Idf(b) Ppp Case Group3

Embed Size (px)

Citation preview

  • 7/31/2019 Idf(b) Ppp Case Group3

    1/21

    INFRASTRUCTURE DEVELOPMENT & FINANCING

    Coimbatore bypassexperience : PPP projectGroup # 3

    Members:

    Ashim Sarkar

    Aravind G

    Maruthi Raj M

    Nikunj Chhaochharia

    Priyanshu Dubey

    Rizurekh Saha

  • 7/31/2019 Idf(b) Ppp Case Group3

    2/21

    Agenda

    Background

    Issues raised

    Lessons learnt

    PPP today

    1

    2

    3

    4

    2

  • 7/31/2019 Idf(b) Ppp Case Group3

    3/21

    BACKGROUND

    Case: Coimbatore Bypass

    3

  • 7/31/2019 Idf(b) Ppp Case Group3

    4/21

    First road privatization scheme to beimplemented in South India, on BOT basis

    GENERAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    4

    Project name: Coimbatore bypass roadScope:1. A bridge (Athupalam bridge) over Noyyal river on NH 47

    2. Road over bridge (ROB) on NH 209 to the Coimbatore bypass road

    Type of PPP : BOT-tollContract authority : MoST, Tamil Nadu State GovernmentContract period : 30 years on Coimbatore bypass

    20 years on Athupalam Bridge

    Project Developer : Larsen & Turbo Transportation Infrastructure

    Limited (LTTIL)

    Athupalam bridge

  • 7/31/2019 Idf(b) Ppp Case Group3

    5/21

    LTTIL was the only bidder

    GENERAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    GENERAL INFORMATION

    5

    Type of bid : Domestic competitive bidNo. of bidders : 1Project Developer : Larsen & Turbo Transportation Infrastructure

    Limited (LTTIL)

    Total length : 27.67 KmsContract sign date : 13 Oct 1997Bid Amount : Rs. 90 Crore

  • 7/31/2019 Idf(b) Ppp Case Group3

    6/21

    Investments Estimated Cost of Project: Rs 90 crore (Rs 87 crore for

    Coimbatore bypass and Rs 3 crore for Athupalam

    Bridge).

    Actual Cost of Project: Rs 110 crore

    Project Benefitsand Outcomes :

    The bypass has eased the traffic congestion inCoimbatore city, Tamil Nadu and the Salem-Cochin

    highway running between Tamil Nadu and Kerala.

    Shippers, mostly from export oriented Units relying on the

    Cochin Port for shipments, are other major beneficiaries

    as transportation time is saved using the new road. usersincluded less pollution, pleasant drive, good wayside

    amenities and lastly, safety. L&T gave special emphasis

    to safety aspect of the road. Crash barriers were provided

    on the high embankment of the road, along with thermo

    plastic road markings

    Rs 87 crore for Coimbatore bypass and Rs 3crore for Athupalam Bridge

    GENERAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    BIDDING INFORMATION

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    GENERAL INFORMATION

    6

  • 7/31/2019 Idf(b) Ppp Case Group3

    7/21

    Risk due to non-payment of tolls lies with theState Government

    GENERAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    FINANCIAL INFORMATION

    GENERAL INFORMATION

    7

    Legal Instrument BOT - Toll

    RISK DESCRIPTION

    Construction To be borne by LTTIL

    Operational To be borne by LTTIL

    Commercial To be borne by LTTIL. Risk due to non-payment of tolls lies with

    the State Government.

    (The project ran into problems when users refused to pay toll. L&T

    agreed to the subsidized toll rates on the condition that the StateGovernment should compensate the revenue losses sustained by

    the company)

    Financial To be borne by LTTIL

    Political Government of Tamil Nadu

    Regulatory Government of Tamil Nadu

    Force Majeure Government of Tamil Nadu

  • 7/31/2019 Idf(b) Ppp Case Group3

    8/21

    Around 62% of project cost funded byinstitutional financiers as debt

    GENERAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    FINANCIAL INFORMATION

    BIDDING INFORMATION

    PROJECT BENEFITS &COSTS

    LEGAL INSTRUMENTS

    GENERAL INFORMATION

    8

    Cost of project : Rs. 110 Cr.Funded by LTTIL : Rs. 42 Cr.(Equity)

    Funded by financiers : Rs. 68 Cr.(Debt)

    Revenue projected : 60% from Athupalam bridge

    40% from bypass roadEstimated cumulative loss : Rs. 12.6 Cr. (LTTIL Annual report 02)

    About 230 buses made a minimum of 2180 trips a day

    Bus owners association (BOA) refused to pay the toll

    Cost of deployment of police was also borne by LTTIL & the outcome

    was futile

    It paid security charges of Rs. 53 Lacs. in 2001-02

    Insitutional financiers were putting pressure on LTTIL for additional

    securities

    The interest payment worked out to be Rs.9 Crore per year

  • 7/31/2019 Idf(b) Ppp Case Group3

    9/21

    Timeline of events

    9

    ' 95 1995 1996 1997 1998 1999 2000 2002 ' 02

    Athupalam bridge opened

    12/12/1998

    Work commenced12/1997

    Contract signed

    13/10/1997

    MoST floated global tender09/1995

    Tendering ProcessSep, 1995 Oct , 1997

    Project WorkDec , 1997 Dec 12, 1998

    Toll collection issueDec , 1998 July, 2002

    2001

    Financially not viable for the company

    LTTIL contemplated requesting state government to take over the project by invoking the force

    majeure class

    SITUATION IN JULY, 2002

  • 7/31/2019 Idf(b) Ppp Case Group3

    10/21

    ISSUES RAISED

    Case: Coimbatore Bypass

    10

  • 7/31/2019 Idf(b) Ppp Case Group3

    11/21

    Issues raised (1/2)

    11

    Project Structuring

    Lack of proper structuring of the project lead to a single bidder

    Deficiencies both in scope and financial terms

    Public Consultation

    Public opinion on the perceived utility of the project was not considered

    Willingness to pay was not assessed before levying toll on the bridge

    Biased Revenue Analysis

    Toll from the bridge was used to cross subsidize the bypass

    Projected revenue in ratio of 40:60 from the bypass and bridge, while

    investment was in the ration 87:13

    Queuing Delays

    Toll collection led to delays because of Queuing causing hindrance to public

  • 7/31/2019 Idf(b) Ppp Case Group3

    12/21

    Issues raised (2/2)

    12

    Local Traffic

    Volume of local traffic on the Athupalam bridge was high

    These users were unwilling to pay the new toll

    Multiple Trips

    Toll was collected during every trip across the bridge

    It particularly hampered people who made multiple trips per day

    Toll on Existing bridge

    Toll was collected even on the earlier two-lane bridge, which was now used

    uni-directionally

    Public was opposed to paying toll for the bridge which had already existed

    Enforcement

    Local players such as Taxi, Bus and Commercial fleet operators did not pay

    toll and had formed associations to protest against the toll

    In general there was low compliance with the existing tolling structure

  • 7/31/2019 Idf(b) Ppp Case Group3

    13/21

    LESSONS LEARNT

    Case: Coimbatore Bypass

    13

  • 7/31/2019 Idf(b) Ppp Case Group3

    14/21

    Lessons learnt

    14

    Lack of unanimity between the government and the developer for resolvingunexpected problems

    It discourages private players from investing in road development project

    Fundamental Deterrents

    Risks involved in estimating traffic demand and willingness to pay must beaddressed for BOT Toll based projects to succeed

    Demand sensitivity

    Projects based on Tolls are dependent on the willingness to pay of the

    consumers

    WTP is very less in case of Urban roads, and hence identifying user segmentsand developing proper tolling structure is paramount

    Project Structuring

    Instances of inappropriate bundling to make projects attractive must be

    avoided

    1

    2

    3

  • 7/31/2019 Idf(b) Ppp Case Group3

    15/21

    PPP TODAY

    Case: Coimbatore Bypass

    15

  • 7/31/2019 Idf(b) Ppp Case Group3

    16/21

    Public Private Partnership (PPP)

    PPPs refer to a collaboration between the public and the private sector for delivering a service orinfrastructure.

    These include a wide variety of arrangements ranging from Management contracts on one

    extreme to full privatization or divestiture on the other extreme of the spectrum

    These projects can be classified based on the extent to which risks and responsibilities are

    transferred from the public to the private sector

    In case of PPP models like BOT (Build Operate Transfer), Critical risks like Market risks are borne

    by the private sector

  • 7/31/2019 Idf(b) Ppp Case Group3

    17/21

    Build Operate Transfer (BOT) models

    BOT based on Tolls: Private partner bears the commercial and

    technical risks related to construction, operation,and maintenance of the project.

    Critical risks like Traffic revenue risk is alsoallocated to the Private developer

    Projects are awarded by a two-stage biddingprocess

    First stage (Qualification stage)

    Second stage (Bidding stage): Bids are evaluatedon basis of Lowest financial grant requirementand Revenue sharing

  • 7/31/2019 Idf(b) Ppp Case Group3

    18/21

    Build Operate Transfer (BOT) models

    BOT based on Annuities: Traffic risk-neutral PPP model

    Private developer bears risks relating to construction,technical, operation, and maintenance of the project

    Critical risks such as land acquisition, permit/approval,

    traffic risk, and toll collection risk are borne by the Publicsector

    Two stage Bidding process

    First stage (Qualification) Technical and Financialstrength evaluation

    Second stage (Financial Bid) - Quoting the annuitypayment required based on the costs of the project

    Lowest annuity quote is awarded the project.

    The granting authority pays the annuities to the developeraccording to the agreed payment schedule, after adjustingfor project delays and other factors

  • 7/31/2019 Idf(b) Ppp Case Group3

    19/21

    Challenges in PPP models

    Bidding process

    Land Acquisition Methodology

    Technical Capability of Private developer

    Methodology for dealing with changes in Project scope

    Other Issues

    Maintenance of Existing Roads

    Road Safety Measures

  • 7/31/2019 Idf(b) Ppp Case Group3

    20/21

    References

    20

    "Coimbatore Bypass Road". New Delhi: Department of

    Economic Affairs, Ministry of Finance, Government of India.

    "Project Financing: A Case study on Coimbatore Bypass

    Road Project" (PDF). Larsen and Toubro. p. 1

    "Coimbatore By-pass (Tamil Nadu)". L&T IDPL.

    http://www.pppindiadatabase.com

    "Financing Road Projects in India Using PPP Scheme" by

    Satyanaryana N. Kalidindi and L. Boeing Singh (IIT M)

    http://www.pppindiadatabase.com/http://www.pppindiadatabase.com/http://www.pppindiadatabase.com/
  • 7/31/2019 Idf(b) Ppp Case Group3

    21/21

    Thank You!