Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
.
kU. S. NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTI0tl AtlD ENFORCEMENT
REGI0ft IV
Report No. 50-445/78-23; 50-446/78-23
Docket No. 50-445; 50-446 Category A2
Licensee: Texas Utilities Generating Company2001 Bryan TowerDallas, Texas 75201
Facility Name: Comanche Peak, Units 1 & 2
Inspection at: Comanche Peak Site, Glen Rose, Texas
Inspection conducted: December 18-20, 1978
ed /[' -f* *-Inspectors:
A. B. Rosenberg, Reactor Inspector, Engineering Date'Support Section (Paragraphs 1, 2, 3 & 4)
31_cr k _. 1/2|[79.
A. B. Beach, Reactor Inspector, Engineering Support DateSection (Paragraph 3)
Reviewed- b /[f 9R. G. Taylor, Resident inspector, Projects Section Date
m- -- //f!79Approved: WW. A. Crossman, Chief, Projects Section Date
:- | r |-
,
.A { if-7/<
R. E. Hall, Chief, Engineering Support Section Date
7 9 0 2 2 8 01(o b
.
Inspection Summary:
Inspection on December 18-20,1978 (Report No. 50-445/78-23; 50-446/78-23)Areas inspected: Routine, unannounced inspection of construction activi-ties related to an overall review and inspection of the licensee's siteQA program implementation. Specific areas inspected included the QA/QCorganization, document control, design control, procurement control,equipment installation control and audits. The inspection involvedforty-five inspector-hours on site by two NRC inspectors.Results: No items of noncanpliance or deviations were identified.
-2-
DETAILS
1. Persons Contacted
Principal Licensea Personnel
*D. E. Deviney, TUSI, QA Technician*H. O. Kirkland, TUSI/B&R, Project General Manager*J. T. Merritt, TUSI, Resident Manager*R. G. Tolson, TUGCO, Site QA Supervisor
_0ther Personnel
R. Backer, Procurement Vendor Surveiliance, Brown & Root (B&R)J. Davis, QA Supervisor, B&RR. V. Fleck, Civil Inspection Supervisor, Gibbs & Hill (G&H)C. W. Killough, Site Surveillance Coordinator, B&RR. Murray, Field Support Design Group, B&RR. M. Osborne, Senior QC Supervisor, B&RR. C. Scott, Site QA Manager, B&RK. W. Silverthorne, QC Engineer-Mechanical, B&RR. Taylor, Document Control Supervisor, B&R
The IE inspectors also interviewed other licensee and contractorpersonnel d-ing the course of the inspection.
* denotes those present at the exit interview.
2. Site Tour
The IE inspectors toured the various areas of the site to observeconstruction activities in progress and to inspect housekeeping.
No items of noncompliance or deviations were identified.
3. Mid Term Construction Pennit QA Inspection
The mid term QA inspection is performed to determine whether theestablishment and implementation of the site quality assuranceprogram for past, current and upcoming site related activitiesin the areas of design, procurement, and construction are con-sistent with the status of the project and the Quality Assuranceprogram described in the Safety Analysis Report. The specificareas inspected included: QA/QC organization; QA manual-documentcontrol; procurement control; control of equipment installations;and audits. Mr. R. G. Taylor (NRC Resident Inspector) performeda portion of the mid term QA inspection concerning Qualty Assurancemanuals review. The manuals review of the inspection is documentedin inspection report No. 50-445/78-20; 50-446/78-20.
-3-
a. QA/QC Organization
Brown & Root is the designated constructor for Comanche PeakStear r!ectric Station (CPSES). The B&R QA and QC Managersrepo, ;rectly to the TUGC0 Site QA Supervisor. The TUGC0Siic Supervisor also has three non-B&R supervisors report-,
ing directly to him (Civil Inspection, Product Assurance andRecords Management).
The IE inspector determined that personnel were assigned re-sponsibility for: (1) continuing development of QA/QC procedures;(2) inspections; (3) audits and site surveillance; and (4)management of the site QA/QC program implementation.
b. QA Manual Document Control
The QA manual and QA manual procedures were reviewed with twoindividuals that were assigned unrelated QA/QC activities. Thecivil discipline manual and the civil quality procedures werereviewed with the Civil Inspection Supervisor. The ASME me-chanical discipline manual and the mechanical quality procedureswere reviewed with the QC Mechanical Engineer. Each individualdiscussed in general the QA/QC document control portions of theirrespective manuals and their responsiblities in relation to QA/QCactivities.s
Several procedures from the QA/QC manual documents were selectedand were made available by each of the individuals. The indi-vidual then verified that the documents were not superseded bya later revision. The Civil Inspection Supervisor verified thefollowing procedures were to the most current revision:
Ql-QP-ll.0-1 Cadweld Inspection Activities
CP-QP-ll.0 Civil Inspection Activities
The QC Mechanical Engineer verified the following procedures wereto the most current revision:
Ql-QAP-10.3-2 Welder Surveillance
CP-QAP-10.1 Field Inspection
_4-.
c. Design Control
Site-originated design activities are controlled by CPP-EP-1.This procedure was reviewed with the Field Support DesignSupervisor, as were the field documents used for site-origi-nated design changes. This review included a discussion asto how tne requirements of CPP-EP-1 were being implementedwithin the design activities being followed at the site.A general sampling of five design changes indicated timelyresolution and close out.
Licensee surveillance records of site-design activities werealso reviewed. Surveillance records, specif%11y auditsTGH-4 and TGH-8, indicated timely surveillars and auditsare being performed by the licensee as prescribed by ANSIN45.2.11.
d. Drawing Control
Drawing control procedures for both on-site and off-siteoriginated drawings were reviewed. The Document ControlSupervisor reviewed his responsibilities in relation to theBrown & Root and/or TUSI QA manual provisions for the DocumentControl Center. A sampling of approximately ten drawings werereviewed to verify that reproducibles were available and toverify that the drawings i are to the most current revision.The individual then reviewed the procedures used in the DocumentControl Center to ensure that a drawing revision was consistentwith the revision number indicated on the drawing b9ing used.
Facilities relating to storage and control of both working anddesign drawings were physically examined. Microfilm and cardfacilities were also toured.
e. Procurement Control
Site-originated procurement activities are controlled by theBrown & Root and/or TUSI QA manual. These procedures werereviewed with the Vendor Surveillance Supervisor. The VendorSurveillance Supervisor reviewed the QA manual provisions re-lative to his job function. Facilities used for the storageand control of all procurement documents were physically examined.A general description of how documents were reviewnd for qualityinput and checked to ascertain compliance with the specificationswas then explained by the Vendor Surveillance Supervisor.
-5-
'
.
Two separate procurement packages were investigated; one wasselected for structural support materials (AFC0 Steel, JobNumber 35-1195-18G27), and one was selected for weld rodmaterials (Chemtron, Job Number 35-1195-20726). The properstandards were specified and the proper material certificationswere provided. Each supplier had been prequalified, and allof the activities investigated were performed as required bythe applicable procedures.
From a review of audits TCP-1 and TCP-2, it was verified thatsurveillance and audits were being performed of site-procurementactivities.
f. Control of Equipment Installations
The IE inspector reviewed the installation documentation forfour components: pressurizer; diesel generators; positivedisplacement pumps (chemical and volume control system); andventilatioci exhaust filter racks. These components were invarious stages of installation from stored-in-place to prelim-inary alignment. Mechanical and electrical hook-ups were notcomplete. The rigging and mechanical installation travelerswere reviewed and found to reflect a logical sequence for theinstallations. Quality Control routinely verifies that theapproved traveler, which includes the specific installationprocedures is available at the installation. Where portionsof the installations were complete, the travelers were appro-priately signed off. In the case of the diesel generator,the travelers reflected the installation requirements of themanufacturer.
g. Audits
The IE inspector reviewed the licensee and constructors auditand site surveillance activities. The specific topics dis-cussed in the audits and site surveillance activities includeprocurement, document control, receiving inspection, concreteconstruction, piping and cable trays. Each of the eighteenquality assurance criteria of 10 CFR 50, Appendix B werereviewed on an annual basis or more frequently. The recordsreviewed for six audits indicated that findings were consist-ently corrected and followed up.
No items of noncompliance or deviations were identified.
-6-