About Us > Business > Pipelines >Projects under Implementation Projects under Implementation Print PARADIPRAIPURRANCHI PIPELINE Project Cost: Rs. 1793.00 crore Expected Commissioning: Project is delayed due to delay in receipt of Forest Clearance. 2nd stage Forest clearance for the project in Odisha received on 4.9.2013 and in Jharkhand on 8.10.2013. Tree cutting permissions in Odisha (10/14 Divisions and Jharkhand (2 Divisions) is awaited. Benefit: The proposed pipeline would ensure the evacuation of Paradip Refinery products and uninterrupted supply to major parts of Orissa, Chhattisgarh and Jharkhand. Brief Description: Project consists of laying of 1108 km long product pipeline with intermediate pumping stations at Jatni and New Sambalpur and delivery stations at Jatni, Jharsuguda, Ranchi, Raipur and Korba. The pipeline will be having a telescopic diameter of 18"/14"/12"/10" OD. AUGMENTATION OF PARADIPHALDIABARAUNI CRUDE OIL PIPELINE Project Cost: Rs. 586.00 crore Expected Commissioning: August, 2015 Benefit: The project would enhance the existing capacity from 11.0 MMTPA to 15.2 MMTPA Brief Description: The proposal envisages laying of 65 Km loopline and construction of 5 nos. of 60,000 KL tanks at Paradip and 1 tank of 40,000 KL capacity at Barauni. The project also envisages construction of one additional pumping station and providing additional pumping units at 3 locations. ENNORETRICHYMADURAI LPG PIPELINE Project Cost: Rs. 711.00 crore Expected Commissioning: 30 months after receipt of statutory clearances. Benefit: The proposed pipeline would ensure a safe, costeffective, environmentfriendly and uninterrupted transportation of LPG to the bottling plants at Chengalpet, Pondicherry, Trichy and Madurai. Brief Description: The proposal envisages laying of 10.75”/8.625” OD, 615 km long dedicated EnnoreTrichyMadurai Pipeline of 0.9 MMTPA capacity for transportation of LPG from Ennore LPG Import Terminal to the existing bottling plants of IOC at Chengalpet, Pondicherry, Trichy and Madurai. DEBOTTLENECKING OF SALAYAMATHURA CRUDE PIPELINE Project Cost: Rs. 1584.00 crore Expected Commissioning: 30 months after receipt of statutory clearances Benefit: With the proposed debottlenecking/augmentation of SMPL, the refineries would be in a position to process more crude oil. Brief Description: The proposal is for enhancing the capacity of SalayaViramgam section Screen Reader Access हद व बसाइट Color Themes Home Search

Indian Oil Corporation _ Projects Under Implementation

Embed Size (px)

DESCRIPTION

Projects under Implementation

Citation preview

  • 6/30/2015 IndianOilCorporation|ProjectsunderImplementation

    https://www.iocl.com/Aboutus/ProjectsunderImplementation.aspx 1/2

    AboutUs >Business >Pipelines >ProjectsunderImplementation

    ProjectsunderImplementation PrintPARADIPRAIPURRANCHIPIPELINE

    ProjectCost:Rs.1793.00croreExpectedCommissioning:Project isdelayeddue todelay in receiptofForestClearance.2ndstageForestclearancefortheprojectinOdishareceivedon4.9.2013andinJharkhandon 8.10.2013. Tree cutting permissions in Odisha (10/14 Divisions and Jharkhand (2Divisions)isawaited.Benefit:TheproposedpipelinewouldensuretheevacuationofParadipRefineryproductsanduninterruptedsupplytomajorpartsofOrissa,ChhattisgarhandJharkhand.Brief Description: Project consists of laying of 1108 km long product pipeline withintermediatepumpingstationsatJatniandNewSambalpuranddeliverystationsatJatni,Jharsuguda,Ranchi,RaipurandKorba.Thepipelinewillbehavingatelescopicdiameterof18"/14"/12"/10"OD.

    AUGMENTATIONOFPARADIPHALDIABARAUNICRUDEOILPIPELINE

    ProjectCost:Rs.586.00croreExpectedCommissioning:August,2015

    Benefit:Theprojectwouldenhancetheexistingcapacityfrom11.0MMTPAto15.2MMTPABriefDescription:Theproposalenvisages layingof65Km looplineandconstructionof5nos.of60,000KLtanksatParadipand1tankof40,000KLcapacityatBarauni.Theprojectalso envisages construction of one additional pumping station and providing additionalpumpingunitsat3locations.

    ENNORETRICHYMADURAILPGPIPELINE

    ProjectCost:Rs.711.00croreExpectedCommissioning:30monthsafterreceiptofstatutoryclearances.Benefit:The proposed pipeline would ensure a safe, costeffective, environmentfriendlyanduninterruptedtransportationofLPGtothebottlingplantsatChengalpet,Pondicherry,TrichyandMadurai.Brief Description: The proposal envisages laying of 10.75/8.625 OD, 615 km longdedicatedEnnoreTrichyMaduraiPipelineof0.9MMTPAcapacityfortransportationofLPGfrom Ennore LPG Import Terminal to the existing bottling plants of IOC at Chengalpet,Pondicherry,TrichyandMadurai.

    DEBOTTLENECKINGOFSALAYAMATHURACRUDEPIPELINE

    ProjectCost:Rs.1584.00croreExpectedCommissioning:30monthsafterreceiptofstatutoryclearancesBenefit:Withtheproposeddebottlenecking/augmentationofSMPL,therefinerieswouldbeinapositiontoprocessmorecrudeoil.BriefDescription:Theproposal is forenhancing thecapacityofSalayaViramgamsection

    ScreenReaderAccess

    ColorThemes

    Home Search

  • 6/30/2015 IndianOilCorporation|ProjectsunderImplementation

    https://www.iocl.com/Aboutus/ProjectsunderImplementation.aspx 2/2

    BriefDescription:Theproposal is forenhancing thecapacityofSalayaViramgamsectionfrom21MMTPAto25.0MMTPA,[ViramgamKoyalisectionfrom8.5MMTPAto9.0MMTPA,ViramgamChaksusectionfrom13.5MMTPAto16.5MMTPA,ChaksuMathurasectionfrom7.5MMTPAto9.2MMTPAandChaksuPanipatsectionfrom6MMTPAto7.3MMTPA].

    PARADIPHALDIADURGAPURLPGPIPELINE

    ProjectCost:Rs.913.00croreExpectedCommissioning:30monthsafterreceiptofstatutoryclearancesBenefit:The pipeline will facilitate costeffective transportation of LPG from Paradip andHaldiatotheLPGbottlingplantsatBalasore,BudgeBudge,Kalyani&Durgapur.

    BriefDescription:TheproposalenvisageslayingapipelinefortransportationofLPGfromParadip and Haldia to the LPG bottling plants at Balasore, Budge Budge, Kalyani &Durgapur.Totallengthofthepipelineisestimatedtobeabout700km.

    Ason20thMarch2014

    UpdatedonMarch20,2014

    Pipelines

    CrudeOilPipelines

    PetroleumProductPipelines

    ProjectsUnderImplementation

    WebDevelopmentbyPhiStreamConsultingPvtLtd

    VisitorssinceFebruary01,2012:61694998|Today'sHits:

    23000

    CopyrightIndianOilCorporationLtd.[Termsofuse|Privacypolicy|Sitemap]