17
ILRS Standardization of Hardware, Software, and Procedures: Extending the Range the Range Randall Ricklefs The University of Texas at Austin Center for Space Research Center for Space Research 17 th International Workshop on Laser Ranging Bad Kötzting, Germany

ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

ILRS Standardization of Hardware, Software, and Procedures: Extending

the Rangethe Range

Randall RicklefsThe University of Texas at Austin

Center for Space ResearchCenter for Space Research

17th International Workshop on Laser RangingBad Kötzting, Germany

Page 2: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Introduction

What level of standardization best promotes What level of standardization best promotes the goals of the ILRS?

�Current status

�What is/can be standardized?

�How are standards enforced?

LR Station Reference design

16-20 May 2011 17th International Workshop on Laser Ranging 2

�LR Station Reference design

Page 3: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Standardizing on Performance

�Yearly Data Quantity Guidelines

�1000 Low Earth Satellite (LEO) passes

�400 LAGEOS 1,2 passes

�100 High Satellites passes

�Data Quality Guidelines

�1 cm LAGEOS normal point precision

�2 cm short term bias stability

�1 cm long term bias stability

�Operational Compliance Guidelines

16-20 May 2011 17th International Workshop on Laser Ranging 3

�Data delivery with 12 hours (latency)

�Specified ILRS normal point format

�Current site and system information form (i.e., site log)

Also, standard procedures, algorithms, formats, and software are on the web site

Page 4: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Quarterly Quarterly Quarterly Quarterly Report CardCardCardCard

Page 5: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

What do we want from standardization?What do we want from standardization?What do we want from standardization?What do we want from standardization?

�Encourage reliable, accurate performance

�Provide the best, mature methods�Provide the best, mature methods

�Reduce cost of design and maintenance

�Reduce duplication of effort

�Permit innovation and flexibility

�For software, both the algorithm and software to implement it are desirableto implement it are desirable

A good standard is a resource, not a ball and A good standard is a resource, not a ball and A good standard is a resource, not a ball and A good standard is a resource, not a ball and chainchainchainchain

Page 6: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Who Is Involved?

�Stations (Most of our discussion lies here)

•Hardware, software, procedures•Hardware, software, procedures

�Operations Centers

•Procedures

�Data Centers

•Procedures

�Analysis Centers

•Procedures

16-20 May 2011 17th International Workshop on Laser Ranging 6

•Procedures

Page 7: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Hardware (Stations)

�Time standards (GPS, cesium, etc.)

�Laser (10Hz, 100Hz, 2kHz)

�Range gate generator

�Timers (event and interval; some to avoid)

�Detectors (APD, SPAD, MCP)

�Calibration piers

16-20 May 2011 17th International Workshop on Laser Ranging 7

�Calibration piers

�Radar

�Telescope/dome/infrastructure

Every station (network) is its own standard

Page 8: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Procedures (Stations)

�Surveys (how often; what gets surveyed)

�Range calibrations (how often, etc.)

�Prediction and restriction (Go/No-go) downloads

�Ranging data uploads

�Status messages (NASA LORs; EUROLAS real-time status)

�Adding new targets

�Site log maintenance

16-20 May 2011 17th International Workshop on Laser Ranging 8

�Site log maintenance

�Station change notice (for data quarantine)

Some of these are already standardized

Page 9: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Procedures (Centers)

Operations centers

−Data ingestion (schedule; location)

−Data screening (format checks; data quality checks)−Data screening (format checks; data quality checks)

−Quarantine data handling

−Data distribution (schedule; location)

Data centers

−Data ingestion (schedule; location)

−Data distribution and reporting

Analysis centers

16-20 May 2011 17th International Workshop on Laser Ranging 9

Analysis centers

−Data ingestion

−Data screening and fitting

−Data product creation and distribution

A work in progress

Page 10: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Procedures (Centers) II

�There are still inconsistencies in meaning of daily files (CDDIS/EDC). Seems to be OK with daily files (CDDIS/EDC). Seems to be OK with users.

�EDC and NASA OCs use different screening checks

�Centers are coming to agreement on quarantine procedures

16-20 May 2011 17th International Workshop on Laser Ranging 10

procedures

Page 11: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Software/Algorithms(Station Data Acquisition)

�Telescope mount model fitting (candidate)

�Star / planet prediction / Refraction (USNO NOVAS; RAL SLALIB; JPL; Mendes/Pavlis)

�Sun avoidance (candidate)

�Tracking restrictions (candidate?) Formats in place.

�Prediction sample routines: CPF read/write/check/interpolate/convert

�Range data sample routines: CRD read/write/check/convert

16-20 May 2011 17th International Workshop on Laser Ranging 11

�Challenges: Hard to go beyond this level, as software may be

−O/S- and library-dependent (coding standards; GUIs)

−hardware-dependent, depending on level of hardware abstraction used

Page 12: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Software/Algorithms(Station Data Processing)

•Prediction download/preparation and data upload

•Data pre-filtering, e.g. Poisson filtering (candidate)

•Normal point generation (candidate)

•Data distribution statistics: distrib

•CPF /CRD sample routines: read/write/check

•Normal point checking: npcheck

16-20 May 2011 17th International Workshop on Laser Ranging 12

•Normal point checking: npcheck

Need more standard station software/algorithms

Page 13: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Software/Algorithms(Centers)

•CRD/CPF sample code: checking/conversion

•POD software:

−GEODYN (JCET, ASI, GA) - EPOS (GFZ)

−DOGS (DGFI) - GINS (GRGS)

−SATAN (NSGF) - NAPEOS (ESA)

−Bernese (BKG)

•IERS Conventions (currently 2003) is the standard for

16-20 May 2011 17th International Workshop on Laser Ranging 13

•IERS Conventions (currently 2003) is the standard for gravity field, ocean loading, tides, refraction models, constants, etc.

Mainly performance based

Page 14: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Standards Enforcement

•Need some type of enforcement for standards •Need some type of enforcement for standards to mean anything

•The ILRS is a volunteer organization, but stations have united to gain benefits from cooperating

•Education: Ensure every ILRS component

16-20 May 2011 17th International Workshop on Laser Ranging 14

•Education: Ensure every ILRS component knows standards and their benefits

•Report card and the station “cut line”

Page 15: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

SLR Reference Design - I

•Proposal: maintain an SLR station reference design, probably on the ILRS websitedesign, probably on the ILRS website

•Incorporate the best, proven and available hardware and software and “best practices” procedures, providing viable alternatives and compatibility with other components

•Need not be built, but is a starting point for any

16-20 May 2011 17th International Workshop on Laser Ranging 15

•Need not be built, but is a starting point for any group wanting to build or update an SLR station

Page 16: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Block diagrams of hardware, software and

proceduresprocedures

List of manufacturers

List of deprecated components

Reference articles by subsystem

List of “experts” for each component or sub-List of “experts” for each component or sub-

system

Augments existing standards on the ILRS web site

17th International Workshop on Laser Ranging16-20 May 2011 16

Page 17: ILRS Standardization of Hardware, Software, and Procedures ......ILRS Standardization of Hardware, Software, and Procedures: Extending the Range Randall Ricklefs The University of

Conclusion

•Absolute standardization is not possible

•Current standardization on performance, not •Current standardization on performance, not hardware and software is probably best

•Must enforce standards to be of any value

•More “standard” software should be made available on the ILRS web site

16-20 May 2011 17th International Workshop on Laser Ranging 17

•Maintaining some type of standard reference system or list of inter-operating critical components could be helpful