15
ICE ICE INTERNATIONAL COMMISSIONING ENGINEERS

ICE INTERNATIONAL COMMISSIONING ENGINEERS

Embed Size (px)

DESCRIPTION

ICE INTERNATIONAL COMMISSIONING ENGINEERS. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. Cx Sequence of Events. - PowerPoint PPT Presentation

Citation preview

Page 1: ICE INTERNATIONAL COMMISSIONING ENGINEERS

ICEICEINTERNATIONAL COMMISSIONING ENGINEERS

Page 2: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities

Cx RFP

Response to RFP Owner issues Cx contract

Initialization Letter to Architect

Page 3: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Issue "SD" documents

Review "SD" & issue comments

Response to Cx comments

Page 4: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Issue “DD" documents including Cx comments

Review “DD" & issue comments

Response to Cx comments

Issue Preliminary Cx Plan

Page 5: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Issue “CD" documents including Cx comments

Review “CD" & issue comments

Response to Cx comments

Issue construction documents

Page 6: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Schedule Cx Kick-Off Meeting

Cx Kick-Off Meeting

Issue Meeting Minutes

Page 7: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 30% MEP progress (2 weeks)

Perform 30% field inspection

Issue Action Items Response to Cx comments

Page 8: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Preliminary O&M Manual w/ submittals

Issue Final Cx plan Response to Cx Plan

Page 9: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 60% MEP progress (2 weeks)

Perform 60% field inspection

Issue Action Items Response to Cx comments

Page 10: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities

Equipment Start-up

Issue Equipment Start-up Verification

Page 11: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 90% MEP progress (2 weeks)

Perform 90% field inspection

Issue Action Items Response to Cx comments

Page 12: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities

TAB Field Work

Controls Field Work

Issue TAB Deficiency List

Page 13: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Notify Cx of 100% MEP completion (2 weeks)

Begin FPT Support FPT effort

Issue Preliminary FPT Report

Response to FPT Report

Page 14: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Finish FPT Support FPT effort

Issue FPT AIS Report Response to Cx AIS

Deficiencies remedied appropriately

Notify Cx of remedies

Page 15: ICE INTERNATIONAL COMMISSIONING ENGINEERS

Cx Sequence of Events

ICE Activities OAC Activities Verify deficiency remediation

Issue Final Report Schedule 12 Month Warranty Inspection

Participate in 12 Month Warranty Inspection