Upload
lamlien
View
213
Download
0
Embed Size (px)
Citation preview
INDEX
S. N. Item No. Description Page No.
1. 5.1 Re-consideration of Old Proposals for Environmental Clearance.
2
2. 5.1.1 Application for environmental clearance of M/s Nahar Industrial Enterprises Ltd: Nahar Fabrics-II, Lalru, Tehsil Dera Bassi, Distt. Mohali – A 12 MW co-generation Project.
3
3. 5.1.2 Application for environmental clearance of M/s Lakshmi Energy and Foods Ltd., Khamanon, Distt. Fatehgarh Sahib – A Co-generation plant.
5
4. 5.1.3 Application for environmental clearance of M/s Gillanders Arbuthonot & Co. Ltd. (Textile Division), Vill. Akbarpur, Post Box. 1, Ahmedgarh, Distt. Sangrur – A co-generation plant.
10
5. 5.1.4 Application for environmental clearance of M/s JCT Ltd. Phagwara, Distt. Kapurthala – A 8 MW co-generation plant.
12
6. 5.2 Consideration of New Proposals for Environmental Clearance.
14
7. 5.2.1 Application for environmental clearance of M/s Universal Bio-Mass Energy Pvt. Ltd. at Vill. Channa, Tehsil Malout, Distt. Muktsar – A 14.5 M.W. Co-generation power plant.
15
8. 5.2.2 Application for environmental clearance of M/s Ajnala Co-operative Sugar Mills Ltd., Vill. Bhalla Pind, Tehsil Ajnala, Distt. Amritsar – A 12 MW bagasse based co-generation project
16
9. 5.2.3 Application for environmental clearance of M/s The Gurdaspur Co-operative Sugar Mills Ltd., Gurdaspur – A 10 MW bagasse based co-generation power plant
17
10. 5.2.4 Application for environmental clearance of M/s The
Budhewal Co-operative Sugar Mills Ltd., Ludhiana – A 8
MW bagasse based co-generation power plant.
18
11. 5.2.5 Application for environmental clearance of M/s The Morinda Co-operative Sugar Mill Ltd. Morinda - A 10 MW bagasse based co-generation power plant.
19
12. 5.2.6 Application for environmental clearance of M/s Punjab Bio-mass Power Ltd. at Vill. Baghaura, Tehsil Rajpura, Distt. Patiala – A 12 MW Bio-Mass based power project.
20
Item No. 5.1 Re-consideration of Old Proposals for Environmental Clearance.
Item No. 5.1.1 Application for environmental clearance of M/s Nahar Industrial Enterprises Ltd: Unit Nahar Fabrics-II, Lalru, Tehsil Dera Bassi, Distt. Mohali – A 12 MW Co-generation Project.
The application of the industry was placed before the Committee in its 3rd
meeting held on 24/3/2008 vide item No. 3.2 (copy attached as Annexure-I) (Page no. 21).
Please peruse.
Sh. H.N. Singhal, Corporate Manager and Sh. M.D. Sharma, Senior Manager
(Power Plant) made presentation on their project proposal for expansion of their existing
industry namely M/s Nahar Fabrics (Unit-II) by installing co-generation power plant of capacity
12 MW alongwith a boiler of 55 TPH at Lalru, Teh. Dera Bassi, Distt. Mohali. The estimated cost
of the project is Rs. 42.00 Crores and is likely to be commissioned in November 2008. They
informed that fresh water requirement for this project is 55 m3/hr. The coal will be used as fuel in
the proposed boiler and ESP will be installed as air pollution control device for control of air
pollution.
Dr. Babu Ram, Senior Environmental Engineer (Secretary, SEAC) informed
that as per report of Environmental Engineer, Punjab Pollution Control Board, Nodal
Office, Mohali, the site is located at an approx. distance of 7 km. from the Interstate
Boundary of Punjab and Haryana. As per the General Condition applicable in this case,
the project is to be treated as Category ‘A’ Project as the project site is located within 10
km. from the Interstate Boundary of Punjab and Haryana. Thus, this project is not in the
purview of State Expert Appraisal Committee.
Sh. H.N. Singhal, Representative of the project proponent submitted that
the project site is located beyond 10 km. from the Interstate Boundary and it appears that
the distance has not been measured accurately. He therefore, requested that this
distance should again be verified by the State Expert Appraisal Committee or Punjab
Pollution Control Board.
After discussion, it was decided that a Committee of the following three
officers may be constituted to reconfirm the distance of proposed site of the project from
the Interstate Boundary of Punjab and Haryana:
1. Er. Dev Raj Goyal, Environmental Engineer, PPCB.
2. Er. S.S. Matharu, Assistant Environmental Engineer, PPCB.
3. Tehsildar, Dera Bassi.
Accordingly, the abovesaid officers were requested vide letter no. 15192-94
dated 11/4/2008 to reconfirm the distance of proposed site of the project from the Interstate
Boundary of Punjab and Haryana.
The above said committee vide its letter no. 16995 dated 30/4/2008 (Copy of
Report enclosed as Annexure-V) has submitted a copy of the report of the team comprising
of Er. Dev Raj Goyal, Environmental Engineer, PPCB and Er. S.S. Matharu, Assistant
Environmental Engineer, PPCB. The Tehsildar, Dera Bassi could not be contacted on 23/4/2008
(date of visit) as he was busy in some urgent official work. At the time of visit, Sh. Naveen
Sharma, Vice President of the industry handed over a certificate issued by the Technical Officer,
Survey of India, which states as under :
1. Aerial distance as measured on topographical map on scale 1:50,000 based
upon indent / marked location as per given by the industry is as under :
Nahar Industrial Enterprises Ltd.,
Unit (Nahar Fabrics) 10.3 Km
to Jharmari Border
Distt. Mohali (Punjab)
2. SOI is not responsible for the correctness of the Survey point marked on map
and description and ownership of the property supplied by the industry. This
certificate is issued to the industry based upon their letter to enable it to apply for
Pollution Control Board, Patiala.
The Committee has concluded its report as under :
a) The team is unable to measure the shortest aerial distance of the site of the industry
from the nearest boundary of Haryana State physically due to number of obstructions /
hurdles in between the site and the State boundary. Moreover, to measure such
distance, equipments / infrastructure are required, which are not available with the
Board.
b) State Expert Appraisal Committee may place the certificate issued by the Technical
Officer, Survey of India before the Committee for consideration and deliberations.
The matter is again placed before the State Expert Appraisal Committee for
consideration.
Item No. 5.1.2 Application for environmental clearance of M/s Lakshmi Energy and Foods Ltd., Khamanon, Distt. Fatehgarh Sahib – A Co-generation plant.
The application of the promoter was placed before the Committee in its
3rd meeting held on 24/3/2008 vide item No. 3.4 (copy attached as Annexure-II) (Page no.
23). Please peruse.
Sh. G.S. Dhiman, President (Agri. Business) and Sh. Sanjay Gopi,
Representatives of the project proponent alongwith their consultants made presentation
on their project proposal for expansion of existing industry namely M/s Lakshmi Energy
and Foods Ltd., by installing bio-mass based co-generation power plant of capacity 2x15
MW at Khamanon, Distt. Fatehgarh Sahib. They informed that the estimated cost of the
project is Rs. 118.09 crores for thermal power plant. The industry has already obtained
NOC of Punjab Pollution Control Board vide no. 671 dated 20/11/2007 for 2x15 MW co-
generation power plant.
They further informed that the industry is already engaged in the manufacturing
of rice, rice bran solvent oil, refined rice, cattle feed and has proposal to expand manufacturing
capacity of existing products and to manufacture additional product wheat flour and also install
co-generation power plant. This application has been submitted to State Environment Impact
Assessment Authority for grant of environmental clearance for installation of co-generation
power plant of 2x15 MW capacity. 65 acre land will be converted from agricultural land to
industrial land for the project. The industry will have 300 permanent and 150 temporary
employees. The industry will use rice husk/ wheat/ paddy straw as fuel @ 2.6 MT/annum in the
fluidized bed boiler furnace (two nos.), the steam of which will be used for the generation of
electricity. The sources of air pollution from the industry are boiler ash and boiler flue gases
containing suspended particulate matter (SPM). In order to control air pollution, the industry will
provide electrostatic precipitator (ESP) as air pollution control device (APCD). About 65 MT/day
boiler ash will be generated and same shall be used for land filling inside the premises as well
as contract will be made with contractor for its effective disposal. The effluent from
demineralization plant, which is about 4 KL/hr. will be used for ash handling system and green
belt development. About 137 KL/hr. cooling water after recirculation system will be generated.
After detailed deliberations on the presentation and discussions, it was
decided to categorise the project into B1 category and that the project proponent should
submit an Environment Impact Assessment Study Report. The project proponent
informed that he had already got EIA study done based on field data generated over a
period of three months from 15th March to 15th June, 2006. However, the Committee
observed that the data is old and therefore, fresh EIA study is required to be got
conducted with monitoring of present environmental scenario at site. Therefore, the
Committee approved the following Terms of Reference for Environmental Impact
Assessment Study of the proposed project:-
1. All the coordinates of the plant site should be provided with toposheet.
2. The study area should cover an area of 10 km. radius around the proposed
site.
3. Land use of the study area as well as the project area shall be given.
4. Location of any National Park, Sanctuary, Elephant / Tiger Reserve (existing as
well as proposed), eco-sensitive area, interstate boundary, migratory routes, if
any, within 10 km. of the project site shall be specified and marked on the map.
5. Land requirement for the project to be optimized. Item wise break up of land
requirement and its availability to be furnished.
6. Topography of the area should be given clearly indicating whether the site
requires any filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
7. Impact on drainage of the area and the surrounding.
8. Information regarding surface hydrology and water regime and impact on the
same, if any, due to the project.
9. Sustainability study for groundwater in the existing tubewells and quality of
groundwater including concentration of selenium, arsenic as per BIS: 10500
(drinking water standards) should be provided.
10. One season site-specific meteorological data shall be provided.
11. One complete season Ambient Air Quality (AAQ) data (except monsoon) to be
given along with the dates of monitoring. The parameters to be covered shall
include SPM, RPM, SO2 and NOx. Monitoring shall be carried out for at least 8
different locations all around the project within 10 km. radius. The location of
the monitoring stations should be so decided so as to take into consideration
the pre-dominant downwind direction, population zone and sensitive receptors
including reserved forests. There should be at least one monitoring station in
the upwind direction.
12. Impact of the project on the AAQ of the area, details of the model used and the
input data used for modelling should also be provided. The air quality contours
may be plotted on a location map showing the location of project site,
habitation nearby, sensitive receptors, if any. The wind roses should also be
shown on this map. It may be kept in view that SPM in the stack emissions are
to be restricted within 100 mg/Nm3.
13. Analysis of each fuel from more than one source alongwith report be provided.
14. Reassessment of quantity of each fuel required, its source and mode of
transportation.
15. Source of water and its availability.
16. Details of rainwater harvesting and how it will be used in the plant.
17. Re-circulation and reuse of treated effluents within the plant. In case of any
proposed discharge, its quantity, quality and point of discharge, users
downstream etc. should be provided.
18. Water conservation measures proposed in the project should be given.
19. Details of water balance taking into account the reuse and re-circulation of
effluents.
20. Details of green belt i.e. land with not less than 1500 trees per hectare giving
details of species, width of plantation, planning schedule etc.
21. Assessment of ash generation and details of ash utilisation / management
plan.
22. Details regarding infrastructure facilities such as sanitation, fuel, restroom etc.
to be provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
23. Public hearing points to be raised and commitment of the project proponent on
the same. An action plan to address the issues raised during public hearing
and the necessary allocation of funds for the same should be provided.
24. Measures of socio economic influence to the local community proposed to be
provided by project proponent. As far as possible, quantitative dimensions to
be given.
25. Impact of the project on local infrastructure of the area such as road network
and whether any additional infrastructure would need to be constructed and the
agency responsible for the same with time frame.
26. Environment Management Plan (EMP) to mitigate the adverse impacts due to
the project along with item wise cost of its implementation.
27. Risk assessment to be undertaken. Based on the same, proposed safeguard
measures should be provided.
28. Any litigation pending against the project and / or any direction / order passed
by any Court of Law against the project, if so, details thereof.
29. A detailed environmental protection budget would also be presented and
earmarked.
30. The source of getting secondary data, wherever applicable, should be
intimated alongwith its reference.
31. Generic structure of Environment Impact Assessment Document, given in
Appendix III of EIA Notification 2006 shall be followed in preparation of Rapid
Environmental Impact Assessment report.
32. Besides the above, the following general points / guidelines will also be
followed:
a) All documents to be properly referenced with index, page numbers and
continuous page numbering. A uniform system of units to be used while reporting
data.
b) Where data is presented in the report especially in table, the period in which the data
was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an English
translation should be provided.
The Terms of Reference were conveyed to the industry vide letter no. 15201
dated 11/4/2008 and the industry was requested to submit EIA study report of the
proposed project as per the Terms of Reference given by State Expert Appraisal
Committee.
Now, the industry vide its letter no. LEFL/2008-2009/04 dated 23/4/2008 (copy enclosed as
Annexure-VI) has submitted pointwise reply of letter dated 11/4/2008 of the Committee and
submitted amended EIA report as per new generic structure, based on old data for the
period from 15th March to 15th June, 2006. The industry has once again requested to do the
needful to have environmental clearance of its project.
Therefore, the matter is again placed before the State Expert Appraisal
Committee for consideration.
Item No. 5.1.3 Application for environmental clearance of M/s Gillanders Arbuthonot & Co. Ltd. (Textile Division), Vill. Akbarpur, Post Box. 1, Ahmedgarh, Distt. Sangrur – A co-generation plant.
The application of the industry was placed before the Committee in its 3rd
meeting held on 24/3/2008 vide item No. 3.7 (copy attached as Annexure-III) (Page no. 25).
Please peruse.
Sh. Inder Rakheja, Corporate Head of the industry and Sh. H.S. Matharu,
consultant of the industry made presentation on their project proposal for expansion of
existing industry namely M/s Gillanders Arbuthonot & Co. Ltd. (Textile Division).
They informed that the industry is an existing textile unit engaged in the
manufacturing of Acrylic, Viscose, Cotton and Blended yarns. It has applied for grant of
environmental clearance under the provisions of EIA notification dated 14.9.2006 for setting up
of 6.5 MW Co-generation Captive Power Plant in its industrial unit. This industrial project is
located near SH-11 at Ahmedgarh, Distt. Sangrur. The total cost of the project is Rs. 25.68
crores for co-generation plant. The boiler will be primarily fired with rice husk to the extent of
85% of the time and coal for maximum of 15% of the time. The industry will install a stack of 61
mt. height for 34 TPH capacity boiler. ESP shall be provided for control of air pollution to
maintain emission level below 150 mg/Nm3. The industry has already obtained approval of site
from Govt. of Punjab, Deptt. of Labour for the installation of 6.5 MW co-generation plant as
required under the provision of Factories Act, 1948. It has also obtained NOC of Punjab
Pollution Control Board vide no. SGR/NOC/2006/Expansion/272 dated 19.12.2006 for 6.5 MW
co-generation plant.
Sh. Inder Rakheja further informed that the industry has already got Environment
Impact Assessment study done based on the final Terms of Reference (TOR) fixed by the
Ministry of Environment & Forests and conveyed to the project proponent vide letter no. J-
13012/134/2007-IA II(T) dated 5.10.2007. The Punjab Pollution Control Board has also fixed
public hearing of their project based on EIA study submitted by the project proponent, which is
to be held on the same date i.e. 24/3/2008 at 11.30 a.m.
After detailed deliberations on the presentation and discussions, it was
decided that the project will be appraised by the State Expert Appraisal Committee after
receiving outcome of the public consultation including public hearing proceedings from
Punjab Pollution Control Board and it was decided to defer the project till the
proceedings of public hearing are received from Punjab Pollution Control Board and / or
from the industry.
Accordingly, the project was deferred in the last meeting. The public hearing of
the industry was conducted by Punjab Pollution Control Board on 24/3/2008. However, the
proceedings of the same and the final EIA report / supplementary report to draft EIA and
EMP has not been received from the applicant so far.
The matter is again placed before the State Expert Appraisal Committee for
Appraisal of the project.
Item No. 5.1.4 Application for environmental clearance of M/s JCT Ltd., Phagwara, Distt. Kapurthala – A 8 MW co-generation plant.
The application of the promoter was placed before the Committee in its
3rd meeting held on 24/3/2008 vide item No. 3.8 (copy attached as Annexure-IV) (Page no.
27). Please peruse.
Sh. C.D. Singh, DGM (Commercial) and Sh. Anil Sharma, Manager (Purchase)
representatives of the project proponent alongwith their consultant Sh. Yash Pal Garg made
presentation on their project proposal for expansion of existing industry namely M/s JCT Ltd.
located at G.T. Road, Phagwara by installing one additional co-generation plant of 8 MW
capacity.
They informed that the industry is an existing composite textile unit engaged in
the production of textiles of various qualities. The average daily electrical energy requirement of
the industry is 3.6 lac unit. It is accomplished through 5.5 MW existing turbine, which produces
1.08 lac units per day and balance is drawn from Punjab State Electricity Board grid. In order to
achieve self-sufficiency, JCT Ltd. has proposed to install an additional 8 MW power co-
generation plant, requiring 50 TPH boiler, alongwith 8 MW turbine and its auxiliaries.
Accordingly, the industry has applied for grant of environmental clearance under the provisions
of EIA notification dated 14.9.2006 for setting up of 8 MW Co-generation Captive Power Plant in
its industrial unit.
The manufacturing processes for this project involves charging of rice husk / coal
in the furnace of a boiler of steam generating capacity 50 T/hr., operation of turbine and
generation of electricity. The industry has already obtained approval of site from Govt. of
Punjab, Deptt. of Labour for the installation of 8 MW Co-generation Plant as required under the
provision of Factories Act, 1948. The Punjab Pollution Control Board has already granted NOC
vide no. JAL/2007/NOC/Co-generation/35 dated 20.11.2007 for installation of new turbine of 8
MW capacity with the 50 TPH steam generating capacity boiler.
The industry has proposal to use rice husk / coal as fuel in the fluidized bed
boiler furnace, the steam of which will be used for generation of electricity. The sources of air
pollution from the industry are boiler ash and boiler flue gases containing suspended particulate
matter (SPM). In order to control the air pollution, it has proposed to provide electrostatic
precipitators (ESP) as air pollution control device (APCD).
The consultant of the industry further informed that the industry has got
Environment Impact Assessment study done based on the additional Terms of Reference
(TOR) fixed by the Ministry of Environment & Forests and conveyed to the project proponent
vide letter no. J-13012/204/2007-IA II(T) dated 14.12.2007. Moreover, Ministry of Environment &
Forests vide its letter no. J-13012/204/2007-IA II(T) dated 30.1.2008 has informed the project
proponent that since the proposed power plant will be an expansion of already existing 5 MW
co-generation power plant, therefore, it has been decided to exempt the said project from
conduct of public consultation.
After detailed deliberations on the presentation and discussions, the
project proponent was advised to submit pointwise reply of Terms of Reference (TOR)
given by Ministry of Environment & Forests in an annotated form alongwith relevant
details wherever required. The industry should also submit its site plan of the plant on A0
sheet.
Accordingly, the project proponent was requested vide letter no. 15189 dated
11/4/2008 to submit pointwise reply of Terms of Reference given by Ministry of Environment
& Forests, Govt. of India in an annotated form.
The industry vide its letter no. JCT/2008/133 dated 16/4/2008 has submitted
reply of letter no. 15189 dated 11/4/2008 issued by SEAC. (copy attached as Annexure-
VII).
The matter is again placed before the State Expert Appraisal Committee for consideration.
Item No. 5.2 Consideration of New Proposals for Environmental Clearance. Item No. 5.2.1 Application for environmental clearance of M/s Universal Biomass Energy
Pvt. Ltd. at Vill. Channo, Tehsil Malout, Distt. Muktsar – A 14.5 M.W. Co-generation power plant.
M/s Universal Biomass Energy Pvt. Ltd. has proposed to install a 14.5
MW bio-mass based power plant at Vill. Channo, Tehsil Malout, Distt. Muktsar alongwith a
boiler of 70 TPH capacity. The project is covered under Category-B {at sr. no. 1(d)} of the
Schedule attached to EIA notification dated 14/9/2006. Accordingly, the industry has applied for
grant of environmental clearance under the provisions of EIA notification dated 14.9.2006 for
setting up of 14.5 MW Bio-mass based Power Plant.
This industrial project is proposed to be located at Vill. Channo, Tehsil Malout,
Distt. Muktsar. As per project report, rice husk is proposed to be used as the main fuel. No use
of coal has been envisaged for the project. The industry has further mentioned in its project
report that since bio-mass power plants cannot depend on a single fuel source, multi fuel
adaptability of the boiler is of much importance, which is not possible in FBC boiler. Considering
this, traveling grate boiler has been selected for this project.
The sources of air pollution from the industry are boiler ash and boiler flue gases
containing suspended particulate matter (SPM). In order to control air pollution, the industry has
proposed to provide one no. electrostatic precipitators (ESP) as air pollution control device
(APCD) to ensure outlet dust conc. from chimney to 50 mg/Nm3 with all fields in operation.
It is mentioned here that the project is covered under category 1(d) of the
Schedule attached to EIA notification dated 14.9.2006. As per the General Condition (GC)
applicable in this case, any project or activity specified in Category ‘B’ will be treated as
Category A, if located in whole or in part within 10 km from the boundary of inter-State
boundaries.
The site of this project is located near the inter-State boundary of Punjab and
Haryana State. However, the industry has not submitted any certificate from competent
authority that it is located beyond 10 km from the Inter-State Boundary. Thus the competency of
State Expert Appraisal Committee to consider this project is not clear.
The other details of the project have been given in the Form 1 & Project Report
submitted by the industry (Annexure-VIII).
State Expert Appraisal Committee may consider the case.
Item No. 5.2.2 Application for environmental clearance of M/s Ajnala Co-operative Sugar Mills Ltd., Vill. Bhalla Pind, Tehsil Ajnala, Distt. Amritsar – A 12 MW bagasse based co-generation project
M/s Ajnala Co-operative Sugar Mills Ltd., Vill. Bhalla Pind, Tehsil Ajnala,
Distt. Amritsar is an existing sugar mill having cane-crushing capacity of 2500 TCD. The
industry has proposed to install a 12 MW bagasse based power plant in its existing Sugar Mill at
Vill. Bhalla Pind, Tehsil Ajnala, Distt. Amritsar alongwith a boiler of 64 TPH steam generating
capacity. The project is covered under Category-B {at sr. no. 1(d)} of the Schedule attached to
EIA notification dated 14/9/2006. Accordingly, the industry has applied for grant of
environmental clearance under the provisions of EIA notification dated 14.9.2006 for setting up
of 12 MW bagasse based power plant.
The industry has proposed to install co-generation power plant in its existing
sugar mill located at Vill. Bhalla Pind, Tehsil Ajnala, Distt. Amritsar. As per project report,
bagasse is proposed to be used as the main fuel. The sources of air pollution from the proposed
project are boiler ash and boiler flue gases containing suspended particulate matter (SPM). In
order to control air pollution, the industry has proposed to provide one no. electrostatic
precipitators (ESP) as air pollution control device (APCD) to ensure outlet dust conc. from
chimney to 115 mg/Nm3.
The other details of the project have been given in the Form 1 & Project Report
submitted by the industry (Annexure-IX).
State Expert Appraisal Committee may consider the case.
Item No. 5.2.3 Application for environmental clearance of M/s The Gurdaspur Co-operative Sugar Mills Ltd., Village Paniar, Gurdaspur – A 10 MW bagasse based co-generation power plant
M/s The Gurdaspur Co-operative Sugar Mills Ltd., Village Paniar,
Gurdaspur is an existing sugar mill having cane-crushing capacity of 2000 TCD. The industry
has proposed to install a 10 MW bagasse based power plant in its existing Sugar Mill at Village
Paniar, Gurdaspur alongwith a boiler of 55 TPH steam generating capacity. The project is
covered under Category-B {at sr. no. 1(d)} of the Schedule attached to EIA notification dated
14/9/2006. Accordingly, the industry has applied for grant of environmental clearance under the
provisions of EIA notification dated 14.9.2006 for setting up of 10 MW bagasse based power
plant.
The industry has proposed to install co-generation power plant in its existing
sugar mill located at Village Paniar, Gurdaspur. As per project report, bagasse is proposed to be
used as the main fuel. The sources of air pollution from the proposed project are boiler ash and
boiler flue gases containing suspended particulate matter (SPM). In order to control air pollution,
the industry has proposed to provide one no. electrostatic precipitator (ESP) as air pollution
control device (APCD) to ensure outlet dust conc. from chimney to 115 mg/Nm3.
The other details of the project have been given in the Form 1 & Project Report
submitted by the industry (Annexure-X).
State Expert Appraisal Committee may consider the case.
Item No. 5.2.4 Application for environmental clearance of M/s The Budhewal Co-operative Sugar Mills Ltd., VPO Budhewal, Distt. Ludhiana – A 8 MW bagasse based co-generation power plant.
M/s The Budhewal Co-operative Sugar Mills Ltd., VPO Budhewal, Distt.
Ludhiana is an existing sugar mill having cane-crushing capacity of 1250 TCD. The industry has
proposed to install a 8 MW bagasse based power plant in its existing Sugar Mill at VPO
Budhewal, Ludhiana alongwith a boiler of 45 TPH steam generating capacity. The project is
covered under Category-B {at sr. no. 1(d)} of the Schedule attached to EIA notification dated
14/9/2006. Accordingly, the industry has applied for grant of environmental clearance under the
provisions of EIA notification dated 14.9.2006 for setting up of 8 MW bagasse based power
plant.
The industry has proposed to install co-generation power plant in its existing
sugar mill located at VPO Budhewal, Distt. Ludhiana. As per project report, bagasse is
proposed to be used as the main fuel. The sources of air pollution from the proposed project are
boiler ash and boiler flue gases containing suspended particulate matter (SPM). In order to
control air pollution, the industry has proposed to provide one no. electrostatic precipitator (ESP)
as air pollution control device (APCD) to ensure outlet dust conc. from chimney to 115 mg/Nm3.
The other details of the project have been given in the Form 1 & Project Report
submitted by the industry (Annexure-XI).
State Expert Appraisal Committee may consider the case.
Item No. 5.2.5 Application for environmental clearance of M/s The Morinda Co-operative Sugar Mill Ltd., Morinda, Distt. Ropar - A 10 MW bagasse based co-generation power plant.
M/s The Morinda Co-operative Sugar Mill Ltd., Morinda is an existing
sugar mill having cane-crushing capacity of 2300 TCD. The industry has proposed to install a 10
MW bagasse based power plant in its existing Sugar Mill at Morinda, Distt. Ropar alongwith a
boiler of 60 TPH steam generating capacity. The project is covered under Category-B {at sr. no.
1(d)} of the Schedule attached to EIA notification dated 14/9/2006. Accordingly, the industry has
applied for grant of environmental clearance under the provisions of EIA notification dated
14.9.2006 for setting up of 10 MW bagasse based power plant.
The industry has proposed to install co-generation power plant in its existing
sugar mill located at Morinda, Distt. Ropar. As per project report, bagasse is proposed to be
used as the main fuel. The sources of air pollution from the proposed project are boiler ash and
boiler flue gases containing suspended particulate matter (SPM). In order to control air pollution,
the industry has proposed to provide one no. electrostatic precipitator (ESP) as air pollution
control device (APCD) to ensure outlet dust conc. from chimney to 115 mg/Nm3.
The other details of the project have been given in the Form 1 & Project Report
submitted by the industry (Annexure-XII).
State Expert Appraisal Committee may consider the case.
Item No. 5.2.6 Application for environmental clearance of M/s Punjab Bio-mass Power Ltd. at Vill. Baghaura, Tehsil Rajpura, Distt. Patiala – A 12 MW Bio-Mass based power project
M/s Punjab Bio-mass Power Ltd. has proposed to install a 12 MW bio-
mass based power plant at Vill. Baghaura, Tehsil Rajpura, Distt. Patiala alongwith a boiler of 60
TPH capacity. The project is covered under Category-B {at sr. no. 1(d)} of the Schedule
attached to EIA notification dated 14/9/2006. Accordingly, the industry has applied for grant of
environmental clearance under the provisions of EIA notification dated 14.9.2006 for setting up
of 12 MW Bio-mass based Power Plant.
This industrial project is proposed to be located at Vill. Baghaura, Tehsil Rajpura,
Distt. Patiala. As per project report, straw / cane trash is proposed to be used as the main fuel
or in part with combination of other fields. Rice husk and coal are also proposed to be used as
auxiliary fuels.
The sources of air pollution from the industry are boiler ash and boiler flue gases
containing suspended particulate matter (SPM). In order to control air pollution, the industry has
proposed to provide one no. electrostatic precipitators (ESP) as air pollution control device
(APCD) to ensure outlet dust conc. from chimney to less than 150 mg/Nm3.
It is mentioned here that the project is covered under category 1(d) of the
Schedule attached to EIA notification dated 14.9.2006. As per the General Condition (GC)
applicable in this case, any project or activity specified in Category ‘B’ will be treated as
Category A, if located in whole or in part within 10 km from the boundary of inter-State
boundaries.
The site of this project is located near the inter-State boundary of Punjab and
Haryana State. However, the industry has not submitted any certificate from competent
authority that it is located beyond 10 km from the Inter-State Boundary. Thus the competency of
State Expert Appraisal Committee to consider this project is not clear.
The other details of the project have been given in the Form 1 & Project Report
submitted by the industry (Annexure-XIII).
State Expert Appraisal Committee may consider the case.
ANNEXURE-I
Item No. 3.2 "Nahar Industrial Enterprises Ltd: Nahar Fabrics-II, Lalru, Tehsil Dera Bassi, Distt. Mohali - 12 MW Co-generation Project.
M/s Nahar Industrial Enterprises Ltd., 21st Mile Stone Ambala-Chandigarh Highway, Lalru,
Tehsil Dera Bassi, Distt. Mohali is an existing unit engaged in the production of Cotton blended
fabric and yarn dyeing. The industry has proposed to install a 12 MW power co-generation
plant alongwith a boiler of 55 TPH capacity. Accordingly, the industry has applied for grant of
environmental clearance under the provisions of EIA notification dated 14.9.2006 for setting up
of 12 MW Co-generation Power Plant in its industrial unit.
This industrial project is located at Lalru, Tehsil Dera Bassi, Distt. Mohali. The manufacturing
processes of the industry involve charging of coal in boiler of steam generating capacity 55
T/hr., operation of turbine and generation of electricity. The industry has obtained NOC of
Punjab Pollution Control Board vide no. PTA/NOC/2007/V-60 dated 23.10.2007 for installation
of co-generation plant of 12 MW capacity by installing another boiler of 55 TPH capacity in its
existing premises.
The industry has proposal to use Coal as fuel in the boiler furnace, the steam of which will be
used for generation of electricity. The sources of air pollution from the industry are boiler ash
and boiler flue gases containing suspended particulate matter (SPM). In order to control the air
pollution, it has proposed to provide electrostatic precipitators (ESP) as air pollution control
device (APCD).
It is mentioned here that the project is covered under category 1(d) of the Schedule attached to
EIA notification dated 14.9.2006. As per the General Condition (GC) applicable in this case, any
project or activity specified in Category ’B’ will be treated as Category A, if located in whole or in
part within 10 km from the boundary of inter-State boundaries. The site of this project is located
within 10 km from the inter-State boundary of Punjab and Haryana State and, therefore, the
project is to be treated as category A project. Thus this project is not in the purview of State
Expert Appraisal Committee.
The matter is placed before the Committee for consideration of the project in view of above
observations.
ANNEXURE-II
Item No. 3.4 "Lakshmi Energy and Foods Ltd., Khamanon, Distt. Fatehgarh
Sahib" – A Co-generation plant.
M/s Lakshmi Energy and Foods Ltd., Khamanon, Distt. Fatehgarh Sahib is an existing
integrated industrial unit engaged in the manufacturing of products like rice, solvent extraction
plant, cattle feed etc. It has applied for grant of environmental clearance under the provisions of
EIA notification dated 14.9.2006 for setting up of 2 X 15 MW Bio-Mass Based Co-generation
Power Plant in its industrial unit. This industrial project is going to be located at 1 Km. towards to
Chandigarh from Khamanon, Distt. Fatehgarh Sahib. The total cost of the project is 118.09
crore for thermal power plant. The manufacturing processes of the industry involve charging of
rice husk in boilers, operation of turbines and generation of electricity, which will be further
transferred to transformer and then to grid. The industry has already obtained approval of site
from Govt. of Punjab, Deptt. of Labour for the installation of 2 X 15 MW Co-generation Plant as
required under the provision of Factories Act, 1948. It has also obtained NOC of Punjab
Pollution Control Board vide no. 671 dated 20/11/2007 for 2 X 15 MW Co-generation Plant.
The industry has proposal to use rice husk/ wheat/ paddy straw as fuel @ 2.6 MT/Annum in the
fluidized bed boiler furnace (two nos.), the steam of which will be used for the generation of
electricity. The source of air pollution from the industry are boiler ash, boiler flue gases
containing suspended particulate matter (SPM). In order to control the air pollution, it has
proposed to provide electrostatic precipitator (ESP) as air pollution control device (APCD). The
effluent from demineralization plant, which is about 4 KL/hr. will be used for ash handling
system and green belt development. About 137 KL/hr. cooling water after recirculation system
will be generated. However, in the application, the industry has also mentioned that the industry
will discharge 52 KL/hr. from the plant and the same is proposed to be used in ash handling
system and green belt development (This needs clarification from the project proponent).
The industry has submitted proposed Terms of Reference (TOR) in which the scope of the
study has been proposed to be covered under the following disciplines: -
· Ambient Air Quality · Meteorological Study · Water Quality · Noise Levels Monitoring · Soil Quality Analysis · Biological Environment Studies · Socio-economic and Demography · Hydrology · Land Use
The case of the industry / project is placed before the State Expert Appraisal Committee (SEAC)
for screening to decide whether the project is to be covered under category B1 or B2 of the
schedule attached to EIA notification dated 14/9/2006.
Further, in case the Committee decides that the project is covered under category B1, the
necessary Terms of Reference (TOR) for the purpose of preparation of Rapid Environment
Impact Assessment Study Report by the project proponent are required to be fixed/ framed by
the Committee.
The matter is placed before the Committee for consideration as above.
ANNEXURE-III
Item No. 3.7 "Gillanders Arbuthonot & Co. Ltd. (Textile Division), Vill. Akbarpur,
Post Box. 1, Ahmedgarh, Distt. Sangrur – A co-generation plant.
M/s Gillanders Arbuthonot & Co. Ltd. (Textile Division), Vill. Akbarpur, Post Box- 1, Ahmedgarh,
Distt. Sangrur is an existing textile unit engaged in the manufacturing of Acrylic, Viscose, Cotton
and Blended yarns. It has applied for grant of environmental clearance under the provisions of
EIA notification dated 14.9.2006 for setting up of 6.5 MW Co-generation Captive Power Plant in
its industrial unit. This industrial project is located near SH-11 at Ahmedgarh, Distt. Sangrur.
The total cost of the project is 2568 lac for co-generation plant. The manufacturing processes of
the industry involve charging of rice husk/ coal (in the ratio of 85:15) in boiler of steam
generating capacity 34 T/hr., operation of turbines and generation of electricity. The industry has
already obtained approval of site from Govt. of Punjab, Deptt. of Labour for the installation of 6.5
MW Co-generation Plant as required under the provision of Factories Act, 1948. It has also
obtained NOC of Punjab Pollution Control Board vide no. SGR/NOC/2006/Expansion/ 272
dated 19.12.2006 for 6.5 MW Co-generation Plant.
The industry has proposal to use rice husk / coal as fuel in the fluidized bed
boiler furnace, the steam of which will be used for generation of electricity. The sources of air
pollution from the industry are boiler ash and boiler flue gases containing suspended particulate
matter (SPM). In order to control the air pollution, it has proposed to provide electrostatic
precipitators (ESP) as air pollution control device (APCD). The DM Plant reject and cooling
tower discharge will be treated and re-used. A treatment plant shall be set up for the liquid
effluents to treat the effluents to statutory standards.
The industry has submitted Environment Impact Assessment Report based on
the final Terms of Reference (TOR) fixed by the Ministry of Environment & Forests and
conveyed to the project proponent Vide letter no. J-13012/134/2007-IA II(T) dated 5.10.2007.
The Punjab Pollution Control Board has informed that the public hearing of the
project has been fixed on 24.3.2008 as per the Terms of Reference given by Ministry of
Environment & Forests.
The matter is placed before the Committee for its information.
****
ANNEXURE-IV
Item No. 3.8 "JCT Ltd., Phagwara, Distt. Kapurthala” – An 8 MW co-generation
plant.
M/s JCT Ltd., Phagwara, Distt. Kapurthala is an existing composite textile unit engaged in the
production of textiles of various qualities. The average daily electrical energy requirement of the
industry is 3.6 lac unit. It is accomplished through 5.5 MW existing turbine, which produces 1.08
lac units per day and balance is drawn from Punjab State Electricity Board grid. In order to
achieve self-sufficiency, JCT Ltd. has proposed to install an additional 8 MW power co-
generation plant, requiring 50 TPH boiler, alongwith 8 MW turbine and its auxiliaries.
Accordingly, the industry has applied for grant of environmental clearance under the provisions
of EIA notification dated 14.9.2006 for setting up of 8 MW Co-generation Captive Power Plant in
its industrial unit.
This industrial project is located at G.T. Road, Phagwara. The manufacturing processes of the
industry involve charging of rice husk / coal in boiler of steam generating capacity 50 T/hr.,
operation of turbine and generation of electricity. The industry has already obtained approval of
site from Govt. of Punjab, Deptt. of Labour for the installation of 8 MW Co-generation Plant as
required under the provision of Factories Act, 1948. The Punjab Pollution Control Board has
already granted NOC vide no. JAL/2007/NOC/Co-generation/35 dated 20.11.2007 for
installation of new turbine of 8 MW capacity with the 50 TPH steam generating capacity boiler.
The industry has proposal to use rice husk/ Coal as fuel in the fluidized bed boiler
furnace, the steam of which will be used for generation of electricity. The sources of air pollution
from the industry are boiler ash and boiler flue gases containing suspended particulate matter
(SPM). In order to control the air pollution, it has proposed to provide electrostatic precipitators
(ESP) as air pollution control device (APCD).
The industry has submitted Environment Impact Assessment Report based on
the additional Terms of Reference (TOR) fixed by the Ministry of Environment & Forests and
conveyed to the project proponent vide letter no. J-13012/204/2007-IA II(T) dated 14.12.2007.
More over, Ministry of Environment & Forests vide its letter no. J-13012/204/2007-IA II(T) dated
30.1.2008 has informed the project proponent that since the proposed power plant will be an
expansion of already existing 5 MW co-generation power plant, therefore, it has been decided to
exempt the said project from conduct of public consultation.
The matter is placed before the Committee for Appraisal of the project as the
Ministry of Environment & Forests has already given additional Terms of Reference to the
industry after screening and scooping of the project and based on these TOR, the project
proponent has submitted Environment Impact Assessment study report.