Upload
trankhue
View
237
Download
4
Embed Size (px)
Citation preview
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 1 of 20
INDIAN RAILWAYS
PARTICULAR SPECIFICATION
FOR
BOGIE LIGHT WEIGHT POL TANK WAGON
TYPE ‘BTFLN’
BROAD GAUGE – 1676 mm
ISSUED BY
WAGON DIRECTORATE
RESEARCH DESIGNS AND STANDERDS ORGANISATION MINISTRY OF RAILWAYS
LUCKNOW – 226011
May, 2017 Price: Rs.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 2 of 20
CONTENTS Clause Description Page No. 1. Scope 3 2. Definitions 3 3. General Description of the Wagon 4 4. Welding 4 5. Test Requirements 5 6. Standard Specification 5 7. Use of Alternative 5 8. Particular Requirements 5 9. Testing of Tank barrel, Valves and wagon 11 10. Guarantee 12 11. Painting & Markings 13 12. Inspection 13 13. Dispute regarding Interpretation 13 14. Drawings 14 15. As Made Drawings 14 16. Photographs & Models 14
ANNEXURES I Method of Determining tare weight of wagon II Procedure of Calibration III Nylon 66 Bushes in the Hand Brake Gear of Wagon
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 3 of 20
Particular Specification for Broad Gauge
Bogie Light Weight POL Tank Wagon type ‘BTFLN’ Fitted With Bogie Mounted Air Brake System
1. SCOPE 1.1 This specification covers the particular requirements for the manufacture and
supply of Broad Gauge Bogie light weight POL Tank Wagon type ‘BTFLN’ (81.28 t. Gross Load) fitted with bogie mounted air brake system and bogie strictly to relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration) and the requirements of General Standard Specification No. G-72 with latest revision and amendments if any, which can be had from Director General, RDSO, Lucknow-226011. These wagons shall be supplied complete in all respects.
1.2 Bogie, Coupler and Draft Gear as referred to in Clause 8.3 and 8.4 and Air brake
equipment along with pipes and pipe joints as referred to in Clause 8.5 shall be fitted with these wagons.
1.3 The Contractor shall prepare his own working drawings based on the aforesaid key design drawings and submit them to the ‘Engineers’ for approval before undertaking construction. The Contractor shall ensure that working drawings submitted for approval of the ‘Engineers’ are fully in accordance with key design drawings and deviations, if any, are specially pointed out. Approval of the ‘Engineers’ will only pertain to the design features, important controlling dimensions and the deviations from the design drawings specially pointed out by the Contractor. Correctness of the details in drawings will not be checked by the ‘Engineers’ and the responsibility for the same will be that of Contractor.
2. DEFINITIONS 2.1 ‘Purchaser’ means the President of Republic of India. 2.2 ‘Engineers’ means Research, Designs & Standards Organization, Ministry of
Railways, Manak Nagar, Lucknow-226 011 2.3 ‘Inspecting Officer’ means the person, firm or department nominated by the
Purchaser to inspect the work on his behalf and the deputies of the Inspecting Officer so nominated.
2.4 ‘Contractor’ means the person, firm or company with which the order for the
supply is placed and shall be deemed to include the Contractor’s successors (approved by the Purchaser), representatives, heirs, executors and administrators, as the case may be unless excluded by the terms of the Contract.
2.5 ‘Sub-Contractor’ means the person, firm or company from whom the Contractor
may obtain any material or fittings to be used in the manufacture of the above parts.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 4 of 20
3. GENERAL DESCRIPTION OF THE WAGON 3.1 The profile of the wagon infringes with the Maximum Moving Dimensions of 1929,
but remains within the dimensions of ‘X-class’ engine. Structurally, it comprises of a cylindrical tank barrel mounted on under frame. The assembly is rested on a pair of bogies for mobility. The under frame consists of a pair of stub center sill, side sills, bolsters, head stocks, and cradles. The center sill and side sills run from the headstock upto bolster at either end. Between bolsters there is no under frame member except a pair of middle stringers (inverted T-section) welded to the underside of the barrel. This design of under frame results in substantial saving in tare weight.
3.2 The tank barrel is inclined at 1 degree towards the discharge points located at the
bottom of the barrel to facilitate easy flow of POL products. The discharge points are provided with taper plug valves.
3.3 There are two domes on the top of barrel for loading. Each dome carries a filling
pipe, vapour extractor cock, the dip stick guide pipe and hand wheel for operation of the master valve. The barrel carries one safety valve on the top.
3.4 The wagon is fitted with Bogie mounted brake system in which each bogie carries
a brake cylinder which applies tread brake in the bogie through brake beams and push rods. The brake cylinder has a built-in double acting slack adjuster to take up wear in K-type brake shoes and partially wear on wheels.
4. WELDING 4.1 The welding of tank barrel, testing and certification should be strictly as detailed in
Clause No. 8.6. 4.2 Welding of wagon parts other than tank barrel should be strictly as specified in
Clause 8 of General Standard Specification No. G-72 with latest revision and amendments if any.
4.3 Wherever welding is specified or adopted in the manufacture of the wagons or in
the fabrication of sub-assemblies and components, the manufacturer shall submit his proposed welding procedure and sequence to the Inspecting Officer for approval. This, however, will not in any way reduce the Contractor’s responsibility for satisfactory execution of the Contract in all respects as stipulated in “Standard Conditions of Contract for Construction, Supply and Delivery of Underframes and Goods Wagons” as stipulated in Clause 4 of General Standard Specification No.G-72 with latest revision and amendments if any.
5. TEST REQUIREMENTS
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 5 of 20
5.1 First wagon to be completed by the Contractor will be treated as Pattern Wagon. Tank barrel to be tested and certified as given in 8.6 and other tests as mentioned in Clause 9.
5.2 The performance of Air Brake equipment for each wagon shall be tested by
means of single car test rig. 6. STANDARD SPECIFICATION
All material required for the manufacture of the wagons shall conform to the latest issue of relevant specifications as adopted by RDSO for Railway use unless otherwise specified herein.
7. USE OF ALTERNATIVES
Certain alternatives, showing different method of manufacture or use of alternative material, which are technically permissible, have been indicated in the relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration). Whenever such alternative use has been permitted, the tenderer must quote separately for the alternatives.
8. PARTICULAR REQUIREMENTS 8.1 Leading Particulars of the BTFLN Wagon are given in relevant drawings outlined
in Index Drg. No RSD-6315-051 (latest alteration). 8.1.1 Barrel Mounting
The details of barrel mountings are given in relevant drawings outlined in Index Drg. No RSD-6315-051 (latest alteration).
8.1.2 BTFLN wagon shall be capable of transporting the products listed in relevant
drawings outlined in Index Drg. No RSD-6315-051 (latest alteration).
8.1.3 Loading and Unloading
Top loading through the filling pipes accommodated in the domes and unloading
through the discharge valves fitted at the bottom of the barrel.
8.2 Material of Construction
The materials of construction of BTFLN wagon are listed in relevant drawings
outlined in Index Drg. No RSD-6315-051 (latest alteration).
8.3 Bogies and Wheels
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 6 of 20
The wagon shall be equipped with Cast Steel BG Bogies as per RDSO
Specification with latest revision and amendments as indicated in relevant
drawings outlined in Index Drg. No RSD-6315-051 (latest alteration). This bogie
shall be complete with wheel sets, cartridge bearings, narrow jaw adapters, spring
plank, long travel helical springs, and load proportionate friction damping
arrangement suitable for 20.32 t axle load.
8.4 Draft and Buffing Gear 8.4.1 The BTFLN wagon shall be equipped with High Tensile Centre Buffer Coupler
(Non-Transition CBC) to RDSO Specification with latest revision and amendments as mentioned in relevant drawings outlined in Index Drg. No RSD-6315-051 (latest alteration).
The fitment of coupler, draft gear, striker casting, yoke, yoke pin support and back stop shall conform to relevant drawings outlined in Index Drg. No RSD-6315-051 (latest alteration).
8.4.2 Coupler operating mechanism shall be positioned as shown in relevant drawings
outlined in Index Drg. No RSD-6315-051 (latest alteration).
8.5 Air Brake 8.5.1 The wagon shall be equipped with graduated release air brake equipment to
RDSO Specification with latest revision and amendments in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration.
8.5.2 The air brake equipment and pipe layout of the wagon shall be in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration.
8.5.3 The pipes and pipe joints consisting of brake pipe, feed pipe, branch pipes and
pipe joints shall be as specified in RDSO Specification with latest revision and amendment in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration.
8.5.4 The complete air brake equipment including the pipes and joints shall be fitted on pattern wagon in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration and offered to the ‘Engineers’ for approval. Before fitment of pipes on wagons, inside of pipes shall be cleaned thoroughly by dry compressed air to remove dirt, dust etc. The Contractor shall be obliged to carry out any modification on the layout of the air brake equipment, if found necessary by the ‘Engineers’.
8.5.5 Contractor shall proceed with the bulk production of pipe and joints only after the
final approval of the layout of complete air brake equipment, on the pattern wagon.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 7 of 20
8.5.6 During the bulk production of wagons, Contractor shall ensure that the complete air brake equipment is fitted on the wagon correctly as per the dimensions shown in the layout drawing. Special care must be taken with regard to the clamping of pipes.
8.5.7 The wagon shall be fitted with hand brake gear arrangement in accordance to
relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration. The Contractor shall also ensure correct functioning of the brake gear components in conjunction with air brake equipment. Only Nylon 66 bushes in lieu of steel bushes wherever indicated in the drawing of Hand Brake Arrangement to be provided as per details given in Annexure-III.
8.5.8 The wagon shall be fitted with side operated screw type hand brake as indicated
in relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration. 8.6 Tank Barrel 8.6.1 Tank barrel shall be of seven-course construction in accordance to relevant
drawings outlined in Index Drg. No. RSD-6315-051 latest alteration. Any deviation should have the prior approval of the ‘Engineers’.
8.6.2 Circumferential and longitudinal seams as shown in relevant drawings outlined in
Index Drg. No. RSD-6315-051 latest alteration shall be done by automatic submerged arc welding.
8.6.3 Manufacture and Workmanship: The manufacture and workmanship shall
conform to the requirements of Section II of IS: 2825 (Code for Unfired Pressure Vessels) to latest revision and amendments.
8.6.4 Welding of Barrel: Welding shall conform strictly to the requirements laid down in
Section II of IS: 2825 (Code for Unfired Pressure Vessels) with latest revision and amendments. Mechanical tests of fusions, welded seams shall also conform strictly to the requirements laid down in Section III of IS: 2825 to latest revision and amendments. The electrodes used for welding purposes should have physical properties equivalent to or better than the parent metal.
8.6.5 Inspection & Test of Tank Barrel: Inspection, test and repairs to all welded
joints shall conform to the requirements laid down in Section II of IS: 2825 to latest revision and amendments. In case, the tank barrel and the underframe are manufactured in the same place the tank barrel after placement on the underframe and being anchored shall be subjected to hydraulic test. In case, the tank barrel is manufactured away from the shop making the under frame and the tank has to be transported, the barrel shall be first hydraulically tested at the barrel manufacturer’s premises. A second hydraulic test shall be carried out after assembly of the barrel with the under fame.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 8 of 20
8.6.6 The procedure and sequence of welding and assembly of barrel should have the prior approval of the ‘Engineers’.
8.6.7 Dished ends having any sign of crack shall be rejected. Repair by welding on the
dished ends are not permissible. 8.6.8 Certification pertaining to Tank Barrel: Certification and record pertaining to
tank barrel should be as stipulated in Section III of IS: 2825 (latest revision and amendments). The manufacturer shall furnish a certificate of manufacture and production tests generally in the format given at Annexure-II of IS: 2825. In addition, the format should include the certification of the provisions of this specification also. The barrel shall be tested & certified by the Inspecting Officer. The scope of work of the Inspecting Officer is as under:
Certification of material. Certification that fabrication of barrel is as per IS: 2825. Certification of hydrostatic & air tests as called for in this specification. Certification of functioning of all the dome fittings. Certification as to the proper mounting of the barrel on the underframe. Certification & approval of the drawings submitted by the manufacturer. Any
deviation from design drawings can be approved only with the concurrence of the ‘Engineers’.
8.6.9 After receiving the certification papers pertaining to barrel and its mounting over
the underframe, Engineers or any other agency approved by the Engineers will finally inspect the wagon and certify the following aspects of the wagons:
There is no visual abnormality. The wagon is generally fit to run. All the underframe components are in position and in working order. Buffer heights of the wagon are within the prescribed limits. Height of the wagon is within the prescribed limits. The painted surface of the barrel has reasonable reflecting characteristics &
the markings are strictly in accordance with the marking diagram. 8.6.10 Welds inside the barrel shall be ground flush after welding. 8.6.11 All valves and mountings shall be procured by the contractor and subjected to
bench test separately before fitment. 8.6.12 The barrel shall be fitted with the following valves and accessories:
2 Nos. of 100 mm dia filling pipe with its attachments to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration.
2 Nos. of 25 mm dia dip reading pipe with its attachments to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 9 of 20
2 Nos. of vapour extractor cocks to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration.
1 No. safety valve to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration.
2 Nos. of master valve as per relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration) complete with spindle and operating hand wheel.
2 Nos. of lubricated taper plug valve for bottom discharge generally to RDSO Particular Specification with latest revision and amendment as mentioned in relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration. The valves should be procured only from RDSO approved suppliers.
8.6.13 Tolerances on dimensions of the tank barrel shall be as under:
1 Length of barrel measured over the centers of two dished ends.
+ 10 mm - 3 mm
2 Circumferential length The external circumference of the completed barrel shall not depart from the calculated circumference based upon nominal inside diameter and the actual thickness by ± 0.25% of the outside diameter for barrels having over 600 mm outside dia.
3 Ovality or “out of roundness” The difference between max. and minimum diameter at any cross section of the barrel shall be within 1% of the nominal internal diameter with a maximum limit of- (Inside diameter+ 1250)/200
4 Irregularities in profile When checked by 20 degree gauge, the irregularities in profile shall not exceed 3 mm plus 5% of the minimum plate thickness. The maximum value may be increased by 25% if the length of irregularity does not exceed one quarter of the length of the barrel ring, with a maximum of 1000 mm.
5 Inside diameter of manhole ± 2.0 mm
6 Height of dome ± 2.5 mm
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 10 of 20
8.6.14 Each dished end of the barrel shall be made in two pieces welded together as shown in relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration. Joining of the two pieces by welding should be done before dishing. After dishing, 100% radiographic examination of the welding joint should be done to ensure that no defect has crept in during the process of dishing.
8.6.15 Each dome of the barrel shall be provided with a rubber sealing ring as shown in
relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration. The ring shall be fitted in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 latest alteration. .
8.7 Underframe and Cradles 8.7.1 The under frame is of all welded construction and shall be in accordance to
relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration) and cradle shall be in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration).
8.7.2 The procedure and sequence of welding and assembly should have the prior approval of the ‘Engineers’.
8.8 Platform and Ladder
Platform & ladder shall be in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration).
8.9 Welding (other than Barrel) 8.9.1 General requirements and comprehensive guidance with regard to fit up for
welding, welding procedure and inspection of welded joints shall be in accordance with instructions contained in Tech. Pamphlet No.G-72 (latest revision with amendments) issued by RDSO. These shall be strictly followed.
8.9.2 Wherever welding is specified or adopted in the manufacture of the wagons or in
the fabrication of the sub-assemblies and components, the Contractor shall submit his proposed welding procedure and sequence to the ‘Engineers’ as well as to the ‘Inspection Officer’ for their prior approval. This, however, will not, in any way, reduce the Contractor’s responsibility for satisfactory execution of the contract in all respects.
8.9.3 Three copies of welding procedure and sequence of assembly of the wagon finally
approved by the ‘Inspecting officer’ shall be furnished to the ‘Engineers’ by the Contractor before commencement of regular production.
9. TESTING OF TANK BARREL, VALVES AND WAGON 9.1 Hydraulic Test of Barrel
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 11 of 20
The barrel complete with internal fittings including master valve and bottom discharge valve after being mounted on the under frame shall be tested hydrostatically to pressure of 2.8 kg/cm2 against leakage of longitudinal and circumferential weld seams of the barrel. The joints should not show any sign of leakage when the pressure is maintained for 30 minutes. Caulking to prevent/close the leakage is prohibited. Openings of domes and safety valve shall be closed by dummy flanges during hydraulic test. Water for the test shall preferably be free of dissolved chlorine.
9.2 Pneumatic Test of Barrel Mountings
The barrel shall be mounted on and anchored to the under frame and all barrel fittings shall be mounted on the barrel before the pneumatic test. The pressure inside the barrel shall gradually be increased to 1.2 kg/cm2 and the same pressure will be maintained for sufficient length of time to enable a thorough examination to be made against leakage at all the flange joints of the valves and accessories. The pneumatic test can be carried out by filling the entire barrel with air and the pressure raised to the required value. Alternatively, after the hydraulic test, the fittings can be mounted on the barrel and the barrel drained partially leaving 10% empty space and pneumatic pressure built up to the required value in the empty space.
9.3 Master Valve of Barrel 9.3.1 Master valve shall be tested in assembled position against leakage in the
following sequence of operations:
Close the master valve tightly. Fill the barrel with water upto a height of 1 metre. Operate the valve 10 times in quick succession and finally close it.
There should not be any leakage at the bottom opening of the valve.
9.4 Discharge Valve
Discharge valve shall also be tested in assembled position against leakage.
9.5 Load testing of Wagon
9.5.1 Before proceeding with the regular production of wagon, the pattern wagon shall
be fabricated and offered for inspection and load testing in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration). The wagon shall be inspected and tested for load deflection under gross load and also with 25% overload. Clearances found between the various members of the under frame and the bogies shall be measured under tare, fully loaded, 25% overload
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 12 of 20
and unloaded conditions at various locations. The report of the tests shall be submitted to the ‘Engineers’ through Inspecting Officer.
9.5.2 Any other tests to be conducted on the pattern wagons shall be decided by the
Inspecting Officer in consultation with the Engineers.
9.5.3 Any modifications that may be called for as a result of these tests and inspections, will have to be made free of cost by the Contractor during the bulk production of wagons
9.6 Calibration 9.6.1 Preparation of Calibration Chart
20% of the total no. of tank wagons ordered shall be physically calibrated and calibration chart prepared by the Contractor in their premises as per procedure outlined in ANNEXURE-II as accepted by the Chairman, Calibration Committee. The carrying capacities both in tonnes and litres alongwith corresponding dip height for the commodities given in the following table shall also be incorporated in the calibration chart.
TABLE
S. No. Name of Commodity
1. Motor Sprit (Petrol)
2. Naphtha
3. Superior Kerosene
4. ATF
5. HSD
6. LDO
7. FO
The work of calibration shall be witnessed and certified by Inspecting Officer.
10. GUARANTEE
Tank barrels supplied in conformity with this specification shall be guaranteed against defects of workmanship and materials for a period of 18 months from the date of dispatch of the tank wagon or for a period of 12 months from the date of their being put into service.
11. PAINTING AND MARKINGS 11.1 Painting
The surface preparation and painting of wagons shall be as stipulated in General Standard Specification No. G-72 with latest revision and amendments if any.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 13 of 20
11.2 Marking 11.2.1 Markings shall be done in accordance to relevant drawings outlined in Index Drg.
No. RSD-6315-051 (latest alteration). 11.2.2 The tare weight of the wagon shall be marked in tonnes up to one decimal place
as determined by method detailed in ANNEXURE I. 11.2.3 The direction of operation of hand brake wheel shall be marked as ‘ON’ and ‘OFF’
as indicated in relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration).
11.2.4 Cast iron standard plates shall be screwed on to the underframe sole bars at
diagonally opposite corners as shown in relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration). One plate on each underframe shall be in English and the other shall be in Hindi. Mild steel drop stamped standard plate is acceptable as an alternative.
11.2.5 Railways initials to be marked will be intimated later. The mechanical code
‘BTFLN’ is to be stenciled and stamped at locations shown in relevant drawings
outlined in Index Drg. No. RSD-6315-051 (latest alteration).
12. INSPECTION
The inspection of the wagon with all its fittings is to be carried out by RDSO, Wagon Inspection Wing. The wagon manufacturer will provide all the facilities to the Inspecting Officer.
13. DISPUTE REGARDING INTERPRETATION
In case of dispute between the manufacturer and the purchaser regarding the interpretation of any clause/clauses of this specification, the decisions of the ‘Engineers’ will be final and binding on both the parties.
14. DRAWINGS
The wagons shall be manufactured strictly in accordance to relevant drawings outlined in Index Drg. No. RSD-6315-051 (latest alteration). The alteration number against each drawing are, however, subject to advancement in course of construction of these wagons and the contractor shall comply with these amendments in manufacturing of components. The detailed design drawings can be had from Director General (Wagon), Manak Nagar, RDSO, Lucknow. Copies of such amended drawings will be supplied to the Contractor free of cost. The
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 14 of 20
drawings listed are complete in all respects and any detailing, if necessary, will be done by the Contractor.
15. ‘AS MADE’ DRAWINGS 15.1 The contractor shall supply two sets of ‘As Made’ Polyster film tracings (50 micron
thick matte) of each drawing of the complete set of drawings followed in the manufacture of the wagon to the ‘Engineers’ for their record. The diagram shall indicate the leading particulars, overall dimensions and salient features.
15.2 The contractor shall incorporate in the above set of tracings of ‘As Made’ drawings
any deviations, modifications and relaxations granted in the course of manufacture of wagons.
15.3 ‘As Made’ drawings detailed above shall contain full details of each component/
sub-assembly/assembly inclusive of material specification, actual average weight and reference drawings. The general order of the drawings title block etc. shall be strictly as indicated in RDSO’s Drg. No. SK.67521 with space for Drg. Number. The size of the sheet shall be A-1 (841 mm x 594 mm) and the Code of Practice for Drawing shall conform to IS Specification No. 696.
16. PHOTOGRAPHS AND MODELS 16.1 The Contractor shall furnish free of cost the following negatives and photos of the
assembled wagon to the Purchaser/Engineer: 16.1.1 Two copies of the coloured negatives. 16.1.2 Two copies of the black and white negatives. 16.1.3 Three enlarged photographs – prints in colour (size 60 cm x 45 cm). 16.1.4 Three enlarged photographs in black & white (size 25.4 cm x 30.5 cm). 16.1.5 Any other photographs of the wagon as desired by the Purchaser/Engineer. 16.2 One 1/16-scale model made out of sheet steel or as indicated by the
Purchaser/Engineer. ***************************
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 15 of 20
ANNEXURE-I
METHOD OF DETERMINING THE TARE WEIGHT OF WAGONS All contractors will arrange to weight each wagon. Tare weight of the wagon shall also be intimated to ‘Engineers’ duly certified by the Inspecting officer.
Payload of the wagon would be fixed as given on its ‘Diagram/ Drawing’.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 16 of 20
ANNEXURE-II
Procedure of Calibration Start filling the tank wagon with water from a tank with a static head through a reliable calibrated bulk-meter. The quantity of water shall gradually be increased in the following steps till it is filled up to brim and corresponding dip-height in nearest millimeters against different volumes of water in litres shall be recorded in a register to be maintained by the Contractor.
DIP READINGS TO BE TAKEN FROM BOTH DIP-HOLES
Quantity Steps Steps of No. of Steps
250 to 500 Litres 250 Litres* 2
500 to 1000 ,, 500 ,, 1
1000 to 5000 ,, 1000 ,, 4
5000 to 10000 ,, 5000 ,, 1
10000 to 50000 ,, 10000 ,, 4
50000 to 60000 ,, 5000 ,, 2
60000 to 61000 ,, 1000 ,, 1
61000 to 61500 ,, 500 ,, 1
61500 to up to Brim ,, 250 ,, As per actuals
*First two steps dips to e taken from dip hole and also from fill pipe. The volume of water contained in the tank when filling up to brim shall also be noted. Calibration Chart
The chart shall be drawn up using the readings recorded in the register mentioned above. The maximum carrying capacity in litres shall be worked out by deducting minimum prescribed air space of the full volume capacity of the barrel. This maximum carrying capacity divided by conversion factor of the particular commodity will give the carrying capacity in tonnes provided the figure so obtained does not exceed the max. carrying capacity/max. payload in tonnes of the wagon. Maximum pay load in tonnes shall be obtained by deducting the average tare weight from the max. permissible gross load. However, if it exceeds the max. payload, the max. payload itself is to be taken as carrying capacity in tonnes and the corresponding carrying capacity in litres shall be worked back by multiplying this value by the conversion factors in litres/tonne of the commodity.
The dip heights corresponding to the carrying capacity in mm for the various commodities listed in the clause 9.6.1 shall be arrived at from the table of dip height against various volumes in litres (Interpolation of reading may be resorted to if necessary). The calibration chart shall thus be prepared as per sample chart attached herewith.
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 17 of 20
SAMPLE CALIBRATION CHART Dip (mm) Volume (lit.) Dip (mm) Volume (lit.) Dip (mm) Volume (lit.)
10 24 440 6931 870 18542
20 68 450 7163 880 18843
30 125 460 7398 890 19145
40 193 470 7634 900 19448
50 269 480 7873 910 19752
60 354 490 8114 920 20058
70 447 500 8357 930 20364
80 546 510 8602 940 20671
90 652 520 8849 950 20979
100 763 530 9098 960 21288
110 881 540 9349 970 21598
120 1004 550 9602 980 21909
130 1132 560 9857 990 22220
140 1264 570 10114 1000 22533
150 1402 580 10373 1010 22846
160 1544 590 10633 1020 23160
170 1691 600 10895 1030 23475
180 1842 610 11159 1040 23791
190 1996 620 11424 1050 24108
200 2155 630 11692 1060 24425
210 2318 640 11960 1070 24743
220 2484 650 12231 1080 25061
230 2655 660 12503 1090 25380
240 2828 670 12777 1100 25700
250 3005 680 13052 1110 26021
260 3186 690 13329 1120 26342
270 3369 700 13607 1130 26664
280 3556 710 13886 1140 26986
290 3746 720 14168 1150 27309
300 3939 730 14450 1160 27633
310 4135 740 14734 1170 27957
320 4334 750 15019 1180 28281
330 4536 760 15306 1190 28606
340 4741 770 15594 1200 28932
350 4949 780 15883 1210 29258
360 5159 790 16174 1220 29584
370 5371 800 16466 1230 29911
380 5587 810 16759 1240 30239
390 5805 820 17053 1250 30566
400 6025 830 17348 1260 30894
410 6248 840 17645 1270 31223
420 6473 850 17943 1280 31552
430 6701 860 18242 1290 31881
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 18 of 20
Dip (mm) Volume (lit.) Dip (mm) Volume (lit.) Dip (mm) Volume (lit.)
1300 32210 1750 47082 2200 60995
1310 32540 1760 47408 2210 61280
1320 32870 1770 47733 2220 61564
1330 33200 1780 48057 2230 61847
1340 33530 1790 48381 2240 62128
1350 33861 1800 48705 2250 62407
1360 34192 1810 49028 2260 62686
1370 34523 1820 49350 2270 62962
1380 34854 1830 49672 2280 63238
1390 35186 1840 49993 2290 63511
1400 35517 1850 50314 2300 63783
1410 35849 1860 50634 2310 64054
1420 36181 1870 50953 2320 64323
1430 36513 1880 51272 2330 64590
1440 36845 1890 51590 2340 64855
1450 37177 1900 51907 2350 65119
1460 37509 1910 52223 2360 65381
1470 37841 1920 52539 2370 65642
1480 38173 1930 52854 2380 65900
1490 38505 1940 53168 2390 66157
1500 38837 1950 53481 2400 66412
1510 39169 1960 53794 2410 66665
1520 39501 1970 54105 2420 66916
1530 39833 1980 54416 2430 67165
1540 40165 1990 54726 2440 67412
1550 40497 2000 55035 2450 67657
1560 40828 2010 55343 2460 67900
1570 41160 2020 55650 2470 68141
1580 41491 2030 55957 2480 68380
1590 41822 2040 56262 2490 68617
1600 42153 2050 56566 2500 68851
1610 42484 2060 56869 2510 69083
1620 42814 2070 57171 2520 69313
1630 43145 2080 57472 2530 69541
1640 43475 2090 57772 2540 69766
1650 43804 2100 58071 2550 69989
1660 44134 2110 58369 2560 70210
1670 44463 2120 58666 2570 70427
1680 44791 2130 58961 2580 70643
1690 45120 2140 59255 2590 70856
1700 45448 2150 59549 2600 71066
1710 45776 2160 59840 2610 71273
1720 46103 2170 60131 2620 71478
1730 46430 2180 60420 2630 71680
1740 46756 2190 60708 2640 71879
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 19 of 20
Dip (mm) Volume (lit.)
2650 72075
2660 72268
2670 72458
2680 72645
2690 72829
2700 73009
2710 73186
2720 73360
2730 73530
2740 73696
2750 73859
2760 74018
2770 74173
2780 74323
2790 74470
2800 74612
2810 74750
2820 74883
2830 75011
2840 75133
2850 75251
2860 75363
2870 75468
2880 75567
2890 75600
2900 75745
2910 75822
2920 75889
2930 75946
2940 75990
2950 76014
WD-02-BTFLN-2017 (Superseded WD-01-BTFLN-2006)
Particular Specification for Bogie POL Tank Wagon Type BTFLN
Page 20 of 20
ANNEXURE-III
NYLON HAND BRAKE GEAR BUSHES IN THE HAND BRAKE GEAR ARRANGEMENT OF THE WAGON
1. Hand brake bushes of Nylon 66 shall be procured as per RDSO Specification with latest revision and amendments.
2. Nominal dimensions of Nylon 66 bushes to be used will be same as of steel bushes, inclusive of step sizes, outside diameter. However, the tolerances and the chamfering should be as per STR.
3. Undersized holes should be drilled initially in the fork type support brackets or fork
end of pull/push rods. These holes should be drilled together to the required size only after the assembly but before the Nylon bushes are fitted therein. This will ensure that the two holes are concentric and therefore, the pins passing through the bushes fitted therein will not tilt.
4. Steel pins used with Nylon 66 bushes shall be with fine finish machined on all
contact surfaces with the bush.
***********