Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Ireland-France Subsea Cable Limited
IFC-1
Marine survey scope of work for foreshore licence application, Loughbeg landfall
242080-00_SOW001
Issue 1 | 27 March 2017
This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.
Job number 242080-00
Ove Arup & Partners Ireland Ltd
Arup
One Albert Quay
Cork
T12 X8N6
Ireland
www.arup.com
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Contents Page
1 Introduction 1
2 General Requirements 1
2.1 Quality assurance 1
2.2 Health, Environment, and Safety 1
3 Marine survey scope of work 2
3.1 Survey area 2
3.2 Survey description 6
3.2.1 Shallow water survey 7
3.2.2 Inshore water survey 8
3.2.3 Diver swim survey 8
3.2.4 Landing site surveys 8
3.2.5 Burial Assessment Survey (BAS) 9
3.3 Operational requirements 10
3.3.1 Schedule 10
3.3.2 Vessels 10
3.3.3 Survey navigation 11
3.3.4 Operating permits 12
3.4 Survey Equipment 12
3.5 Mitigation measures 12
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 1
1 Introduction
Ireland-France Subsea Cable (IFSC) Limited was founded in Ireland in early 2015
as a single purpose entity to develop a submarine fibre-optic cable system
between Ireland and France.
IFSC propose to construct IFC-1, a submarine fibre-optic cable system that will
be the first and only direct subsea cable between Ireland and France. The IFC-1
system will be a state-of-the-art subsea cable and provide ultra-high capacity
transmission to telecommunication carriers, Internet companies and large
enterprises in Ireland looking for connectivity to continental Europe. For more
information visit www.ifc-1.com.
This document forms part of a foreshore licence application to the Department of
the Housing, Planning, Community and Local Government to undertake marine
survey works within the foreshore to support the route selection and design of the
IFC-1 project. The scope and methodology of the marine survey is described in
this document.
Once the marine survey works are completed, the routing and design of the IFC-1
project will be finalised for inclusion in a separate future foreshore licence
application for the cable installation works.
2 General Requirements
2.1 Quality assurance
The marine survey Contractor shall
operate Quality and Environmental Management Systems based on and
conforming to ISO9001:2008.
provide a Quality Management Plan for all the marine operations.
provide operational procedures for all the marine operations.
2.2 Health, Environment, and Safety
The marine survey Contractor shall operate International Safety Management
(ISM) and Health Environmental and Safety (HES) systems based on legislation
relevant to the proposed activities. The marine survey Contractor shall have an
overall Health, Safety, Security and Environmental (HSSE) plan for each stage of
all marine operations. The plan and shall cover all parties and operations.
Where required as a condition of permitting, the Contractor shall form and
comply with the obligations of an appropriate Environmental Management Plan.
All vessels shall comply with the latest International Maritime Organization
(IMO) and Safety of Life at Sea (SOLAS) and environmental requirements for
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 2
their classification and with any national requirement of the territorial or
continental / EEZ waters to be operated in.
All vessels shall operate under a certificated Safety Management System (SMS)
that provides policies, procedures, and a framework for continuous improvement
to ensure the safety of personnel on-board.
All vessels shall comply with the International Convention for the Prevention of
Pollution from Ships 1973 MARPOL 73/78.
The vessel’s officers and crew shall comply with relevant merchant shipping
legislation. All personnel shall be made aware of their obligations under ISM and
HES regulations, and shall possess the appropriate protective clothing and safety
equipment.
The vessels provided by the marine survey Contractor shall be seaworthy, suitably
equipped for the Work as required for the scope of work and by the operational
procedures.
All survey works that involve the use of acoustic instrumentation will follow the
Code of Practice for Protection of Marine Mammals during Acoustic Seafloor
Surveys in Irish Waters.
An Underwater Archaeological Impact Assessment (UAIA) and associated
foreshore/intertidal and coastal assessment shall be carried out by suitably
qualified underwater archaeologist in advance of any site investigation, survey
works or trial pits. The results of the UAIA will be submitted to the Underwater
Archaeology Unit (UAU) of the National Monuments Service (NMS) for their
consideration prior to commencement of any works.
3 Marine survey scope of work
3.1 Survey area
The location of the area within the foreshore within which the marine survey
works will be carried out is shown in Figure 3.1. A table of the survey area co-
ordinates (to WGS-84) are provided in Table 1. The general basis for survey area
is a 500m wide survey corridor centred on the preliminary IFC-1 cable route,
extending from the high water mark (HWM) of the landfall site at Loughbeg in
Ringaskiddy to the 12 nautical-mile limit.
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 3
Figure 3.1: Survey location
Northing Easting
51° 34.200’ N 8° 01.786’ W
51° 32.881’ N 8° 05.076’ W
51° 42.274’ N 8° 08.110’ W
51° 40.660’ N 8° 11.342’ W
51° 43.073’ N 8° 12.115’ W
51° 42.903’ N 8° 12.489’ W
51° 43.650’ N 8° 13.479’ W
51° 43.532’ N 8° 13.871’ W
51° 47.218’ N 8° 15.915’ W
51° 47.124’ N 8° 16.324’ W
51° 49.052’ N 8° 16.313’ W
51° 48.804’ N 8° 16.488’ W
51° 49.384’ N 8° 18.283’ W
Table 1: Survey Area Co-ordinates (to WGS-84)
Please refer to drawings 242080-00_CSK200 for further information.
The preliminary IFC-1 cable route extends from the landfall at Loughbeg, running
parallel to an existing outfall pipe, before turning south to pass through the mouth
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 4
of Cork Harbour and then turning approximately south-southeast and crossing the
Kinsale Head Gas Pipeline to the 12 nautical-mile limit, and beyond that to the
North coast of France.
Figure 3.2 shows the preliminary route of the cable and survey area close to shore.
Figure 3.2: Survey Area close to shore
The Loughbeg landfall site was selected following a site selection process that
considered numerous landfall sites on the south coast of Ireland. The Loughbeg
landfall site was selected on the basis of an assessment against a combination of
terrestrial and maritime requirements including technical, geotechnical,
environmental, construction and economic factors. The site has particular benefits
given the ready availability of land for the cable landing termination kiosk
(located above the HWM) in an already-developed location and proximity to e-net
terrestrial and other fibre facilities at Ringaskiddy. Figure 3.3 to 3.5 show the
nature and characteristics of the landfall.
The IFC-1 cable routing and design will be finalised following completion of the
survey works.
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 5
Figure 3.3: Photograph looking south along the landfall beach from cable
route (Hovione industrial facility visible on the right)
Figure 3.4: Photograph looking north along the landfall beach from cable
route at the HWM (DePuy industrial facility visible in the distance)
Figure 3.5: Photograph looking west (inland) from the HWM. The fibre optic
cable route onshore will be to the left of the existing path. (Hovione industrial
facility to the left).
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 6
3.2 Survey description
The marine survey shall be used to confirm or amend the preliminary cable route
with regard to the optimum route for cable design, installation, burial, protection,
survivability and subsequent maintenance of the system. The assessment of data
acquired during the survey shall determine deviations from the initial proposed
route.
The Marine Survey shall produce sufficient data to allow decisions to be made
regarding the procedures for marine installation, cable armouring, cable slack,
additional protection and the extent of cable burial.
The Contractor shall carry out surveys, charting and reporting, which shall include
the identification, location, measurement, study, investigation and presentation of
the following:
general bathymetry
morphology and nature of the seabed
sea bottom and sub-bottom characteristics
sea bottom temperature and seasonal variations
surface, sub-surface and seabed current influences
seismic activity
turbidity currents
climatological conditions
in-service and out-of-service and planned pipelines
in-service and out-of-service and planned cables (including scientific,
telecommunication and power)
wrecks and other seabed hazards
The survey vessel used to survey the cable route will use a multi-beam echo
sounder (MBES) system. In shallower waters, the vessel will use a towed device
to facilitate Side Scan Sonar and a Sub-bottom Profiling. The position of this
towed device will be tracked acoustically using an ultra-short base line (USBL)
tracking system. The acoustic signal transmitted from the sub-bottom profiling
device will provide adequate resolution within the uppermost layers of sediment.
A magnetometer will be carried on-board for use in the event that additional
investigations (of pipelines, cables etc.) are required. The collection of sediment
samples shall be undertaken along the route using grab sampling devices.
Analysis of these samples will help determine information about the soil in the
subsurface at a specific location.
Hull mounted or towed swath bathymetry systems shall be used to obtain
continuous recordings centred on the preliminary routes. Additional sounding
lines may be required to develop any features that may be encountered. All
soundings shall be corrected for the speed of sound in seawater and recorded in
metres. In each area, the width of the corridor shall be as set out in Table 2 below.
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 7
Survey Area Minimum corridor width
Shallow Water 15m-1000m 500 m
Inshore Area <15m
100m at landing point expanding to 500 m at 15 m water depth
Table 2: Minimum Survey Corridor Widths
Overlaps are required between surveys performed by different vessels or
equipment. The minimum overlap within the foreshore area shall be 500 metres
between the Inshore Water and Shallow Water surveys.
3.2.1 Shallow water survey
A multibeam swathe bathymetry survey shall be undertaken. The multibeam
swathe bathymetry system (MBES) shall have a real-time display capable of 50m
depth resolution, or better, and a bathymetric accuracy of 1% of water depth, or
better. The MBES equipment shall be integrated with the vessels navigation
system.
In areas where the main survey vessel is not able to operate, usually shallower
waters, a smaller survey vessel equipped with similar equipment (side scan sonar,
sub-bottom profiler, echo sounder) will be used to determine any potential
engineering constraints to the cable route within the 500m corridor.
Swath bathymetric, side scan sonar and shallow geological data shall be collected
simultaneously. A minimum overlap of 20% shall be maintained for the
multibeam data.
Sufficient survey lines shall be undertaken to identify a usable corridor centred on
the preliminary route and to determine the positions and status of all pipelines,
any cables, obstructions or potential obstructions.
Side scan sonar with seafloor mapping shall be used to locate and identify all
artificial and natural seabed features. The minimum operating frequency of the
side scan sonar shall be, 100kHz. A 50% overlap between swathes shall be
achieved over the entire route.
A high resolution sub-bottom profiler (SBP) shall be used to determine the
thickness and nature of the sediments. In most areas, this information is needed in
the top 2 metres of seabed with optimisation of data in the top metre of seabed.
However, in some areas where specific burial requirements are in place the
optimised information is needed down to the specific depth of sediments, as a
minimum.
The method for SBP will be the use of a towed fish with the transmit and receive
mounted in the same fish as the seabed mapping equipment. All hull mounted
SBP equipment will be fully motion compensated.
Cone Penetrometer Tests (CPTs) and seabed samples shall be taken as necessary
to aid interpretation of the sub-bottom profile data. The maximum number of
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 8
samples shall be determined based on an average interval of 4 km. Core samples
shall be attempted first at any location. However, if a core sample has not been
obtained after three (3) attempts then, a grab sample shall be attempted. For CPTs,
where the penetration is less than would be expected from the geophysical
interpretation, a second CPT attempt must be made.
Seabed sampling will be undertaken using a gravity corer/vibrocorer and grab
sampler. The corer will have minimum recovery capability of 4 metres. The grab
sampler will be deployed if gravity core recovery is not possible. Cores will be
undertaken, on average, every 10 km along the route to the maximum predicted
depth for burial.
A magnetometer search within the survey corridor is required to determine the
presence and location of in-service or out-of-service cables and/or pipelines not
positively located and identified by other means. If, after all reasonable
endeavours are made to locate a charted cable or pipeline, it cannot be detected,
an action plan shall be agreed before the survey proceeds.
3.2.2 Inshore water survey
Swath bathymetric, side scan sonar and shallow geological data shall be collected
simultaneously. A minimum overlap of 20% shall be maintained for the
multibeam data. Sufficient survey lines shall be undertaken to identify a usable
corridor of 500 metres wide centred on the preliminary route.
A high resolution sub-bottom profiler shall be used to determine the thickness and
nature of the sediments. In most areas, this information is required in the top 2
metres of seabed. However in some areas with specific burial requirements, the
information may be required down to the appropriate depth of sediments.
The requirements for seabed sampling and use of magnetometer are generally the
same as for the shallow water survey mentioned above except that samples will be
taken at a greater frequency to ensure adequate coverage in inshore areas.
3.2.3 Diver swim survey
A diver swim team equipped with cameras will be used to identify any potential
hazards and constraints for the cable at the shore approaches.
In water depths of less than 3 metres, a diver swim survey shall be carried out to
establish a corridor centred on the proposed cable route free of any obstructions. It
shall determine the nature of the seabed and identify and locate any obstructions.
The inshore diver swim shall be undertaken along the proposed post-survey cable
route.
3.2.4 Landing site surveys
The area around the landing point will be surveyed using land survey techniques
to position all relevant features. The beach manhole is likely to be located at the
cable landing termination kiosk, 100m inland from the HWM.
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 9
The beach shall be probed to a depth of 3 metres to determine sediment thickness
except at locations where special requirements exist.
The sampling required on the beach may require a number of trial pits spread
between the low and high water marks. The trial pits will be excavated using a
mechanical excavator, logged, photographed and backfilled.
The landing site surveys shall be carried out over a 100 metre wide corridor
centred on the proposed route.
3.2.5 Burial Assessment Survey (BAS)
The BAS shall be performed during or immediately following the Marine Survey
in the areas assessed during the marine survey.
The objective of the Burial Assessment Survey (BAS) is to assess the burial
feasibility of the route selected i.e. to determine its suitability for the simultaneous
laying and burial of the cable.
The BAS shall assess that part of the route that has been surveyed and determined
suitable for burial, either by plough or by another tool, of the submerged plant.
The BAS shall include the measurement, study and investigation of the following:
Burial conditions.
Cable armouring and protection.
Recommendation for installation procedures.
Updated Straight Line Diagrams and Route Position Lists.
Reporting and Charting.
The data obtained from the BAS shall allow for the cable route to be amended
within the surveyed corridor in order to allow improved protection of the System,
by increasing the length of the route that can be buried, and/or enhance the depth
of burial achievable including alternative methods of burial. The BAS shall also
provide additional information to assist in cable type selection. Finally, the BAS
may provide information to assist in the engineering, installation and subsequent
maintenance of the submerged plant.
The BAS shall be undertaken based on the CPT tests and coring undertaken as
outlined above.
The BAS shall be undertaken as close to the landings as is safe and practicable
and at least as close as the 10m contour.
In all circumstances, no towed or penetrative equipment shall be used within a
security distance of 500m from any known pipeline or in-service submarine cable.
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 10
3.3 Operational requirements
3.3.1 Schedule
The survey works shall be carried out between June and September inclusive.
The marine survey Contractor shall prepare a detailed marine survey schedule in
advance of the works. The schedule shall include appropriate weather
contingency.
3.3.2 Vessels
The marine survey shall be carried out from dedicated vessels able to operate in
deep and shallow water as required. Shallow draught vessels shall be required for
operating in the inshore waters at the approaches to the landfalls.
The vessels shall conform to the following minimum requirements as appropriate:
1. station-keeping and sea keeping capabilities for the specified Work at the
proposed time of year. The marine survey Contractor may provide
supplemental tug assistance where such assistance will benefit the
operation;
2. endurance (e.g. fuel, water, stores, etc.) to undertake the Work in
accordance with the Plan of Work;
3. staffing to allow all planned work to be carried out as a continuous
operation (on a 24 hour per day basis for the offshore activities and on a
12 hour per day basis for the inshore activities);
4. equipment and spares with necessary tools for all specified works;
The marine survey Contractor shall be responsible for all shipboard systems and
equipment calibration and re-calibration, including spares. For every 30 days of
operations the vessel will accrue one day of maintenance time.
Vessels used for surveys will be sound and capable of remaining safely at sea for
a minimum period of thirty (30) days under weather conditions normally to be
encountered in the Marine Survey area at the time of year that the operations are
to take place.
Vessels shall have breadth and draft of suitable proportions to provide adequate
stability for the duration of the intended operation. The vessels shall be capable of
passage speeds in excess of ten (10) knots and extended survey operations at
speeds less than two (2) knots.
Vessels shall be equipped with the following communication facilities as a
minimum:
Multi-channel VHF R/T capable of working all frequencies.
Vessel Shore R/T capable of operating with any shore station in the survey
area and with a range of two hundred (200) miles.
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 11
Inmarsat A or M system.
Fax and e-mail, both capable of communicating between the survey vessel
and land.
Voice communications between the navigation bridge, survey room and
back deck. The use of walkie-talkie radios operating on a private channel
is acceptable.
Vessels shall be equipped with the following navigational equipment exclusive of
special survey equipment:
Gyro and magnetic compass with gyro input into the navigation computer
unless a separate specific gyrocompass is fitted for survey purposes
Marine radar (stabilized/interfaced to a gyrocompass)
Echo sounder with hull mounted transducer (or equivalent)
Auto Pilot
Bridge control of engines and thrusters
Marine sextant.
Vessels shall carry, as a minimum, an up to date corrected set of nautical charts
covering the port of mobilization, passage to and from the survey site and any
other area of operations together with charts, to the largest scale appropriate, of
nearby ports of refuge. In addition, vessels shall carry up to date pilot books,
almanacs, light lists, radio signals, etc.
Vessels shall be classed by a recognized classification society and all certification
required by that society shall be up to date.
3.3.3 Survey navigation
Each vessel shall have fully adequate navigational and positioning capability and
have a global positioning system (GPS) capable of real-time vessel positioning
with an accuracy of better than +/- 10 meters at all times.
All navigation equipment and instrumentation will be calibrated and used
correctly. Calibration and/or verification shall be repeated in the event of any
equipment malfunction, which may nullify earlier calibrations and/or
verifications.
Qualified surveyors will be used to operate the navigation and positioning
equipment continuously throughout the survey while maintaining a continuous log
of all navigation activities throughout the survey.
Sufficient survey and positioning spares and consumables will be provided to
enable the survey to be completed without any degradation of navigation and
positioning quality and effectiveness and without the need to return to port to
acquire additional equipment.
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 12
A precision dual frequency digital echo sounder capable of operating in the water
depths throughout the survey area, given the expected seabed soil conditions shall
be used. Both transducers (frequencies) shall be enabled unless the water depths
are beyond the specified range of the higher frequency transducer. In such
circumstances the low frequency transducer only shall be used. A speed of sound
profiler capable of measuring the speed of sound throughout the water column and
to the maximum water depth in the survey area shall be provided. For the duration
of the survey the speed of sound in the echo sounder shall be set at 1,500m/sec.
An Ultra Short Base Line (USBL) positioning system shall be capable of tracking
multiple targets throughout the water column and on the seabed both directly
below the survey vessel and offset from the survey vessel.
3.3.4 Operating permits
The marine survey Contractor shall obtain and comply will all necessary marine
operational permits including routine and customary vessel/crew/equipment
clearances from Customs Agencies, Port Authorities, Marine Survey Office, etc.
In particular, the marine survey Contractor shall maintain close liaison with the
Port of Cork while within their functional area.
3.4 Survey Equipment
The survey equipment acoustic properties will be as follows:
Equipment Frequency
(Energy level in dB re 1uPa) Dual Frequency Single Beam Echosounder 33 and 210kHz (168-213)
Shallow water Multibeam Echo Sounder 455kHz (224)
Dual Frequency Side Scan Sonar 100 and 450kHz (235)
USBL 25kHz (202)
Sub-bottom Profiler 2-7.5kHz (205-220)
The survey vessel characteristics will be as follows:
Vessel
Length
(LOA)
Water Depths used Vessel Speed
6-10m 3-15m 3-6 knots dependent on equipment
used >40m 15m+
Details of the exact survey vessel and equipment characteristics shall be made
available prior to commencement of the surveys works. This data will include
contact details for the vessel Captain and full detail of the survey equipment
acoustic properties.
3.5 Mitigation measures
All survey works that involve the use of acoustic instrumentation will follow the
Code of Practice for Protection of Marine Mammals during Acoustic Seafloor
Ireland-France Subsea Cable Limited IFC-1 Marine survey scope of work for foreshore licence application, Loughbeg
landfall
242080-00_SOW001 | Issue 1 | 27 March 2017 | Arup
J:\242000\242080-00\4. INTERNAL\4-04 REPORTS\4-04-03 INFRASTRUCTURE\242080-00_SOW001_MARINE SURVEY SCOPE OF WORK_ISSUE1.DOCX
Page 13
Surveys in Irish Waters. Measures to be implemented include but are not limited
to:
A qualified and experienced marine mammal observer (MMO) shall be
appointed to monitor for marine mammals and to log all relevant events
using standardised data forms
Pre start monitoring: If marine mammal species are detected within 500m
distance of the sound source, seismic survey shall not commence.
Periods of peak sensitivity to survey operations for marine mammals will
be avoided where possible.
Ramp-up Procedures will be used - a controlled build-up of acoustic
energy output shall occur in consistent stages to provide a steady and
gradual increase over the ramp-up period.
An Underwater Archaeological Impact Assessment (UAIA) and associated
foreshore/intertidal and coastal assessment shall be carried out by suitably
qualified underwater archaeologist in advance of any site investigation, survey
works or trial pits. The results of the UAIA will be submitted to the Underwater
Archaeology Unit (UAU) of the National Monuments Service (NMS) for their
consideration prior to commencement of any works.
All geophysical survey shall be undertaken to the specifications and resolutions
that allow for the identification of underwater cultural heritage.