Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
REPUBLIC OF SOUTH AFRICA
IN THE HIGH COURT OF SOUTH AFRICA GAUTENG DIVISION, PRETORIA
CASE NO: 50919/2017
In the matter between:
DR NOMATHEMBA BLAAI MOGKETHI
and
THE SPEAKER OF COUNCIL: NORTH WEST 405
APPLICANT
(VENTERSDORP/TLOKWE LOCAL MUNICIPALITY) 15r RESPONDENT
THE EXECUTIVE MAYOR OF THE NORTH WEST 405 (VENTERSDORP/TLOKWE LOCAL MUNICIPALITY) 2ND RESPONDENT
THE COUNCIL OF NORTH WEST 405 (VENTERSDORP/TLOKWE LOCAL MUNICIPALITY) 3RD RESPONDENT
NORTH WEST 405 (VENTERSDORP/TLOKWE LOCAL MUNICIPALITY) 4TH RESPONDENT
THE MEC FOR THE NORTH WEST PROVINCIAL LOCAL GOVERNMENT AND HUMAN SETTLEMENTS DEPARTMENT 5™RESPONDENT
HENDRIK ERIC LOUW 5THRESPONDENT
JUDGMENT
MOOSAAJ:
2
Introduction:
[1] This is an application wherein the applicant applies for the following
interim interdictory rel ief pending the outcome of an application to be
launched within 10 days of the order:
1.1 The First to Fourth Respondents are interdicted and restrained
from acting upon the letter alternatively notice of decision from the
office of the Fifth Respondent addressed to and received by the
Second Respondent in July 2017 and which is annexed to the founding
affidavit marked "FA9".
1.2 Interdicting and restraining the First to Fourth Respondents from
tabling, discussing, deliberating and/or deciding the validity of the
Applicant's employment and contract with the Fourth Respondent.
[2] Properly construed , the applicant prays in her notice of motion for
interim interdictory relief, which can be framed as follows:
The First to Fourth Respondents are interdicted and restrained :
[a] from acting upon the letter alternatively notice of decision from
the office of the Fifth Respondent addressed to and received by the
Second Respondent during July 2017 and which is annexed to the
founding affidavit marked "FA9".
[b] from tabling, discussing, deliberating and/or deciding the validity
of the Applicant's employment contract with the Fourth Respondent.
[3] The aforementioned interdict to operate as an interim interdict pending
the outcome of an application by the Applicant, to be issued within 10 (ten)
days of the order:
3.1 to review the decision of the Fifth Respondent as contained in
the letter alternatively notice of decision from the office of the Fifth
Respondent addressed to and received by the Second Respondent
3
addressed to and received by the Second Respondent in July 2017
and which is annexed to the founding affidavit marked "FA9"; and/or
3.2 declaring that the Applicant is the appointed Municipal Manager
of the Fourth Respondent by fixed term contract until 30 June 2018
alternatively 05 December 2020; and/or
3.3 directing that the Fourth Respondent comply with the Applicant's
contract of employment and interdicting and restraining the First to
Sixth Respondents from bringing about the termination of the
Applicant's employment without due process of law and compliance
with the terms of her contract of employment.
[4] Accordingly, the main application includes a review application in terms
of Rule 53 of the Uniform Rules of Court.
[5] All the Respondents oppose the interim interdictory relief sought.
Points in Limine:
[6] Urgency - After hearing argument and considering the submissions that
were made regarding the urgency of the matter, the Applicant's first prayer
that the matter be disposed off in terms of Rule 6(12) of the Uniform Rules of
this court was granted.
[7] Jurisdiction - The applicant's counsel submitted that the CCMA 1 was
unable to deal with this matter, as it only deals with unfair labour practices and
the nature of the current dispute between the parties clearly could not be dealt
with by the CCMA. Arguing further that this court enjoyed the necessary
jurisdiction to adjudicate the matter. The Respondents however contended
differently. Briefly arguing that the Labour Court was the correct forum where
1 Council for Conciliation Mediation and Arbitration
4
the dispute relating to the termination of the contract could be dealt with. After
hearing argument and considering the matter, I accordingly ruled that the High
Court enjoyed jurisdiction to adjudicate this matter.
[8] Res Judicata - Counsel for the Fifth and Sixth Respondents
subsequently raised the defence of res judicata, which became highly
contentious. It is noteworthy to mention that a very substantial part of the
proceedings of the day was spent on hearing argument in this regard , and
which point was argued relentlessly by the relevant litigants.
In essence, the point taken by counsel for the aforementioned Respondents
concerned the dismissal of the application at the hearing during the previous
week before the North West High Court, by his Lordship Mr Acting Deputy
Judge President (ADJP) Hendriks. Mr Scholtz who appeared for the Fifth
Respondent in that court and who now raised this point contented that the
application was dismissed with costs and implying that the application was
dismissed on it's merits. Further submitting to this court, upon query, that he
"was unable to get into the head of the judge in knowing why the application
was dismissed with costs". Counsel for the Sixth Respondent also joined the
fray to argue this point relentlessly; arguing that the point raised by the Sixth
respondent was a 'red herring', despite the Sixth Respondent not being a
party to the proceedings before the court a quo.
Mr Willis on behalf of the Applicant submitted that the application was
dismissed purely on the basis of lack of jurisdiction and not premised on the
merits. Arguing in the .circumstances that the application before this court was
not res judicata. Despite these submissions made by counsel for the
applicant, the aforementioned Respondents counsel were adamant that this
application was res judicata, and were unrelenting with their persistence on
this point.
Having due regard fo the fact that there were two diametrically opposed
versions before this court, which could possibly on the one hand sound the
death knell of this application or conversely allow it to proceed, this court
5
deemed it imperative that further clarification be obtained from the Honourable
Hendriks ADJP. Efforts to contact him proved fruitless and the litigants were
duly informed of the outcome of such efforts. In the circumstances, the
litigants were requested to agree to the terms of a postponement sine die,
with interim relief for the applicant, pending the furnishing of reasons by the
court a quo.
Upon reconvening a short while later, much to the surprise and consternation
of this court, counsel for the Fifth and Sixth Respondents informed this court
that they now chose to abandon the res judicata point and accordingly
attempted to withdraw their defence and argument. Having carefully
considered the lengthy_ and vociferous arguments raised, the interests of the
parties, the fact that the entire application could turn on this pivotal point and
that the credibility of the parties hinged on the reasons furnished, this court
was of the view that it was imperative in the interests of justice that the
reasons be obtained from the court a quo.
Accordingly, this court did not accede to the request of the Fifth and Sixth
Respondents and the following order was granted:
"[a] The current proceedings are stayed pending the furnishing of reasons
by the Honourable Acting Deputy Judge Preident Hendriks in case number
UM 03/17 which was held on 18 July 2017 at Mmabatho, wherein he
"dismissed the application with costs".
[b] The First to Fourth Respondents are interdicted and restrained from
dealing with the employment and contract of the Applicant with the Fourth
Respondent, pending the judgment of th is court on the urgent application
before it.
[c] Costs reserved".
The reasons were subsequently received and the matter proceeded on
14 September 2017. It is clear from the reasons obtained that the argument
6
raised by the Fifth and Sixth Respondents was spurious and disingenuous. In
essence, Hendriks ADJP submitted, inter alia, as follows: [6] "It is common
cause that Potchefstroom does not resort under the jurisdiction of the North
West Division of the High Court but rather under the jurisdiction of the North
Gauteng Division. Due to the lack of jurisdiction over this matter, this court
could not entertain this matter because it was in the incorrect or wrong forum.
No other aspect relating to this matter could have been entertained by this
court due to the lack of jurisdiction. [7] It is for this reason that I dismissed the
application with costs".
Accordingly, this point in limine was dismissed and the matter proceeded to
be argued on the merits.
Ad Merits:
[9] The main dispute between the Applicant and the Respondents pertains
to whether or not the Applicant's appointment as Municipal Manager of the
Ventersdorp/Tlokwe Municiplity had expired on 09 August 2017.
[1 O] It is common cause that the Applicant was duly appointed as the
Municipal Manager of the Tlokwe Municipality in terms of a fixed term
employment contract, effective 01 July 2014 for a fixed period of four years i.e
until 30 June 2018, subject to the applicable legislation and in particular
Section 57(6)(a) of the Local Government: Municipal Systems Act2
("Systems
Act").
[11] Section 57(6)(a) of the Systems Act provides as follows:
"(6) The employment contract for a municipal manager must -
z 32 of 2000
(a) be for a fixed term of employment up to a maximum of
five years, not exceeding a period ending one year after the
election of the next council of the municipality."
7
[12] It is clear from the aforementioned that a Municipal Manager's
employment contract would terminate upon the expiry of its fixed period of
employment up to a maximum of five years, or one year after election of the
next council, which ever occurs first.
[13] It is common cause that upon or about 03 August 2016 the Tlokwe and
Ventersdorp Municipalities were disestablished and a new Municipality known
as NW 405, to be renamed in due course, was established.
[14] Section 14(1) of the Local Government: Municipal Structures Act3
("Structures Act") provides as follows:
(1 )(a) A municipality established in terms of Section 12 in a particular
area, supersedes the existing municipality or municipalities to the
extent that the existing municipality or municipalities fall within that
area.
(b) The superseding municipality becomes the successor in law of
the existing municipality subject to paragraph (c).
(c) Where a district municipality and one or more local
municipalities within the area of the district municipality supersedes
the existing municipality or municipalities in that area, the district
and local municipalities in that area become the successors in law
of the existing municipality or municipalities depending on the
specific assets, liabilities, rights and obligations allocated to the
district and local municipalities respectively in terms of the relevant
section 12 notice or notices".
[15] Pursuant to the terms of Section 14( 1 )(b) NW405 became the
successor in law of the existing municipalities4.
3117 of 1998 4 City of Cape Town & others v Robertson & others: 2005(2)SA 323 (CC) para SO
8
[16] Section 14(3)(a) of the Structures Act provides as follows:
"(3)(a) The transfer of a staff member in terms of a Section 12 notice
must be-
(i) on conditions of service not less favourable than those
under which the staff member served in the existing municipality;
and;
(ii) in accordance with the Labour Relations Act 1995 (Act
No. 66 of 1995)."
[17] Accordingly, in terms of Section 14(3)(a) of the Structures Act, the staff
of the existing municipalities were transferred to the employ of the
superseding Municipality, on such terms and conditions of service not less
favourable under which they previously served, subject to the provisions of
the Municipal Systems Act.
[18] On 01 August 2016, the Fifth Respondent issued a directive (Post
Election Transitional Measures), whose purpose was to direct and guide the
two Municipalities to manage the post elections Senior Management staffing
capacity. The Applicant was duly appointed as the Acting Municipal Manager
until the new Council of the Municipality was constituted.
[19] Concerns were subsequently raised regarding the impact and effect of
the aforementioned directive and the appointment of acting
Managers/Directors. This resulted in a legal opinion 5 being sought from
Messrs Willem Coetzee Attorneys regarding the validity of the acting
appointments, and which concluded, inter alia, that:
19.1 The MEC's directive was unlawful, ultra vires and invalid, as it
was not authorised by the empowering legislation.
s dated 14 September 2016
9
19.2 The MEC's directive was in addition procedurally fatally flawed
as it was not published in the Provincial Gazette and therefore on this
ground invalid.
19.3 The Municipality was therefore not bound by the directive.
19.4 The Municipal Council should as a matter of urgency attend to
the staff matters at its next meeting, including taking transitional
measures in compliance with labour law principles.
19.5 The Municipality should inform the MEG according ly.
(20] It is clear that neither the Municipal Systems nor Structures Act
empowers the Fifth Respondent to appoint or terminate the contracts of
Municipal Managers. Such power clearly vests in the Municipality and it's
Council and not the Fifth Respondent. Pursuant to the receipt of the opinion
and advice the Municipality proceeded to attend to it's staffing matters.
[21] It is common cause that at the Council meeting of the NW405
Municipal'ity, held on 06 December 2016, and in respect of item
C46/2016-12-06 on the agenda, the following was re.solved :
21.1 "That cognisance be taken of the report and legal opinion
received from Messrs Willem Coetzee Attorneys.
21.2 That the directives of the MEG Department of Local Government
and Human Settlement dated 1 August 2016 (attached to item
SPC3/2016-08-17) be corrected and that the following
Directors be appointed according to the conditions and
terms as stipulated in their respective contracts":
(my emphasis)
Dr N E Blaai-Mokgethi
C P Henri
P C Labuschagne
RT S Masitenyane
Ms B M B Mosepele
L J Nkhaumane
BM Zungu
Municipal Manager
Director Sports Arts and Culture
Director Economic Development
Director Corporate Services
Director Community Services
Director Public Safety
Director Infrastructure
10
21.3 That the Municipal Manager add an addendum to the contracts
of the abovementioned Directors to make provision for the replacement
of the name Tlokwe City Council and Ventersdorp Municipality with the
name Ventersdorp/Tlokwe Local Municipality MW 405 as well as the
changes depicted in paragraph 2 above."
[22] The Applicant submits that the Council duly took the aforementioned
decision and passed the resolution with the full knowledge and appreciation of
it's powers and authority under the Municipal Systems Act and the powers of
the Fifth Respondent in terms of the Municipal Systems and Structures Act.
Accordingly, all the aforementioned persons were appointed according to the
conditions and terms as stipulated in their respective contracts.
[23] Consequently, it is argued by the Applicant that her fixed term contract
of four years applied and that according to the terms and conditions therein
she would continue to be the Municipal Manager until 30 June 2018. In the
alternate, the Applicant contends that a second contract was concluded
effective 06 December 2016 for a fixed period of four years, expiring on
05 December 2020. Arguing further that the applicant has as extant contract
of employment with the superseding municipality NW405.
[24] The Applicant argues further that the intervening event of the
disestablishment of the Tlokwe Municipality on 03 August 2016 derailed it's
next election, and accordingly that 03rd August 2016 be regarded as the date
of the first election of the Council of the superseding Municipality (NW405) as
11
envisaged by Section 12(2)(b) of the Structures Act. The empowering section
states that the establishment of a council takes effect at the commencement
of the first election of the Council of that municipality.
[25] In essence, arguing that the first election of the Council of the NW405
Municipality cannot be regarded as the "next Council of the Tlokwe
Municipality" and therefore in the circumstances the latter provision of Section
57(6)(a) has no application. In effect, that the Applicant's tenure does not
come to an end on 09 August 2017 as argued by the Respondents, but on
30 June 2018, as per her fixed term contract.
[26] The Applicant further argued that the resolution of 06 December 2016,
wherein it was resolved that the Applicant be appointed as the Municipal
Manager is an administrative act, as defined in the Promotion of Access to
Justice Act6 (PAJA). As such, an administrative act, including an act which
appears unlawful, can only be set aside by a court of law7
.
[27] I do not deem it necessary to deal in minute detail with the individual
arguments of counsel on behalf of the Respondents for the sake of brevity
and to avoid prolix. In essence, having distilled the arguments, the
Respondents oppose the relief sought on the basis that:
27 .1 The employment contract of the Applicant has come to an end
on 09 August 2017, by virtue of the fact that the election of the
superseding Council was on 03 August 2016; and as provided for in
Section 57(6)(a) of the Systems Act "that the employment contract for a
municipal manager must not exceed a period ending one year after the
election of the next council of the Municipality".
6 3 of 2000 7 Oudekraal Estates Pty (Ltd) v City of Cape Town & others: 2004(6) SA 222
(SCA) para 26
12
27.2 That the ~econd contract of employment as contended by the
Applicant to endure until 05 December 2020 is clearly in contravention
of Section 57(1) and (3) of the Systems Act as the Applicant is unable
to rely on any written contract of employment signed by both parties on
06 December 2016.
27.3 That the applicant has failed to meet and prove the
requirements for the grant of an interlocutory interdict, as required by
law.
Requisites for an interlocutory interdict:
[28] The requirements which the applicant has to satisfy for the grant of
interim relief sought are as follows:
28.1 That the right which is the subject matter of the application and
which is sought to be protected by means of interim relief, is at least
prima facie established.
28.2 A well grounded apprehension of irreparable harm to the
applicant if the interim relief is not granted and the ultimate relief is
eventually granted.
28.3 That the balance of convenience favours the granting of interim
relief.
28.4 That the applicant has no other satisfactory remedy8
a Setlogelo v Setlogelo 1914 AD 221 at 227; Tshwane City v Afriforum 2016 (6) SA 279 (CC) at 298F-306B; National Treasury v Opponents to Urban Tolling Alliance 2012 (6) SA 223 (CC) at 235D-E
13
[29] It is trite and well established that the court has a general and
overriding discretion whether to grant or refuse an application for interlocutory
relief, which discretion must be exercised judicially upon a consideration of all
the facts9
. As to the manner in which the requisites for an interim interdict are
to be considered, these must not be viewed separately or in isolation but in
conjunction with one another in order to determine whether the Court should
exercise its discretion in favour of the grant of the interim relief sought.
Furthermore, there is, in particular, a clear interaction between the balance of
convenience and the strength of the prima facie case required. See:
Cambridge Plan AG and Another v Moore and Others 1987 (4) SA 821 (0) at
833F.
[30] The factors which should be taken into consideration in the exercise of
the discretion are:
(i) the applicant's prospects of success in the main action/
application;
(ii) the availability or not of an adequate ordinary remedy;
(iii) the balance of convenience and the respective prejudice which
would be suffered by each party as a result of the grant or refusal of an
interlocutory interdict.
[31] Where an applicant's right is clear and the other requisites are present,
no difficulty presents itself about granting an interim interdict 1°.
[32] It is duly accepted that the right to be set up by an applicant for a
temporary interdict need not be shown on a balance of probabilities. If it is
prima facie established though open to some doubt, that is enough (emphasis
added) 11. The prescribed manner of approach to determine whether a prima
facie right has been proven where the right is not clear on the affidavits then
the test for whether the applicant has established a prima facie case for an
9 Knox D'Arcy v Jamieson & Others 1996 (4) SA 348(A) at 361 H-1 10 Olympic Passenger Service (Pty) Ltd v Ramlagan 1957(2) SA 382 (D) at 383A 11 Webster v Mitchel 1948(1) SA 1186 (W) at 1189
14
interim interdict has been formulated by the court in the Webster case supra,
as follows:
"The proper manner of approach I consider is to take the facts as set out by
the applicant, together with any facts set out by the respondent which the
applicant cannot dispute, and to consider whether, having regard to the
inherent probabilities, the applicant could ("should" per the Goo/ case 12) on
those facts obtain final relief at the trial. The facts set up in contradiction by
the respondent should then be considered. If serious doubt is thrown upon the
case of the applicant he could not succeed in obtaining temporary relief, for
his right, prima facie established, may only be open to some doubt."
[33] In considering the inherent probabilities, as articulated in the Webster
case, the Court must also look at the question of the ultimate onus. As part of
the overall test however, Webster's case and Goof's case, when the Court
comes to consider whether the evidence tendered by the Respondents casts
a serious doubt on the Applicants' prima facie case, the Court, in considering
that particular aspect, namely whether the case put up by the Respondents,
casts a serious doubt, the Court is enjoined, as part of that exercise, to take
into account any onus which the Respondents would carry in the principal
case, that is when final relief is sought13. See also: Godbold v Tompson 1970
(1) SA 61 (0) at 63C 0.
[34] As regards a consideration of legal issues at the stage of interim relief,
the correct approach would appear to be that ordinary questions of law should
be decided at the interim stage whereas involved issues of law should be left
for determination by the trial Court.
[35] The fact that any interim relief granted may prove prejudicial to a party
does not mean that such relief amounts to a final and definitive order. In this
regard see African Wanderers Football Club (Pty) Ltd v Wanderers Club
1977(2) SA 38 (A) at 48G - H where the Court said : "The fact that the order
made by HOWARD J, could well prove to be prejudicial to the company does
12 Gool v Minister of Minister of Justice 1955(2) SA 682(C) 13 Salt of the Earth Creations et al v Stuttafords et al (unreported) 4720/ 2007
15
not therefore justify a contention that the order was a final and definitive order
and not merely an order ad servandam causam. Indeed, it very often happens
that, when a court is asked to grant a temporary interdict, and the right which
it is sought to protect is not clear, the court weighs, inter alia, the prejudice to
the applicant, if the interdict is refused, against the prejudice to the
respondent if it is granted14".
Applicants submissions for grant of interlocutory interdict:
[36] The applicant contends that she enjoys a prima facie right for the relief
sought and contends further that she has established such right for the
following reasons:
36.1 That she has a fixed term contract with the Municipality, which
expires on 30 June 2018 and accordingly can only be terminated on its
terms and lawfully. In this regard it is argued that on 06 December
2016 the resolution of Council confirmed her fixed term of employment,
in that she was appointed together with other Directors according to the
conditions and terms as stipulated in their respective contracts.
Effectively granting her security of tenure until 30 June 2018, in terms
of her fixed term employment contract.
36.2 That no other grounds are relied upon for the termination of her
contract other than the rationale in the letter of the Fifth Respondent
and the Report of the Second Respondent.
36.3 That her contract is extant and enforceable and she has a right
to performance and for the contract not to be interfered with,
repudiated or breached.
36.4 That she enjoys the right to negotiate the renewal of the
contract, as per the terms and conditions of her employment contract.
14 Eriksen Motors (Welkom) v Protea Motors Warrenton and another 1973(3) SA 685 (A)
16
36.5 That she enjoys a right to specific performance in terms of her
fixed term contract.
36.6 That she enjoys a right that the First to Fifth Respondents
conduct themselves in accordance with the Municipal Systems and
Structures Acts.
36.7 That she has a right to a review with prospects of success,
having due regard to the contents of the Second Respondent's report
which is premised on the Fifth Respondent's letter. It is further
submitted that the letter is factually incorrect and invalid.
36.8 That she has a right to lawful process. In this regard, submitting
that if the Fifth Respondent believes that she has any power to bring
about the termination of the Applicant's employment contract, she
should do so by way of the rule of law and that the court be
approached on valid and lawful grounds.
[37] The Applicant sets out the following reasons in support of a reasonable
apprehension of harm that she would suffer, if not granted temporary relief:
37.1 That there has been repeated non-compliance with the protocols
for tabling matters for discussion. Submitting further that the repeated
tabling of the proposal for the termination of her contract of
employment has not occurred in the normal course of business, and as
such there is clearly a ploy to force through the termination of her
contract of employment by unlawful means.
37.2 That there is a faction of Councillors who wish to unlawfully
force through her removal from office, in the hope of protecting
themselves in the face of an investigation by the Hawks into allegations
of intimidation and death threats on her life. In this regard, she fingers
the Sixth Respondent as aligning himself with such faction within the
Municipality.
17
37.3 That the Respondents have not allayed any fears that she has,
and if anything, their conduct has confirmed their intention of
termination at the first opportunity presented.
37.4 That the apprehension of harm to her rights are reasonable,
having due regard to the history of the matter and the conduct of the
Respondents.
38 As regards the requisite of a balance of convenience favouring the
relief sought by the Applicant, it is argued that:
38.1 The Respondents would not suffer any prejudice to wait for a
court of law to determine the issue regarding her contract of fixed term
employment, which in any event is a process as envisaged by
legislation.
38.2 There i~ no other reason raised for her dismissal than the
reasoning contained in the letter of the Fifth Respondent, which is ill
conceived and wrong. Further, to the extent that it is an administrative
action as contended by the Fifth Respondent that the only way to set
such action aside is by way of a review.
38.3 The prevailing facts and circumstances of this case are not
specifically or at least adequately dealt with by the applicable
legislation concerning the amalgamation of existing Municipalities into
a new Municipality.
38.4 The Applicant submits that she apprehends the unlawful
termination of her contract of employment, without the due process of
law. Further, that she enjoys no other remedy to prevent such
termination, save for the relief which she prays for in the notice of
motion.
18
Respondents submissions for refusal of interlocutory interdict:
[39] The Respondents on the other hand oppose the grant of the interim
relief and argue that the Applicant is not entitled to the relief as prayed for in
her notice of motion. I pause to mention that I do not intend to separate the
arguments of the respective Respondents, but will proceed to capture the
main thrust of their opposition and deal with such opposition cumulatively.
[40] The Respondents argue that the prima facie right relied upon by the
Applicant is the alleged right to remain in the Fourth Respondent's employ
until 30 June 2018, alternatively until 05 December 2020. Further arguing that
the Applicant has failed to establish a prima facie right, as set out
herein below:
40.1 Section 54A(3)(b) of the Systems Act provides that a decision to
appoint a person as Municipal Manager, and any contract concluded
between the Municipal Council and that person in consequence of the
decision, is null and void if the appointment was made in contravention
of the Systems Act.
40.2 Section 57(6)(a) of the Systems Act limits the duration of a
contract of employment for a Municipal Manager to a maximum of five
years, or one year after the election of the next Council of the
Municipality, whichever comes first. In this regard, the employment
contract of the Applicant has therefore lapsed on 09 August 2017, with
effluxion of time and operation of law.
40.3 Clause 2.2 of the Applicant's contract of employment which
provides that it terminates on 30 June 2018 is clearly in contravention
of the Systems Act and therefore visited with invalidity insofar as it
purports to exceed the election date of the Council elected after the
conclusion of the contract of employment, by more than twelve months.
Further that a finding of invalidity in respect of Clause 2.2 poses no
19
difficulties in respect of the remainder of the contract, due to the
severability provisions contained in Clause 19.
40.4 The results of the 2016 Municipal elections had become official
on 10 August 2016. Therefore the maximum period of twelve months
for the continuation of the Applicant's contract expired on 09 August
2017, which is a period of twelve months after the 2016 election.
40.5 The Applicant has failed to establish a prima facie right in
respect of the contention that a new (second) contract of employment
has been concluded between her and the Municipality which would
endure to 05 December 2020, by virtue of the Council resolution of 06
December 2016. In this regard, it is argued that such an appointment
was made in contravention of the Systems Act and accordingly null and
void, having due·regard to the provisions of Section 54A(3)(b).
[41] It has been argued that the Applicant will not suffer irreparable harm in
the event of it being proved that the termination of her employment was
unlawful as she will have a claim for damages.
[42] The Respondents contend that the balance of convenience does not
favour the Applicant at all. Arguing that the First to Fourth Respondents will be
compelled to give effect to an employment contract that is contrary to
legislative prescript. The Applicant, on the other hand has a claim for
damages should she be able to prove an unlawful termination of her
employment contract.
[43] The Respondents further contend that the Appl icant in fact does enjoy
an alternative remedy in the form of a claim for damages.
20
Analysis:
[44] The dispute between the parties can be crisply summarised as follows:
44.1 The Applicant contends that she has a fixed term contract with
the Fourth Respondent which endures until 30 June 2018 and that this
fact was further entrenched by the resolution of Council dated
06 December 2017, wherein she was appointed on the same terms
and conditions of her fixed term contract, effective 01 July 2014.
For the appointment until 30 June 2018, the Applicant relies on the
transfer of her contract of employment as Municipal Manager from
Tlokwe Local Municipality to the Fourth Respondent in terms of Section
14(3)(a) of the Municipal Structures Act, as well as a Council resolution
(C46/2016-12-06) adopted on 06 December 2016. It was resolved that
the directives of the MEC Department of Local Government and
Human Settlement dated 01 August 2016 (attached to item
SPC3/2016-08-17) be corrected and that the Applicant and other
Directors "be appointed according to the conditions and terms as
stipulated in their respective contracts".
The Respondents on the other hand contend that the Council
resolution of 06 December 2016 was unlawful and stands to be set
aside and to be declared null and void.
44.2 The Applicant further argues that at the time when her
employment contract was concluded the next election of the Tlokwe
Municipality, at the time, was to take place during the second half of
2016, after the results of those municipal elections would be published
in the Government Gazette. But for the intervening events and what
was contained in the written agreement, the Applicant's appointment as
Municipal Manager with the Tlokwe Municipality would have terminated
by operation of law "one year after the election of the next council" of
21
the Tlokwe Municipality at some stage during the second half of 2017,
all depending on the actual date of the election of the next council.
Submitting that the next election of the Tlokwe Municipality was
overtaken by the disestablishment of the Tlokwe Municipality on or
about 03 August 201'6, on which date the first election of the Council of
the superseding municipality commenced, as envisaged by Section
12(2)(b) of the Structures Act.
In this regard, the Respondents contend that the election of
03 August 2016 was in fact the "next meeting of council" of the Tlokwe
Municipality, and as such the Applicant's contract ended on
09 July 2017. On the other hand the Applicant interprets the election of
03 August 2016, as the first election of the new municipality. In
addition, relying heavily upon the resolution of 06 December 2016 that
in terms of her fixed term contract grants her security of tenure until
30 June 2018.
44.3 For the appointment until 05 December 2020, the Applicant
contends that a second employment contract was constituted by the
terms of her previous employment contract (01 July 2014) read with the
resolution of 06 December 2016. The Respondents are clear in their
opposition on this point by contending that such contract is unlawful, as
it does not comply with the legal requirements in terms of the
legislation.
[45] As regards a consideration of legal issues at the stage of interim relief,
the correct approach would appear to be that ordinary questions of law should
be decided at the interim stage whereas involved issues of law should be left
for determination by the trial Court. In my view the issues raised are involved
and cannot be determined by this court that is approached for interlocutory
relief.
22
[46] It is trite that the Applicant has to satisfy the requirements for the
interim relief sought. To this end, the Applicant contends that she has a prima
facie right to be employed as the Municipal Manager until 30 June 2018, by
virtue of her fixed term contract of employment and the Council resolution of
06 December 2016. I have also taken into account the different interpretation
of the litigants regarding the disestablishment and establishment of the
superseding council and whether the election of 03 August 2016 was the first
election of the council of the next meeting of the disestablished councils.
In my view that this is not an ordinary question of law as this scenario is not
specifically or at least adequately dealt with by the applicable legislation
concerning the amalgamation of existing Municipalities into a new
Municipality. Accordingly, this aspect is one that cannot be dealt with by a
court before which interlocutory relief is sought.
(47] After carefully considering the totality of the evidence before me,
having due regard to the applicable law and exercising my discretion, I am
satisfied that the Applicant has established a prima facie right to an extant
contract of employment with the Fourth Respondent, even if open to some
doubt. I am further satisfied that the Applicant has placed sufficient factors to
convince this court that she would suffer irreparable harm if she were not
granted the interim relief as prayed for, and that the balance of convenience
favours her. I pause to mention that I do not find favour in respect of the
argument of the Applicant regarding her contentions of a second contract of
employment enduring until 05 December 2020.
In the circumstances, the only appropriate remedy is the grant of an interdict
to the Applicant.
23
[48] In the result, I make the following order:
1. The First to Fourth Respondents are interdicted and restrained
from acting upon the letter alternatively notice of decision from
the office of the Fifth Respondent addressed to and received by
the Second Respondent in July 2017, and which is annexed to
the founding affidavit marked "FA9".
2. The First to Fourth Respondents are interdicted and restrained
from tabling, discussing, deliberating and/or deciding the validity
of the Applicant's employment and contract with the Fourth
Respondent.
3. Paragraphs 1 and 2 shall operate as an interim interdict and
Court order, pending the outcome of an application by the
Applicant, to be issued within 1 O days of this order:
3.1 to review the decision of the Fifth Respondent as
contained in the letter alternatively notice of decision from
the office of the Fifth Respondent addressed to and
received by the Second Respondent addressed to and
received by the Second Respondent in July 2017 and
which is annexed to the founding affidavit marked "FA9";
and/or
3.2 declaring that the Applicant is the appointed Municipal
Manager of the Fourth Respondent by fixed term contract
until 30 June 2018 alternatively 05 December 2020;
and/or
3.3 directing that the Fourth Respondent comply with the
Applicants Contract of employment and interdicting and
restraining the First to Sixth Respondents from bringing
about the termination of the Applicant's employment
24
without due process of law and compliance with the terms
of employment.
4. The costs of the application launched by the Fifth and Sixth
Respondents on 24 July 2017, in respect of the res judicata
defence are awarded jointly and severally against the Fifth and
Sixth Respondents on the scale as between attorney and client,
pursuant to the dismissal of such point in limine.
5. In addition, the First to Sixth Respondents are ordered to pay
the costs of the main application jointly and severally.
~A ACTING JUDGE OF THE HIGH COURT
GAUTENG DIVISION
PRETORIA
Counsel for Applicant:
Instructed by:
Mr RS Willis
Dev Maharaj & Associates
Bryanston
Tel: 0117063333
Counsel for 1st & 4th Respondents: Mr R Grundlingh
Instructed by: Scheepers & Aucamp Attorneys
Potchefstroom
Tel: 0182971217
Counsel for 2nd & 3rd Respondents Mr J J Pretorius
Instructed by: Henk Wissing Incorporated
Potchefstroom
Counsel for 5th Respondent
Instructed by:
Counsel for 6th Respondent
Instructed by:
Tel : 0182930190
Mr MG Hitge
The State Attorney
Mr M Tshingwala
Mmabatho
Tel: 0183840269
Mr L Nyangiwe
Morathi & Mataka Attorneys
Potchefstroom
Tel: 0182933669
25
Dates of hearing 24 July 2017 & 14 September 2017
Date of Judgment 13 October 2017