Implementation Update of PG&E’s 2009-2011 LIEE and CARE Programs Presentation to the LIOB June 25, 2009 San Diego, CA

Implementation Update of PG&E’s 2009-2011 LIEE and CARE Programs

Embed Size (px)

DESCRIPTION

Implementation Update of PG&E’s 2009-2011 LIEE and CARE Programs. Presentation to the LIOB June 25, 2009 San Diego, CA. Low Income Energy Efficiency at PG&E: 2007-2011. The 2009-2011 program is a major expansion of LIEE program goals and budget. - PowerPoint PPT Presentation

Citation preview

Page 1: Implementation Update of PG&E’s  2009-2011 LIEE and CARE Programs

Implementation Update of PG&E’s 2009-2011 LIEE and CARE Programs

Presentation to the LIOBJune 25, 2009

San Diego, CA

Page 2: Implementation Update of PG&E’s  2009-2011 LIEE and CARE Programs

2

Low Income Energy Efficiency at PG&E: 2007-2011

The 2009-2011 program is a major expansion of LIEE program goals and budget.

-

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

Homes Treated 63,319 61,034 90,903 124,991 124,991

Budget (,000) $75,337 $75,580 $109,056 $151,067 $156,789

2007 2008 2009 2010 2011

Page 3: Implementation Update of PG&E’s  2009-2011 LIEE and CARE Programs

3

LIEE Program Activity: January 1 – April 30, 2009

PG&E LIEE Activity

Homes Treated 9,649

2009 Homes Treated Goal 90,903

Expensed $12,847,988

2009 Budget $109,056,366

   

kWh 4,238,652

kW 743

Therm 176,652

PG&E LIEE Installations

Furnaces 225

Room AC 178

Evaporative Coolers 263

Envelope & Air Sealing 6,522

Duct Sealing 217

Attic Insulation 549

Water Heater Conservation 6,436

CFLs 38,801

Interior Hardwired Fixtures 14,800

Exterior Hardwired Fixtures 4,154

Refrigerators 2,054

Occupancy Sensors 3,213

Torchieres 646

PG&E has trained:100 Energy Specialists, 97 Weatherization Specialists, and 61 Natural Gas Appliance Testing Technicians

PG&E has: 10 new Weatherization contractors 15 new HVAC contractors

Page 4: Implementation Update of PG&E’s  2009-2011 LIEE and CARE Programs

4

Implementing the Whole Neighborhood Approach

Recent and Upcoming PG&E WNA events:• Firebaugh (Fresno County) – June 11, 2009

• Napa Senior Housing Apartment Complex – June 15, 2009

• City of Madera, Madera County – June 15, 2009

• Fremont, Alameda County – June 25, 2009

• Oakland Fruitvale District, Alameda County – June 30, 2009

The Energy Partners Program has participated in over 25 community events and programs promoting our services to income qualified customers. Including distribution of our program information through the various local food banks.

Neighborhood Targeted(County, Zip code, Zip+7 etc.)

Total Residential

Customers 1

Total Estimated

Eligible 2

Total Treated2002-2008 3

TreatedThrough

WNA 4

Firebaugh, Fresno County (Zip 93622) 5 2,307 1,411 1,005

Napa, Napa County (Zip 94558) 415 360 55

Madera, Madera County TBD TBD

Fremont, Alameda County TBD TBD  

Page 5: Implementation Update of PG&E’s  2009-2011 LIEE and CARE Programs

5

CARE

PG&E CARE 2009 Update (Through April 30, 2009)

• Eligible Customers 1,563,484

• Enrolled YTD 123,503

• Recertified YTD 114,136

• Attrition YTD 83,483

• CARE Participants 1,176,257

• Penetration Rate 75%