Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Improving On-Time Delivery at Madera y Metal A Major Qualifying Project report in partial fulfillment of the Bachelor of Science degree at Worcester
Polytechnic Institute
Submitted by: Hector Benitez
Manuel Freile
Matthew Outama
In collaboration with: Sharon Johnson, Advisor, WPI, Worcester, MA
Madera y Metal, Manufacturing Company, Asuncion, Paraguay
Date Submitted: March 6th, 2020
i
Abstract
Our project goal was to help Madera y Metal, a trophy manufacturing company in Paraguay,
reduce the number of orders delivered later than the internal due date. The team used A3
problem-solving to examine root causes and develop solutions. The team guided the
implementation of a new software system to track orders and set due dates, analyzed seasonality
in demand, and created an order prioritization ranking tool, to allow the company to be more
proactive in avoiding late orders.
ii
Acknowledgements
We want to thank our advisor, Prof. Johnson, for the insight in the technical and research
guidelines that helped us design an ambitious but achievable project.
We would also like to thank Madera y Metal, their sales department, management and the
production floor supervisor for meeting with us on a regular basis, providing us with data and
information useful for our project, as well as helping us test and implement our countermeasures
since we could not be physically present to do it ourselves.
iii
Authorship Statement Manuel Freile
Manuel focused on figuring out what was causing orders to be late using surveys, the
fishbone analysis and 5-Whys. He was responsible for finding methods to determine what
countermeasures to implement through communication with Madera y Metal Management and
an analysis of the difficulty of implementation. He took major responsibility for the prioritization
countermeasure. He also focused on the internal communication within the team making sure
everyone’s opinion was voiced.
Hector Benitez
Hector focused on measuring and averaging production times for calculating the lead
times that were used as standards/benchmarks for the actual production, in finding and setting up
a tool that would support our production process (Monday Software) and in communicating with
the company.
Matthew Outama Matthew focused on collecting and organizing the data, specifically the sales data utilized
in the development of the seasonality countermeasure. With the collected data, and other
information that was gathered, he also designed many of the figures and tables. Additionally, he
ensured everyone stayed on track, created / outlined the presentations, and reports.
iv
Table of Contents Abstract .......................................................................................................................................................... i
Acknowledgements ....................................................................................................................................... ii
Authorship Statement ................................................................................................................................... iii
Table of Figures ........................................................................................................................................... vi
Table of Tables ............................................................................................................................................ vi
1. Introduction ............................................................................................................................................... 1
2. Background and Literature Review .......................................................................................................... 3
2.1. Madera y Metal .................................................................................................................................. 3
2.2. Current Conditions ............................................................................................................................. 6
2.3. Case Studies ....................................................................................................................................... 7
2.4. Countermeasure Literature ................................................................................................................. 8
2.4.1. Aggregate Production Planning .................................................................................................. 8
2.4.2. Production Prioritization ............................................................................................................. 9
2.4.3. Order Due Date Estimation ....................................................................................................... 10
3. Methodology ........................................................................................................................................... 11
3.1. Objective 1: Developing Problem Statement and Collecting Background Information .................. 12
3.2. Objective 2: Identifying Causes of Late Order Delivery ................................................................. 12
3.2.1 Fishbone Diagram ...................................................................................................................... 12
3.2.2 Five-Whys .................................................................................................................................. 13
3.3. Objective 3: Determining the Most Important Root Causes ............................................................ 15
3.3.1 Fishbone Diagram Ranking ....................................................................................................... 15
3.3.2 Effort-to-Impact Ratio................................................................................................................ 17
3.3.3 Late Order Survey and Order Tracking Log Sheet .................................................................... 18
3.4. Objective 4: Developing Countermeasures ...................................................................................... 19
3.5. Objective 5: Providing Final Recommendations ............................................................................. 20
4. Results ..................................................................................................................................................... 21
4.1. General Organizational Improvements ............................................................................................ 21
4.2. Response to Seasonality ................................................................................................................... 22
4.2.1. Sales Data Analysis ................................................................................................................... 22
4.2.2 Production Ramp Up .................................................................................................................. 24
4.2.3 Preventative Maintenance .......................................................................................................... 25
4.2.4 Marketing ................................................................................................................................... 27
4.3. Product and Order Prioritization ...................................................................................................... 28
4.3.1 Multi Attribute Decision Making (MADM) Tool ...................................................................... 29
v
4.3.2 Tool Limitations ......................................................................................................................... 30
4.3.3 Tool Benefits .............................................................................................................................. 31
4.4. Improved Due Date Estimation........................................................................................................ 32
4.4.1 Unitary Production Calculation ................................................................................................. 33
4.4.2 Limitations of New Due Date Estimation Method .................................................................... 33
5. Conclusion, Recommendations, and Reflection ..................................................................................... 34
5.1 Conclusion ........................................................................................................................................ 34
5.2 Recommendations ............................................................................................................................. 34
5.3 Reflection .......................................................................................................................................... 35
5.3.1 Design Reflection ....................................................................................................................... 35
5.3.2 Design Constraints and Impact .................................................................................................. 36
5.3.2 Lifelong Learning Reflection ..................................................................................................... 36
5.3.4 Project Teamwork ...................................................................................................................... 37
References ................................................................................................................................................... 38
Appendices .................................................................................................................................................. 40
vi
Table of Figures Figure 1: Factory Layout .............................................................................................................................. 5 Figure 2: Fishbone Diagram ....................................................................................................................... 13 Figure 3: Fishbone Diagram Ranking ......................................................................................................... 15 Figure 4: Effort to Impact Diagram ............................................................................................................ 17 Figure 5: Total Orders (by month) .............................................................................................................. 23 Figure 6: Average Work per Day (by month) ............................................................................................. 24 Figure 7: Sample Maintenance Form (Orbit, 2014) .................................................................................... 26 Figure 8: Multi Attribute Decision Making Tool ........................................................................................ 30
Table of Tables Table 1: Approximated Machine Capacities ................................................................................................. 7 Table 2: Optimal Number of Workers ........................................................................................................ 25
1
1. Introduction
Madera y Metal (Wood and Metal) is a trophy manufacturing company located in
Asuncion, Paraguay. The company is one of the few trophy manufacturers in the area and the
only one offering customizable options, which causes a high demand. As demand continues to
increase, the risk of potential problems also increases. Madera y Metal is hoping to better meet
their customers’ demands by combating the potential problems. Their main objectives are to
reduce process times, improve response to seasonality, develop a new scheduling system for
order placement, and implementation of lean practices.
Madera y Metal produces a variety of award recognition products with a focus on
trophies, cups, and medals. To date, Madera y Metal has struggled with delivering products to
customers on time. More specifically, the company is having issues meeting their own internal
due dates. We think that the company will substantially benefit from taking a more data-oriented
approach; the team kept track of the time it takes to manufacture several orders for the products
of interest (trophies, cups and medals), and extrapolated durations for the overall fabrication
process for each product. These measurements were used to implement quantitative internal
deadlines and monitoring the impact on internal deadlines coverage. The percentage of fulfilled
orders by internal deadlines was used as the main metric for measuring project success.
The main goal of our project was to help Madera y Metal improve their on-time delivery
of products to customers, which was achieved through the overall sub goals of setting order
prioritization, accounting for seasonal demand and reviewing the internal due date setting
method currently used by Madera y Metal. We were able to accomplish this by analyzing sales
data and developing protocols to respond to seasonality, developing a product prioritization
2
model, and implementing new software to help generate better due date estimations. The
methods used to determine the countermeasures included; a PICK chart to help identify which
countermeasures are viable and likely to make an impact; a Fishbone diagram to find what
problems were causing issues with meeting due dates; and the 5 Whys method to understand the
root cause of the problems ranked as more important by Madera y Metal Management. We
developed Surveys and Log Sheets to track orders and understand why orders were late.
Looking ahead, our report first introduces Madera y Metal and the current conditions
within the company. We then discuss the methods used to develop our countermeasures,
followed by a results chapter that describes the countermeasures. Finally, we provided
recommendations to the company, and investigated potential areas that could have been
expanded on throughout this project.
3
2. Background and Literature Review
This chapter provides background information and current conditions of Madera y Metal,
and a review of how similar problems have been resolved. Each section supports the following
chapters of this report.
2.1. Madera y Metal
Madera y Metal is a manufacturing company located in Asuncion, Paraguay. The
company currently employs 20 people. The employees are divided between management, sales,
and production: 2 in management, 4 in sales, and 14 in production. The primary business of
Madera y Metal is the production of recognition awards such as trophies, cups, and medals.
Trophies and cups are similar. The main difference between trophies and cups is that
trophies have an MDF wood base. Furthermore, even though they both use aluminum for the top
part and the whole thing respectively, the process and the material are actually different.
Trophies are entirely produced using aluminum discs and use an embossing lathe machine for
shaping, placed on top of the MDF base. Cups on the other hand are produced using a molding
process; another option is cutting stainless steel.
The production of medals has a different process as well. This process can be divided into
two separate steps. The first part of the process is called spin casting which is used to give the
medals shape, it consists of making the molds for the medals. The second part of the process is
called electrolytic deposition or electroplating. This part of the process focuses on coloring the
metal of the medals, the three most common colors of medals are: gold (first place), silver
(second place) and bronze (third place). The materials used for medals are low melting point
4
alloys such as lead, tin, or antimony. If a more resistant material with a lighter weight is desired
medals are made from Zamak 3, which is an alloy made of zinc, aluminum, magnesium and
copper.
Madera y Metal’s philosophy is that every customer is unique, so customers have the
option to make their own designs. Another characteristic that can vary between customers is the
volume or demand. Personalized products are reviewed and assessed by Madera y Metal with the
purpose of giving a fast but plausible lead time, the time from when the order is placed until it is
completed and delivered to the customer. Madera y Metal uses an enterprise resource planning
system (ERP system) to plan the management of resources based on customer orders: volume,
value, and types of products. The ERP system is not used consistently. Orders are put in the
system when the order was placed but not updated after the order was delivered. The system also
lacks critical information on lead times and capacities.
Even though each product has a different production process, up to 70% of the machinery
is shared between different products, the newer machinery is more commonly shared because it
has fewer specific purposes. There are some exceptions to this, for example the spin casting
machine is used exclusively for medal production. A visualization of the production floor can be
seen in figure 1, which shows the sales department, the design and assembling workshop and the
management offices on the left. While to the right, the figure 1 shows the carpentry workshop
and the foundry workshop. These are the essential spaces in Madera y Metal’s operations.
5
Figure 1: Factory Layout
In addition, the three main products all go through a design process where they share
packaging and finishing processes. The steps of the process that are shared and those that are
specific to the three products can be seen in Appendix A.
6
2.2. Current Conditions
Madera y Metal’s current methods for setting internal deadlines are not rigorously
elaborated. Whenever an order is placed by a customer, the sales assistant who took the order
creates an internal deadline for the order based on the following rule of thumb:
• If the anticipated production time for the order is 1 week, the available internal
production time would be 5 days.
• If the anticipated production time for the order is 2 weeks, the available internal
production time would be 1 week and 3-4 days.
• If the anticipated production time is 1 month, the available internal production
time would be 3 weeks.
Machinery is also an important factor in the efficiency of a production process. At
Madera y Metal, there are many new machines being used to produce the recognition awards.
The newer machines consist of CNC technology (CNC Router) and Laser cutting. According to
the company, 70% of these newer machines are being used for multiple processes. In contrast,
the older machines tend to be used for only one purpose. Some of the older machines are
carpentry saws, sanders, smelters, and a spin casting machine. A list of machines and their
capacities is shown in Table 1.
7
Table 1: Approximated Machine Capacities
2.3. Case Studies
To help us better understand how to improve on-time delivery and lean process
improvement, we looked at three case studies. The first case study looked at the implementation
of different lean improvements within a knife manufacturing company (Vinas, 2018). The
second case study looked at the implementation of value-stream mapping within the automotive
industry (Rahani, 2012). The third case study looked at the use of lean focused on the customer
promise date (Hyden, n.d.). Some of the key points from these cases studies include:
• Utilizing a variety of Kanban systems to improve flow of production
• Level loading production planning for the biggest clients
• Using mapping techniques and GEMBA walks to identify bottlenecks within the
system
• Encouraging operators to value the needs of the customer and the “promise” date
8
• Creating flexible capacity by offering advancement opportunities and rate
adjustments to meet increasing demands
More detail on the case studies can be found in Appendix B.
2.4. Countermeasure Literature
2.4.1. Aggregate Production Planning
Aggregate production planning deals with the quantity and scheduling of production for
the future (Gallego, Guillermo). An aggregate plan usually works within a 3 to 18 month time
frame. In order to develop an aggregate plan, one must investigate forecasting. Additionally,
timing is very important. Seasonality and seasonal demand impact a company’s aggregate plan.
Some strategies that a company can use to deal with sudden changes in demand are:
a. Increasing or decreasing workforce through hiring and firing cycles
b. Changing the rate of production with overtime, idle time, or
subcontracting
c. Holding seasonal inventory
d. Backorder planning
Two models that are used to develop an aggregate production plan are: just-in-time
(chase strategy) and production-smoothing (level strategy). A just-in-time production plan leads
to changes in production rate to meet demand. When implementing a just-in-time strategy, it can
result in lower holding costs, but higher costs in areas such as hiring or firing costs). This plan is
best when the costs to change the rate of production is manageable. For production-smoothing,
production rates are kept constant. When using production-smoothing, the production costs are
reduced but the holding costs may be high. The high holding costs are a result of constantly
9
building inventories to match increases in demand. Thus, production-smoothing is best when
inventory carrying costs are low (Gallego, Guillermo).
Specific information is needed when creating an aggregate production plan. The
information can be utilized in a linear program to get the optimal inputs and outputs. The
information that is needed for an aggregate production plan include (Cholette, n.d.):
• Demand forecast (for each period)
• Production costs
• Labor / Machine hours per unit
• Material requirements per unit
• Holding costs
• Stock-out / backlog costs
• Company constraints
2.4.2. Production Prioritization
The main reason priorities are needed in production is because we can reduce the lead
time for certain orders but when we do this the lead time for other orders would consequently
increase. According to All About Lean website an approach for prioritization of orders is called a
VIP (Very Important Parts) lane. If there's a single lane of production there is no prioritization,
when adding a second one, identified through KANBAN cards that mark what parts are very
important parts for its lane. prioritization for orders that are made to stock is an approach that lets
you account for seasonal demand as well as prioritizing orders., tackling two problems at the
same time. The article How to Prioritize Your Work Orders recommends creating a new stock
system that will prepare for emergency situations when products run out of stock fast, by
10
creating a plan that goes along the seasonal demand analysis priorities could also account for
material availability. According to Pareto distribution 80% of the work put in production comes
from 20% of the products. Those 20% are what is known as exotic products and it is where the
prioritization should primarily focus, mainly because a system that prioritizes 80% of its work is
not sustainable. Furthermore, prioritization should begin right before production to avoid waste
as the Lean article explains, and it should be done by small batches, having clear schedules that
are available in all areas of production and clearly defining which orders are priority since the
beginning could be very beneficial for the Paraguayan company (Roser, 2018).
2.4.3. Order Due Date Estimation
Lead time refers to the time taken between the start and completion of an operation or
project (Corporate Finance Institute, n.d.). Using this definition, we proceeded to track the time it
takes for a product or products to be produced, from the time the order containing it enters the
system to the time the order is delivered.
We also found recommendations for future improvements aside from the manufacturing
lead times that were measured. Snapp suggests developing standard lead times for procurement
lead times and shipping lead times, to take s bigger scope of the supply chain into account, which
will make the minimum possible due date estimation more accurate (Snapp, 2019).
11
3. Methodology
The main goal for Madera y Metal was to improve the delivery time of products relative
to their internal due date. The company provided us with several areas they believed could be
improved, and also allowed us to identify any additional problems that could be resolved. The
objectives that our team set out to meet are as follows:
• Develop problem statement and gather background information
• Identify the root causes for the late order delivery of products
• Determine which root causes are the most important
• Develop countermeasures for the most important root causes
• Provide recommendations to the company based on our observations, research,
analysis, and results
To understand the full scope of the project, we used an A3 process which allows us to
identify, analyze and find tentative solutions/countermeasures to the company’s problems. An
A3 process is ultimately a problem-solving tool that allows for continuous improvement.
According to Quality One, who provide business consulting and training as well as project
support justifies the use of A3 to identify problems and possible solutions recommending that
“Companies must start viewing problems as opportunities of improvement” (Quality-One
International, n.d.). The first part of an A3 process is to develop a problem statement. The next
step is to gather background information to understand the current conditions. After that is
completed, a root cause analysis is conducted, and root causes are identified. Once the root
causes are identified, countermeasures are developed in response.
12
3.1. Objective 1: Developing Problem Statement and Collecting Background Information
The first task our team worked on for this project was to develop a problem statement.
This was done by discussing areas of improvement with Madera y Metal and pulling information
from the written notes they provided us.
The next task was to collect background information to learn more about the current
conditions of the company. This was also done by holding phone calls with members from both
sales and production within Madera y Metal.
3.2. Objective 2: Identifying Causes of Late Order Delivery
After identifying Late Order as the main problem to tackle through the A3 method we
used two tools widely used in LEAN organizations to understand what causes the problem. The
following Fishbone Diagram and Five Whys methods complement each other as our root cause
analysis of why orders are running late.
3.2.1 Fishbone Diagram
In order to understand what caused the problem of orders being internally late we did a
root cause analysis. The selected tools to do this was first to create a fishbone diagram. A
fishbone diagram is a tool used to identify potential root causes to a problem. In addition to
helping determine the root causes, the diagram also encourages group participation and identifies
areas where data can be collected (Ciocoiu, 2010).
With research and information provided by our liaisons in Madera y Metal we looked at
probable causes that had to do with delays caused by the machinery, problems with the process
in general, and how management and sales could improve to help reduce late orders. In addition,
13
we looked at what could cause delays in how the production workers interact with the process,
how materials could potentially cause delays to the finished goods, and other factors like the
environment associated with the industry. The fishbone diagram we designed can be seen in
figure 2 below.
Figure 2: Fishbone Diagram
3.2.2 Five-Whys
We also carried out a root cause analysis using a five-whys exercise. A five-whys
analysis is a systematic questionnaire technique to identify probable causes. One uses the tool by
asking “why?” until it becomes difficult to respond to the question (Pojasek, 2000).
14
After performing the five-whys analysis ourselves, we identified the following causes for
late orders: seasonal demand, order prioritization, and the current rule of thumb to determine
internal due dates.
First, seasonal demand is hard to control, but we found that this causes late orders
because the company’s workload is uneven throughout the year. This is a consequence of
tournaments generally taking place towards the end of the year. This would not be a problem if
customers put in their orders with a lot of time before the tournament begins, but they do not.
Customers might be more eager to plan ahead and design and order their products with more lead
time if promotions made it cheaper for them to order earlier. To improve this we believe that the
visualization of demand has shaped in the past (orders) will help the company to anticipate
peaks; They would be able to develop a better organization to fulfill demand on time (data for
volume of every product in every order for several years are required for a forecast like this to be
successful).
We also found out that the cause of a delay in many orders was because they decided to
prioritize other orders. Time is lost while choosing how to prioritize because the process is not
automated, this causes inconsistency when prioritizing. This inconsistency could be alleviated if
the decisions for prioritization were driven by data but the root cause of this is that there are no
defined measures for prioritization not enough data being tracked to make it a data driven
process. For this we implemented a log that helps keep better track of orders as well as one that
is more integrated with the ERP system, which is not being used to its full potential as explained
in the background.
Finally, we focused on their rule of thumb because there seems to be a lot of late orders
internally and we think that it could have to do with how these internal due dates are set. We
15
think these dates are set by the sales department solely to fit their purposes but not that of the
whole operation. Meaning the dates, they set can often be somewhat unrealistic. The cause of
this comes again to the problem of lack of data to be able to set internal due dates based on
realistic data driven systems that can tell decision makers how much should an order of a
particular size take based on orders of different sizes done in the past.
3.3. Objective 3: Determining the Most Important Root Causes
3.3.1 Fishbone Diagram Ranking
We discussed all problems with Madera y Metal management and asked them to rank in
orders all the causes they felt really affected why the orders are late. They do not think that
machinery, materials, or management and sales are real causes for production to be late. We do
think that better organization and clear consistency when inputting data and constantly keeping
track of the data can help the company follow orders more successfully throughout the system.
Figure 3: Fishbone Diagram Ranking
16
Madera y Metal found the environment to be the main cause for late orders. Furthermore,
seasonal demand was ranked as cause number 1 which makes sense since we know that demand
is based on the tournament schedules which usually follow the same seasons. Under
environmental causes we also found disorganized workspace and humidity ranked in number 3
and 7 respectively. Humidity being ranked last and having a high effort vs low impact solution
was disregarded. Another category that seemed to cause delayals was the process itself, the main
cause being the lack of any product/order prioritization. The lack of established guidelines for
prioritization caused several orders to be late in surveys we gave people from sales to fill in for
all orders that are late. They found a lack of communication between the production floor and
the sales department was ranked 5/7 as a problem, we believe this is related to the lack of use of
data through the company as a whole as well as the lack of visual representation of the data in
the production floor which would, help keep the work space more organized. Finally, the
remaining two causes ranked by management were related to the production workers, which are
problems more out of reach for the team. The rankings themself can be seen in figure 3.
17
3.3.2 Effort-to-Impact Ratio
Figure 4: Effort to Impact Diagram
Figure 4 is a Pick Chart which is a commonly used Lean tool that allows to evaluate
problem solving ideas based on how much effort they require to be implemented and how much
impact will these ideas have when fully implemented (Icasas). For this area we qualified the
effort to impact ratio of applying different countermeasures, the lower right quadrant are ideal
solutions while the upper right quadrant are countermeasures that would require more effort but
could still have a significant impact in the reduction of late internal orders for Madera y Metal.
We want to stay away from the upper left quadrant since those countermeasures require too
much work in comparison to the impact they have. The lower left quadrant does not have a huge
effect, but it is good to consider them since they don't require a lot of effort.
18
3.3.3 Late Order Survey and Order Tracking Log Sheet
The team designed a survey to be filled out by the sales department every time an order
was late. The form meant to figure out what type of product and what quantity was the order for.
It tracks the orders lead time through the dates it was ordered until it was delivered. It asks a
reason for why the order was late, if there was any contact with the customer informing them
about the late order. The survey aims to figure out the current workload in the production floor
and finally all the machines that were used for the production in this product to find out if there
are any common bottlenecks between late orders. The survey can be found in Appendix C.
We also created an order tracking log sheet. The purpose of this sheet is to help get a
sense of the lateness of specific orders. The results collected from this tool were very little; the
implementation did not go as planned. Had we gathered a significant amount of data; we would
have been able to verify the late order percentage. An example of the order tracking sheet can be
found in Appendix D.
19
3.4. Objective 4: Developing Countermeasures
Before developing the actual countermeasures, we had to determine the root causes for
late orders. This was done with the fishbone diagram, which was then used to rank each problem.
From this ranking, we decided to focus on seasonality, product prioritization, and due date
estimation.
After we narrowed our focus on the problems we would try to resolve, we brainstormed
potential countermeasures. The first step in this process was through research of literature. The
next step in this process was to create a preliminary list of countermeasures. For each
countermeasure we created, we linked it back to the root causes found in the fishbone diagram.
The discount for low demand seasons, design stocking system, looking into patterns and trends
to plan ahead, and understanding triggers linked back to seasonality. The prioritization based on
customer loyalty, effort, and value linked back to product prioritization. The rule of thumb based
on past orders and data collection linked back to due date estimation.
Next, we took the preliminary list and identified the levels of effort and impact associated
with each countermeasure. In picking the best problems to prioritize, we were looking for
countermeasures with high impact. This left us with: design a stocking system, look into patterns
and trends to plan ahead, base the rule of thumb on past orders, collection of data, prioritization
(based on effort and value), and understanding the current triggers.
From the countermeasures that were left, we conducted more research to help in our
design of each countermeasure. This research included looking at data that was collected (sales
data) and background research. We also considered the feasibility of each resolution to finalize
the countermeasures to be used in response to each major problem (seasonality, product
prioritization, and due date estimation).
20
Once each countermeasure was developed, we detailed them in our results, and discussed
how they would be implemented.
3.5. Objective 5: Providing Final Recommendations
Finally, we provided several recommendations to Madera y Metal based on our findings
and the development of each countermeasure. For the recommendations, we analyzed the results
and impact of each countermeasure to determine the best follow-up actions for the company. The
recommendations highlight the benefits the company should expect.
21
4. Results
Through the late order surveys, the team found that the main problem causing orders to
be unexpectedly delayed was that there was no established prioritization method or criteria.
Alongside with the prioritization tool explained below the team recommended hiring a
Supervisor that could help follow orders being produced closely and to aid in the communication
between Sales Department and Production Floor.
4.1. General Organizational Improvements
Monday Software is a critical tool for accomplishing the following; inputting the
specifications for orders that arrive, tracking orders wherever they are in the manufacturing
process in real time, monitoring if production is going as planned (using the standard lead times
as reference) and fixing unplanned, recurring variabilities in production. With this digital tool, we
can infer what the production capacity is, and in case we are not meeting these expectations, work to fix
any problem that might be causing it. Screen shots from the software can be seen in Appendix E. In order
to implement the use of this system, Madera y Metal hired a person familiar with the use of computers
and with working in teams to operate the software, leaving him in charge of monitoring the status of
production for the orders that are being produced at any given moment.
22
4.2. Response to Seasonality
After analyzing the data and conducting further background research, our team designed
solutions for Madera y Metal to respond to busier production periods. The design of this solution
is broken down into three categories: production ramp up, preventative maintenance, and
marketing.
The goal of these solutions is to improve how Madera y Metal manages sudden increases
in production. The proposed pocess will begin with the marketing team notifying the production
manager when they can expect the number of orders to significantly increase. This will allow the
production manager to let the supervisors know production needs to be ramped up. The
production manager can then look at increasing the workforce (whether it be long-term or
temporary). To prevent any delays in production, a preventative maintenance team runs through
a list of tasks (which should be conducted during slower production periods) to ensure all
machinery is in good condition. To help ease the burden of peak production periods, the
marketing team will also be in charge of communicating with regular customers and getting them
to plan their orders ahead of time (purchase orders sooner).
4.2.1. Sales Data Analysis
Our team confirmed seasonality was a relevant area of concern after analyzing the sales
data. Madera y Metal currently utilizes an online database to track their orders. The data itself has many
limitations. The limitations include: no delivery date, a lack of clarity in order quantity / volume, and a
lack of clarity on the status of orders.
Therefore, to make use of the data, we analyzed total and daily production for each month. This
would not provide any data on late orders, but it would give us a sense of how much work the company
handles each day. One useful function of the database was the ability to generate reports of sales. From
23
these reports, we were able to isolate the data by month more easily. The data itself was counted from the
reports and inputted into a separate excel file.
Based on the sales data, we identified that the most orders occur in November, at 497.
The least amount of orders occurred in January, at 196. This was found by analyzing sales data
across 3 years (from 2017 to 2019) and taking the average (for each month across 3 years). This
analysis is sumamrized in figure 5 below.
Figure 5: Total Orders (by month)
Further analysis of the data also shows that the average number of orders worked on per
day was also greatest in November. This result can be seen in figure 6 below. For November
there was an average of 22 orders per day across the 3 years. The month with the lowest average
was January, with about 9 orders per day. Taking this data into account, we can also estimate the
number of orders each operator could complete per day. We calculated that the average work per
day was about 16. The number of operators working on the manufacturing floor is 14. This
means that one operator could probably take care of about 1 order per day (16/14 = 1.14).
24
Figure 6: Average Work per Day (by month)
After looking at the data, we were able to confirm that specific times of the year vary in
production levels. This meant that Madera y Metal’s concern in meeting seasonal demand was
relevant in the countermeasure development process.
4.2.2 Production Ramp Up
Based on the data we analyzed for seasonality, we were able to model how changing the
workforce size impacted production. If we kept the standard number of workers (14), this group
could produce 224 orders in one month. This production rate would only be able to meet the
demand of January. Considering the average demand for each month, we determined the optimal
number of workers for each month, as seen in table 2.
25
Table 2: Optimal Number of Workers
4.2.3 Preventative Maintenance
When production is increased, there is likely to be more risk of machine failure. Our team
developed a preventative maintenance plan for Madera y Metal to utilize. This plan will ensure
that machine failure is kept at a minimum.
Starting at the beginning of the year, January, production is the lowest. Which means the
ideal time to conduct a preventative maintenance check would be at the start of the year. The
steps that go into a preventative maintenance check varies depending on the company, and the
type of machine being used. For Madera y Metal, a sample of what a preventative maintenance
form / schedule can be seen in Figure 7.
26
Figure 7: Sample Maintenance Form (Orbit, 2014)
27
4.2.4 Marketing
In addition to utilizing preventative maintenance practices and ramping up production,
we designed protocols for the marketing team to handle. The first protocol we designed was a
peak season alarm system. This alarm system would be initiated by the marketing team. Based
on our analysis of the sales data, we have already predetermined the months where production
rises and falls. Using this information, we recommend that the marketing team set up alarms or
notifications that let the production team know when to start ramping up or ramping down
production (increasing the workforce).
The second protocol would be for the marketing team to contact regular customers to
order products earlier. This would be done through various mediums such as email, social media,
and word of mouth. To incentivize customers to order earlier, we designed a rewards program. A
rewards program is a marketing tool that helps to increase customer loyalty (earlier orders in
Madera y Metal’s case). The idea behind this rewards program would be to give more rewards to
customers who consistently order ahead of time (Thomsen, 2019). This rewards program
provides customers with various benefits (with points being allocated with more purchases). The
benefits include: discounts, credits towards a future purchase, and company apparel. By doing
this, Madera y Metal can start orders sooner, and have them ready in advance of when the
customer needs it by.
28
4.3. Product and Order Prioritization
The late order survey was filled by Madera y Metal Sales Department. Surveys showed
that some orders were reported late because of the prioritization of orders. The new supervisor,
who has been collaborating with the team, will be in charge of filling in daily orders to calculate
the priority of customer orders as an initial run. The Supervisor is expected to be in charge of
communicating the order of production, based mostly on the outcome of the priority calculating
tool, further explained in Section 4.3.1. Although, the results of the prioritization order are not
set in stone and are subject to change in case of special circumstances, for example a
prioritization by customer loyalty (broad implementation of this idea was discarded by the team
because of scoring poorly in the effort-impact ratio).
To prioritize orders our team used a Multi-Attribute Decision Making (MADM) method
to rank customer’s orders according to priority relevance. The aim of MADM, is to find the most
desirable alternative or rank the feasible alternatives for supporting decision making as explained
in Ding et al. (2016). We created our own Multi Attribute Decision Making tool to aim in the
most desirable order priority for Madera y Metal. The three attributes (criteria) used to prioritize
orders are lead time, due date (both internal and customer), and orders currently in production.
Each criterion follows different rules. Orders with lower lead time will be ranked with a higher
priority. Customer due dates are used alongside lead time to predict if orders are going to be late,
orders that are going to be late have a lower priority since Madera y Metal prefers to have an
order which was going to be late to be slightly later, as opposed to more orders being delayed.
Finally, orders in progress are used as a tiebreaker; orders that are in progress have a higher
priority.
29
4.3.1 Multi Attribute Decision Making (MADM) Tool
With exception for orders with Lead Times shorter than a week, the hired supervisor
should fill in the spreadsheet on a weekly basis. In order to follow customer orders closely, Lead
Time is measured in hours. The data needed for the spreadsheet can be found on the Monday
Software used to calculate the internal deadlines through the revised rule of thumb. The data that
needs to be processed from the Monday Software are precisely the 3 attributes (criteria)
mentioned above. Lead Time, Due Dates (Customers and Internal) while Orders in progress will
be updated manually by the Production Floor Supervisor with a simple “SI” for orders that are
already in production. The initial score is taken by using lead time and =NOW formula in Excel
to approximate when the product would be finished, this is subtracted by the deadline given by
Monday Software. This gives us the amount of time available to fulfill the order on time. If
orders are already predicted to be late (negative initial score) they get a *10 weight, making their
score significantly higher. The lowest scores have higher priority, making an order already late a
lower priority, to avoid delaying other orders. In contrast, orders marked as already in progress
will be given a weight of (1/10) to decrease the score and increase priority. Following LEAN
fundamentals of waste reduction orders that are in production would waste time and resources
going back to the queue.
Figure 8 shows the Multi Attribute Decision Making Tool with mock data. Order tracking
numbers are to be inputted into the first column. The supervisor should fill in the lead time in
hours provided in the Monday System, in the second column. The third column converts lead
time to regular 8-hour shift days and calculates (using the excel function now and the lead time
(days)) when the order would be finished if begun immediately. The first score is given by
subtracting the customer due date (inputted by supervisor, calculated through the Monday
30
System) minus the minimum predicted due date that was automatically calculated. The due date
tiebreaker adds a weight of *5 and takes the absolute value if the order is marked as “LATE
ORDER” in the second to last column, decreasing the priority of this order. If the initial score is
negative orders are marked as “LATE ORDERS”. The last score is the order in progress tie
breaker that checks for a “SI” for orders that are in progress and gives them a weight of *(⅓)
increasing the order’s priority.
Figure 8: Multi Attribute Decision Making Tool
4.3.2 Tool Limitations
There are limitations to the tool created that should be acknowledged. For example, the
calculated lead time and the internal due date calculations are not dynamic, meaning that they do
31
not consider the current/scheduled amount of work on the production floor. The tool also needs
to be manually updated, deleting finished orders, inputting new orders and for identifying orders
that have begun production as in progress. Additionally, the supervisor should also update lead
times and customer due dates.
4.3.3 Tool Benefits
The Multi Attribute Decision Making tool automates the conversion of lead time hours to
lead time of available hours per day. The conversion helps automatically predict the date it
would be finished if order began immediately. The tool uses this date to calculate available lead
time and if the order is late, automatically gives it a lower priority. If the company keeps track of
the orders in the Monday scheduling program successfully, the lead time and internal due dates
can be easily accessed in the program, although we recommend using customer given deadlines
instead of internal deadlines given that customer deadlines aren't as tight as the internal ones and
this allows a more accurate prediction if the orders will actually be late or not. Using internal
deadlines might lead to reducing the priority of orders that are not necessarily going to be late to
the customer. Finally inputting a textual yes to the question ‘Has order begun production?’ takes
little time from the supervisor, who has the responsibility to keep close track of orders. Keeping
close track of orders by using this tool and the Monday Scheduling program will help the
supervisor and Madera y Metal have cleaner data for future analysis.
32
4.4. Improved Due Date Estimation
Our team found out that there was no specific method for calculating internal production
due dates. Whenever an order was placed by a customer, the sales assistant that took the order
created an internal deadline for the order based on their current rule of thumb.
After analyzing this rule of thumb for creating internal deadlines, we concluded that the
deadlines that emerge from this approach do not represent the real time needed for the
production of orders very well, since they are using only empirical (experience-based)
knowledge for approximating the time it will take to fabricate the demanded products. We
thought that the company would substantially benefit from taking a more data-oriented approach;
thus, we designed a system to track the time it takes to manufacture several orders comprised by
the products of interest (trophies, cups and medals), and then we extrapolated durations for the
overall fabrication process for each product. Using these standard lead times, we transitioned to
more evidence-based internal deadlines.
For setting the internal deadlines, we used Monday, a project management-oriented
software that will allow the sales department to assign time lapses to the production department
and keep track of the manufacturing process progress for reach order in real time.
To estimate the time it will take for any given order placed by the customer to be
produced, our team proceeded to measure the production time for the three products with the
highest demand (medals, trophies and cups). We made three measurements for each product and
calculated the averages of those measurements, which we used as the standard lead times for
each category. Using a project management tool (Monday), we created templates with the
standard lead times for the three products; by inputting the specifications of any given order
33
(product type and product quantity), the software multiplies those variables, resulting in the
actual lead time for the order.
4.4.1 Unitary Production Calculation
For each product of interest (medals, trophies and cups), the associated lead times are
calculated as mentioned above, with the addition of a cushion time of 5% of the total lead time
for that specific order. The specifications of each order are also introduced in the project
management tool as mentioned above. However, in the case that an order cannot be finished
before its deadline, the sales department will receive directions to contact the customer and
reestablishing a new deadline that fits the customer’s needs.
4.4.2 Limitations of New Due Date Estimation Method
In our new due date estimation methods, we found that we have two main limitations:
WIP and production methods. We do not account for work that is already being produced or
scheduled prior to any incoming order. This might have a big impact in the case that the
company is working at a high capacity or over capacity. Also, the Monday software accounts for
unitary production time of products multiplied by the quantity of the products in the order.
However, with this we are not taking into account the fact that at some steps in the actual
manufacturing process, the products are produced in batches; this dramatically decreases the
theoretical rate at which products can be produced using the software, when compared to the
actual achievable production rate when producing in batches. In other words, measurement of
lead times is considered in unitary production, disregarding the benefit of production in batches.
34
5. Conclusion, Recommendations, and Reflection
5.1 Conclusion
The manufacturing company, Madera y Metal, is seeking to improve their on-time
delivery rate. After collecting data and analyzing it, several different countermeasures were
developed. The current project was done with a limited set of data and information which
resulted in a more simplistic approach to the solution design. Although the solutions are not as
complex as they could be, they still can provide value to the relatively small company.
Our countermeasures focused on three specific problem areas within the company:
responding to seasonality, the prioritization of orders, and the estimation of order due dates. Each
of these problem areas was determined to be a factor in the bigger problem of poor on-time
delivery performance. Based on our understanding of the data, and the design of each solution,
the rest of the chapter provides several recommendations for Madera y Metal to consider as they
continue to improve their processes.
5.2 Recommendations
Our first recommendation is for Madera y Metal to implement the designed protocols in
response to seasonality and increase in demand. By utilizing these protocols, Madera y Metal
will be prepared to meet a sudden increase in demand and can improve their on-time delivery of
products. Our second recommendation is for the Madera y Metal sales department to use
Monday Software to track orders. By inputting the product type (trophy, medals and/or cups) and
volume (amount of product/order), they will automatically have estimated lead times, by using a
unitary production measure, which will provide information on the minimum suggested due date.
35
Finally, our last recommendation is for the new production floor supervisor to keep track of data
in Monday Software. This will allow them to be able to input data into the Multi Attribute
Decision Making Tool that will help guide the priority of customer orders based on the order’s
lead time, and if the order will be late or is already in production. A second role the new
supervisor should play is focused on eliminating the communication gap between the sales
department and the production floor. The software and tool implemented will help the entire
organization be more aware of what is in production and have cleaner data to keep track of
orders.
5.3 Reflection
5.3.1 Design Reflection
The design process is used to develop systems or products that meet company or
customer needs. There are many different variations of a design process. The method our project
follows is that of an A3. The A3 model first starts by defining the problem, then moves onto
background information on the current conditions within the company, identification of root
causes, development of countermeasures, implementation, and evaluation of results. Instead of
creating physical machines or products, industrial engineers design processes, techniques, or
models.
To design the countermeasures used for this project, data collection, analysis, and
background research was used. After each countermeasure design, our project team, advisors,
and members of Madera y Metal provided necessary feedback. The feedback was used to help
finalize the countermeasures.
36
5.3.2 Design Constraints and Impact
An important consideration in the design process is considering various constraints. In
constructing our countermeasures, we were limited in the amount and type of data to be used. A
large reason for this was the lack of current database upkeep and integration within Madera y
Metal. Therefore, our countermeasures are approximations of the actual situation, and may not
capture the best picture. Thus, our countermeasures must be monitored and continuously
improved to ensure they provide the best result to the company.
If Madera y Metal were to consider and implement some of our recommendations, it
would greatly improve their relationship with their customers. By improving their on-time
delivery, customers will appreciate the reliability and timeliness of the company.
Looking at the bigger picture, sports in Paraguay are very popular. Soccer is a large part
of the culture in Paraguay (Wood, 2014). With an improved reputation in the community,
Madera y Metal can look to be a major contributor to both recreational and professional soccer
tournaments.
5.3.2 Lifelong Learning Reflection
Working on this project allowed our team to apply what we have learned in the classroom
to a real-world problem. We were able to get first-hand experience working with an external
organization and were responsible for meeting the expectations of our university and our
sponsor. The data collection, analysis, and countermeasure design were beyond anything we
have done on in-class work. The variety of topics that this project covered required further
understanding and learning of familiar and new concepts.
37
Over the course of this project, our professional speaking skills have improved
significantly. Each one of us has become more comfortable presenting to an audience, as well as
deep discussions with professionals. These skills will be a great benefit for us after graduation.
When we started working on this project, the company had very little put in place to
combat on-time delivery. However, the desire to improve was evident, and the company itself is
hoping to take even more initiative in developing their processes. The work we conducted with
this project has helped to provide potential solutions that will help in the company’s future
aspirations, but they are not limited to just these solutions.
5.3.4 Project Teamwork
Our team met on a weekly basis with our advisor, another time with our sponsors and
another by ourselves in order to guide our project, to make sure that the teams’ objectives and
our sponsors objectives are aligned. Each team member took different equally important
leadership roles in organizing data, material and information, in defining the problems and
countermeasures, and another role in cross functional communication between our team and our
sponsor. All members of the team contributed with ideas and worked on the implementation on
the different countermeasures. Everyone's voice was heard, and all members contributed in
defining goals while having Madera y Metal’s best interest in mind. When planning the work
everyone contributed and was able to bring their own strengths to the table. Team members were
always available to help each other fulfill the objectives and did not limit their responsibilities
upon the aspects of the project they took leadership on.
38
References
Cholette, (n.d.). Forecasting and Aggregate Planning [PDF File]. Retrieved from
http://online.sfsu.edu/cholette/SDCM/ppt/SCC-chapters8-9.pdf
Ciocoiu, C.N., & Ilie, G. (2010). Application of Fishbone Diagram to Determine the Risk of an
Event with Multiple Causes [PDF File]. Retrieved from http://mrp.ase.ro/no21/f1.pdf
Ding, T., Liang, L., Yang, M., & Wu, H. (2016). Multiple Attribute Decision Making Based on
Cross-Evaluation with Uncertain Decision Parameters. Mathematical Problems in
Engineering, 2016, 1–10. doi: 10.1155/2016/4313247
Hyden, D. (n.d.). Case Studies/Results. Retrieved from
http://www.tpslean.com/resultsall.htm#sheetmetal
Icasas, P. (2017, May 18). Project Management 101: What is a PICK Chart? Retrieved from
https://explore.easyprojects.net/blog/project-management-101-pick-chart
Lead Time - Overview, Components, and How to Reduce LT. (n.d.). Retrieved from
https://corporatefinanceinstitute.com/resources/knowledge/other/lead-time/
Orbit. (2014, January 15). Maintenance Record Form. Retrieved from
http://www.inpaspages.com/maintenance-record-form/
Pojasek, R.B. (2000). Environmental Quality Management [PDF File]. Retrieved from
http://faculty.washington.edu/rsmcpher/Class%20Cases%20and%20Assignments/5%20
Whys.pdf
Quality-One International. (n.d.). A3 Problem Solving. Retrieved from https://quality-
one.com/a3/
39
Rahani, A., & Al-Ashraf, M. (2012). Production Flow Analysis through Value Stream Mapping:
A Lean Manufacturing Process Case Study. Procedia Engineering, 41, 1727–1734. doi:
10.1016/j.proeng.2012.07.375
Roser, C., patel, D., Roser, C., Stekelenborg, R. van, Podziewski, B., & Mall, A. (2018, April
16). How to Prioritize your Work Orders – Basics. Retrieved from
https://www.allaboutlean.com/how-to-prioritize-work-
basics/?fbclid=IwAR19nZEKBgLeXUgAb32p4XChO_GZTDzTQX76dBQUSzAnp0jyx
WxIxDTfqtY
Snapp, S. (2019, November 30). Shaun Snapp. Retrieved from
https://www.brightworkresearch.com/supplyplanning/2017/01/24/how-to-best-calculate-
lead-times/
Thomsen, R. B. (2019, October 30). 7 Proven Customer Loyalty Programs That Work. Retrieved
from https://sleeknote.com/blog/customer-loyalty-programs
Vinas, T. (2018, May 6). Knife Company Hones Competitiveness by Bucking the Status Quo.
Retrieved October 10, 2019, from https://www.lean.org/common/display/?o=811.
Wood, R. (2014). Sport in Paraguay. Retrieved from
https://www.topendsports.com/world/countries/paraguay.htm
40
Appendices Appendix A: Process Map
41
42
Appendix B: Case Studies
Lean in a Knife Manufacturing Company
Tonya Vinas describes the application of lean in a knife factory. Reading this case study,
we discovered a couple of important aspects that we should consider for our project (Vinas,
2018). First is that the price of metals can be volatile and therefore in order to consider real cost
and not those estimated when models were made with a lot of assumptions. In our case it is even
more important to update to real costs since most customers make their own designs, so products
cannot be catalogued priced exactly since the prices of products are subject to change depending
on the design and the actual cost of the materials. Furthermore, another thing that was useful to
find out in this lean implementation case study was how they tackled the inconvenience of
having an uneven demand. To deal with this the following was implemented and can be taken
into consideration; a variety of Kanban systems, reducing the inventory of finished goods (since
in our case it is already a demand pull system this is not a big concern), level loading production
planning for biggest clients, which makes it easier to react for a situation in where material
inventory is running short. Finally, the 5S philosophy was also implemented, where the 5S
stands for: separating needed and unneeded items, neatly arranged what is left, clean and wash,
regularly repeating the first three steps to maintain cleanliness, and finally discipline. It is
important to implement good visual control so that this philosophy can be followed and used as a
LEAN implementation.
43
Value-Stream Mapping in Malaysia-Japan Automotive Industries
Another method used in lean manufacturing is Value-Stream mapping. An automotive
corporation located in Asia had been experiencing problems with daily production forecasts for a
specific disc assembly (Rahani, 2012). Upper management took action by proposing a lean
approach to solving the issue. The goal of using lean was to eliminate waste, maintain inventory
control, and improve product quality.
Using mapping techniques and GEMBA walks, the corporation was able to identify
bottlenecks within the production system. The mapping techniques that were used included a
current state map. The current state map was created by walking along the process flow and
interviewing the operator at that process. This technique allowed them to also collect data on takt
time and cycle time.
Takt time and cycle time can both be used to determine if there are any bottlenecks or
constraints in the production line. When analyzing the data, if the cycle time is greater than takt
time, that process is a potential problem area.
By using VSM, the company was able to eliminate wastes and reduce causes. Along with
VSM, the company used cycle time evaluations to pinpoint areas that needed to be changed
(Rahani, 2012).
44
Sheet Metal Stamping, Forming, and Painting
Problems: Pressure from their customers for shorter lead times and improved on-time delivery
performance was causing this privately held company severe difficulty. They faced a very real
risk of losing some critical accounts. Key customers were demanding “next day” shipment. They
expected to be able to place an order today and pick up or have their order shipped first thing the
next day. The company had spent many months attempting to make the transition to lean on their
own, with minimal success. Lead times were still too long, and delivery performance was
unacceptable.
Lean Solutions: In addition to the more traditional lean techniques such as instituting Kanban
controls and improving change-over times, this client required some more fundamental
disciplines. Step one was to immediately change the attitude regarding schedule attainment. Brief
all-employee meetings were held on all shifts. The need for absolute schedule adherence was
explained and personalized: “A commitment date to a customer is a ‘promise’. How do you feel
when someone breaks their promise?” We instituted a simple policy: The day ends when the
schedule is complete, … NOT the other way around. Overtime was authorized and basically
automatic if needed to attain the daily schedule. The next step was to “stagger” the shifts so that
each shift could be held accountable for schedule attainment. Improvement curves (goals) were
set by the employees and monitored daily. The next problem was in creating flexible capacity
(the “rubber” factory). Like most companies, most of their work force was on the first shift. This
posed a problem: Many orders were received late in the day, for next day shipment. They
obviously needed to change the balance of the shifts. Goals were set to gradually move toward a
45
50/50 balance of the day and night shifts. This was accomplished through volunteers,
replacements for attrition, advancement opportunities, and rate adjustments.
Impact/Results: Within weeks, on-time delivery was at or near 100%. Average lead times were
cut from two weeks to three days. Set-up times and lot sizes were cut by 75%. Total inventory
was reduced by 50%, and one entire building was freed up for new product introduction (Hyden,
n.d.).
46
Appendix C: Late Order Form
47
Appendix D: Order Tracking Sheet
48
Appendix E: Monday Software
Screen shots of Monday software.
49