ICDS Systems Strengthening and Nutrition Improvement Project. Project Launch Workshop: New Delhi, May 9-10, 2013 CHHATTISGARH. Key Project Data: Chhattisgarh. * No. of projects/AWCs as on Sept-2010, used for project cost estimation. Rs. Lakh. Check-list for Preparatory Actions. - PowerPoint PPT Presentation

Citation preview

Page 1: ICDS Systems Strengthening and Nutrition Improvement Project

Project Launch Workshop: New Delhi, May 9-10, 2013

CHHATTISGARH

ICDS Systems Strengthening and Nutrition Improvement

Project

Page 2: ICDS Systems Strengthening and Nutrition Improvement Project

No. of districts covered

As on Sep

2012

Revised Status

Total

No. of projects (blocks)*

92 134 220

No: of AWCs*/Mini 28682 28682 50311

Total cost of the project (Phase 1 & 2)

Total cost of Phase 1(3 year) of project 4502.67

State’s share for Phase 1 45.03

Cost of Component 1: Institutional and Systems Strengthening

2482.66

Cost of Component 2: Community mobilization and behavior change communication

1455.03

Cost of Component 3: Piloting Convergent Nutrition Actions

53.15

Cost of Component 4: Project Management, Technical Assistance and Monitoring & Evaluation

511.82

* No. of projects/AWCs as on Sept-2010, used for project cost estimation

Rs. Lakh

Page 3: ICDS Systems Strengthening and Nutrition Improvement Project

Actions Status(Put a ‘√’ or ‘X’)

Expected Date

1. Has an approval of project been received from the competent authority in the State. If not, by when expected?

[ √ ]

2. Has government order been issued notifying identified 12 districts of their participation in ISSNIP? If not, by when expected?

[ × ]Awareness workshop has been planned in Phase-1 Year-01 with HBDs and subsequently at block level.

3. Has an administrative/financial sanction been received for 10% State contribution to the project? If not, by when expected?

[ √ ]Vide F No 109/F

1005664/B-1/4 dt 23rd March 2013

4. Has a specific budget head for project (EAP) been created? If not, by when expected?

[ √ ]Budget Head no. 5354 and 7543

5. Is the total cost of the project including 10% State contribution approved by the State Govt.? If not, by when expected?

[ √ ]

6. Has any provision been made in the BE 2013-14 for the project? If yes, what amount? If not, by when expected?

[ √ ] Rs. 940.00 lakhsRe-appropriation required to match 90:10 sharing pattern. Concurrence of activity wise budget is required.

Page 4: ICDS Systems Strengthening and Nutrition Improvement Project

Actions Status(Put a ‘√’

or ‘X’)

Expected Date

7. Have an administrative order been issued for establishment of the SPMU for ISSNIP? If not, by when expected?

[ × ] By June 2013

8. Has a Project Director been nominated for ISSNIP? If yes, Name? [ √ ]

Mr Dilip Wasnikar Director, WCD is proposed as Director ISSNIP

9. Have the Joint Project Coordinators (JPCs) been identified and assigned for each of the following areas under ISSNIP?

- Project Management and Monitoring & Evaluation

- Administration and Finance- Procurement- IEC/BCC & Training

Please share names. If not, by when expected?

[ √ ]1. Mr Nand Lal Choudhary

2. Mr Sajid Meman

10. Has an Office space been identified and provided for ISSNIP SPMU? If not, by when expected?

[ √ ]Office of ICDS-(R) and ISSNIP will be roofed

together in same building

11. Have the SPMU office needs (equipments/furniture etc) been assessed? Please share. If not, by when expected?

[ × ] Will be assessed and mentioned separately in

PIP

Page 5: ICDS Systems Strengthening and Nutrition Improvement Project

Actions Status(Put a ‘√’

or ‘X’)

Expected Date

12. Are there any comments on the financial management and procurement manuals for the Project from the State?Please share.

[ √ ]Financial

threshold should clearly point out

item-wise sanctioning authority

13. Has a procurement plan been prepared for first 18 months of project?If not, by when expected.

[ × ] To be submitted with PIP

14. Has the procurement plan been approved by the State Govt.? If not, by when expected?

[ × ] To be submitted with PIP

15. Have the activities under the four project components been reviewed and identified for implementation during 2013-14?

[ √ ]Preparatory

activities will be focused from

July to Oct 2013, during P-1/Y-1

Page 6: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

Model TOR for recruitment– state specific requirement to be later incorporated.

Page 7: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

Recruitment Agency selection – TOR- Guidelines, Budget limits etc.

Page 8: ICDS Systems Strengthening and Nutrition Improvement Project

Flexibility – Activity and Fund Shift permission in the project duration, phase-wise.

Issues / Challenges / Solutions for full roll-out of ISSNIP

Page 9: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

National Guidelines – TNA/Urban Pilot/Social Audit /PPP model/BBC Strategy / Convergence Strategy/ others.

Page 10: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

P-1/Y-2 clearance upto December 2013 – for accurate fund earmarking in state budget.

Page 11: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

11 districts now carved to 17 district – number of AWC/Mini are same – 28682- revision requested - vide letter no. 8662 dated 29.01.2013

Page 12: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

Timeline of Concurrences - obtaining timely approval from GOI to ensure timely action from State.

Page 13: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

Clear Financial, administrative and other powers of Project Director ISSNIP

Page 14: ICDS Systems Strengthening and Nutrition Improvement Project

Issues / Challenges / Solutions for full roll-out of ISSNIP

Financial threshold of WB-PP should clearly point out item-wise sanctioning authority

Page 15: ICDS Systems Strengthening and Nutrition Improvement Project

Thank you

Page 16: ICDS Systems Strengthening and Nutrition Improvement Project

District Bifurcation

Original District Year 2007 Year 2012

Mahasamund

Korba

Durg BalodBemetara

Kawrdha

Jashpur

Kanker

Dantewada Bijapur Sukma

Bastar Narayanpur Kondagaon

Raipur Baloda bazarGariaband