Upload
ernest-harmon
View
212
Download
0
Embed Size (px)
Citation preview
Implications of Energy-Only Procurement on Transmission Planning
CPUC Workshop: Revisions RPS Calculator v6.0
Robert SparksManager Regional Transmission - SouthFebruary 11, 2015
Implications of Energy-Only Procurement on Transmission Planning
• The ISO fully supports procurement and planning for energy only generation
• We have been asked to comment on the potential implications of this, so that we ensure successfully meeting the renewable goal
Page 2
Deliverability Overview
• FCDS generation– assumed to displace other
remotely located FCDS– does not mean that the new
generation can be delivered to the major load pockets.
– still expected to result in congestion.
• EO generation– generation displacing other
nearby generation. – expected to substantially
add more congestion to the system
FCDS
FCDS
Load
FCDS
EO
Load
All Resources Fully Deliverable
Combination of Fully Deliverable & Energy Only Resources
3
Transmission Planning
• Traditionally, transmission planning in California focused on the summer peak load level with all transmission facilities in-service
• Allows transmission facilities to be removed from service for maintenance or upgrades during lower load period
• It also allows local generation capacity to be unavailable for maintenance conditions during the lower load period
• Transmission and generation capacity planning have been closely aligned.
• Generation planning appears to be changing direction
• Realigning transmission planning adds considerable complexity to the already complex transmission planning challenge.
4
Energy Only Transmission Planning
• Need much more focus on studies of the transmission system under lower load periods with transmission facilities out for routine maintenance or upgrades.
• Deliverability study process assumes all lines are in-service.
• Production simulation studies do not monitor the underlying subtransmission system.
• Reliability studies focus on worst case conditions which in the past are a much more limited set of system operating conditions than what can be expected in a future where generation planning is based on energy
Page 5
Transmission Planning and System Operations
• The ISO market and system operating procedures have been proven to work very well under the conditions as they are currently planned
• Transmission planning is typically based on the assumption that the market and system operating procedures will be able to accommodate the system that will exist in the future
• The ISO and transmission and generation operators obviously need to ensure that this happens
Page 6
33% Transmission Plan
• Based on renewable generation also contributing to capacity needs, and we have done that successfully to plan on getting to 33%
• Resulted in the need for much less new transmission than many in the industry expected
7
Energy Planning & Procurement
• Adds considerable complexity• ISO is committed to supporting this approach. • Expected to be iterative. • Production simulation models are reasonably accurate
only when they are analyzing system operating conditions that have been thoroughly studied using detailed powerflow and stability study models
• Generation needs to be studied as a portfolio to reasonably estimate how much of the energy can be expected to be delivered from a particular zone
8