18
IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH CIRCUIT Bennett Brown, et al., ) Petitioners, ) v. ) No. 11-1441 U.S. Nuclear Regulatory Commission, et al. ) Respondents. ) FEDERAL RESPONDENTS' REPLY TO PETITIONERS' RESPONSE TO FEDERAL RESPONDENTS' MOTION TO DISMISS The Federal Respondents have moved to dismiss this case because Petitioners (1) did not file their Petition for Review within 60 days of entry of the NRC Order as the Hobbs Act requires, 28 U.S.C. §2344, and (2) did not exhaust their administrative remedies by fully participating as parties in the NRC hearing process, as the Atomic Energy Act ("AEA") and NRC regulations require. Petitioners' Response to our Motion is unpersuasive. Background. This lawsuit challenges the NRC's environmental review of an application to renew the operating license for the Duane Arnold Energy Center. Petitioners submitted comments either during the environmental scoping process or in response to the publication of the Draft Supplemental Environmental Impact Statement (SEIS). But Petitioners never attempted to intervene or seek a hearing in the administrative proceeding to review the license renewal application.

IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

IN THE UNITED STATES COURT OF APPEALSFOR THE EIGHTH CIRCUIT

Bennett Brown, et al., )Petitioners, )

v. ) No. 11-1441U.S. Nuclear Regulatory Commission, et al. )

Respondents. )

FEDERAL RESPONDENTS' REPLYTO PETITIONERS' RESPONSE

TO FEDERAL RESPONDENTS' MOTION TO DISMISS

The Federal Respondents have moved to dismiss this case because

Petitioners (1) did not file their Petition for Review within 60 days of entry of the

NRC Order as the Hobbs Act requires, 28 U.S.C. §2344, and (2) did not exhaust

their administrative remedies by fully participating as parties in the NRC hearing

process, as the Atomic Energy Act ("AEA") and NRC regulations require.

Petitioners' Response to our Motion is unpersuasive.

Background.

This lawsuit challenges the NRC's environmental review of an application

to renew the operating license for the Duane Arnold Energy Center. Petitioners

submitted comments either during the environmental scoping process or in

response to the publication of the Draft Supplemental Environmental Impact

Statement (SEIS). But Petitioners never attempted to intervene or seek a hearing

in the administrative proceeding to review the license renewal application.

Page 2: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-2-

The NRC issued a Final SEIS in October, 2010, and formally announced it

in the Federal Register. See 75 Fed. Reg. 64,748 (Oct. 20, 2010). The NRC then

issued the renewed license on December 16, 2010, and formally announced it in

the Federal Register on December 29, 2010. See 75 Fed. Reg. 82,091 (Dec. 29,

2010). On February 28, 2011, Petitioners filed this case challenging the NRC's

response to their comments more than 60 days after the December 16th entry of the

NRC renewal of the license.

The Petition for Review Is Untimely.

The Hobbs Act requires a party aggrieved by a final order to file a petition

for review within 60 days of its "entry." In attempting to show their petition is

timely, Petitioners argue that the meaning of "entry" differs by party depending on

when a party is served or receives notice of the order. They maintain that the 60-

day filing period under the Hobbs Act did not start to run until the publication of

the Federal Register Notice on December 29, 2010, because that is the date that

the Duane Arnold Renewed License became "final, complete, and a matter of

public record." Response at 8 (citing Chem-Haulers, Inc. v, United States, 536

F.2d. 610, 616 (5th Cir. 1976)). Petitioners also claim that they did not know how

the NRC responded to their comments (both during the scoping process and on the

Draft SEIS) until publication of the December 29th Federal Register Notice - the

Page 3: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-3-

first time they knew (they say) the Final SEIS was available. Response at 8-9

(citing Affidavits of Bennett Brown, Robert Schultes, and Pamela Mackey Taylor).

Petitioners also allege the NRC violated its own regulations by not mailing a copy

of the Final SEIS to all who commented. Response at 9.

Petitioners' claims are contradicted by the record. First, as noted above (and

in the Motion to Dismiss at page 3), the NRC issued a Federal Register Notice on

October 20, 2010, announcing issuance of the Final SEIS. The October Notice

also listed an "accession number" - ML 102790308 - enabling members of the

public to find, view and print the Final SEIS from the NRC's Web-based document

retrieval system. See 75 Fed. Reg. at 64,749. And when the final license-renewal

order was entered - on December 16 - it was announced in an NRC press release

and immediately reported in the press. See Motion to Dismiss at 7 and Exhibit 2.1

Thus, it is simply not true that Petitioners "had no way of knowing the contents of

1Petitioners complain that "even now" they cannot access the renewed

license itself on the NRC webpage associated with the Duane Arnold relicensing.Response at 9. The renewed license is available on the NRC website through theNRC document-retrieval system, ADAMS. See ML102930586. But our Motionincorrectly states the license was made available on December 16th; we have sincelearned it was made available on December 30th. We apologize for the error - andfor the delay. The SEIS is now - and has been since October 20, 2010 - availableon the Duane Arnold relicensing webpage for viewing and downloading.

Page 4: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-4-

the final order until it appeared in the Federal Register on December 29, 2010."

Second, the SEIS itself lists the names of all those to whom copies were

mailed. The SEIS mailing list (attached as Exhibit 1) includes the Petitioners in

this lawsuit. See Exhibit 1, pp.4 & 5. "[A] presumption of regularity attaches to

the actions of government agencies." U.S. Postal Service v. Gregory, 534 U.S. 1,

10 (2001). "[I]n the absence of clear evidence to the contrary, courts presume that

[public officials] have properly discharged their official duties." United States v.

Chemical Foundation, Inc., 272 U.S. 1, 14-15 (1926). See also Wilburn v. Astrue,

626 F.3d 999, 1034-04 (8th Cir. 2010). Thus, this Court must presume the NRC

did indeed mail copies of the Final SEIS to Petitioners, as the SEIS itself states.

Finally, and most importantly, Petitioners' argument that the December 29th

Federal Register Notice started their 60-day window to file their Petition for

Review contradicts the plain terms of the Hobbs Act, which provides that any

lawsuit must be filed within 60 days of the "entry" of the agency order challenged.

See 29 U.S.C. § 2344. "Entry" of a decision, order, or judgment refers to one

specific time, e.g., "the court entered judgment on [a specific date]." Under

Petitioners' argument, the date of "entry" would differ depending on when any

given party learned of the order. But the Hobbs Act does not say a petition must

be filed within 60 days after "service" of the order or after it was first "noticed"- it

Page 5: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-5-

specifies "entry" of the order as the trigger date. "[W]ith respect to filing deadlines

a literal reading of Congress' words is generally the only proper reading of those

words." United States v. Locke, 471 U.S. 84, 93 (1985).2

Section 2344 also states that "on entry of a final order ... the agency shall

promptly give notice thereof by service or publication in accordance with its

rules[,]" showing that "entry" is something different from "notice," "service," or

"publication." Here, as required by Section 2344, the NRC promptly gave notice

of the "entry" of the decision by publication in the Federal Register. Thus, the

December 29th Federal Register Notice placed Petitioners on notice of that the

agency decision was "entered" on December 16, 2010. While the question may be

more complicated when the agency fails to provide any notice of a decision, that is

not this case. Here, the NRC published timely notice of the decision and correctly

identified the date of "entry" as December 16.

In sum, even if Petitioners were unaware of the "entry" of the license until

December 29th, they were still obligated to file suit within 60 days of the order's

actual "entry," i.e., by February 14, 2011. Because they did not file this petition

2See also Avia Dynamics v. FAA, __ F.3d _,201.1 WL 1466330 at *3-*5(D.C. Cir., Apr. 19, 2011); Heide v. FAA, 110 Fed. App'x 724, 725 (8th Cir. 2004).

Page 6: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-6-

for review until February 28 - 2 weeks later - their lawsuit should be dismissed as

untimely.

Petitioners Failed to Exhaust Their Administrative Remedies.

The Hobbs Act permits suits only by "parties" to agency proceedings. See

28 U.S.C. § 2344. Petitioners argue that by virtue of filing comments they became

"parties," within the meaning of the Hobbs Act, to the NRC administrative

proceeding to review the license renewal application, held under Section 189a of

the AEA, 42 U.S.C. § 2239(a). Thus (they argue), they did not need to intervene in

the NRC's hearing process. See Response at 13-15. This argument misapprehends

the nature of the interplay between the Hobbs Act and the AEA.

If this Court has jurisdiction over the petition for review, that jurisdiction is

based on the Hobbs Act, 28 U.S.C. § 2341, et seq. That statute gives this Court

jurisdiction over "all final orders of the [Nuclear Regulatory] Commission made

reviewable by section 2239 of title 42." 28 U.S.C. § 2342(4). In turn, 42 U.S.C.

§ 2239(b) provides

[t]he following Commission actions shall be subject to judicial review under[the Hobbs Act and the Administrative Procedure Act]: (1) Any final orderentered in any proceeding of the kind specified in subsection (a).

Subsection (a) provides:

In any proceeding under this Act, for the granting, suspending, revoking, oramending of any license[,] ... the Commission shall grant a hearing upon the

Page 7: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-7-

request of any person whose interest may be affected by the proceeding, andshall admit any such person as a part)' to the proceeding.

42 U.S.C. § 2239 (a)(1) (emphasis added). Here, Petitioners challenge the granting

of the 20-year renewal of the Duane Arnold operating license. So to challenge the

NRC decision to issue the renewed license under the Hobbs Act, Petitioners must

show they were a "party" to a "proceeding" as defined in 42 U.S.C. § 2239(a).

Here, Petitioners argue that they became a "party" for purposes of the Hobbs

Act by participating in the "scoping process" or by commenting on the draft SEIS.

Response at 14-16. But the nature of an NRC proceeding is defined by NRC

regulations, which explicitly state that participation in the scoping process (or

commenting on environmental documents) is not participation in the NRC's

administrative hearing process. See 10 C.F.R. § 51.28(c). Instead, persons who

wish to challenge the issuance of a license must participate in the NRC

adjudicatory process. This includes claims under the National Environmental

Policy Act (NEPA), 42 U.S.C. § 4321, etseq. See 10 C.F.R. § 2.309(0(2).

As the Supreme Court noted years ago in a landmark NRC case,

"administrative agencies should be free to fashion their own rules of procedure and

to pursue methods of inquiry capable of permitting them to discharge their

multitudinous duties." Vermont Yankee Nuclear Power Corp. v. NRDC, 415 U.S.

519, 543 (1978) (internal quotation marks and citations omitted). See also,

Page 8: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-8-

Citizens Awareness Network v. United States, 391 F.3d 338, 349 (1st Cir. 2004);

Union of Concerned Scientists v. NRC, 920 F.2d 50, 53-54 (D.C. Cir. 1990). Thus,

the NRC has acted well within its authority in requiring persons seeking to litigate

environmental issues to proceed through its "adjudicatory process" rather than

allowing them to proceed through a "comment process."

In addition, the "party" analysis under the Hobbs Act necessarily is linked to

the kinds of administrative remedies available. While it is true that some agencies

provide participation by "comment" only, the NRC requires persons who wish to

litigate environmental issues to seek an agency hearing at the earliest possible

moment. See 10 C.F.R. § 2.309(f)(2); Motion to Dismiss at 4. The NRC provides

an extensive hearing process to have complaints heard by, and remedied by, the

agency prior to judicial review. See Motion to Dismiss at 5 & nn. 2-3.

The NRC's additional "public comment" process covering environmental

documents such as the SEIS flows from the NEPA, 42 U.S.C. § 4321, et seq., not

from the AEA, 42 U.S.C. § 2201, et seq. Thus, mere participation in a NEPA

"comment" process does not entitle a "person" to become a "party" in an NRC

administrative proceeding held under the authority of the AEA's Section 189a, 42

U.S.C. § 2239(a). Instead, to be a "party" under the Hobbs Act, a person must

seek to intervene as a "party" in an AEA proceeding under the NRC's rules.

Page 9: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-9-

The Hobbs Act's "party" requirement, in essence, codifies the general

administrative law requirement that those seeking judicial relief first exhaust their

administrative remedies. A person participating in an agency proceeding cannot

simply stop in the middle of the process and, ignoring any remaining available

steps, proceed immediately to court. As the Supreme Court has held repeatedly, a

court should dismiss a lawsuit where the litigant did not fully exhaust available

administrative remedies. E.g., Woodford v. Ngo, 548 U.S. 81, 90 (2006). This

Circuit has consistently followed that principle, requiring parties to exhaust all

available remedies before proceeding to court, regardless of the statute involved.

See, e.g., U.S. v. Dico, Inc., 136 F.3d 572-575-76 (8th Cir. 1998); Sharps v. U.S.

Forest Service, 28 F.3d 851, 853-54 (8th Cir. 1994); Madsen v. Department of

Agriculture, 866 F.2d 1035, 1038 (8th Cir. 1989); United States v. Bisson, 839

F.2d 418 (8th Cir. 1988). Here, Petitioners effectively acknowledge they did not

exhaust their administrative remedies because they failed to seek intervention and

request a hearing. Had they done so, they might have obtained relief from the

NRC, obviating the need to seek relief in this Court.

Finally, Petitioners make much of Massachusetts v. United States, 522 F.3d

115 (1st Cir. 2008), but misinterpret the case. Response at 17-19. In that case, the

Court held principally that the Commonwealth could not obtain party status to

Page 10: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-10-

challenge an NRC regulation in an agency adjudicatory proceeding. 522 F.3d at

119-25. But the NRC acknowledged that the Commonwealth could "participate"

in the proceeding under 10 C.F.R. § 2.3 15 (which allows participation by states),

id. at 125, 128, and that if it participated in the proceeding under that provision, it

would be considered a "party" for Hobbs Act purposes if it later decided to

challenge the result of the proceeding in Federal Court. Id. at 130-31. The Court

stated that in that situation the Commonwealth would appear to have "directly and

actually ... participated in the administrative proceedings." Id. at 131 (quoting

Clark & Reid Co. v. U.S. 804 F.2d 3 (1st Cir. 1986)). The Court then held that

because participation in the NRC proceeding under section 2.315 was still

available, the Commonwealth had not yet exhausted its administrative remedies.

Id. at 132.

The applicability of Massachusetts to this case is obvious. Here, Petitioners

- like the Commonwealth - have not exhausted their administrative remedies.

CONCLUSION

For the foregoing reasons, and the reasons stated in our Motion to Dismiss,

this court lacks jurisdiction over the petition for review and it must be dismissed.

Respectfully submitted,

Page 11: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

-11 -

IGNACIO S. MORENOAssistant Attorney General

_s/Allen M. Brabender/cemAttorney, U.S. Department of JusticeEnvironment and Natural Resources

Division, Appellate SectionP.O. Box 23795, L'Enfant Plaza StationWashington, D.C. 20026-3795(202) 514-5316

JOHN F. CORDES, JR.Solicitor

s/Charles E. MullinsSenior AttorneyOffice of the General CounselU.S. Nuclear Regulatory

Commission11555 Rockville PikeRockville, Maryland 20852(301) 415-1618

May 9, 2011

Page 12: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

FEDERAL RESPONDENTS' REPLYTO PETITIONERS" RESPONSE

TO FEDERAL RESPONDENTS' MOTION TO DISMISS

EXHIBIT 1

Page 13: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

12.0 LIST OF AGENCIES, ORGANIZATIONS, AND PERSONS TOWHOM COPIES OF THE SUPPLEMENTAL ENVIRONMENTAL IMPACT

STATEMENT ARE SENT

Name and Title

Mr. M. S. Ross

Managing Attorney

Ms. Marjan MashhadiSenior Attorney

T. 0. JonesVice President, Nuclear Operations

Steven R. CatronManager, Regulatory Affairs

Affiliation and Address

Florida Power & Light CompanyP.O. Box 14000Juno Beach, FL 33408-0420

Florida Power & Light Company801 Pennsylvania Avenue, NWSuite 220Washington, DC 20004

Mid-West RegionFlorida Power & Light CompanyP.O. Box 14000Juno Beach, FL 33408

Duane Arnold Energy Center3277 DAEC RoadPalo, IA 52324

Resident Inspector's Office U.S. Nuclear Regulatory CommissionResident Inspector's OfficeRural Route #1Palo, IA 52324

Florida Power & Light CompanyP.O. Box 14000Juno Beach, FL 33408

Mr. Mano Nazar

Senior Vice President and Nuclear ChiefOperating Officer

Mr. D. A. Curtland Duane Arnold Energy CenterPlant Manager 3277 DAEC Road

Palo, IA 52324-9785

Vice President, Engineering Support Florida Power & Light CompanyP.O. Box 14000Juno Beach, FL 33408

Melanie RasmussonBureau of Radiological Health

Iowa Department of Public Health

Bureau of Radiological Health

321 East 12th StreetLucas State Office Building, 5th Floor

Des Moines, IA 50319-0075

NUREG-1437, Supplement 42October 2010 12-1

Page 14: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

List of Agencies, Organizations, and Persons

Name and Title Affiliation and AddressAffiliation and Address

Chairman Linn CountyBoard of Supervisors930 1st Street SWCedar Rapids, IA 52404

Florida Power & Light CompanyP.O. Box 14000Juno Beach, FL 33408-0420

Peter WellsActing Vice President, Nuclear Training andPerformance Improvement

Mark E. WarnerVice President, Nuclear Plant Support

George Thurman.Principal Chief

Florida Power & Light CompanyP.O. Box 14000Juno Beach, FL 33408-042

Sac and Fox Nation of OklahomaRoute 2 Box 246Stroud, OK 74079

Fredia Perkins Sac and Fox Nation of MissouriChairperson 305 North Main Street

Reserve, KS 66434

Christie Modlin Iowa Tribe of OklahomaChairperson Route 1, Box 721

Perkins, OK 74059

Steve Cadue Kickapoo Tribe in KansasChairman P.O. Box 271

Horton, KS 66439

Steve Ortiz Prairie Band of Potawatomi Indians

Chairman 16281 Q RoadMayetta, KS 66509

Joshua Weston Flandreau Santee Sioux Tribe

President P.O. Box 283Flandreau, SD 57028

Mr. Roger Trudell Santee Sioux Nation

Chairman 108 Spirit Lake Avenue, WestNiobrara, SD 68760-7219

John Blackhawk Winnebago Tribe of NebraskaChairman 100 Bluff Street

P.O. Box 687Winnebago, NE 68071

NUREG-1437, Supplement 41 12-2 October 2010

Page 15: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

List of Agencies, Organizations, and Persons

Name and Title Affiliation and Address

Ronald Johnson Prairie Island Indian CommunityPresident 5636 Sturgeon Lake Road

Welch, MN 55089

Stanley R. Crooks Shakopee Mdewakanton Sioux Community ofChairman Minnesota

2330 Sioux Trail NWPrior Lake, MN 55372-9077

Kevin Jensvold Upper Sioux Community of MinnesotaChairman P.O. Box 147

Granite Falls, MN 56241-0147

Wilfred Cleveland Ho-Chunk NationPresident W9814 Airport Road

P.O. Box 667

Black River Falls, WI 54615

Adrian Pushetonequa The Sac and Fox Tribe of the Mississippi:Chairman 349 Meskwaki Road

Tama, IA 52339

Lori Nelson Lower Sioux Indian Community of MinnesotaActing Chair 39527 Res Highway 1

P.O. Box 308Morton, MN 56270

Amen Sheriden Omaha Tribal Council

Chairman P.O. Box 368Macy, NE 68039

Marion E. Frye Kickapoo Tribe of OklahomaChairman P.O. Box 70

McCloud, OK 74851

John Shotton Otoe-Missouria Tribe of Indians8151 Highway 177Red Rock, OK 74651

Leon Campbell Iowa Tribe of Kansas and NebraskaChairman 3345 Thrasher Road

White Cloud, KS 66094

Wayne Gieselman Iowa Department of Natural ResourcesAdministrator Environmental Services Division

502 East 9th StreetDes Moines, IA 50319.

October 2010 12-3 NUREG-1437, Supplement 42

Page 16: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

List of Agencies, Organizations, and Persons

Name and Title

Richard Nelson

Field Supervisor

Affiliation and Address

U.S. Fish and Wildlife Service

Rock Island Field Office

1511 4 7th Ave.

Moline, Illinois 61265

Robert F. StewartRegional Environmental Officer

United States Department of the InteriorOffice of the SecretaryOffice of Environmental Policy andComplianceDenver Federal Center, Building 67, Room118Post Office Box 25007 (D-108)Denver, Colorado 80225-0007

Charlene Dwin Vaughn

Assistant Director

Federal Permitting, Licensing, and AssistanceSection

Advisory Council on Historic Preservation

Old Post Office Building1100 Pennsylvania Ave, NW, Suite 803Washington, DC 20004

Office of the State Archaeologist

700 South Clinton Street Building

University of Iowa

Iowa City, IA 52242-1030

John DoershuckState Archaeologist

Jerome Thompson State Historical Society of Iowa

Interim State Historic Preservation Officer 600 East Locust Street

Des Moines, IA 50319

Doug Jones State of Iowa Historical Building (Des Moines)600 East LocustDes Moines, Iowa, 50319515-281-5111

Dusky Terry Central Iowa Power CooperativeCitizen 2600 Grand Avenue, Suite 410

Des Moines, IA 50312

Bennett Brown 1025 Friendly AveCitizen Iowa City, IA 52240

Amir H. Moazzez 3650 Joseph Siewick, Dr. #309Fairfax VA 22033

NUREG-1437, Supplement 41 12-4 October 2010

Page 17: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

List of Agencies, Organizations, and Persons

Name and Title Affiliation and Address

Hiawatha Public Library Hiawatha Public Library150 W. William St.,Hiawatha IA

Mr. Joseph Cothern Environmental Services DivisionEnvironmental Review Coordinator USEPA, Region 7

901 North 5th StreetKansas City, KS 66101

Northwest University Northwest University

Northwestern University Library1970 Campus DriveEvanston, IL 60208-2300

Dr. Robert Schultes 1000 Prairie Drive NECedar Rapids, Iowa 52402

W. L. Taylor, Legal Chair and Sierra ClubP. M Taylor, Energy Committee Chair Iowa Chapter Headquarters

3839 Merle Hay RoadSuite 280Des Moines, IA 50310

October 2 010 12-5 NUREG-1437, Supplement 42

Page 18: IN THE UNITED STATES COURT OF APPEALS FOR THE EIGHTH … · 2012. 12. 4. · 2010). On February 28, 2011, Petitioners filed this case challenging the NRC's response to their comments

CERTIFICATES OF SERVICEFOR DOCUMENTS FILED USING CM/ECF

Certificate of Service When All Case Participants Are CM/ECF Participants

I hereby certify that on May 5, 2011 , I electronically filed the foregoing with the Clerk ofthe Court for the United States Court of Appeals for the Eighth Circuit by using the CM/ECFsystem. I certify that all participants in the case are registered CM/ECF users and that servicewill be accomplished by the CM/ECF system.

s/ Charles E. Mullins