Inception Report SHway-Modified

Embed Size (px)

DESCRIPTION

inception report southern highway 2

Citation preview

  • 5/21/2018 Inception Report SHway-Modified

    1/22

    Table of Contents

    1. Introduction

    1.1 General

    1.2 Description of the Project

    2. Objectives of the Study

    3. Ters of !eference "TO!#

    $. %ethodolo&y

    $.1 'oents on TO!

    $.2 'oposition of the Study Tea

    $.3 Inforation 'ollection

    $.$ !evie( and )nalysis

    $.* Ipact Identification and %iti&ation

    *. !eportin&

    +. Tie Schedule

    ,. 'onsultations and -isits

    Annexures

    )nneure 1 / Ters of !eference

    )nneure 2 / 'urriculu -itae of Study Tea

    )nneure 3 / 0ist of Docuents

    1

  • 5/21/2018 Inception Report SHway-Modified

    2/22

    1. Introduction

    1.1 General

    niversity of %oratu(a "O%# (as entrusted to conduct a Suppleentary nvironental

    )ssessent and an pdatin& of nvironental %ana&eent Plan "%P# of the SouthernTransport Developent Project "STDP# by Director Project %ana&eent nit "P%# of the

    !oad Developent )uthority "!D)#. )ccordin&ly the O% study tea coenced (or4 in

    early October 255$. 6o(ever as of 2* October 255$ P% directed O% to teporarily

    suspend the studies. The inception report for the (or4s coenced and copleted up to then

    (as subitted to the !D) SPDP and the )D7 in Deceber 255$. pon resolution of any

    issues bet(een the t(o parties O% reactivated the studies on 1 Septeber 255* based on a

    revised Ters of !eference "TO!# presented by P%. This Inception !eport outlines

    objectives of the study its ethodolo&y and schedule of (or4 pro&ra.

    1.2 Description of the Project

    The Southern Transport Developent Project "STDP# is presently bein& ipleented by

    Governent of Sri 0an4a "GOS0# throu&h !oad Developent )uthority "!D)#. The project

    is financed fro parallel fundin& by the )sian Developent 7an4 ")D7# and the 8apan 7an4

    for International 'ooperation "87I'#. The ain coponent of this project is the construction

    of an epress(ay "Southern 6i&h(ay# bet(een 9otta(a and %atara. The construction has

    already coenced over a lar&e section of the road financed by the )D7.

    The project approved by the )D7 (as based on a tentative :'obined Trace; (ithin a

    corridor subject to subse

  • 5/21/2018 Inception Report SHway-Modified

    3/22

    2. Objectives of the tud! and TO"

    The objectives of the study by O% as etracted fro the revised TO! ay be stated as

    follo(s@

    2.1.

    "i# !evie( all previous reports on the project pertainin& to environental issues@

    includin& the nvironental Ipact )ssessent "I)# and Suary nvironental

    Ipact )ssessent "SI)# to deterine their applicability to the entire len&th of

    :=inal Trace; coprisin& both 87I' and )D7 funded sections and Galle Port )ccess

    !oad "GP)!#.

    "ii# Identify locations on the :=inal Trace; (hich re

  • 5/21/2018 Inception Report SHway-Modified

    4/22

    The aps tables and fi&ures in the draft for (ill be included for the preliinary (or4

    reports. In the final report they (ill be done in a suitable forat for presentation. ?o

    estiates have been ade for GIS (or4s and the tea do not intend to carryout di&itiBation of

    aps.

    TOR Item 6(i)

    The revie( and

  • 5/21/2018 Inception Report SHway-Modified

    5/22

    nder this section the tea (ould copare the cobined trace and the final trace and revie(

    the %P in the contet of the )D7 &uidelines. This (or4 (ill span the entire len&th of the

    final trace.

    a# In this section the revie( (ould be carried out for the sub sections &iven in the )D7

    nvironental )ssessent Guidelines of 2553 under the ain section %P. Theade

  • 5/21/2018 Inception Report SHway-Modified

    6/22

    TOR Item 6(x)

    The environental assessent report and %P (ill be finalised by the tea after a discussion

    foru preferably includin& interested parties !D) and )D7. It is epected that the

    coents fro the )D7 and other concerned parties as per !D) assessent (ill be received

    (ithin ten days fro subission. The suary environental report (ill be done accordin&to the &uidelines of the )D7 and the forat is to be received by the tea at the

    coenceent of the (or4.

    The tea (ould have periodical discussions (ith both !D) and )D7 re&ardin& the process

    and ethodolo&y of (or4 prior to the subission of each interi report.

    The reportin& as per the TO! (ill be the Interi !eport Preliinary Study !eport Draft

    =inal !eport and the =inal !eport respectively.

    The studies (ill ostly utiliBe the available base data since it is only a suppleentary study as

    it has been indicated. The tea (ould ephasiBe on the si&nificant deviations fro (hat hasbeen done previously. The other sections (ill be revie(ed and reported. The consultations

    (ill be liited to that has been carried out so far the responses received by the !D) and

    available inforation fro the social ipact assessent tea. =ro tie to tie the data

    and inforation of the suppleentary social assessent should be ade available to the tea

    to carryout the ipact assessent. The tea (ould fro tie to tie re

  • 5/21/2018 Inception Report SHway-Modified

    7/22

    #.' Infor&ation Collection

    #.'.1 General

    The inforation that (ill be collected by each specialist staff eber of the study tea in

    outline for is presented in Table $.2. The ajor deviations of the =inal Trace haven alreadybeen identified "=i&. $.1# and each tea eber (ill focus on &atherin& relevant inforation

    (ithin these deviations. Details of inforation to be collected on ajor aspects of the study

    are described in sections $.3.2 to $.3.15.

    )ll eetin&s and site visits as felt necessary by the tea need to be coordinated and assisted

    by the !D). It is epected that the !D) (ould release t(o field en&ineers failiar (ith the

    Southern Transport Developent Project or&aniBation at !D) site locations of the trace

    control points and other landar4s to facilitate the site visits and necessary eetin&s (ith

    interested parties. If possible release of personnel (ho have earlier (or4ed (ith the I)

    tea of 1CCC is preferred. The tea epects a roo of reasonable siBe in the !D) buildin&

    (ith furniture to conduct tea discussions (ith !D) and other officials and at least t(oresource persons could use des4 space and for the duration of the environental assessent

    (or4 under this TO!.

    #.'.2 (!drolo%! and Draina%e

    )a* +,IC ection

    The follo(in& inforation (ill be collected@

    )vailable hydrolo&ical data fro previous Draina&e !eport "O%# and6ydrolo&ical Study report.

    0and use land topo&raphy (ater bodies and draina&e patterns (ithin a *55

    corridor of the deviated stretches of previous !D) and 'obined Traces identified

    fro preliinary site reconnaissance.

    !ainfall evaporation and strea flo( data alon& the identified road stretches.

    )b* AD, ection

    )ll previous I)! reports and the draina&e study reports (ill be revie(ed to cull the baselineinforation to perfor the suppleentary environental assessent. The study area

    stipulated in the To! (ill be identified in ters of draina&e and hydrolo&y throu&h site

    reconnaissance in consultation (ith the !D) en&ineers (ho has the 4no(led&e of the site and

    its environs. The 4ey study areas (ill beA

    The entire stretch fro 9urundu&ahahet4a to %atara (ith respect to the ipacts

    caused by the on&oin& construction processes.

    The deviated stretches in full.

    Galle Port )ccess !oad in full

    ,

  • 5/21/2018 Inception Report SHway-Modified

    8/22

    -i%. #.1 Dev

    H

  • 5/21/2018 Inception Report SHway-Modified

    9/22

    #.'.' Geotechnical Aspects

    The follo(in& inforation (ill be collected@

    o %aps and des4 study considerin& topolo&ical aps &eolo&ical aps land use

    aps

    o Data fro previous study reports other data available (ith !D) Irri&ation

    Departent Geolo&ical Survey and %ines 7ureau "GS%7#

    o

    Site reconnaissance alon& the final trace in the 87I' and )D7 sections andGalle Port )ccess !oad includin& a survey of eistin& borro( pits and

  • 5/21/2018 Inception Report SHway-Modified

    10/22

    #.'.7 ociolo%ical Aspects

    The inforation collection (ill be carried out by the consultant to&ether (ith his field

    assistants fro several saple locations of the entire trace and especially t(o deviations and

    Galle access road (ill be studied in detail usin& participatory approaches.

    #.'.8 Transportation and Traffic -lo9

    #.'.1: 3nviron&ent and Polic! Plannin%

    #.# "evie9 and Anal!sis

    #.#.1 General

    The revie( and

  • 5/21/2018 Inception Report SHway-Modified

    11/22

    (ill be done (ith the inforation fro the reports and the observations at the sites.

    !ecoendations (ill be ade for satisfactory environental iti&ation.

    This (or4 involves the entire final trace and the study of the environental ipacts. The

    (or4 (ill be done in consultation (ith the parties indicated in the TO!. The consultations

    (ill be liited to those or&aniBed and facilitated by the !D) and the )D7. The list ofconcerned personnel (ith the !D) (ill also be ta4en and their concerns (ill be ta4en into

    consideration of the study. The public (ill be ade a(are of the road trace and the chan&es

    ade fro the cobined trace done in the 1CCC I)!. The tea (ill carryout field

    inspection and des4 studies (here there had been chan&es fro the cobined trace and

    perfor the assessent of the environental ipacts. This study (ill cover all sections (ith

    siilar iportance. Data &aps (ith respect to the eistin& environent (ill be covered in a

    siilar anner as in the 1CCC I)!. The updated report (ill refer to the 1CCC I)! (here

    there are no si&nificant chan&es and (ill include a detailed contents (here there are chan&es

    that need to be ta4en for the environental assessent. The !D) is epected to provide the

    list of personnel available (ith the !D) (ho are included in the cross section of personnel for

    the consultative process as indicated in the TO! ite.

    The revision of the %P (ill be done based on the identifications and studies done for the

    environental assessent. The revisions (ill be done inline (ith the )D7 &uidelines and the

    indicators level of iti&ation etc. (ill be identified siilar to the %P for the project that

    has been prepared in )u&ust 255$.

    The details of revie( and analysis of inforation pertainin& to ajor aspects covered durin&

    the study are described belo(.

    #.#.2 (!drolo%! and Draina%e

    )a* +I,IC ection

    =ollo(in& t(o reports (ill be revie(ed

    o Draina&e report "O%#

    o 6ydrolo&ical study report 87I' section

    )t the deviated stretches of the previous !D) and cobined trace draina&e

    pattern of the *55 corridor (ill be analyBed (ith chan&es of draina&e pattern

    and its ipact to the environent.

    )b* AD, ection

    It is epected to study the follo(in& hydrolo&y and draina&e related paraeters especially for

    the deviations (hich are no( in the ipleentation (here the environental ipacts have

    not been sufficiently covered.

    1. Surface (ater

  • 5/21/2018 Inception Report SHway-Modified

    12/22

    +. =lood Pea4 and !etention area> preparation of flood survey aps (ith locations and

    etent of floodin& and Table of !etention )reas len&th alon& the road trace "len&th and

    'haina&e

    ,. Siltation and Sedient !unoff "related to flood and draina&e#

    H. Irri&ation and =lood Protection Schees> Preparation of the 0ocation and tent

    aps.C. 6ydraulic Structures in the deviated routes> 0ocation of 'ulvert and 7rid&es / %ap

    and Table

    #.#.' Geotechnical Aspects

    1. Ipact of the activities durin& pre>construction construction and post construction

    phases related to the solutions for follo(in& &eotechnical&eolo&ical probles (ill be

    assessed

    i. ban4ent construction on soft &roundsA

    ii. =oundations for brid&es and other structuresA

    iii. Stability of slopes and earth retainin& structuresA andiv. Disposal of the construction (aste.

    2. Investi&ation of the availability of construction aterials such as@ =ill aterialA Sand

    and a&&re&ate "etal# in ters of both

  • 5/21/2018 Inception Report SHway-Modified

    13/22

    #. I&pact Identification and $iti%ation

    #..1 General

    The identification of the environental ipacts that have a bearin& on the desi&n

    construction and operation of the project (ould be based on the site visits by the epertsproject docuentation (ith the !D) includin& the coents fro the public and other

    a&encies. In case the detail desi&ns are not available the tea (ould a4e interpretations and

    recoendations based on the data ade available.

    The ethodolo&y used for ipact assessent (ill be consistent (ith that adopted in 1CCC

    I). The project (ill be divided into 2$ project eleents coverin& investi&ation construction

    and operation sta&es. The affected environent (ill be divided into environental eleents

    considerin& the &eneral environent of the area and the environental issues hi&hli&hted in

    the TO!. These environental eleents (ill cover physicalcheical aspects biolo&ical

    aspects and socialsocio>econoic aspects.

    Once the eleents are identified it (ill be possible to for the !elevance %atri. The

    coluns in the !elevance %atri (ill be the identified project eleents (hile the ro(s (ill

    be the environental eleents. The list of environental eleents (ill be divided aon&

    study tea core ebers in accordance (ith their specialties. This eans that each eber

    (ill be loo4in& at fe( ro(s and all coluns in the full atri. 7ased on the assessents

    ade by each eber the Tea 0eader (ill eventually finaliBe the full !elevance %atri in

    consultation (ith the entire tea.

    Once the relevance atri is prepared the tea (ill be in a position to select areas that need

    to be studied in detail. )ll ipacts identified as :hi&hly si&nificant; in the !elevance %atrineeds to be studied in detail in order to

  • 5/21/2018 Inception Report SHway-Modified

    14/22

    =or the places (here deviation have been affected the ipacts (ill be considered for

    all three phases viB. Investi&ation and Preparation Phase 'onstruction Phase and the

    Operation Phase. In these deviated stretches the critical ipact occurrin& places and

    the ipact doains (ill be identified (ith special ephases. The ipact evaluation

    criteria adopted in the previous study reports (ill be follo(ed .

    %iti&atory easures and the onitorin& pro&rae alon& (ith the necessary details

    to up&rade the %P (ill be presented after assessin& the ipacts. Inforation

    necessary to prepare the Ipact %atri also (ill be obtained.

    #..' Geotechnical Aspects

    Durin& the preliinary revie( of the previous study reports it (as found that detailed I)

    (ere already conducted for !D) trace and the 'obined trace at that sta&e and

    nvironental %iti&ation Plans (ere also prepared. Therefore in this suppleentary studyattention (ill be ainly focused to the deviations of the final trace fro the cobined and

    !D) traces. 6o(ever the localities (hich are si&nificantly chan&ed since the previous

    studies due to the construction (or4s in the )D7 section or due to other reasons (ill be

    identified and studied in detail. Identification of the already eperienced or anticipated

    chan&es to the eistin& conditions of the environental eleents pertainin& to Geotechnical

    en&ineerin& and Geolo&y durin& the construction sta&e of the project / )lready eperienced

    chan&es in the project area (ill be studied throu&h field visits and anticipated chan&es (ill be

    forecast based on "a# The Detailed Desi&n of the road eban4ent and other structures alon&

    the trace and "b# The nvironental =indin&s !eport "2555# by Filbur Sith )ssociates Inc.

    %oreover ipleentation of the previously proposed environental iti&ation easures and

    its effectiveness (ill also be scrutiniBed.

    #..#. ater /ualit!0 Air Pollution and oise Control

    #.. 3colo%ical Aspects

    Priary and secondary data inforation re

  • 5/21/2018 Inception Report SHway-Modified

    15/22

    vie(s to assess sae proble fro different an&les to verify the practical feasibility of

    ipleentin& such sta4eholder su&&ested recoendations.

    #..8 Transportation and Traffic -lo9

    #..1: 3nviron&ent and Polic! Plannin%

    1*

  • 5/21/2018 Inception Report SHway-Modified

    16/22

    Table #.1 Co&position of the tud! Tea&

    a&e Position Affiliation

    1. Prof. ?.T.S. Fijese4ara Tea 0eader6ydrolo&ist niversity of %oratu(a

    2. Prof. "%rs#. ?. !atnaya4a 'o>Tea 0eaderI) and Policy Planner niversity of %oratu(a

    3. Dr. P.P. Gunaratna Deputy Tea 0eader "!evie( and !eports# niversity of %oratu(a

    $. Dr. ?.P.D. Gaa&e Deputy Tea 0eader>87I' niversity of %oratu(a

    *. n&. D.).8. !an(ala Deputy Tea 0eader>)D7

    +. Prof. 0.0. !atnaya4a Traffic n&ineerTransport Planner niversity of %oratu(a

    ,. Dr. 6.S. Thila4asiri Soil and Geotechnical n&ineer niversity of %oratu(aH. Dr. %. F. 8aya(eera nvironental n&ineer niversity of %oratu(a

    C. Dr. "%rs# %.D. )arasin&he colo&ist niversity of 9elaniya

    15. 9. 8inapala Sociolo&ist International Fater %ana&eent Institute

    11. Dr. O. )arasin&he )&ricultural conoist niversity of !uhuna

    12. )rcht. S. da(atta 0andscape and )esthetics Specialist

    1+

  • 5/21/2018 Inception Report SHway-Modified

    17/22

    Table #.2 Details of Planned Infor&ation and Data Collection

    "esource Personnel ature of Infor&ation to be

    Collected

    $ethod of Data

    Collection

    ources of Infor&ation pecial ite ;isits

    1. 6ydrolo&ist 0and use land topo&raphy (ater bodies and draina&e patterns of

    selected stretches (ithin a *55corridor (ithin the final hi&h(ay

    trace and Galle Port access road

    identified fro preliinary sitereconnaissance. !ainfall

    evaporation and strea flo( data.

    =ield observations !evie(of available topo&raphical

    aps land>use aps.)ccess to data available at

    Irri&ation and

    %eteorolo&icalDepartents.

    Topo&raphical aps land>useaps hydrolo&ical data fro

    Irri&ation Departent and%eteorolo&ical Departent.

    Site visits to cover selectedse&ents ostly not

    coincidin& (ith cobinedtrace identified fro

    preliinary reconnaissance.

    2. I) and Policy Specialist nvironental ipacts identified by

    other resource personnel

    'onsultations (ith project

    staff and !D) officials

    Periodic pro&ress reports by

    resource personnel Inforationprovided by !D) officials

    Site visi ts to onitor

    activities of other resourcepersonnel

    3. Deputy Tea 0eader"!evie( !eports#

    )ll inforation copiled by otherresource personnel and all relevant

    docuents and past study reports

    Throu&h re)D7 )ll inforation copiled by other

    resource personnel and all relevant

    docuents and past study reports

    pertinent to )D7 section of thehi&h(ay.

    Throu&h consultations in

    the )D7 section pro&ress

    reports relevant to this

    section received fro othertea ebers.

    Pro&ress reports of other tea

    ebers (or4in& in this

    section inforation provided

    by local residents

    Site visi ts to onitor

    activities of other resource

    personnel in the )D7 section.

    +. Traffic n&ineerTransport

    Planner

    Infrastructure facilities of the project

    area eistin& public and privatetransport facilities Planned

    developent activities in the project

    area.

    !evie( of relevant

    previous reportsconsultations (ith officials

    of !D) D) Provincial

    'ouncils

    Previous study reports of STDP

    and other relevant projectreports

    Site visits to clarifyverify

    inforation &athered toselected stretches.

    1,

  • 5/21/2018 Inception Report SHway-Modified

    18/22

    "esource Personnel ature of Infor&ation to be

    Collected

    $ethod of Data

    Collection

    ources of Infor&ation ite ;isits

    ,. Soils Slopes and Geolo&ySpecialist

    Data on ineral resourcesconstruction %aterials "a# !oc4A "b#

    Gravel and fill aterial and "c# sand

    Sub>surface condition 0and forstability of natural and an>ade

    slopes.

    !evie( of previous studyreports field observations

    consultations (ith local

    residents &roups andor&aniBations.

    Previous study reports &eolo&ical aps of the project

    area field observations and

    local residents.

    Site visits to cover criticalsensitive areas in ters of

    &eotechnical&eolo&ical

    stability as identified durin&preliinary reconnaissance.

    H. Fater uality and

    nvironental n&ineerin&Specialist

    istin& bac4&round data alon& the

    proposed trace on air

  • 5/21/2018 Inception Report SHway-Modified

    19/22

    "esource Personnel ature of Infor&ation to be

    Collected

    $ethod of Data

    Collection

    ources of Infor&ation ite ;isits

    11. )&ricultural conoist 0and use ployent )&riculturaland industrial production systes

    Socio>econoic profile and resource

    base 7usiness and self eployent6oe &arden systes )nial

    husbandryfishin& and environentaletracts Ta revenues of local

    authorities istin& ar4et prices of

    land labour inputs and outputs and

    their chan&in& patterns Touris andsupportin& services 6andicrafts andother area specific production

    systes

    Intervie(s of authoritiesand persons in the potential

    area !apid rural appraisal

    ethods to iniiBe thetie

    Divisional Secretariats "DS#Graa ?iladaris "G?# 0ocal

    )uthori ties "Provincial

    'ouncils rban 'ouncils#)&rarian Service 'entres

    =arer Or&aniBations?GOs7usiness enterprises !eli&ious

    and social leaders People in the

    affected area.

    9o&&ala la4e %atte&odaarea !antotu(ila 7orala

    tan4 7ol&oda tan4 7ol&oda

    la4e Panape ela Pol(atu&an&a lo(er catchent

    6i44adu(a tourist area.

    12. 0andscape and )esthetics

    Specialist

    0andscape alon& final road trace

    historical and archaeolo&icalonuents places of (orship and

    reli&ious interest

    !evie( of relevant

    previous reportsconsultations (ith officials

    of Departent of

    )rcheolo&y field visits

    Inforation &athered fro

    Departent of )rcheolo&yprevious study reports field

    study findin&s

    Site visits to identified

    stretches durin& preliinaryreconnaissance.

    1C

  • 5/21/2018 Inception Report SHway-Modified

    20/22

    . "eportin%

    The follo(in& reports (ill be subitted (ithin the course of the study period.

    1. Inception !eport on proposed ethodolo&y approach and assessent teas (ithin 1

    (ee4 fro the coenceent of (or4.2. Interi !eport (ithin , (ee4s fro the coenceent of (or4.

    3. Draft =inal !eport for )D7 revie( (ithin 15 (ee4s fro the coenceent of (or4.

    $. =inal !eport 1* (ee4s after coenceent of study.

    4. Ti&e chedule

    The tie schedule of activities planned (ithin the study period is as &iven Table +.1.

    25

  • 5/21/2018 Inception Report SHway-Modified

    21/22

    Proposed Time Schedule

    Item Description 0

    .5

    1

    .0

    1

    .5

    2

    .0

    2

    .5

    3

    .0

    3

    .5

    4

    .0

    4

    .5

    5

    .0

    5

    .5

    6

    .0

    6

    .5

    7

    .0

    7

    .5

    8

    .0

    8

    .5

    9

    .0

    9

    .5

    1

    0

    .0

    1

    0

    .5

    11.

    0

    11.

    5

    1

    2

    .0

    1

    2

    .5

    1

    3

    .0

    1

    3

    .5

    1

    4

    .0

    1

    4

    .5

    1

    5

    .0

    1 Mobilisation and Initial Meetings

    1-1 Inception Report

    2 TOR items 6(i),(ii),(iii), (iv),(v)

    2-1 es! "or! and Meetings

    2-2 #ite Inspection and ata $ollection

    2-3 Internal Report %reparation

    3 TOR item 6(vi)

    3-1 &otices' $orrespondance ( es! "or!

    3-2 #ite inspection' )ield "or! and Meetings

    3-3 Maps' )ig*res' +ables and +e,t

    4 TOR item 6(vii)-(ix)

    4-1 Reision and es! "or!

    4-2 Report )ormatting and preparaion

    4-3 Interim Report

    4-4 ra.t )inal Report

    4-5 $omments o. R/' /0 and oters

    4-6 )inal Report .or R/

    5 TOR item 6(x)

    5-1 $omment Incorporaton and #*mmar /

    5-2 Report and #*mar / %reparation

    5-3 Interim Report

    5-4 ra.t )inal Report

    5-5 R/ and /0 comments

    5-6 )inal Report

    *Commencement is from the signinig of the contract and receipt of the first advance payment

    "ee!s .rom $ommencement

    Table 4.1 Proposed Ti&e chedule

  • 5/21/2018 Inception Report SHway-Modified

    22/22

    5. $eetin%s0 Consultations and ;isits

    5.1 $eetin%s

    Since the reSTDP# as &iven in

    Table ,.1.

    Table 5.1 Details of $eetin%s bet9een tud! Tea&0 "DA0 AD, and $CSTDP and )D7

    * October 255$ !D) O% !D) and %'>STDP

    H October 255$ )D7 O% )D7

    1$ October 255$ !D) O% !D) STDP>%'

    25 8uly 255* !D) O% !D) / STDP STDP>%' SecyJ%inistry of 6i&h(ays

    5.2 ;isits

    The O% study tea undertoo4 t(o preliinary site reconnaissance visits to 87I' and )D7

    sections of the hi&h(ay on 15>11 October 255$ and 1+>1, October 255$. The findin&s of

    these visits (ere revie(ed by the individual ebers to&ether (ith available inforation and

    data to plan specific individual site visits.

    Since the reactivation of study the O% study tea undertoo4 a reconnaissance study on $

    Septeber 255* (hich covered both 87I' and )D7 sections.

    5.' Consultations

    'onsultations (ith local residents and other concerned parties (ill ta4e place if deeed

    necessary durin& this study period and (ill be or&aniBed and facilitated by the !D) and )D7.

    7. Pro%ress of or=

    The pro&ress of (or4 ade to>date ay be suariBed as follo(s@

    1. Several reports and docuents relevant to the study "See )nneure 3# collected copiesand dispatched aon& tea ebers.

    2. Di&ital aps of the hi&h(ay trace prepared and distributed aon& tea ebers.

    3. 6ydrolo&ical and environental data and relevant aps purchased.

    $. ) eetin& of the study tea (as held to coordinate and distribute the (or4.

    *. Three field reconnaissance surveys successfully copleted in 255$ and 255*.

    +. Soe individual site visits by specialist staff already underta4en.

    23