

a third runway (07R/25L) parallel to the current 07L-25R, an aircraft apron of

800,000m² and a system of taxiing strips. In addition, the project also required new

car parks and new service buildings for logistical, industrial and aircraft servicing

activities, as well as new hotels and security buildings.

In the other hand, the previous A, B, C terminals merged into one single terminal

called T2 with its respective modules A, B and C, whereas on landside the

construction of a new vehicle parking building has been carried out.

Page 81: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

80

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.6. Barcelona-El Prat airport future view [ W7]

A further satellite terminal, able to absorb traffic of 15 million passengers a year, is

now also included in the Master Plan with a completion date of 2012 (this will give the

airport a capacity of 70 million passengers a year). During the new expansion period

up to 2009 the airport is expected to expand in area from 8.45km² to 15.33km².

Figure 6.7. Barcelona-El Prat airport future satell ite. Artist’s impression

Surface s [m 2] [W8]

TERMINAL 544,066 PASSENGER ZONE - Waiting areas

Baggage claim

VIP rooms

Public areas

-

20,000

6,066

155,200

Page 82: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

81

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Commercial area

Car rental offices

Office space

Shops and restaurants

VIP rooms and others

28,612

2,800

14,600

18,976

9,816

Business centre 2,583 Support areas 212,900 APRON 600,000 VEHICLE PARKING 34,500

Other [W8]

Check-in counters 166

Auto check-in counters 52

Information screens 256

Information desks 7 + 2 itinerants

Passenger assistance desks 14

Security control zones 3

Security control counters 28

Passport control zones 5

Passport control counters 52

Customs zones 3

Gates 99

Aircraft parking positions 74

Fingers 37

Carrousels 15

Boarding zones 6

VIP rooms 8

Shops 81

Bars & Restaurants 43

Table 6.2. Barcelona-El Prat airport T1 terminal in numbers

Figure 6.8. Barcelona–El Prat T1 floor plan [W8]

Page 83: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

82

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.9. Check-in Figure 6.10. Sky Cen tre

Figure 6.11. Intermodal Hall Figure 6.12. Baggage claim

Figure 6.13. Departures Figure 6.14. La Plaça

Figure 6.15. Arrivals

Page 84: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

83

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.16. Barcelona–El Prat T1 boarding / deboar ding areas [W8]

As said before, T1 has 102 gates, and accounts 5 boarding zones: A, B, C (situated

on the 1st floor), D and E (on the 3rd floor). A and D are on the north dike, B in the

longitudinal dike and C and E on the south dike.

Some A gates are exclusive for the BCN-MAD route (known as Corredor BCN-MAD);

the rest of A gates and D gates contain UE-UE Schengen and Non UE-UE Non

Schengen boardings; B gates accommodate UE Schengen boarding except in the

triangular zone (at the end of B module) where some doors are non-Schengen; C

gates are devoted to regional flights and E gates to UE Schengen.

Figure 6.17. Barcelona–El Prat T1 terminal 3 rd floor plan

Page 85: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

84

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.1.3 T2 Terminal building

Figure 6.18. Barcelona–El Prat T2 Terminal breakdow n [W7]

Module A gathers the most of flights belonging to foreign airlines.

Module B looks after the billing of national and foreign airlines integrated in the

Oneworld and Star Alliance and those maintaining commercial agreements with

them, such as Iberia, Air Europa, Spanair, British Airways o Lufthansa.

Module C houses the Iberia Air Shuttle and Iberia Regional Flights.

The boarding gates are grouped into 5 zones: A, B and C, which are on P2, and D

and E, which can be found on P3. Each module contains a certain group of gates

which are called M-0 (gates 1 to 8), M-1 (gates 10 to 19), M-2 (gates 20 to 29), M-3

(gates 30 to 39), M-4 (gates 40 to 49) and M-5 (gates 50 to 59).

Figure 6.19. Barcelona–El Prat T2 Terminal plan [W 8]

Page 86: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

85

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.20. Barcelona–El Prat T2A Terminal plan [ W8]

Figure 6.21. Barcelona–El Prat T2B Terminal plan [W 8]

Page 87: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

86

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.22. Barcelona–El Prat T2C Terminal plan [W 8]

Terminal T2A Terminal T2B Terminal T2C

Terminal [m2] 2,200

Check-in counters 36 109 24

Auto check-in counters 0 7 0

Information desks 5 5 1

Passenger assistance desks 1 9 1

Security control zones 1 2 2

Security control counters 4 10 6

Passport control zones 5 2 0

Passport control counters 19 2 0

Customs zones 1 1 0

Gates 20 20 19

Fingers 12 12 6

Carrousels 8 9 4

Boarding zones 2 2 2

VIP rooms 0 0 1

Shops 20 35 4

Bars & Restaurants 6 13 5

Table 6.3. Barcelona-El Prat airport T2 terminal in numbers [W8]

Page 88: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

87

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.23. Barcelona–El Prat airport T2 Terminal [W8]

Figure 6.24. Barcelona–El Prat airport T2A Terminal [W8]

Figure 6.25. Barcelona–El Prat airport T2B Terminal [W8]

Page 89: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

88

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.26. Barcelona–El Prat airport T2C Terminal [W8]

6.1.4 Corporate Aviation Terminal building

Corporate aviation has a high number of business and company travellers, which

provides added value to the airport and the cities around it.

The total surface area of the terminal is 2,118 m2. On the ground floor are the waiting

rooms, the VIP lounges and the public areas; on the upper floor there are the

meeting rooms and company offices. It is open 24 hours a day, 365 days a year.

It is situated opposite the corporate aviation apron which has capacity for 26 places.

It offers the following facilities and comforts, among others:

• It takes 7 minutes to get from the Terminal car park to the aircraft.

• The Commercial Aviation Terminal is 7 minutes away.

• Passport control and security in the same terminal.

• VIP lounges.

• The facilities on the apron ensure quick, safe operation.

Figure 6.27. Barcelona–El Prat corporate aviation t erminal plan [W8]

Page 90: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

89

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Barcelona airport currently has 26 corporate aviation spaces, which are used by the

following companies: CNAir, Gestair, Universal Jet, Bks, Punto Fa, Corporate Jets,

Bcn Jets and Executive Airlines.

Figure 6.28. Barcelona–El Prat airport Corporative Aviation Terminal [W8]

Surfaces [m 2] [W8]

Terminal 2,118

Other [W8]

Check-in 0

Auto check-in machines 0

Information desks 1

Security controls 1

Passport control 0

Customs zones 0

Gates 1

Fingers 0

Carrousels 0

Boarding zones 1

VIP rooms 2

Shops 0

Bars & Restaurants 0

Table 6.4. Barcelona-El Prat airport corporate avia tion terminal in numbers

Page 91: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

90

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.1.5 Accesses

6.1.5.1 Car / Bus / Taxi

Figure 6.29. T2 parking areas [W8]

Entrance

Exit

Payment machines

Car hire Parking offices and information

The Barcelona airport T2 terminal has 11,911 parking spaces, 2,009 of which are

located in the parking building connected to T2C Terminal by an airbridge, and 2,600

more are found in the car park located across from T2A Terminal, which is also

connected by an elevated corridor.

Due to T1 terminal construction, the inter-modal nature of the airport has been

emphasised by being remodelled around the current road access, extending it to the

new intra-runway terminal, at the same time as introducing new accesses to the

industrial, logistics and service areas.

The new wave / curve roof T1 terminal has been designed to be based towards

public transport although there will also be substantial facility for cars with a 12,000

space car park, 9,400 are situated in two 9 floor buildings in front of the terminal and

are covered and the 1,600 left are outdoor spaces over the surface. Also, over 2,300

spaces are dedicated to employees, 1,015 for long stages and 1,000 to VIP and

contingency. The car park is divided into 7 modules (A, B, C, D, E, F and G).

Moreover, T1 has an exclusive cycle lane for cyclists.

Regarding taxi stops, there are be two passenger loading zones: one, the principal,

at the exit of the processor building, with capacity for 250 taxis waiting and 24 picking

up passengers simultaneously, and another in the north dam to service the Pont Aeri

Madrid-Barcelona, with capacity for 200 taxis waiting and 12 picking up passengers.

Page 92: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

91

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

The supply of bus stops and parking of coaches is multiplied by 3 to 60 places of

contact with or proximity to the passenger terminals thanks to the construction of the

new terminal T1. Both arrival (0th floor) and departure (3rd floor) lanes will stop regular

city and intercity buses (L-77, PR1, line 46, N-17), regional lines (Directbus, Business

Plan, Mon-Bus, Alsa, Novatel Autocars) and the Aerobus.

6.1.5.2 Train

The airport is also currently accessible by RENFE commuter train on the C10 line,

which runs from Estació de França, with a major stop at Sants train station, providing

transfer to the Barcelona Metro system.

Railroads had also been greatly enhanced with the construction of railway stations in

each of the terminals and suburban and metro branches connected directly to the

airport with the city, the metropolitan public transport networks and the future TGV

station in Prat de Llobregat.

6.1.6 Airport numbers

Traffic (in millions) 2008 [W8] 2007 2006 2005 2004

Domestic passenger 15.158 14.370 13.368 11.853

International passenger 17.550 15.466 13.574 12.511

Terminal passengers 32.708 29.836 26.941 24.364

Transit passengers 0.086 0.165 0.180 0.187

Total passengers 30.272 32.795 30.001 27.122 24.551

Table 6.5. Traffic of passengers in Barcelona-El Pr at airport [W9]

Freight (in thousands) 2008 [W8] 2007 2006 2005 2004

Domestic freight 16.1 20.2 22.5 23.9

International freight 80.6 73.2 67.7 61.1

Total freight 103.9 96.8 93.4 90.2 85.0

Mail 3.6 5.6 7.0 6.4

Table 6.6. Freight in Barcelona-El Prat airport [W9 ]

Aircraft Movements 2008 [W8] 2007 2006 2005 2004

Total commercial 349,45 324,104 304,570 287,956

Other 3,039 3,546 3,228 3,413

Total movements 321,693 352,489 327,650 307,79 291,369

Table 6.7. Aircraft movements in Barcelona-El Prat airport [W9]

Page 93: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

92

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.2 Girona–Costa Brava airport

Figure 6.30. Girona–Costa Brava airport [W6]

Girona-Costa Brava Airport is an airport located 12 km south of the city of Girona,

next to the small village of Vilobí d'Onyar, in the north-east of Catalonia, Spain. It is

well connected to the Costa Brava, Barcelona and the Pyrenees.

The airport was built in 1965, but passenger traffic was modest. The early 2000s saw

passenger numbers grow spectacularly after Ryanair chose Girona as one of its

European hubs. In 1993, Girona Airport dealt with only 275,000 passengers; but in

the last six years the number of passengers increased ten times from 557,000 in

2002 to 5,507,000 in 2008.

Figure 6.31. Girona–Costa Brava airport [W6]

Girona Airport is also run by AENA (like Barcelona – El Prat), and at present, is in the

9th position of Aena’s airports list regarding passenger traffic, while for cargo traffic

and operations occupies positions 16 and 23 respectively. The profile of its

passenger traffic is mainly tourism, with a predominance of regular traffic of airlines

with destinations within the European Union.

Page 94: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

93

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

It is an airport in a competitive environment, with four international airports in the

vicinity20 (provided that Lleida Airport will begin to operate in 2009/2010). The airports

of Reus and Perpignan compete with Girona in attracting leisure passengers on low

cost flights. Passengers who meet this profile generally do not have inconvenient to

travel long distances to reach an airport if, in the other hand, flights have cheap

fares.

Many people use Girona Airport as an alternative airport for Barcelona, though the

airport is 85 km north of Barcelona. Passengers can transfer to Barcelona by bus or

taxi from the airport or by train from Girona railway station.

The majority of regular routes operated from Girona Airport are international with

destinations to EU.

Figure 6.32. Girona–Costa Brava airport main destin ations [W8]

Coordinates 41°54 ′00″N 2°46 ′00″E

Elevation (amsl) 142 m (465.8 ft)

IATA code GRO

ICAO code LEGE

Type of Operations Civil

20 See Figure 6.1

Pescara

Bologna

Trapani

Marrakech

Oslo

Oporto

Wroclaw

Alghero

Billund

Bremen

Cagliari

Eindhoven

Estocolmo

Birmingham

Doncaster

Granada

Florència

Glasgow

Newcastle

Dublin

Karlsruhe

Leeds

Linz

Liverpool

London

Madrid

Malta

Manchester

Milà

New quay

NiederrheinBournemouth

Nottingham

París

PoznanFrankfurt

Fez

Maastricht

RomaGirona

Shannon

Bristol

Blackpool

Eivissa

VenetiaTurí

Page 95: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

94

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Types of Traffic Domestic, International

Number of Airlines 6

Figure 6.33. Girona–Costa Brava Control Tower [W8]

6.2.1 Runways

Girona’s airfield has two exit taxiways, one of them high-speed or rapid-exit taxiway,

and taxiway running parallel to the runway that serves both headers.

Figure 6.34. Girona–Costa Brava Airfield [W8]

Runways

Name Length(m) Width(m) Surface ILS PCN

20/02 2400 45 asphalt YES 079FDWT

Table 6.8. Girona-Costa Brava airport runway descri ption

Page 96: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

95

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.2.2 Terminal building

Girona Airport has a single terminal with the ground floor dedicated to departures and

baggage collection and the top floor dedicated to boarding.

For arrival flows, the airport has two arrivals halls (one for flights from the European

Union and countries of the Schengen agreement and another one dedicated to flights

from outside the European Union or non-Schengen countries).

Figure 6.35. Girona–Costa Brava airport Terminal [W 8]

Surfaces [m 2] [B1]

TERMINAL 22,557

PASSENGER ZONE 15,492

Toilettes, stairs and others 1,022

Waiting areas

Departures hall

Baggage claim

Arrivals hall

Boarding areas

10,652

1,601

1,686

990

6,375

Passage areas

Security control

Passport control

1,218

496

722

Commercial area 2,600

APRON 235,000

CONTROL TOWER 150

Page 97: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

96

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Other [W8]

Check-in counters 33

Auto check-in counters 0

Information desks 2

Passenger assistance desks 3

Security control zones 4

Security control counters 5

Passport control zones 1

Passport control counters 5

Customs zones 1

Gates 9

Aircraft parking positions 50

Commercial aircraft parking positions 17

Fingers 0

Carrousels 3 (one of them double)

Boarding zones 2

Shops 5

Bars & Restaurants 6

Table 6.9. Girona–Costa Brava airport terminal in n umbers

Figure 6.36. Girona–Costa Brava airport 0 th floor terminal plan [W8]

Figure 6.37. Girona–Costa Brava airport 1 st floor terminal plan [W8]

Page 98: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

97

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.2.3 Accesses

Girona’s airport currently has 3,800 parking spaces approximately, 46 of them

adapted for handicapped, 2,400 for cars and 35 for buses, distributed in three

buildings, called P1-A, P1, and P2-B.

6.2.4 Airport numbers

Traffic (in millions) 2008 [W8] 2007 2006 2005 2004

Domestic passenger 0.236 0.005 0.003 0.002

International passenger 4.593 3.586 3.511 2.941

Terminal passengers 4.829 3.591 3.514 2.944

Transit passengers 0.001 0.002 0.002 0.004

Total passengers 5.551 4.830 3.593 3.517 2.948

Table 6.10. Traffic of passengers in Girona-Costa B rava airport [W9]

Freight (in thousands) 2008 [W8] 2007 2006 2005 2004

Domestic freight - - - - -

International freight 0.2 0.5 0.2 0.1

Total freight 0.18 0.2 0.5 0.2 0.1

Mail - - - - -

Table 6.11. Freight in Girona-Costa Brava airport [ W9]

Aircraft Movements 2008 [W8] 2007 2006 2005 2004

Total commercial 36,252 24,883 24,319 20,633

Other 9,030 8,556 7,800 8,035

Total movements 49,926 45,282 33,439 32,119 28,668

Table 6.12. Aircraft movements in Girona-Costa Brav a airport [W9]

Page 99: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

98

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.3 Lleida–Alguaire airport

Figure 6.38. Lleida–Alguaire airport [W14]

Lleida-Alguaire is an airport under construction which will provide services mainly in

the city of Lleida and the nearby regions. The new infrastructure will be regional, this

means, it will cover any European distance in a similar way to the airport of Reus and

Girona. Works began in the summer of 2007 and is expected to be completed during

the second half of 2009, opening its services from November 2009 on.

Figure 6.39. Lleida–Alguaire airport [W11]

The location of the airport is in Alguaire, in El Segrià region, close to Lleida, aiming at

creating in the western regional area an airport to serve both passengers and the

logistics.

The construction of this project is assured by the Government of Catalunya, the first

airport in Spain built by a government and not managed by AENA. On the other

hand, it will be operated by a public-private mixture:

Page 100: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

99

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

• Management will be carried out by Aeroports de Catalunya (Catalonia

Airports), a public company promoted by the Catalan government and

attached to the Ministry of Town and Country Planning and Public Works

• Operational control will be provided by the air controllers of AENA, like the

rest of Spanish infrastructures, since today is the only authorized organization

competent in aspects of air navigation throughout the state

Some airlines have already shown interest in operating from Lleida, as is the case of

Ryanair, Air Berlin, Easyjet and Vueling. If Lleida can offer an attractive range of

routes and destinations, the new airport will have potential to attract travelers from

the provinces of Barcelona and Lleida. This way, Lleida’s airport could become a

strong competitor for Girona when capturing passengers from low cost airlines that

want to offer flights from the area.

Coordinates 41° 43 ′ 40″ N, 0° 32 ′ 09″ E

Elevation (amsl 21) 350 m (1148.3 ft)

IATA code n/a

ICAO code n/a

Type of Operations Civil

Types of Traffic n/a

Number of Airlines n/a

Figure 6.40. Lleida–Alguaire Control Tower [W11]

21 See Annex 1

Page 101: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

100

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.3.1 Runways

The technical features of the airport will allow the landing of aircraft such as Airbus

A320, A321 and Boeing 737, each of those carrying an average of 150 passengers;

or regional-type aircraft with capacity of 70 or 80 seats.

The aircraft parking area will be able to contain the following combinations of aircraft:

• 6 regional aircraft type (ATR -72)

• 4 regional (ATR-72) and 2 Airbus aircraft type

• 5 regional (ATR-72) and 1 Airbus (A320 or A 321) aircraft type

Runways

Name Length(m) Width(m) Surface ILS

20/02 2500 45 asphalt YES

Table 6.13. Lleida–Alguaire airport runway descript ion

6.3.2 Terminal building

A temporary terminal has been build to bring the airport into operation this year,

before the private manager has finally built the terminal. This is a temporary terminal

building of 804 m2 to serve passengers and their baggage handling. The horizontal

developed building will incorporate the technical and personal services module, the

lobby module and restaurants.

Figure 6.41. Lleida–Alguaire airport Terminal outsi de view (virtual recreation)

[W11]

Page 102: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

101

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.42. Lleida–Alguaire airport Terminal insid e view (virtual recreation)

[W12]

Surfaces [m 2]22

TERMINAL 3,200

PASSENGER ZONE -

Waiting areas

Departures hall

Baggage claim

Arrivals hall

Boarding areas

450

448

350

280

530

APRON 33,000

CONTROL TOWER 300

TECHNICAL BLOCK 1000

Other

Check-in counters 8

Passenger assistance desks 4

Security control zones 1

Security control counters 3

Passport control zones 2

Passport control counters 2

Customs zones 1

Aircraft parking positions 6

Fingers 0

Carrousels 2

Boarding zones 1

Table 6.14. Lleida-Alguaire airport terminal in num bers [B16]

22 Dimension values according to Phase I

Page 103: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

102

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

Figure 6.43. Lleida–Alguaire airport terminal build ing 1 st floor terminal plan

[B16]

Figure 6.44. Lleida–Alguaire airport terminal build ing 2 nd floor terminal plan

[B16]

Page 104: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

103

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6.3.3 Accesses

The parking in front of the terminal building has storage for 240 vehicles.

It is scheduled to integrate the airport with the main road network by connecting both

the current road Lleida - Val d'Aran (N-230) and the future A-14, to be replaced

functionally as a highway connecting Lleida, l’Alt Pirineu and Aran.

It is also scheduled the construction of a new rail access to Alguaire, with a

connection line linked to the current line Lleida-Almacelles and TGV.

Figure 6.45. Lleida–Alguaire airport accesses [W14]

6.3.4 Airport numbers

The objective, during the first year of operation, is to reach traffic of 75,000

passengers by operating 16 flights per day (2 flights per hour) and is expected to

grow to 385,000 in the 10th year. It is clear that the development of the Airport Lleida

will largely depend on the common effort between the manager of the airport and the

administration to encourage the creation of routes and the growth of traffic.

Page 105: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

104

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

7 RUNWAY CAPACITY ASSESSMENT (INDEPENDENT)

1. Select the runway-use configuration which best represents the use of the

airport during the hour of interest.

Now the runway-use configuration which best represents the use of the airport during

the hour of interest is Diagram n. 9.

2. Select the figure number for capacity

3. Determine the percentage of Class C and D aircraft operating on the runway

component and calculate the mix index

The mix index is exactly the same as for segregated mode as we do the assessment

for the same demand.

MIX INDEX

Mix index 2009 108,43

4. Determine percent arrivals (PA)

Again, PA is the same as for segregated mode:

5. Determine hourly capacity base from graph (C*)

%PA 46,67

Hourly capacity base (C*)

IFR conditions

102

Page 106: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

105

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

6. Determine the touch and go factor (T)

7. Determine the location of exit taxiways and determine the exit factor (E)

In this case we will consider Eastern Configuration on both runways, this is to say,

landings coming from Gavà Mar. The exit range is the same as the mix index it is so:

Touch and go factor (T)

IFR conditions

1

N

07L/25R 07R/25L

2

Exit factor (E)

IFR conditions

07L/25R 07R/25L

0.92

EXIT

333.7 m

EXIT

RANGE

Page 107: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

106

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8. Calculate the hourly capacity of the runway component with = ⋅ ⋅*C C T E

Current runway capacity [ops/hour]

IFR conditions

07L/25R 07R/25L

93

In this case we see that independent operations bring a huge increment of the

capacity

Page 108: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

107

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8 AIRCRAFT APPEARING IN THIS REPORT

8.1 A-300

Cockpit crew Two

Manufacturer Airbus

Passengers 266 (2-Class)

Fuselage length 54.08 m

Height 16.62 m

Wingspan 44.85 m

Fuselage width 5.28 m

Operating empty weight 90,900 kg

Maximum take-off weight 171,700 kg

Typical cruise speed mach 0.78

Max cruise speed mach 0.82

Max range, loaded 7,540 km

Maximum fuel capacity 68,150 litres

Takeoff run on MTOW 2,324 m

Service ceiling 35000 ft

Number of engines 2

Engine model CF6-80C2 or PW4158

Table 8.1. A-300-600R specifications [W3]

Figure 8.1. Airbus A-300

Page 109: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

108

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8.2 B-727

Cockpit crew Three

Manufacturer Boeing

Max seating capacity 189

Fuselage length 46.7 m

Height 16.62 m

Wingspan 44.85 m

Tail height 10.3 m

Zero fuel weight 45,360 kg

Maximum take-off weight 95,028 kg

Typical cruise speed 0.81 Mach

Max cruise speed 0.90 Mach

Max range, loaded 4450 km

Takeoff run on MTOW 1,768 m

Max. fuel capacity 37,020 L

Service ceiling 35000 ft

Number of engines 3

Engine model P&W JT8D-7, -17R&S

Table 8.2. B727-200 specifications [W3]

Figure 8.2. Airbus A-300

Page 110: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

109

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8.3 B-747

Cockpit crew Two

Manufacturer Boeing

Passengers 524 (2nd class) 416 (3rd class)

Fuselage length 70.6 m

Height

Wingspan 64.4 m

Fuselage width

Tail height 19.4 m

Operating empty weight 178,756 kg

Maximum take-off weight 396,890 kg

Typical cruise speed Mach 0.85

Max cruise speed Mach 0.92

Max range, loaded 13,450 km

Maximum fuel capacity 216,840 L

Takeoff run on MTOW 3,018 m

Service ceiling 45000 ft

Number of engines 4

Engine model

PW 4062

GE CF6-80C2B5F

RR RB211-524G/H

Engine thrust

PW 282 kN

GE 276 kN

RR 265/270 kN

Table 8.3. B747-400 specifications [W3]

Figure 8.3. Airbus A-300

Page 111: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

110

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8.4 B-767

Cockpit crew Two

Manufacturer Boeing

Passengers 218 (3rd class) 269 (2nd class) 350 (1st class)

Fuselage length 54.9 m

Height

Wingspan 47.6 m

Fuselage width 5.03 m

Fuselage height 5.41 m

Cabin width (interior) 4.72 m

Operating empty weight 86,070 kg

Maximum take-off weight 158,760 kg

Typical cruise speed Mach 0.80

Max cruise speed Mach 0.86

Max range, loaded 7,300 km

Maximum fuel capacity

Takeoff run on MTOW 2,410 m

Service ceiling 11.887 m

Number of engines 2

Engine model P&W JT9D-7R4

Engine thrust PW 220 kN

Table 8.4. B767-300 specifications [W3]

Figure 8.4. B767

Page 112: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

111

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8.5 DC-9

Manufacturer MC Donnell Douglas

Passengers 115 (1st class)

Fuselage length 36.37 m

Wingspan 28.47 m

Tail height 8.38 m

Maximum take-off weight 49,900 kg

Typical cruise speed 570 mph

Max range, loaded 3,030 km

Service ceiling 37,000 feet

Number of engines 2

Engine model Pratt & Whitney JT8D-7, -9, -11 or -15

Engine thrust 68.9 kN

Table 8.5. DC-9-30 specifications [W3]

Figure 8.5. DC-9-30

Page 113: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

112

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8.6 DC-10

Cockpit crew Three

Manufacturer Mc Donnell Douglas

Passengers 380 (1st class), 250 (2nd class)

Fuselage length 51.97 m

Height 17.7 m

Wingspan 50.4 m

Fuselage width 6.02 m

Fuselage height 6.02 m

Operating empty weight 120,742 kg

Maximum take-off weight 259,459 kg

Typical cruise speed Mach 0.82

Max cruise speed Mach 0.88

Max range, loaded 10,010 km (medium to long)

Maximum fuel capacity 138,720 L

Takeoff run on MTOW 2,847 m

Service ceiling 12,802 m

Number of engines 3

Engine model GE CF6-50C

Engine thrust 226.9 kN

Table 8.6. DC-10-30 specifications [W3]

Figure 8.6. DC-10

Page 114: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

113

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8.7 Gulfstream II

Cockpit crew 2

Manufacturer Gulfstream Aerospace

Passengers 19 (maximum certified)

Fuselage length 24.36 m

Wingspan 20.98 m

Fuselage height 7.47 m

Operating empty weight 16.576 kg

Maximum take-off weight 29,711 kg

Typical cruise speed 483 mph

Max cruise speed Mach 0.85

Max range, loaded 6,635 km

Service ceiling 45,000 ft

Number of engines 2

Engine model Rolls-Royce Spey 511-8 turbofan

Engine thrust 51 kN

Table 8.7. Gulfstream II specifications [W3]

Figure 8.7. Gulfstream II

Page 115: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

114

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

8.8 L-1011

Cockpit crew Three

Manufacturer Lockheed

Passengers 263 (3rd class)

Fuselage length 54.2 m

Height 16.9 m

Wingspan 47.3 m

Fuselage width 5.7 m

Operating empty weight 105,100 kg

Maximum take-off weight 211,000 kg

Typical cruise speed Mach 0.86 normal cruise /

Mach 0.84 long range cruise

Max cruise speed Mach 0.90

Max range, loaded 7,420 km

Service ceiling 11,000 m

Number of engines 3

Engine model (x 3) Rolls-Royce RB.211-524B

Table 8.8. L-1011-200 specifications [W3]

Figure 8.8. Delta Airlines L-1011

Page 116: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

115

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

9 REFERENCES

9.1 Bibliography

[B1]. Advanced Logistics Group (ALG), Servicios y Procesos Aeroportuarios, parte

II, 2001

[B2]. AENA, Plan Director del Aeropuerto de Girona, Madrid: Ministerio de

Fomento, Junio 2006

[B3]. Air Transport Association of America, Airline Aircraft Gates and Passenger

Terminal Space Aproximations, AD/SC Report 4, Washington, D.C: The

Association, July 1977

[B4]. Ashford, N. and Wright, P.H., Airport Engineering, New York: Wiley and Sons,

1979

[B5]. Belshe, R.D., A Study of Airport Terminal Gate Utilization, Graduate Report,

Berkeley: Institute of Transportation and Traffic Engineering, University of

California, August 1971

[B6]. EUROCONTROL, Constraints to Growth, vol. 1 and 2, The Administration,

2001

[B7]. EUROCONTROL, Challenges to Growth 2004 Report (CTG04), 1st ed, The

Administration, 2004

[B8]. EUROCONTROL, Challenges of Growth 2008 Summary Report, The

Administration, 2008

[B9]. EUROCONTROL, Airport CDM Cost Benefit Analysis, ed 1.4, The

Adminsitration, 11/04/2008

[B10]. Federal Aviation Administration (FAA), Airport Capacity and Delay (AC

150/5060-5), rev. ed., 1983

[B11]. Federal Aviation Administration (FAA), The Apron and Terminal Building

Planning Manual (FAA-RD-75-191), US Department of Transportation,

undated

[B12]. Federal Aviation Administration (FAA), Techniques for Determining Airport

Airside Capacity and Delay (FAA-RD-74-124), rev. ed. Springfield, Virginia:

National Technical Information Service, 1976

Page 117: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

116

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

[B13]. Federal Aviation Administration (FAA), Planning and Design Considerations

for Airport Terminal Building Development (AC 150/5060-7A), US Department

of Transportation, undated

[B14]. Federal Aviation Administration (FAA), Planning and Design Considerations

for Airport Terminal Facilities (AC 150/5360-13), US Department of

Transportation, undated

[B15]. García Cruzado, M, Ingeniería Aeroportuaria, 3rd ed. Madrid: Aula

Documental de Investigación, 2006

[B16]. Generalitat de Catalunya, Pla Director de l’Aeroport de Lleida – Alguaire,

Barcelona

[B17]. Guidelines for Airport Capacity / Demand Management, Airport Associations

Coordinating Council, Geneva, Switzerland, and International Air Transport

Association, Montseral, Canada, November 1981

[B18]. INDRA, CDM for pre-departure sequence optimization

[B19]. International Air Transport Association (IATA), Airport Development

Reference Manual, 9th ed. Montreal, Quebec, Canada: The Association, 2004

[B20]. International Civil Aviation Organization (ICAO), Gestión del Tránsito Aéreo

(Doc 4444-ATM/501), 15th ed. Montreal: The Organization, 2007

[B21]. International Civil Aviation Organization (ICAO), Manual de Planificación de

Aeropuertos (Doc 9184-AN/902), Parte 1: Planificación General, 2nd ed.

Montreal: The Organization, 1987

[B22]. Jacobs, M., Skinner, R.E., Jr., and Lemer, A., Transit Project Planning

Guidance: Estimation of Transit Supply Parameters (Report UMTA-MA-09-

9015-85-01), Cambridge, Mass.: Transportation Systems Centre, October

1984

[B23]. McKelvey, F.X, Palm Beach International Airport: Interim Airport Operating

and Use Plan, Circinnati, Ohio: Aviation Planning Associates, 1984

[B24]. McKelvey, F.X. and Horonjeff, R., Planning and Design of Airports, 3rd ed.,

New York: McGrawHill, 1983

[B25]. Neufville, R. de, Airport Airside Capacity and Delay – A Critical Look at

Methods and Experience, London: Macmillan Press, 1976

[B26]. Nacho Cruz, SESAR Background, INDRA, 14 May 2009 [PPT]

Page 118: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

117

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

[B27]. Panero, J. and Zelnick, M., Human Dimensions and Interior Space: A Source

Book of Design Reference Standards, New York: Whitney Library of Design,

1979

[B28]. Ralph M. Parsons Company. The Apron and Terminal Building Planning

Report (FAA-RD-75-191), US Department of Transportation, July 1975

[B29]. SESAR Consortium, Air Transport Framework Current Situation D1, July

2006

[B30]. SESAR Consortium, The Performance Target D2, December 2006

[B31]. SESAR Consortium, The ATM Target Concept D3, September 2007

[B32]. SESAR Consortium, The ATM Deployment Sequence D4, January 2008

[B33]. SESAR Consortium, European ATM Master Plan D5, March 2009

[B34]. SESAR Consortium, Work Programme for 2008-2013 D6, April 2008

[B35]. Tilles, R., Curb Space at Airport Terminals. Traffic Quarterly, October 1973

[B36]. Trani, Antonio A., Aircraft Classifications [PPT]

[B37]. Transport Canada, Air Terminal Systems Capacity / Demand Study –

Vancouver International Airport, Ottawa, Ontario, August 1986

[B38]. Transportation Research Board (TRB), Measuring Airport Landside Capacity,

Washington, D.C, 1987

[B39]. Transportation Research Board (TRB), Special Report 209: Highway Capacity

Manual, Washington D.C: National Research Council, 1985

[B40]. Whitlock, E.M., LaMagna, F. and Mandle, P., Collection of Calibration and

alidation Data for an Airport Landside Dynamic Simulation Model (Report

TSC-FAA-80-3), U.S. Department of Transportation, April 1980

[B41]. Whitlock, E.M., LaMagna, F., and Mirsky, H.M., Ground Transportation

Planning Implications of Airline Shuttle Passengers (in Transportation

Research Record 499 (TRB)), Washington D.C: Nation Research Council,

1974

9.2 Web

[W1]. www.sesarju.eu

Page 119: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

118

Stu

dy o

f Airp

ort C

apac

ity v

s. E

ffici

ency

SE

SA

R C

halle

nges

. A

nnex

es /

V.1

.0

[W2]. www.eurocontrol.int/sesar

[W3]. www.wikipedia.org

[W4]. www.iata.org/index.htm

[W5]. www.icao.int

[W6]. www.google.es

[W7]. www.castelldefels.com

[W8]. www.aena.es

[W9]. www.rati.com

[W10]. www.airport-technology.com

[W11]. http://www10.gencat.cat

[W12]. www.aeroportlleida.cat

[W13]. www.barcelona-guide.info

[W14]. www.aeroportlleidaalguaire.com

[W15]. http://bloginfax.com

[W16]. www.fomento.es

[W17]. https://www.atmmasterplan.eu

9.3 Software

[S1]. SESAR EP3 Information Navigator [http://www.episode3.aero], Freeware, 17

February 2009

[S2]. SESAR EP3 Information Navigator [http://www.episode3.aero], Freeware, 23

July 2009

[S3]. Google Earth [http://earth.google.es/], Freeware, 20 August 2007

Page 120: Indra Airports STUDY OF AIRPORT CAPACITY VS . EFFICIENCY ...upcommons.upc.edu/bitstream/handle/2099.1/8898... · Indra Airports STUDY OF AIRPORT CAPACITY VS SESAR CHALLENGES Annexes

www.alg-global.com

www.indra.es

A D V A N C E D L O G I S T I C S G R O U PA D V A N C E D L O G I S T I C S G R O U P