30
Impact assessment of flood mitigation measures ~ some new developments ~ Dr. M. Kok HKV Consultants Delft University of Technology

Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Impact assessment of flood mitigation measures

~ some new developments ~

Dr. M. Kok

HKV ConsultantsDelft University of Technology

Page 2: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess
Page 3: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess
Page 4: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess
Page 5: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

How to select measures?Impacts:

• economic cost/benefit analysis

• nature

• landscape

• ……...

Measures:

disaster management (evacuation, sand bags) and spatial planning

Page 6: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Flood risk evaluation

In the Netherlands the Technical Committee on Flood Defences (TAW) argues that flood defence should be based on:

• criteria on number of deaths (personal risk and societal risk)

• cost benefit analysis

But is not official policy (yet)

Page 7: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess
Page 8: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Is there a flood protection problem in the Netherlands?

• No: ‘we have never been as safe as we are today’ (probability)

• Yes: ‘damage increase and safety standards are set up some 50 years ago, and population increases and economy growths’ (consequences)

According to report of Ministry of Environment (RIVM) there is a serious problem (although the standards are

relatively high!)

Page 9: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Flood risk in the Netherlands: social risk

Number of victims

Externalsafety

Estimate floodrisk

Page 10: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

New developments

Risk = flooding probability * consequences (yearly insurance premium, expected number of deaths,

….)

• often: flooding probability = exceedance probability of design water level (safety standard)

• often: no uncertainty in flood damage

• often: no assessment of economical safety standard

(dynamic investment approach to assess risks)

Page 11: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Flooding probability (1)

• Failure mechanism: overflow /wave overtopping the dike

• The Design water level is used to assess the flooding probability

• In design of dike we have a free board (of 0,5 - 1 meter) for (among others wave runup)

• There is a strong relation between the exceedance probability and the flooding probability. It depends among others on: probability distribution discharge, HQ relation, uncertainty in water levels given the discharge, wind speed and wind direction.

Page 12: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Flooding probability (2)

Design water levelWave runup

Free board

Dike height

Page 13: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Flooding probability (3)

10000 11000 12000 13000 14000 15000 16000 17000 180009

9.5

10

10.5

11

11.5

12

12.5

Afvoer [m³/s]

Wat

erst

and

[m+

NA

P]

Waterstand als functie van de afvoer op km−raai 915 (Waal)

90%−onzekerheidsband

Page 14: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Flooding probability (4)

Stochastic variable

Discharge + wave runup according guidelines 1/1800

Discharge + wave runup all wind directions 1/2200

Discharge + waver runup all wind speeds 1/2500

Discharge + uncertainty water levels 1/1700

Discharge + wind direction + wind speed +uncertainty water levels

1/2600

Discharge + wind direction + wind speed +uncertainty water levels + shape discharge

1/1700

Results for other locations: range 1/1000 -- 1/8000.

Example Tiel: Dike design based on Design water level (exceedance probability of 1/1250) plus free board of 0,5 m

Page 15: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Uncertainty flood damage (1)

• Based on results of R. Egorova (Delft University of Technology and HKV Consultants)

• The general formula:

where:

-- damage factor for category i in cell j,(damage function)

-- number of flooded units in category i in cell j

-- maximum damage per unit in category i (Netherlands Economic Institute)

n – number of grid cellsm – number of damage categories (equal to 51)

10 ≤≤ iα

∑∑==

=n

jijij

m

ii nSS

11α

ijα

ijn

iS

Page 16: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

“Standard” method for Assessing Damage and Casualties as result of

flooding (HIS-SSM software)

Page 17: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Uncertainty flood damage (2)

Main Terms to calculate damage:• Flood scenario• Damage category• Damage: direct, indirect, business interruption • Maximum damage• Damage factor (damage function)

Sources of uncertainty:• damage factor• number of flooded units• maximum damage per unit• flood depth• flow velocities• rate of water rising

Page 18: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Dependence modeling• Spatial dependence

HIS-SSM cells structure

• Complete dependence• Independence• Stratified water depths (complete dependence within

class, independence between classes)

ij

n

i

m

jijiiij

m

j

n

iij nSSnS ∑ ∑∑∑

= == =

==1 11 1

αα

Page 19: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Uncertainty maximum damageMaximum damage per unit object

• Mean• 5th percentile probability

• 95th percentile distribution

90% confidence bounds

DatabaseDamage Function

Maximum damage amount (€)

UnitDamage categories

32 - 63CBS148.6m2Urban area

0.7 - 7.1CBS11.50m2Agriculture direct

Page 20: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Case study: dike-ring area 14 (Central-Holland)

Page 21: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess
Page 22: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Simulation (MATLAB)

Page 23: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Results: 2m (NAP) water level

(a) - complete dependence(b) - independence(c) - stratified dependence

Page 24: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Uncertainty flood damage: results

Page 25: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Economic safety standard (1)

K

A

B

R

K=I+R

I

CX̂ X

Minimising sumof Loss (R) and Investment (I)

Page 26: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Economic safety standard (2)

• Deterioration of watersystem (settlement, climate change)

=> Increase of flooding probability

• Economic growth and increase population

=> Increase of potential damage

• In combination: Expected loss increases

Change of conditions implies more than one decision on height of dikes

Page 27: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Economic safety standard (3)

• Interest rate (r > 0) :

postpone costs as much as possible, do not more than strictly necessary at once

•Fixed investment costs

investment in safety in ‘jumps’

Result: Safety level is not constant• High, directly after investment• Gradually decreasing afterwards untill just before new investment

Page 28: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

New strategy: periodic investments

time

Safety level

How much ? =How long ?

Low s-

High S+

When?

1

2

3

Proposed by Central Planning Office (CPB) (mr. C. Eijgenraam)

Page 29: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Economic safety standard (4)

Conclusions of Central planning Office:

• Constant exceedance probabilities are misleading as

good safety standards

• Expected loss is correct criterion for safety standards

• Actual calculation is needed

In future shift needed towards: control of expected loss

by flooding

Page 30: Impact assessment of flood mitigation measures · Flooding probability (1) • Failure mechanism: overflow /wave overtopping the dike • The Design water level is used to assess

Economic safety standard (5)

dijkring 43

0

500

1000

1500

2000

2500

3000

3500

4000

4500

0 20 40 60 80 100 120 140 160

cm dijkverhoging

milj

oen

euro

kostenSchadeTotaal

Optimum safety level: 1/4800 (now: 1/1250)

Total costs:very flat