1
IBL CO2 cooling lines installation
Review
Didier LaporteCNRS – LPNHE Paris
11 mars 2014
2
1
324
8
6
5
7
132
4
8
6 5
7
• This scenario is about the side A
3
Bottom of the splitter box
Guiding support
Support plate
Place and fasten the splitting box on the welding stand
4
PP1 welding area
Intlet-outlet junctionFemale fitting
Position block
5
Place the isolator/fitting assembly and Tighten by hand the fitting nut on to the corresponding fake female fitting
6
Place the first f18mm flexible line and fasten it on the splitting box
7
Put the A1 liquid line in place
8Weld the lower connection
A1 liquid line
9Weld the upper connection
A1 liquid line
10Same operations for the A1 vapor line
11Transfer to the installation tool
A1 line completed
12Fix the A1 line on the tool
Cover
13
Same operations for the 4 double linesA1 to A4
14Hold the fitting cone
15Close the splitter box
16
Close the tooling with the cover and lock it
The tooling is ready for the installation
17
In the pit
18Installation tooling
19
• LPSC table
Ready to receive 8 lines tool
20
Unwind the lines on to the floor
218 lines set installation on the main frame
22Remove the back cover and the fitting protection
23
Shift the assembly until the splitting box back face touch the plate
24
Unlock line 2x2 and tighten the fitting nuts by hand
25Remove the assembly set
26
And after
• Same operations for 6 lines side A
• Same operations for 8 lines side C
• Same operations for 6 lines side C
27
Planning
• Welding stand,• Installation tooling, • Z table,• Main frame
Delivery 18/03/2014