What is scope?

It examines the activities of the project in terms of what we are trying to achieve

It is about ensuring that the project includes the work required, and only the work required to achieve the objectives

More than this, it is about defining and controlling what is not included in the project

It helps us to avoid over-ambition

Page 3: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

For example….

In IPR Helpdesk the scope of our project includes giving first-line assistance to RTD project users and potential users

It does not include giving legal consultations or a patent service

Page 4: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Scope Planning

Begins with drafting stage described before

Outputs of scope planning are:Scope Statement

Scope Management Plan

And (hopefully) a successful project

Page 5: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Scope Planning - methodology

ProjectDescription

Project Objectives

WorkpackageObjectives

ProjectAnalysis

Tradeoff Analysis

ContingencyPlanning

ScopeStatement

Scope Management

Plan

Support

INPUTS TOOLS OUTPUTS

Page 6: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

The Scope Statement

Forms basis for agreement between project and project ‘customer’ by identifying both project outputs and deliverablesMultiple scope statements are created for multiple work teams In our case, a statement for each workpackage

Page 7: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Scope Statement

Basis for future project decisions concerning direction and changeCould be revised as project progressesShould include:

Justification of the project / workpackageDescription of ‘product’DeliverablesObjectives

Page 8: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Scope Statement: Management Workpackage

“to provide a global administrative and coordination backup to all project stakeholders and workgroups. To be the external point of communication for interested parties. The deliverables of this workpackage include the successful, timely, and on budget completion of the project. Other deliverables include six monthly reports to the Commission”

Page 9: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Scope Management Plan

Defines how scope will be managed

How changes will be implemented

Estimate stability of project scope – how likely is it to change? How frequently? And by how much?

Could be formal or informal, broad or narrowly defined

Page 10: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Scope Management Plan for Management Workpackage

“scope will be managed through careful following of the workplan and project description. Change will be implemented through consultation with the Commission, project partners, and staff. Scope is estimated to be stable”.

Page 11: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Defining Scope

Break down into smaller, more manageable activitiesCritical for project successWithout proper scope definition, costs can be expected to be higher etcBy having a decentralised management struture within a project, decomposition of project activities and deliverables has already been carried out

Page 12: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Verifying Scope

Ongoing process throughout project

Indicators: timely completion,

completion on budget,

reiteration of scope statement,

achievement of objectives, deliverables and milestones

Page 13: INCOME PROJECT TEMPUS SCM MEDA Scope Management Case Study: IPR Helpdesk Project

INCOME PROJECTTEMPUS SCM MEDA

 

 

Inputs and Outputs of ScopeACTION INPUT TOOLS OUTPUT

Initiate -Project description-Strategic plan-Tradeoff

Selection methods, expert judgement

Executive summary, project plan

Definition of Scope

Project description

Analyses, cost / benefit analysis, expert judgement, tradeoff

Scope description, objectives, deliverables, workpackages decided

Verifying Scope

Results obtained Inspection Formal acceptance

Control of Scope

-Workplan-Progress reports-Change requests

Estimating and planning tools

Change to scope, corrective or alternative action