Upload
aravind-govindaraju
View
235
Download
2
Embed Size (px)
Citation preview
7/31/2019 Idf(b) Ppp Case Group3
1/21
INFRASTRUCTURE DEVELOPMENT & FINANCING
Coimbatore bypassexperience : PPP projectGroup # 3
Members:
Ashim Sarkar
Aravind G
Maruthi Raj M
Nikunj Chhaochharia
Priyanshu Dubey
Rizurekh Saha
7/31/2019 Idf(b) Ppp Case Group3
2/21
Agenda
Background
Issues raised
Lessons learnt
PPP today
1
2
3
4
2
7/31/2019 Idf(b) Ppp Case Group3
3/21
BACKGROUND
Case: Coimbatore Bypass
3
7/31/2019 Idf(b) Ppp Case Group3
4/21
First road privatization scheme to beimplemented in South India, on BOT basis
GENERAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
4
Project name: Coimbatore bypass roadScope:1. A bridge (Athupalam bridge) over Noyyal river on NH 47
2. Road over bridge (ROB) on NH 209 to the Coimbatore bypass road
Type of PPP : BOT-tollContract authority : MoST, Tamil Nadu State GovernmentContract period : 30 years on Coimbatore bypass
20 years on Athupalam Bridge
Project Developer : Larsen & Turbo Transportation Infrastructure
Limited (LTTIL)
Athupalam bridge
7/31/2019 Idf(b) Ppp Case Group3
5/21
LTTIL was the only bidder
GENERAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
GENERAL INFORMATION
5
Type of bid : Domestic competitive bidNo. of bidders : 1Project Developer : Larsen & Turbo Transportation Infrastructure
Limited (LTTIL)
Total length : 27.67 KmsContract sign date : 13 Oct 1997Bid Amount : Rs. 90 Crore
7/31/2019 Idf(b) Ppp Case Group3
6/21
Investments Estimated Cost of Project: Rs 90 crore (Rs 87 crore for
Coimbatore bypass and Rs 3 crore for Athupalam
Bridge).
Actual Cost of Project: Rs 110 crore
Project Benefitsand Outcomes :
The bypass has eased the traffic congestion inCoimbatore city, Tamil Nadu and the Salem-Cochin
highway running between Tamil Nadu and Kerala.
Shippers, mostly from export oriented Units relying on the
Cochin Port for shipments, are other major beneficiaries
as transportation time is saved using the new road. usersincluded less pollution, pleasant drive, good wayside
amenities and lastly, safety. L&T gave special emphasis
to safety aspect of the road. Crash barriers were provided
on the high embankment of the road, along with thermo
plastic road markings
Rs 87 crore for Coimbatore bypass and Rs 3crore for Athupalam Bridge
GENERAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
BIDDING INFORMATION
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
GENERAL INFORMATION
6
7/31/2019 Idf(b) Ppp Case Group3
7/21
Risk due to non-payment of tolls lies with theState Government
GENERAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
FINANCIAL INFORMATION
GENERAL INFORMATION
7
Legal Instrument BOT - Toll
RISK DESCRIPTION
Construction To be borne by LTTIL
Operational To be borne by LTTIL
Commercial To be borne by LTTIL. Risk due to non-payment of tolls lies with
the State Government.
(The project ran into problems when users refused to pay toll. L&T
agreed to the subsidized toll rates on the condition that the StateGovernment should compensate the revenue losses sustained by
the company)
Financial To be borne by LTTIL
Political Government of Tamil Nadu
Regulatory Government of Tamil Nadu
Force Majeure Government of Tamil Nadu
7/31/2019 Idf(b) Ppp Case Group3
8/21
Around 62% of project cost funded byinstitutional financiers as debt
GENERAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
FINANCIAL INFORMATION
BIDDING INFORMATION
PROJECT BENEFITS &COSTS
LEGAL INSTRUMENTS
GENERAL INFORMATION
8
Cost of project : Rs. 110 Cr.Funded by LTTIL : Rs. 42 Cr.(Equity)
Funded by financiers : Rs. 68 Cr.(Debt)
Revenue projected : 60% from Athupalam bridge
40% from bypass roadEstimated cumulative loss : Rs. 12.6 Cr. (LTTIL Annual report 02)
About 230 buses made a minimum of 2180 trips a day
Bus owners association (BOA) refused to pay the toll
Cost of deployment of police was also borne by LTTIL & the outcome
was futile
It paid security charges of Rs. 53 Lacs. in 2001-02
Insitutional financiers were putting pressure on LTTIL for additional
securities
The interest payment worked out to be Rs.9 Crore per year
7/31/2019 Idf(b) Ppp Case Group3
9/21
Timeline of events
9
' 95 1995 1996 1997 1998 1999 2000 2002 ' 02
Athupalam bridge opened
12/12/1998
Work commenced12/1997
Contract signed
13/10/1997
MoST floated global tender09/1995
Tendering ProcessSep, 1995 Oct , 1997
Project WorkDec , 1997 Dec 12, 1998
Toll collection issueDec , 1998 July, 2002
2001
Financially not viable for the company
LTTIL contemplated requesting state government to take over the project by invoking the force
majeure class
SITUATION IN JULY, 2002
7/31/2019 Idf(b) Ppp Case Group3
10/21
ISSUES RAISED
Case: Coimbatore Bypass
10
7/31/2019 Idf(b) Ppp Case Group3
11/21
Issues raised (1/2)
11
Project Structuring
Lack of proper structuring of the project lead to a single bidder
Deficiencies both in scope and financial terms
Public Consultation
Public opinion on the perceived utility of the project was not considered
Willingness to pay was not assessed before levying toll on the bridge
Biased Revenue Analysis
Toll from the bridge was used to cross subsidize the bypass
Projected revenue in ratio of 40:60 from the bypass and bridge, while
investment was in the ration 87:13
Queuing Delays
Toll collection led to delays because of Queuing causing hindrance to public
7/31/2019 Idf(b) Ppp Case Group3
12/21
Issues raised (2/2)
12
Local Traffic
Volume of local traffic on the Athupalam bridge was high
These users were unwilling to pay the new toll
Multiple Trips
Toll was collected during every trip across the bridge
It particularly hampered people who made multiple trips per day
Toll on Existing bridge
Toll was collected even on the earlier two-lane bridge, which was now used
uni-directionally
Public was opposed to paying toll for the bridge which had already existed
Enforcement
Local players such as Taxi, Bus and Commercial fleet operators did not pay
toll and had formed associations to protest against the toll
In general there was low compliance with the existing tolling structure
7/31/2019 Idf(b) Ppp Case Group3
13/21
LESSONS LEARNT
Case: Coimbatore Bypass
13
7/31/2019 Idf(b) Ppp Case Group3
14/21
Lessons learnt
14
Lack of unanimity between the government and the developer for resolvingunexpected problems
It discourages private players from investing in road development project
Fundamental Deterrents
Risks involved in estimating traffic demand and willingness to pay must beaddressed for BOT Toll based projects to succeed
Demand sensitivity
Projects based on Tolls are dependent on the willingness to pay of the
consumers
WTP is very less in case of Urban roads, and hence identifying user segmentsand developing proper tolling structure is paramount
Project Structuring
Instances of inappropriate bundling to make projects attractive must be
avoided
1
2
3
7/31/2019 Idf(b) Ppp Case Group3
15/21
PPP TODAY
Case: Coimbatore Bypass
15
7/31/2019 Idf(b) Ppp Case Group3
16/21
Public Private Partnership (PPP)
PPPs refer to a collaboration between the public and the private sector for delivering a service orinfrastructure.
These include a wide variety of arrangements ranging from Management contracts on one
extreme to full privatization or divestiture on the other extreme of the spectrum
These projects can be classified based on the extent to which risks and responsibilities are
transferred from the public to the private sector
In case of PPP models like BOT (Build Operate Transfer), Critical risks like Market risks are borne
by the private sector
7/31/2019 Idf(b) Ppp Case Group3
17/21
Build Operate Transfer (BOT) models
BOT based on Tolls: Private partner bears the commercial and
technical risks related to construction, operation,and maintenance of the project.
Critical risks like Traffic revenue risk is alsoallocated to the Private developer
Projects are awarded by a two-stage biddingprocess
First stage (Qualification stage)
Second stage (Bidding stage): Bids are evaluatedon basis of Lowest financial grant requirementand Revenue sharing
7/31/2019 Idf(b) Ppp Case Group3
18/21
Build Operate Transfer (BOT) models
BOT based on Annuities: Traffic risk-neutral PPP model
Private developer bears risks relating to construction,technical, operation, and maintenance of the project
Critical risks such as land acquisition, permit/approval,
traffic risk, and toll collection risk are borne by the Publicsector
Two stage Bidding process
First stage (Qualification) Technical and Financialstrength evaluation
Second stage (Financial Bid) - Quoting the annuitypayment required based on the costs of the project
Lowest annuity quote is awarded the project.
The granting authority pays the annuities to the developeraccording to the agreed payment schedule, after adjustingfor project delays and other factors
7/31/2019 Idf(b) Ppp Case Group3
19/21
Challenges in PPP models
Bidding process
Land Acquisition Methodology
Technical Capability of Private developer
Methodology for dealing with changes in Project scope
Other Issues
Maintenance of Existing Roads
Road Safety Measures
7/31/2019 Idf(b) Ppp Case Group3
20/21
References
20
"Coimbatore Bypass Road". New Delhi: Department of
Economic Affairs, Ministry of Finance, Government of India.
"Project Financing: A Case study on Coimbatore Bypass
Road Project" (PDF). Larsen and Toubro. p. 1
"Coimbatore By-pass (Tamil Nadu)". L&T IDPL.
http://www.pppindiadatabase.com
"Financing Road Projects in India Using PPP Scheme" by
Satyanaryana N. Kalidindi and L. Boeing Singh (IIT M)
http://www.pppindiadatabase.com/http://www.pppindiadatabase.com/http://www.pppindiadatabase.com/7/31/2019 Idf(b) Ppp Case Group3
21/21
Thank You!