ID Task
Mode
Task Name Duration Start Finish
0 Senior Design - Ventilator Sensor Project
166 days? Fri 9/25/20 Thu 5/6/21
1 Beginning to IR 5 days Fri 9/25/20 Wed 9/30/20
2 Team Meeting with CM 1 day Fri 9/25/20 Fri 9/25/20
3 Identify Goals and Objectives 1 day Fri 9/25/20 Fri 9/25/20
4 Review previous work on prototype by Third Pole
1 day Fri 9/25/20 Fri 9/25/20
5 Develop Initial Report (IR) 5 days Fri 9/25/20 Wed 9/30/20
6 Create flowchart of design plan 2 days Fri 9/25/20 Sat 9/26/20
7 Identify Problems and Sub- Problems
3 days Mon 9/28/20
Wed 9/30/20
8 IR to FDP 15 days Thu 10/1/20 Tue 10/20/20
9 Determine subtask options 1 day Thu 10/1/20 Thu 10/1/20
10 Block diagram system design 1 day Fri 10/2/20 Fri 10/2/20
11 Assign team roles 1 day Mon 10/5/20Mon 10/5/20
12 Create metrics for performance - end goal
1 day Tue 10/6/20 Tue 10/6/20
13 Determine deliverables 1 day Wed 10/7/20Wed 10/7/20
14 List anticipated problems 1 day Thu 10/8/20 Thu 10/8/20
15 List contingency plan 1 day Fri 10/9/20 Fri 10/9/20
16 Create detailed budget 1 day Sat 10/10/20 Sat 10/10/20
17 Create slideshow 8 days Fri 10/2/20 Mon 10/12/20
18 Give Presentation 0 days Thu 10/15/20Thu 10/15/20
19 Submit written report 0 days Tue 10/20/20Tue 10/20/20
10/15
10/20
13 18 23 28 3 8 13
September 2020 October 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Senior Design - Ventila
Date: Fri 3/12/21
10/15
10/20
13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31
October 2020 November 2020 December 2020 January 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: Senior Design - Ventila
Date: Fri 3/12/21
10/15
10/20
31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21
January 2021 February 2021 March 2021 April 2021 May 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: Senior Design - Ventila
Date: Fri 3/12/21
ID Task
Mode
Task Name Duration Start Finish
20 FDP to PRP 36 days Fri 10/16/20 Thu 12/3/20
21 Develop GUI 26 days Fri 10/16/20 Fri 11/20/20
22 Determine GUI requirements 3 days Fri 10/16/20 Tue 10/20/20
23 Determine GUI layout/menu 3 days Wed 10/21/20Fri 10/23/20
24 Code data acquisition and smoothing
20 days Mon 10/26/20
Fri 11/20/20
25 Develop on-device features 26 days Fri 10/16/20 Fri 11/20/20
26 Determine all basic features to be performed on GUI
3 days Fri 10/16/20 Tue 10/20/20
27 Code .csv data storage system 11 days Wed 10/21/20Wed 11/4/20
28 Code data export system 12 days Thu 11/5/20 Fri 11/20/20
29 Temperature and Humidity sensors 26 days Fri 10/16/20 Fri 11/20/20
30 Determine sensor part 3 days Fri 10/16/20 Tue 10/20/20
31 Code sensor monitoring and alarm 10 days Mon 11/9/20
Fri 11/20/20
32 Orientation management system 26 days Fri 10/16/20 Fri 11/20/20
33 Evaluate motor space requirements and orientation tolerances
3 days Fri 10/16/20 Tue 10/20/20
34 Determine sensor for orientation monitoring
3 days Wed 10/21/20
Fri 10/23/20
35 Code and build motor response system
20 days Mon 10/26/20
Fri 11/20/20
36 Develop power management system 26 days Fri 10/16/20 Fri 11/20/20
37 Determine power considerations 3 days Fri 10/16/20 Tue 10/20/20
38 Evaluate past power system and pitfalls3 days Wed 10/21/20Fri 10/23/20
13 18 23 28 3 8 13
September 2020 October 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Senior Design - Ventila
Date: Fri 3/12/21
13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31
October 2020 November 2020 December 2020 January 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: Senior Design - Ventila
Date: Fri 3/12/21
31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21
January 2021 February 2021 March 2021 April 2021 May 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: Senior Design - Ventila
Date: Fri 3/12/21
ID Task
Mode
Task Name Duration Start Finish
39 Design intial power supply plan 20 days Mon 10/26/20Fri 11/20/20
40 Presentation Preparation 7 days Sat 11/21/20 Mon 11/30/20
41 Presentation 1 day Thu 12/3/20 Thu 12/3/20
42 PRP to DVP 88 days? Wed 12/2/20Tue 3/30/21
43 Develop minor systems 88 days? Wed 12/2/20Tue 3/30/21
44 Calibration systems 69 days? Wed 12/2/20Fri 3/5/21
45 Code calibration GUI screens 10 days Wed 12/2/20Tue 12/15/20
46 Code calibration execution 30 days Wed 12/16/20Tue 1/26/21
47 Test calibration systems with gasses at CM Lab
28 days Wed 1/27/21
Thu 3/4/21
48 External monitor setup 69 days? Wed 12/2/20Fri 3/5/21
49 Code alternative large screen GUI for extermal monitor/keyboard/mouse
34 days Wed 12/2/20
Mon 1/18/21
50 Create graphic tools for visualization of data
34 days Tue 1/19/21 Thu 3/4/21
51 Safe power button system 69 days Wed 12/2/20Fri 3/5/21
52 Select switch to serve as user master power
30 days Wed 12/2/20
Tue 1/12/21
53 Code functions of power-on and power-off to enable and disable system
38 days Wed 1/13/21
Thu 3/4/21
54 Make GUI user friendly 21 days? Sat 2/6/21 Fri 3/5/21
55 Resize and regrid all screens to maximize ease of use
14 days Sat 2/6/21 Wed 2/24/21
13 18 23 28 3 8 13
September 2020 October 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Senior Design - Ventila
Date: Fri 3/12/21
13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31
October 2020 November 2020 December 2020 January 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: Senior Design - Ventila
Date: Fri 3/12/21
31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21
January 2021 February 2021 March 2021 April 2021 May 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: Senior Design - Ventila
Date: Fri 3/12/21
ID Task
Mode
Task Name Duration Start Finish
56 Perform testing with CM staff forfeedback
8 days Wed 2/24/21
Fri 3/5/21
57 Presentation Preparation 7 days Sat 3/6/21 Sun 3/14/21
58 Presentation 0 days Tue 3/30/21 Tue 3/30/21
59 DVP to FPP 27 days? Wed 3/31/21Thu 5/6/21
60 Finalize housing 5 days? Wed 3/31/21Tue 4/6/21
61 Transfer components from printed housing to final housing
5 days? Wed 3/31/21
Tue 4/6/21
62 Create documentation 27 days? Wed 3/31/21Thu 5/6/21
63 Validation Protocols 5 days? Wed 3/31/21Tue 4/6/21
64 New Build Instructions 5 days? Wed 4/7/21 Tue 4/13/21
65 User Manual 10 days? Wed 4/14/21Tue 4/27/21
66 Test and Validate 10 days? Wed 4/7/21 Tue 4/20/21
67 Completed set of protocol worksheets on device
10 days? Wed 4/7/21 Tue 4/20/21
68 Boot up systems 21 days Wed 4/7/21 Wed 5/5/21
69 Setup to run python program directly from startup
4 days Wed 4/7/21 Mon 4/12/21
70 Run full screen with shutdown from interface
2 days Wed 4/14/21
Thu 4/15/21
71 Learn battery power communication system and code charge monitoring into GUI
14 days Fri 4/16/21 Wed 5/5/21
72 Prepare final presentation slides 12 days Wed 4/21/21Thu 5/6/21
73 Presentation 0 days Thu 5/6/21 Thu 5/6/21
13 18 23 28 3 8 13
September 2020 October 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Senior Design - Ventila
Date: Fri 3/12/21
3/30
5/6
13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31
October 2020 November 2020 December 2020 January 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: Senior Design - Ventila
Date: Fri 3/12/21
3/30
5/6
31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21
January 2021 February 2021 March 2021 April 2021 May 2021
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: Senior Design - Ventila
Date: Fri 3/12/21