Upload
vohanh
View
214
Download
0
Embed Size (px)
Citation preview
1
IN THE CIRCUIT COURT OF JEFFERSON COUNTY, ALABAMA
BIRMINGHAM DIVISION
C.W. WOODS CONTRACTING SERVICES, INC. )
Plaintiff, )
v. ) CASE NO.
) CV 13-891
CITY OF BIRMINGHAM, a )
municipal corporation, )
Defendant. )
ANSWER AND COUNTERCLAIM OF DEFENDANT CITY OF
BIRMINGHAM TO PLAINTIFF’S COMPLAINT
Come now the Defendant, the City of Birmingham (“City”), a municipal
corporation under the laws of the State of Alabama, by and through its attorney,
files this Answer to the Complaint heretofore filed say as follows:
I. PARTIES
1. Defendant is without sufficient knowledge or information to either admit or
deny the averments of paragraph 1, therefore they are denied.
2. Defendant admits averments contained in paragraph 2.
3. Defendant admits Mayor William a Bell, Sr. is the Mayor of the City of
Birmingham, but denies the remainder of the averments contained in
paragraph 3.
4. Paragraph 4 contains no allegations requiring a response from this
Defendant; however, to the extent the allegations of paragraph 4 can be
construed to require an admission or denial by the Defendant, such
allegations are denied.
ELECTRONICALLY FILED3/3/2014 9:46 AM
01-CV-2013-000891.00CIRCUIT COURT OF
JEFFERSON COUNTY, ALABAMAANNE-MARIE ADAMS, CLERK
2
5. Paragraph 5 contains no allegations requiring a response from this
Defendant; however, to the extent the allegations of paragraph 5 can be
construed to require an admission or denial by the Defendant, such
allegations are denied.
6. Paragraph 6 contains no allegations requiring a response from this
Defendant; however, to the extent the allegations of paragraph 6 can be
construed to require an admission or denial by the Defendant, such
allegations are denied.
II. THE FOUNDATION HIEGHTS RECREATION CENTER PROJECT
7. Defendant admits the averments contained in paragraph 7.
8. Defendant admits the averments contained in paragraph 8.
9. Defendant admits the averments contained in paragraph 9.
10. Defendant denies the averments contained in paragraph 10.
11. Defendant denies the averments contained in paragraph 11.
12. Defendant denies the averments contained in paragraph 12.
13. Defendant denies the averments contained in paragraph 13.
14. Defendant denies the averments contained in paragraph 14.
15. Defendant denies the averments contained in paragraph 15.
16. Defendant admits the averments contained in paragraph 16.
17. Defendant admits the averment that a Notice of Default was sent to the
Plaintiff, but denies the remainder of the averments contained in paragraph
17.
18. Defendant denies the averments contained in paragraph 18.
3
19. Defendant denies the averments contained in paragraph 19.
COUNT ONE
(BREACH OF CONTRACT)
20. Defendant denies the averments contained in paragraph 20.
21. Defendant denies the averments contained in paragraph 21.
22. Defendant denies the averments contained in paragraph 22.
23. Defendant denies the averments contained in paragraph 23.
COUNT TWO
(OPEN ACCOUNT)
24. Defendant denies the averments contained in paragraph 24.
25. Defendant denies the averments contained in paragraph 25.
COUNT THREE
(WORK AND LABOR DONE)
26. Defendant denies the averments contained in paragraph 26.
27. Defendant denies the averments contained in paragraph 27.
COUNT FOUR
(UNJUST ENRICHMENT)
28. Defendant denies the averments contained in paragraph 28.
29. Defendant denies the averments contained in paragraph 29.
30. Defendant denies the averments contained in paragraph 30.
III. THE WEST POLICE PRECINCT PROJECT
4
31. Defendant denies the averments contained in paragraph 31.
32. Defendant admits the averments contained in paragraph 32.
33. Defendant admits the averments contained in paragraph 33.
34. Defendant denies the averments contained in paragraph 34.
35. Defendant denies the averments contained in paragraph 35.
36. Defendant denies the averments contained in paragraph 36.
37. Defendant denies the averments contained in paragraph 37.
38. Defendant denies the averments contained in paragraph 38.
39. Defendant denies the averments contained in paragraph 39.
40. Defendant admits the averments contained in paragraph 40.
41. Defendant admits the averment that a Notice of Default was sent to the
Plaintiff, but denies the remainder of the averments contained in paragraph
41.
42. Defendant denies the averments contained in paragraph 42.
43. Defendant denies the averments contained in paragraph 43.
COUNT FIVE
(BREACH OF CONTRACT)
44. Defendant denies the averments contained in paragraph 44.
45. Defendant denies the averments contained in paragraph 45.
46. Defendant denies the averments contained in paragraph 46.
47. Defendant denies the averments contained in paragraph 47.
5
COUNT SIX
(OPEN ACCOUNT)
48. Defendant denies the averments contained in paragraph 48.
49. Defendant denies the averments contained in paragraph 49.
COUNT SEVEN
(WORK AND LABOR DONE)
50. Defendant denies the averments contained in paragraph 50.
51. Defendant denies the averments contained in paragraph 51.
COUNT EIGHT
(UNJUST ENRICHMENT)
52. Defendant denies the averments contained in paragraph 52.
53. Defendant denies the averments contained in paragraph 53.
54. Defendant denies the averments contained in paragraph 54.
IV. NEW NEGRO SOUTHERN BASEBALL MUSEUM PROJECT
55. Defendant denies the averments contained in paragraph 55.
56. Defendant denies the averments contained in paragraph 56.
57. Defendant admits the averments contained in paragraph 57.
58. Defendant admits the averments contained in paragraph 58.
59. Defendant denies the averments contained in paragraph 59.
60. Defendant denies the averments contained in paragraph 60.
61. Defendant denies the averments contained in paragraph 61.
6
62. Defendant denies the averments contained in paragraph 62.
63. Defendant denies the averments contained in paragraph 63.
64. Defendant denies the averments contained in paragraph 64.
COUNT NINE
(BREACH OF CONTRACT)
65. Defendant denies the averments contained in paragraph 65.
66. Defendant denies the averments contained in paragraph 66.
67. Defendant denies the averments contained in paragraph 67.
68. Defendant denies the averments contained in paragraph 68.
COUNT TEN
(OPEN ACCOUNT)
69. Defendant denies the averments contained in paragraph 69.
70. Defendant denies the averments contained in paragraph 70.
COUNT ELEVEN
(WORK AND LABOR DONE)
71. Defendant denies the averments contained in paragraph 71.
72. Defendant denies the averments contained in paragraph 72.
COUNT TWELVE
(UNJUST ENRICHMENT)
73. Defendant denies the averments contained in paragraph 73.
74. Defendant denies the averments contained in paragraph 73.
7
75. Defendant denies the averments contained in paragraph 75.
AFFIRMATIVE DEFENSES OF DEFENDANT CITY OF BIRMINGHAM
1. The Complaint fails to state a claim against the City for which the Plaintiff
are entitled to relief.
2. The City denies each and every material allegation of the Complaint and
demands strict proof thereof.
3. The City pleads not guilty/liable to the general issue.
4. The City asserts the defense of good faith.
5. The City denies that the Plaintiff was injured in the nature or to the extent
claimed and contests all alleged damages.
6. The City denies Plaintiff is entitled to any damages, cost, or attorney’s fees
or any other relief.
7. Pursuant to the terms of the contracts, the Plaintiff cannot recover attorney’s
fees for an alleged breach or default of the contracts.
8. Pursuant to the terms of the contracts, Consequential Damages Provision
4.3.10 of the General Conditions, the Plaintiff cannot recover damages for
reputation, lost economic opportunity, loss of goodwill, or other
consequential damages.
9. The City denies that the Plaintiff suffered damages as alleged in the
Complaint and that if said damages were in fact sustained, they were caused
by parties other than the City or its officers, agents or employees.
10. The City asserts the defense of immunity, whether qualified, absolute,
discretionary, functional, governmental, good faith or substantive as a
complete bar to this action.
11. The City pleads the defenses of issue and claim preclusion, collateral
estoppels, acquiescence and res judicata.
8
12. Any injury or damage suffered by the Plaintiff were a result of its’ willful,
wanton, or negligent conduct and it is therefore not entitled to recover even
if the Defendant was negligent.
13. The Plaintiff is guilty of contributory negligent and such is the proximate
cause of any damages sustained by the Plaintiff.
14. The Defendant pleads the defenses of assumption of risk.
15. Under the law of the State of Alabama the City, as a duly incorporated
municipal corporation, is immune from the imposition of damages for injury
done or wrongs suffered unless the injury or wrong was done or suffered
through the neglect, carelessness, or unskillfulness of some agent, officer or
employee of the municipality. §11-47-190 Code of Alabama 1975, as
amended.
16. The City of Birmingham is not liable under the law of the State of Alabama
for the intentional, malicious, wanton, willful or reckless acts of its
employees, agents or servants. Hilliard v. City of Huntsville, 585 So. 889
(Ala. 1991); §11-47-190 Code of Alabama 1975, as amended.
17. The City denies that it or any of its agents, officers or employees was
negligent, careless or unskillful with regard to any duty owed to the Plaintiff
or any other similarly situated member of the public.
18. The City pleads the affirmative defense of limitation of damages in an
amount not exceeding $100,000 on all claims. Ala. Code §11-47-190 and
§11-93-1, et seq. as amended.
19. Punitive damages are barred against the City by the provisions of Ala. Code
§6-11-20, 1975, et seq., City of Newport v. Facts Concerts, 453 U.S. 247,
101 S. Ct. 2748 (1981).
20. The defendant asserts the defense of discretionary function immunity as
provided in the Ex Parte City of Birmingham, 624 So.2d 1018 (Ala. 1993),
Ex Parte Cranman, 792 So.2d 392 (Ala. 2000).
21. The Plaintiff’s claims are barred by the doctrine of unclean hands.
9
22. The Defendant states that the Plaintiff violated and breached all said
contracts with the City.
23. The Defendant reserves the right to amend its Answer and raise additional
defenses which become known through the discovery process.
COUNTERCLAIMS OF DEFENDANT CITY OF BIRMINGHAM
The Defendant, the City of Birmingham, by and through its undersigned
attorney, having fully answered the allegations in the Plaintiff’s Complaint, now
files its’ Counterclaims against the Plaintiff.
PARTIES
1. Defendant/Counterclaim Plaintiff, City of Birmingham (“City”), is,
and at all times mentioned in this pleading, a municipal corporation organized
under the laws of the State of Alabama with its principal place of business located
at 710 North 20th Street, in the City of Birmingham, Jefferson County, State of
Alabama.
2. Plaintiff/Counterclaim-Defendant, C.W. Woods Contracting Services
(“Woods”), is, and at all times mentioned in this Counterclaim, a corporation
organized and existing under the laws of the State of Alabama, having its principal
place of business in Birmingham, Alabama.
FACTUAL ALLEGATIONS
The Fountain Heights Recreation Center Project
10
3. In June 2011 the Council of the City of Birmingham adopted Resolution
No. 842-11 whereby, following a competitive bid process, it accepted Woods’ bid
of $2,350,826 to construct the new Fountain Heights Recreation Center located at
1101 15th Avenue North, Birmingham, Alabama (hereinafter “the FHRC Project”).
In that Resolution, the City Council also authorized the Mayor of Birmingham,
William A. Bell, Sr. (“Mayor Bell”), to enter into a contract with Woods for the
FHRC Project.
4. On or about June 23, 2011, Mayor Bell executed the Standard Form of
Agreement between Owner and Contractor for Woods to construct a new
recreation center building and adjacent improvements on the FHRC Project
(hereinafter, the “FHRC Contract”). Under the terms of that Contract, the City
was the “Owner” of the Project, and Woods was designated as the “Contractor”.
5. Among its other obligations arising under the FHRC Contract, Woods
was obligated (a) to construct the FHRC Project in compliance with a set of plans
and specifications developed by the Project Architect, Exford LLC (the
“Architect”), (b) to substantially complete the Project within 270 days after the
City gave Woods notice to proceed with its work, (c) to provide the City a
recovery schedule if Woods fell behind on performing its obligations in accordance
with the recovery schedule, (d) to timely and fully compensate the subcontractors
11
that Woods retained and that provided labor and materials for the FHRC Project,
and (e) to perform work through the services of contractors or subcontractors who
held state licenses appropriate and necessary for their operations.
6. On August 29, 2011 City issued a Notice to Proceed for Woods to begin
work on the FHRC Project. Considering the 270 day construction period for
Woods to perform its work, the initial date of substantial completion under the
FHRC Contract was June 3, 2012.
7. Woods and the City also agreed in the FHRC Contract that issues, claims
and disputes that arose between the parties over the life of the Project would be
presented to the Architect for its determination and resolution. Specifically,
Article 4 of the General Conditions of the FHRC Contract, as amended by the
Supplemental General Conditions, set forth the process for consideration of claims
that either party might have against the other. Section 4.3 of this Article (titled
“Claims and Disputes”) granted the parties the right to make claims for “payment
of money, extension of time or other relief with respect to the terms of the
[Contract].” Further, Subsection 4.3.7.1 established a process by which Woods
could request an extension of time to substantially complete its work.
8. After Woods commenced operations in August 2011, Woods failed to
make sufficient progress required to timely complete the FHRC Project.
12
Consequently, in January 2013 the City requested that Woods provide the City a
recovery schedule and date at which it would substantially complete its work;
Woods failed to provide that recovery schedule.
9. City representatives also met with Woods on February 21, 2013 and
requested then that Woods agree to a Project completion schedule prepared by the
City; Woods refused to accept and abide by that schedule.
10. Following the February 21, 2013, meeting, Woods sporadically
performed construction operations at the Project site, but had not substantially
completed the Project by July 2013. On July 23, 2013, the City sent Woods a
written notice of default and neglect of its duties wherein the City notified Woods
that it had breached numerous contractual responsibilities for the Project (including
failing to timely finish the Project, failing to complete the work according to
specifications and failing to furnish a recovery schedule or completion plan); in
this notice the City requested that Woods cure those defaults. Woods failed to
comply with this request and abide by its contractual responsibilities.
11. Following the receipt of the City’s July 23, 2013 notice of default and
neglect, Woods asserted in correspondence dated July 24, 2013, that it “is not
responsible for any delays that the Project has experienced.” In accordance with
the claims process in Article 4 of the FHRC Contract, a request then was made that
13
the Architect determine whether any additional time for Woods to substantially
complete the Project should be added to the construction schedule.
12. Following an evaluation of all events and circumstances, the Architect
determined that an additional period of 70 days should be added to the construction
schedule over the life of the entire Project. Adding these 70 days to the initial
substantial completion date, the substantial completion date pursuant to the
Contract became August 12, 2012.
13. On or about August 15, 2013, the City sent Woods a second written
notice of default and neglect in which the City again asked Woods to comply with
all its contractual responsibilities with respect to the Project. Woods again failed
to comply with the requests in this second notice.
14. On August 21, 2013, the City the City sent Woods written notice that
the City was terminating the FHRC Contract with Woods due to Woods’
continuous failure to remedy its contractual defaults on the Project. Thereafter,
the City undertook to take over the Project, took action to correct numerous defects
in the work provided by Woods prior to the termination of this Contract and
completed the Project using a combination of its own forces and incurring
additional expenses to hire contractors to complete work that was defective or
14
unfinished by Woods. Using these resources the City completed the Project on or
about November, 2013.
15. Woods has breached the FHRC Contract with the City in each of the
following ways: (a) by failing to meet the substantial completion date of the
Project; (b) by failing to furnish the City or agree to the recovery schedule for the
Project; (c) by ceasing to perform and abandoning work on the Project in violation
of contractual provisions; (d) by performing work on the Project that did not
comply with plans and specifications; (e) by failing to fully and timely pay the
subcontractors that Woods retained for the Project; (f) by retaining and using a
subcontractor, Allstar Realty Company, Inc. (“Allstar Realty”), to perform
significant excavation and site preparation work on the Project when Allstar Realty
did not have the general contractor licensing required by the State of Alabama and
the FHRC Contract to perform those operations; and (f) by failing to supply the
City warranties on the roof and other component systems as required by the FHRC
Contract specifications.
16. Section 9.11.2 of the Supplemental General Conditions of the FHRC
Contract provides that, for each day following Woods failure to substantially
complete the Project, the City shall receive $1500 per day in liquidated damages
related to such default.
15
17. Based on the Architect’s determination that the adjusted substantial
completion date under the FHRC Contract was August 12, 2012, Woods was 374
days late in complying with its obligation to substantially complete the Project
when the City terminated that Contract on August 21, 2013.
The West Police Precinct Project
18. In October 2011 the Council of the City of Birmingham adopted
Resolution No. 1531-11 whereby, following a competitive bid process, it accepted
Woods’ bid of $2,692,000.00 to construct the new Birmingham Police West
Precinct to be located at 2336 47th Street in Ensley. Birmingham, Alabama (the
“West Precinct Project”). In that Resolution, the City Council also authorized the
Mayor of Birmingham, William A. Bell, Sr. (“Mayor Bell”), to enter into a
contract with Woods for the West Precinct Project.
19. On or about December 1, 2011, Mayor Bell executed the Standard Form
of Agreement between Owner and Contractor for Woods to construct the new
West Precinct building and adjacent improvements on the West Precinct Project
(hereinafter, the “West Precinct Contract”). Under the terms of that Contract, the
City was the “Owner” of the Project, and Woods was designated as the
“Contractor”.
16
20. Among its other obligations arising under the West Precinct Contract,
Woods was obligated (a) to construct the West Precinct Project in compliance with
a set of plans and specifications developed by the Project Architect, Exford LLC
(the “Architect”), (b) to substantially complete the Project within 245 days after the
City gave Woods notice to proceed with its work, (c) to provide the City a
recovery schedule if Woods fell behind on performing its obligations in accordance
with the recovery schedule, and (d) to timely and fully compensate the
subcontractors that Woods retained and that provided labor and materials for the
West Precinct Project.
21. On February 1, 2012, the City issued a Notice to Proceed for Woods to
begin work on the West Precinct Project. Considering the 245-day construction
period for Woods to perform its work, the initial date of substantial completion
under the West Precinct Contract was on or about October 8, 2012.
22. Woods and the City also agreed in the West precinct Contract that issues,
claims and disputes that arose between the parties over the life of the Project would
be presented to the Architect for its determination and resolution. Specifically,
Article 4 of the General Conditions of the West Precinct Contract, as amended by
the Supplemental General Conditions, set forth the process for consideration of
claims that either party might have against the other. Section 4.3 of this Article
17
(titled “Claims and Disputes”) granted the parties the right to make claims for
“payment of money, extension of time or other relief with respect to the terms of
the [Contract].” Further, Subsection 4.3.7.1 established a process by which
Woods could request an extension of time to substantially complete its work.
23. After Woods commenced operations in August 2011, Woods failed to
make sufficient progress required to timely complete the West Precinct Project.
Consequently, in January 2013, the City requested that Woods provide the City a
recovery schedule and date at which it would substantially complete its work;
Woods failed to provide that recovery schedule.
24. City representatives also met with Woods on February 21, 2013 and
requested then that Woods agree to a Project completion schedule prepared by the
City; Woods refused to accept and abide by that schedule.
25. Following the February 21, 2013, meeting, Woods sporadically
performed construction operations at the Project site, but had not substantially
completed the Project by June 2013. On June 25, 2013, the City sent Woods a
written notice of default and neglect of its duties wherein the City notified Woods
that it had breached numerous contractual responsibilities for the Project (including
failing to timely finish the Project, failing to complete the work according to
specifications, failing to furnish a recovery schedule or completion plan and
18
abandonment of the Project); in this notice the City requested that Woods cure
those defaults. Woods failed to comply with this request and abide by its
contractual responsibilities.
26. Following the receipt of the City’s June 25, 2013 notice of default and
neglect, Woods asserted in correspondence dated June 28, 2013, that it “ha[s] been
delayed 1 year, 4 months, and 28 days on the project, which amounts to 514 total
days lost due to delays.” In accordance with the claims process in Article 4 of the
West Precinct Contract, a request then was made that the Architect determine
whether any additional time for Woods to substantially complete the Project should
be added to the construction schedule.
27. Following an evaluation of all events and circumstances, the Architect
determined that an additional period of 90 days should be added to the construction
schedule over the life of the entire Project. Adding these 90 days to the initial
substantial completion date, the substantial completion date pursuant to the
Contract was adjusted to on or about January 8, 2013.
28. On or about July 19, 2013, the City sent Woods a second written notice
of default and neglect in which the City again asked Woods to comply with all its
contractual responsibilities with respect to the Project. Woods again failed to
comply with the requests in this second notice.
19
29. On August 21, 2013, the City sent Woods written notice that the City
was terminating the West Precinct Contract with Woods due to Woods’ continuous
failure to remedy its contractual defaults on the Project.
30. Woods has breached the West Precinct Contract with the City in each of
the following ways: (a) by failing to meet the substantial completion date of the
Project; (b) by failing to furnish the City or agree to the recovery schedule for the
Project; (c) by ceasing to perform and abandoning work on the Project in violation
of contractual provisions; (d) by performing work on the Project that did not
comply with plans and specifications; (e) by failing to fully and timely pay the
subcontractors that Woods retained for the Project; and (f) by failing to supply the
City warranties on the roof and other component systems as required by the West
Precinct Contract specifications.
31. Section 9.11.2 of the Supplemental General Conditions of the West
Precinct Contract provides that, for each day following Woods failure to
substantially complete the Project, the City shall receive $1500 per day in
liquidated damages related to such default.
32. Based on the Architect’s determination that the adjusted substantial
completion date under the West Precinct Contract was January 8, 2013, Woods
was 163 days late in complying with its obligation to substantially complete the
20
Project when the City terminated that Contract on August 21, 2013.
33. Following the termination of Woods’ contract to build the West Police
Project, the City filed a claim with Star Insurance Company, the Surety that issued
a Performance Bond on the West Precinct Project, asking Star to cure Woods’s
defaults on the Project by taking over the Project, correcting Woods’s defective
work and completing the Project.
34. Star has identified major, numerous defects in the work that Woods had
performed prior to the termination of the West Precinct Project. As of this date,
Star has not undertaken to complete the Project or correct the numerous defects in
the work that Woods performed prior to the termination of that Project.
COUNTERCLAIM I - BREACH OF CONTACT
FOUNTAIN HEIGHTS PROJECT
35. The City incorporates paragraphs 1 through 17 by reference as if fully
set out herein.
36. As a result of Woods’ breaches of its obligations under the FHRC
Contract, the City has incurred the following damages:
(a) pursuant to Section 9.11.2 of the Supplemental General Conditions
of the FHRC Contract, liquidated damages of $561,000.00 ($1,500 a
day calculated from the adjusted substantial completion date of
August 12, 2012 to termination of the Contract on August 21, 2013),
21
plus pre-judgment interest on that amount, resulting from Woods’
failure to timely complete the Project;
(b) damages of $68,478.20, plus pre-judgment interest, incurred by
the City to retain various contractors required to complete the Project
and to correct defects in the work performed by Woods;
(c) damages of $9,200.00, plus pre-judgment interest, incurred by the
City to retain Donald Ponder to serve as Project Superintendent and
perform services during the fall 2013 that were required to complete
the Project;
(d) damages of $103,914.11, plus pre-judgment interest, expended by
the City for the cost of materials and the expense of its own workers
to perform work required to complete the Project and to correct
defects in the work performed by Woods;
(e) damages of $17,500.00, plus pre-judgment interest, to obtain the
warranty on the roof of the new Recreation Center building that
Woods failed to provide to the City;
(f) damages of $ 83,133.05, plus pre-judgment interest, attributable to
the City’s cost of compensating the Architect for additional,
extraordinary services that the Architect has had to perform on this
22
Project that resulted from Woods’ breaches of the FHRC Contract
(including its failure to timely complete the Project and poor
workmanship).
WHEREFORE, pursuant to Counterclaim I, the City demands judgment of
$843,225.36 against Woods, its costs of court, any further damages to which it may
be entitled and such other relief that the Court deems proper.
COUNTERCLAIM II - BREACH OF CONTACT
WEST PRECINCT PROJECT
37. The City hereby incorporates paragraphs 1 through 2 and paragraphs 18-
34 above by reference as if fully set out herein.
38. As a result of Woods’ breaches of its obligations under the West
Precinct Contract, the City has incurred the following damages:
(a) pursuant to Section 9.11.2 of the Supplemental General Conditions
of the West Precinct Contract, liquidated damages of $244,500.00
($1,500 a day calculated from the adjusted substantial completion date
of January 8, 2013 to termination of the Contract on August 21,
2013), plus pre-judgment interest on that amount, resulting from
Woods’ failure to timely complete the Project;
(b) damages of $5,123.16 attributable to the City’s cost of securing
the unfinished Project site;
23
(c) damages of $ 94,696.34, plus pre-judgment interest, attributable to
the City’s cost of compensating the Architect for additional,
extraordinary services that the Architect has had to perform on this
Project that resulted from Woods’ breaches of the West Precinct
Contract (including its failure to timely complete the Project and poor
workmanship).
WHEREFORE, pursuant to this Counterclaim II, the City demands
judgment of $344,319.50 against Woods, its costs of court, any further damages to
which it may be entitled and such other relief that the Court deems proper.
WHEREFORE, on the basis of the foregoing, Defendant/Counter-Plaintiff
City requests that the Court render a verdict for Defendant/Counter-Plaintiff City,
and against the Plaintiff/Counter-Defendant, Woods, for compensatory damages in
an amount which will adequately compensate Defendant/Counter-Plaintiff City for
the injuries and damages sustained due to Plaintiff/Counter-Defendant’s conduct.
Further, Defendant/Counter-Plaintiff City requests that the Court enter judgment,
and that it also award Defendant/Counter-Plaintiff City interest from the date of
judgment and the costs incurred in managing this lawsuit, and any further damages
to which it may be entitled.
DEFENDANT DEMANDS TRIAL BY JURY
24
Respectfully submitted,
/s/Fredric L. Fullerton, II
Fredric L. Fullerton, II
Chief Assistant City Attorney
City Hall
Law Department
710 N 20th
Street, Room 600
Birmingham, Alabama 35203
(205) 254-2369/(205) 254-2302 (Fax)
CERTIFICATE OF SERVICE
I hereby certify that on March 3, 2014, I electronically filed the foregoing
with the Clerk of the Court using the E-filing system which will send notification
of such filing to the following:
Ronald O. Gaiser, Jr.
Attorney at Law
Gaiser and Johnston
36B Church Street
Birmingham, Alabama 35213
/s/Fredric L. Fullerton, II
Of Counsel