20
Indian Blackouts July 30 & 31, 2012 Recommenda;ons and Further Ac;ons CAMS/RRPA Panel Session Mitigation and Prevention of Cascading Outages: Methodologies and Practical Applications PES General Meeting, Vancouver, Canada July 24, 2013 Anish Gaikwad ([email protected] ) Project Manager, Electric Power Research Ins;tute Knoxville, TN, USA Suresh C Srivastava ([email protected]) Professor, Dept. of Electrical Eng. Indian Ins;tute of Tech. Kanpur, India Contribu;ng Authors: Vikas Singhvi, EPRI and Sudhir Agarwal, General Reliability

Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Indian  Blackouts-­‐  July  30  &  31,  2012  Recommenda;ons  and  Further  Ac;ons

CAMS/RRPA Panel Session Mitigation and Prevention of Cascading Outages:

Methodologies and Practical Applications PES General Meeting, Vancouver, Canada

July 24, 2013 Anish    Gaikwad  ([email protected])  

Project  Manager,  Electric  Power  Research  Ins;tute  Knoxville,  TN,  USA  

 Suresh  C  Srivastava  ([email protected])  Professor,  Dept.  of  Electrical  Eng.  

Indian  Ins;tute  of  Tech.  Kanpur,  India    

Contribu;ng  Authors:  Vikas  Singhvi,  EPRI  and  Sudhir  Agarwal,  General  Reliability  

               

Page 2: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Outline  •  Impact  of  the  two  Indian  blackouts  

– 30th  July,  2012  at  2:35  AM  Indian  Standard  Time  (IST)  

– 31st  July,  2012  at  1  PM  IST  

•  A  summary  of  sequence  of  events  for  the  two  blackouts  

•  Root  cause  analysis  and  recommendaJons  for  system  planning  and  operaJons  

IEEE  Boise,  Nov  16,  2012  

2  

Page 3: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Impact  of  the  July  30th  Blackout  •  Occurred  at  2:33  AM  IST  •  Affected  more  than  300  million  people  in  Northern  Region  

across  9  states  including  the  capital  New  Delhi  •  RestoraJon  Jme        :16:00  PM  •  Collapse  Jme              :  02:33  AM            •  MW  generaJon  lost                                                    :more  than  load  loss  •  MW  load  lost          :36000  MW  •  Number  of  successive  events  :  no  exact  count  but  a  large  no.  •  DuraJon  (from  blackout  to  recovery):  ~  13:30  hrs    •  Approximate  cost      :  No  official  data  available  but  a  huge  

figure                      

IEEE  Boise,  Nov  16,  2012  

3  

Page 4: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Impact  of  July  31st  Blackout  •  Occurred  at  1:00  PM  IST  •  Affected  670  million  people  in  Northern,  Eastern,  North-­‐

Eastern  regions  across  22  states  •  RestoraJon  Jme        :All  regions  by  21:00  PM  •  Collapse  Jme              :  13:00  PM            •  MW  generaJon  lost                                                    :  more  than  load  loss  •  MW  load  lost          :48  000  MW  •  Number  of  successive  events  :  no  exact  count  a  but  large  no.  •  DuraJon  (from  blackout  to  recovery):  ~  5  hrs  (NR),  8  hrs  (ER)  

                         and  2  hrs  (NER)  •  Approximate  cost      :  No  official  data  available  but  a  huge  

figure                       IEEE  Boise,  Nov  16,  2012  

4  

Page 5: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Indian  Regional  Grid  India  has  been  demarcated  into  5  interconnecJons  

• Northern  (NR)  • Eastern  (ER)  • Western  (WR)  • North  Eastern  (NER)  • Southern  (SR)  

NR,ER,NER  and  WR  are  synchronously  interconnected  

SR  is  asynchronously  connected  to  the  rest.    

All  the  regions  except  SR  are  together  referred  to  as  “NEW”  regions  

Source: http://www.desismartregion.com/2012/08/indian-power-region-blackout-reasons-and-future-requirements/

Regions  in  black  show  the  interconnecJons  affected  by  the  two  blackouts  

Page 6: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Blackout-­‐1:  Prior  System  CondiJons  

IEEE  Boise,  Nov  16,  2012  

6  

Western  and  Eastern  regions  were  exporJng  power  to  the  Northern  region  before  the  event:  

• ER  to  NR  export  was  2585  MW  • WR  to  NR  export  was  2862  MW  • Grid  frequency  was  49.68  Hz  A  large  number  of  lines  were  out  of  service  parJcularly  near  WR-­‐NR  interface  before  the  outage.  The  system  was  in  an  insecure  condiJon  

InstrucJons  from  NR  load  dispatch  center  to  shed  loads  were  neglected  by  states  in  NR  

Page 7: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Blackout-­‐1:  Sequence  of  Events  

http://www.thehindu.com/news/national/article3718641.ece http://www.nldc.in/Flasher/Flash%20Report_NLDC_region%20Disturbance%20in%20Northern%20Region_30072012_Revision1.pdf

Outaged  lines  before  the  event  (Red  line  is  a  double  ckt.)  

The  765  circuit    ‘2’(being  operated  at  400  kV)  between  Gwalior-­‐Agra  and    400  kV  Zerda-­‐Kankroli  were  down  before  the  event.    

• Gwalior-­‐Agra  ckt  ‘2’  was  on  planned  outage  since  28th  July  for  upgrade  to  765  kV.    • Zerda-­‐Kankroli  line  was  on  planned  outage  since  07/28  

Page 8: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Blackout  1  :  Sequence  of  events  Northern  states  over-­‐drawing  power  than  what  was  scheduled  (called  as  Unscheduled  Interchange).    

•  This  is  OK  and  allowed  under  Indian  electric  grid  code    •  Normally  done  when  there  is  surplus  of  power  available  from  the  gird  as  it  is  much  cheaper  than  power  from  local  Independent  Power  Producers  (IPPs)  

•  Operators  were  aware  of    overdrawing  of  power  by  the  states  but  had  no  authority  to  take  acJons  such  as  automaJc  tripping  of  the  loads.  

However,  this  resulted  in  tripping  of  Gwalior-­‐Agra  (ckt  1)  765  kV  line  which  was  being  operated  at  400  kV    

• Tripped  due  to  mis-­‐opera;on  on  zone  3  protec;on  due  to  heavy  loading  of  the  line  

• DFR  logs  did  not  indicate  any  faults  on  the  system  prior  to    the  line  trip  The  outage  of  the  Gwalior  -­‐  Agra  (  ckt  1)  caused  a  big  power  swing  in  NR-­‐ER  interface  which  eventually  led  to    cascading  events  •  Power  flow  from  WR  to  NR  started  to  re-­‐route  through  ER  which  resulted  in  tripping  of  other  400  kV  circuits  in  ER  

• Machines  in  NR  started  to  slow  down  as  compared  to  the  rest  of  the  NEW  grid  which  led  to  further  angular  separaJon  

•  UFLS  and  df/dt  protecJon  schemes  were  not  acJvated  in  NR  •  Primary  frequency  response  from  governors  was  disabled  

Page 9: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Blackout  1  –  Frequency  SeparaJon    Frequency  separaJon  between  WR  and  NR  aoer  the  event  

• Rise  in  frequency  in  WR  close  to  51  Hz  indicates  inadequate  primary  frequency  response  from  generators  

Page 10: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Blackout-­‐2:  Prior  System  CondiJons  

Again,  NR  was  imporJng  power  from  Western  and  Eastern  regions  

• ER  to  NR  export  was  1825  MW  • WR  to  NR  export  was  2100  MW  

A  large  number  of  lines  were  out  of  service  before  the  outage.  The  system  was  in  an  insecure  condiJon  

InstrucJons  from  NR  load  dispatch  center  to  shed  loads  were  neglected  by  states  in  NR  

Page 11: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Blackout  2  –  Sequence  of  Events  •  10  min.  prior  to  the  blackout,  two  220  kV  lines  connecJng  NR-­‐WR  were  

tripped  due  to  overload  due  to  tripping  of  a  250  MW  thermal  plant  

•  At  13:00  hrs,  Bina-­‐Gwalior  (ckt  1)  the  line  tripped  again  on  zone-­‐3  mis-­‐opera;on  due  to  overload  

•  This  led  to  angular  separaJon  between  ER  and  WR  and  isolated  WR  from  ER+NER+NR  

•  Not  adequate  relief  from  UFLS  and  df/dt  schemes  in  NR  and  ER  •     •  No  primary  frequency  response  from  governors  in  NEW  grid  

•  Cascade  tripping  of  lines  occurred  due  to  overvoltage,  power  swing,  zone-­‐3  protecJon.  Generators  were  tripped  on  under  frequency    –  This  iniJally  separated  NR  and  then  resulted  in  collapse  of  ER  and  NER  

Page 12: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Blackout  2  –  Frequency  SeparaJon  Frequency  separaJon  between  NR  and  rest  of  the  NEW  grid  

Page 13: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Recommenda;ons  and  Ac;ons  Taken  as  on  3rd  July  2013  (Source:  CEA  New  Delhi)    

CommiZee’s  Recommenda;ons   Ac;ons  Taken    Extensive  review/  audit  of  protecJon  system   ProtecJon  audit  in  all  regions  completed  

Frequency   Control   through   GeneraJon  reserves/Ancillary   services   and   review   of  present  UI  mechanism  

CERC   directed   for   the   formulaJon   of   drao  regulaJons   for   GeneraJon   Reserves/  Ancillary  Services  

Ensure  primary  response  from  generators     -­‐  CERC   re i te ra ted   the   need   fo r  compliance  by  generators    

-­‐  CERC   fixed   responsibility   for   non-­‐implementaJon   of   RGMO   /   FGMO  mode  of  operaJon  

-­‐  A   Task   Force   consJtuted   to   develop  procedure   for   tesJng   of   primary  response  of  generators  

Ensure   operaJon   of   defense   mechanisms,  like  UF  &  df/dt  based  load  shedding  

-­‐  All  STUs  are  directed  to  enable  UF  and  df/dt  based  load  shedding  immediately    

-­‐  High  level  logic  for  an  automated  conJngency  load  shedding  protocol  circulated  by  POSOCO  

Page 14: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

CommiZee’s  Recommenda;on   Ac;ons  Taken  Review   of   Total   Transfer   Capability   (TTC)  procedure  and  congesJon  charges  

-­‐  Real  Jme  security  desk  installed  in  NLDC  -­‐  In  case  of  planned  outages,  LDCs/  NLDC  

to  do  system  studies  using    PSS/E    for  revision  of  TTC    

Coordinated  outage  planning  of  transmission  elements  

NLDC  to  depute  its  representaJve  to  arend  monthly  OCC  meeJngs  in  all  the  five  RPCs  to  ensure  proper  implementaJon  of  this  provision,  for  inter-­‐regional  lines.    

  InstallaJon  of   adequate   staJc   and  dynamic  reacJve  power  compensators  

-­‐  Standing  Commiree  on  Transmission  Planning  approved  InstallaJon  of  fixed  Reactors  of  the  concerned  Regions  

-­‐  Further  study  on  dynamic  reacJve  compensaJon  is  in  progress  by  CTU  and  POSOCO  in  consultaJon  with  CEA  

Review  of   penal   provisions   of   the   Electricity  Act,   2003   to   ensure   berer   compliance   of  instrucJons  of  LDCs  and  Central  Commission  

Under  consideraJon  of  Ministry  of  Power  

Page 15: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

CommiZee’s  Recommenda;on   Ac;ons  Taken  OpJmal  uJlizaJon  of  available  assets  such  as  HVDC,  TCSC,  SVC  controls  

-­‐  Stability  features  of  Rihand-­‐Dadri  HVDC  and  Pasauli  HVDC  has  been  enabled  

-­‐  TCSCs  installed  at  Gorakhpur,  Purnea  and  Raipur  are  funcJonal.  

-­‐  PSS  tuning  for  generators  is  done  Employment  of  Synchrophasor  based  WAMS  for   real   Jme   monitoring,   protecJon   and  control  of  the  system  

Unified  Real  Time  Dynamic  State  Measurement  (URTDSM)  system  with  large  scale  deployment  of  PMUs  is  proposed  

Dynamic   Security   Assessment   and   faster  State   EsJmaJon   tools   at   Load   Dispatch  Centers  

-­‐  Present  system  does  not  have  dynamic  security  assessment  capability.    

-­‐  New  systems  are  being  developed  /  planned  for  the  future.    

Islanding  schemes  for  faster  recovery  in  case  of  grid  disrupJons    

Region  wise  Islanding  scheme  –  North  -­‐  under  implementaJon  West  -­‐  operaJonal  South  -­‐  To  be  implemented  by  Aug,  2013  East  -­‐  Under  feasibility  study  North  East  -­‐  Under  feasibility  study  

Page 16: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

CommiZee’s  Recommenda;on   Ac;ons  Taken  More   autonomy   to   all   the   Load   Dispatch  Centers   in   taking   and   implemenJng  decisions   relaJng   to   operaJon   and   security  of  the  grid  

-­‐  States  to  iniJate  acJon  on  strengthening  of  SLDCs  

-­‐  IncenJve  scheme  for  System  Operators  -­‐  Training  of  system  operators  iniJated  

planning   and   investment   to   avoid  congesJon   in   intra-­‐State   transmission  system  

SLDCs  to  provide  inputs  to  the  respecJve  STUs  for  berer  planning  /  strengthening  of  intra-­‐state  transmission  system  

Proper   telemetry   and   communicaJon   to  Load  Dispatch  Centers  

-­‐  Fiber  OpJc  link  implementaJon  with  STUs  through  RPCs  for  communicaJon    

-­‐  The  status  of  the  availability  of  Telemetry  from  various  staJons  is  being  monitored  closely  by  the  RLDCs/NLDC.    

Shortening   of   startup   Jme   of   generaJng  staJons  

CEA,  POSOCO,  NTPC  &  NRPC  examined  delay  in  extension  of  start-­‐up  power  to  thermal  power  staJons,  and  suggesJons  have  been  made  to  accelerate  the  process.    AcJon  plan  circulated  to  all  Generators  in  NR  for  implementaJon.  

Page 17: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

CommiZee’s  Recommenda;on   Ac;ons  Taken  review  transmission  planning  criteria  in  view  of  the  growing  complexity  of  the  system      

Review  of  transmission  planning  criteria  has  been  implemented  by  the  CEA  and  has  been  put  on  the  website.    

Strengthening  of  system  study  groups   -­‐  CTU  has  procured  system  study  sooware  for  distribuJng  to  various  uJliJes.    

-­‐  First  phase  of  training  program  on  system  studies  has  been  done.  

FormaJon  of  separate  task  force  to  carry  out  a   detailed   analysis   of   the   present   grid   to  avoid  future  disturbances    

-­‐  The  Task  Force  has  been  consJtuted,  It  has  iniJated  the  study  on  present  grid  condiJons  and  anJcipated  scenarios.    

-­‐  Relay  coordinaJon  and  general  philosophy  on  islanding  scheme  is  also  under  study.  

Page 18: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Challenges in Improving Long-term Reliability of the Indian Grid

 •  Inadequate  coordinaJon  in  planning,  operaJon  &  maintenance  

•  Investments  in  T&D  not  in  same  proporJons  as  in  generaJon  •  Lack  of  Grid  Discipline  and  lack  of  adherence  to  grid  protocols  •  Lack  of  transparency  and  red  tape  •  Overlapping  governance  by  a  number  of  ministries,  

departments,  and  states  •  DifficulJes  in  revenue  recovery  

IEEE  Boise,  Nov  16,  2012  

18  

Page 19: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

Acknowledgement    •  We  would  like  to  thank  the  EPRI  personnel:  

–  Arshad  Mansoor,  Sr.  VP,  R&D,  EPRI  – Mark  McGranaghan,  VP,  Power  Delivery  &  UJlizaJon,  EPRI    –  Daniel  Brooks,  Sr.  Program  Manager,  Grid  OperaJons  and  Planning,  EPRI  

–  Karen  Forsten,  Director,  Grid  OperaJons  and  Planning,  EPRI  

•  Central  Electricity  Authority  (CEA)  New  Delhi,  Study  Task  Force  Members  and  Power  System  OperaJon  CorporaJon  Ltd.  (POSOCO)  New  Delhi    

IEEE  Boise,  Nov  16,  2012  

19  

Page 20: Indian&Blackouts/&July&30&&&31,&2012& … · Outline! • Impactof!the!two!Indian!blackouts! – th30 !July,!2012!at2:35!AMIndian!Standard!Time! (IST)! – st31 !July,!2012!at1!PMIST!

IEEE  Boise,  Nov  16,  2012  

20