Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
© Fraunhofer IWES
12. Symposium Energieinnovation, 16.02.2012, Graz, Austria
Dr.-Ing. Jan Ringelstein
Division Engineering and Grid Integration
Fraunhofer IWES, Königstor 59, D-34119 Kassel
Impact of incentive-based demand response on urban low-voltage grid operation
© Fraunhofer IWES
Agenda
� Introduction and Project SHSG
� Considered grid area and software simulation
� Simulation Results
� Conclusions and further work
© Fraunhofer IWES
Public Power Corporation (PPC) S.A.
Industry
Fraunhofer Institute for Wind energy and energy
system technology
Institute of Com-munication and
Computer Systems
Research
Source: http://www.smarthouse-smartgrid.eu/index.php?id=147
SHSG Project Partners
© Fraunhofer IWES
Amalgamated smart grid architecture
Source: the SH/SG team, 2010
© Fraunhofer IWES
BEMI Coordination Algorithm Concept
Device Types
ISET-BEMI+® Functions~
=~
=
~=
~=
~
����
����
Gateway
Low-VoltageNetwork
CommunicationNetwork
Bidirectional Energy Management Interface
� Concept of decentralized decision
� based on central and decentralized information
© Fraunhofer IWES
Practical relevance of Simulations
� The final structure of the future smart grid is yet unknown
� Grid assets must be procured today for lifetimes of > 30 years
� The beginning energy system transition influences daily grid operation
Smart Grid simulations should…
� Allow for developing Smart Grid processes
� Assess applications of Energy Management Systems (EMS) in grid operation
� Quantify influence on grid operation parameters,
i.e. line loadings, voltages and line losses
� Provide a tool for grid operation and future grid design
� Allow for consideration of grid deconstruction scenarios
� Complement field tests and measurements
© Fraunhofer IWES
Simulation studies in SHSG WP4
A: ECN/TNO
�Study I: PowerMatcher improving integration of wind power generation
in a cluster of 3.000 Smart Houses.
�Study II: PowerMatcher impact on grid losses within a single LV feeder
B: IWES/MVV
�Impact of 300 Smart Houses equipped with BEMI
on grid operation parameters for three realistic LV grid topologies (MA-Wallstadt)
�MVV studied impact of DG within real LV networks in Mannheim, Offenbach, Kiel (voltages, line loadings)
C: ICCS/PPC
�Considering MAGIC application for island system operation (Crete)
�Study I: steady-state simulation considering load controller impact
on grid operation parameters (peak load, losses, CO2 emissions, cost)
�Study II: transient simulation in grid disturbance scenario (frequency stabilization)
© Fraunhofer IWES
Considered LV grid area, Mannheim - Wallstadt
Source: http://www.maps.google.de, 2011
© Fraunhofer IWES
Network for SH/SG Simulations
LV busbar with MV connection
LV busbar
1
5
2 3
6
A
C
B
7
100m/11PCC 150m/6 PCC 250m/2 PCC150m
4 PCC
210m
3 PCC
240m
3 PCC
260m
12 PCC
40m/1 PCC250m/18 PCC520m/41 PCC
240-460m
43 PCC
370m/17 PCC
4
100m
2 PCC
� 162 PCCs, 309 Households
� neighbour LV cell interconnections near nodes 1, 4 and 6
� Node 4 is subject to maximum voltage deviations
© Fraunhofer IWES
Network for SH/SG SimulationsConsidered topologies
LV busbar with MV connection
LV busbar
1
5
2 3
6
A
C
B
7
100m/11PCC 150m/6 PCC 250m/2 PCC150m
4 PCC
210m
3 PCC
240m
3 PCC
260m
12 PCC
40m/1 PCC250m/18 PCC520m/41 PCC
240-460m
43 PCC
370m/17 PCC
4
100m
2 PCC
Topology Nr. LV-LV connections LV-MV connection
1 All open All closed
2 All open B&C closed
3 All open A&C closed
© Fraunhofer IWES
IWES Simulation system as used for SH/SG
Module „BEMIVis“
Module „BEMISim“
Module „BEMI_DSIF“ Network simulation software DIgSILENT PowerFactory
Simulation Master
cSimMaster
Haushalte
cHousehold
HaushalteHouseholds
BEMIEnergy managemt.device switching
Customerrandom device
influencing
cBEMI cCustomer
DevicesFridges, Freezers,
Washing Machines,
unmanaged Loads,PV, CHP, ...
cSOC_Device, …
Sim
. data
netw
ork
Clie
nt S
erv
er
User interfaceParameters
Simulation controlData display during
simulation
Pool-BEMI
C/C++
C#
Sim
. data
netw
ork
Clie
nt S
erv
er
C++ DigSilent Programming Language (DPL)
LV network model3phased
Load-flowcalculation
DPLScript
Data exchangeActive/Reactive Power at
grid connection pointsNode voltages,
line loads, ...
Sim. data network
Client Server
ASCIIFiles
TCP/IPModule „BEMIVis“
Module „BEMISim“
Module „BEMI_DSIF“ Network simulation software DIgSILENT PowerFactory
Simulation Master
cSimMaster
Haushalte
cHousehold
HaushalteHouseholds
BEMIEnergy managemt.device switching
Customerrandom device
influencing
cBEMI cCustomer
DevicesFridges, Freezers,
Washing Machines,
unmanaged Loads,PV, CHP, ...
cSOC_Device, …
Sim
. data
netw
ork
Clie
nt S
erv
er
User interfaceParameters
Simulation controlData display during
simulation
Pool-BEMI
C/C++
C#
Sim
. data
netw
ork
Clie
nt S
erv
er
C++ DigSilent Programming Language (DPL)
LV network model3phased
Load-flowcalculation
DPLScript
Data exchangeActive/Reactive Power at
grid connection pointsNode voltages,
line loads, ...
Sim. data network
Client Server
ASCIIFiles
TCP/IP
© Fraunhofer IWES
Refrigerator
MaxOnTm 4800 sec +- 20 %
MaxOffTm 7200 sec +- 20 %
Freezer
MaxOnTm 3430 sec +- 40 %
MaxOffTm 8100 sec +- 30 %
SOC Model: Parameters used for SH/SG
© Fraunhofer IWES
SOC Model: Example
-20
0
20
40
60
80
100
120
Con
tent(g
rün) [%
], S
tor
(bla
u) [%
]
0 6 12 18 24 6 12 18 24 6 12 18 24
Stunden seit jew. Tagesbeginn
© Fraunhofer IWES
Load and Generation within the network
Distributed Generation
� peak generation of ~350 kWp
from PV installed at every PCC (evenly distributed)
� used PV irradiation measurements from Kassel (5 min resolution)
Load
� Peak consumption ~200 kW in grid area
� 3.300 kWh / a consumption per household
ApplicationRelativeconsumption
Absolute Consumption [kWh/a]
Fridges 11% 363
Freezers 11% 363
Washing Machines 7% 231
Dish Cleaners 7% 231
Tumble Dryers 10% 330
Non-controllable 54% 1.782
Sum 100% 3.300
© Fraunhofer IWES
� 6 days in June were simulated in each run
� 5 min simulation stepwidth
� Each run is done for a flat tariff and a PV tariff
� PV tariff designed for incentivizing load switch-on
during high PV infeed:
� three price groups à 103 households
� Price group 1: 15 ct/kWh 11:00-12:59, else 20 ct/kWh
� Price group 2: 15 ct/kWh 11:00-13:59, else 20 ct/kWh
� Price group 3: 15 ct/kWh 11:00-13:59, else 20 ct/kWh
� Repetition for each topology � 3 x 2 simulation runs
Simulation Runs
© Fraunhofer IWES
0 200 400 600 800 1000 1200 1400 1600 18000
50
100
150
200
250
300
350
Time [x5 min]
PV
(re
d);
Tota
l (b
lack),
SO
C (
blu
e)
and F
PS
load (
gre
en)
[kW
]
Example result topology 3: load and generation (flat tariff)
© Fraunhofer IWES
0 200 400 600 800 1000 1200 1400 1600 18000
50
100
150
200
250
300
350
Time [x5 min]
PV
(re
d);
Tota
l (b
lack),
SO
C (
blu
e)
and F
PS
load (
gre
en)
[kW
]
Example result topology 3: load and generation (PV tariff)
© Fraunhofer IWES
Example result topology 3: active power line losses (red: flat tariff, black: PV tariff)
© Fraunhofer IWES
103% Un
100% Un
Example result topology 3: voltage at node 4 (red: flat tariff, black: PV tariff)
© Fraunhofer IWES
Characteristic value Change
Imported energy avg. -3,7 %
Locally used PV energy avg. +3,7 %
Line losses -8 .. -9 %
Transformer losses appr. -1 %
Avg. Voltage node 4
during 11:00-14:00 -1 .. -1.8 V
else +0.1 .. +0.3 V
Avg. Line loading
during 11:00-14:00 -3.2 .. -6.2 %
else +0.1* .. +0.4 %
Avg. Transformer loading
during 11:00-14:00 -7.1 .. -9.7 %
else appr. +0.6 %
marginal effect due to restriced load
shifting potential and short low-price period
lower than ECN/TNO due to different loads
Note: tr. loss ~ lne. loss x 8 .. 2 (top. 1 .. 3)
Peaks reduced by 0.8 .. 1.4 V
Caused by load switch-off at HI-price times*
* Attribution to tariff effect uncertain
Causing increase of peaks by up to 1.2 %
Note: peaks are not occuring in this time
Causing increase of peaks by up to 2 %
Note: peaks are not occuring in this time
Result summary
© Fraunhofer IWES
Conclusions and further work
� Loadings and voltages are uncritical in any case
� PV tariff changing char. values as expected, but in some cases
merely marginal. Reasons: low LM potential, tariff design
� Significant reduction of line losses due to PV tariff design� Tariff design needs to be goal oriented
� Significant reduction of voltages, line & transformer loading
during LO-price times only
� Weaker grids benefit more from tariff effects
� Further Research: Model improvements, study other tariffdesigns, MV studies and practical applicability considerations
� The work continues in project „Modellstadt Mannheim“
© Fraunhofer IWES
SHSG project website
All publications and public final report at:
http://www.smarthouse-smartgrid.eu
© Fraunhofer IWES
Thank you for your attention!
Dr.-Ing. Jan RingelsteinFraunhofer IWES, Königstor 59, D-34119 Kassel,
Tel.: +49 561 7294 – 208, Email: [email protected]
This report is based on a research project partly funded by the EU FP7 project SmartHouse/SmartGrid (Grant no.: FP7-ICT-2007-224628).
The authors are responsible for the content of this publication.