    AED 1313 INTRODUCTION TO BUILT ENVIRONMENT

    Semester 1, Session 2013/2014

    DEPARTMENT OF ARCHITECTURE AND ENVIRONMENTAL DESIGN (AED), CENTRE FOR

    FOUNDATION STUDIES (CFS), INTERNATIONAL ISLAMIC UNIVERSITY MALAYSIA (IIUM)

    QUANTITY SURVEYING

    Compiled by

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    2/44

    2

    CONTENTS: INTRODUCTION TO SURVEYING WHO IS QUANTITY SURVEYOR?

    WHAT QUANTITY SURVEYOR DO? BASIC SERVICE SUPPLEMENTARY SERVICE

    HOW TO BE A QUANTITY SURVEYOR? BQSM ISM

    WHERE QUANTITY SURVEYOR WORKS? OTHER SURVEYING PROFESSION

    LAND SURVEYING BUILDING SURVEYING PROPERTY MANAGEMENT,VALUATIONESTATE AGENCY SURVEYING

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    3/44

    Surveyingwas traditionally a science ofdetermining the relative positions ofpoints above, on or beneath the surfaceof the earth (both land and sea) throughcollection and analysis of data.

    During the Industrial Revolution in the1800s, more people began to questionthe exact property boundaries and with

    the increasing demand for publicinfrastructures like railroads, roads andbridges, surveying became in demand.

    INTRODUCTION TO SURVEYING

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    4/44

    A surveyor uses the science of measurement

    to collect and analyse land and geographic

    data.

    Surveyors analysis, important to building,construction and real estate industries, and

    used for planning and implementing solutions

    for projects like building construction and land

    development.

    Surveyor co-ordinates analysis with the help

    of engineers, architects, valuers and clients.

    INTRODUCTION TO SURVEYING

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    5/44

    In short, a surveyor

    1. Collects and analyses land and geographicinformation

    2. Co-ordinates the usage of information inprojects with industry-related personnel likearchitects and engineers

    3. Makes sure legal, economic,environmental and socialissues are takeninto account in the implementations ofproject solutions.

    INTRODUCTION TO SURVEYING

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    6/44

    The surveying profession is multi-faceted with varied

    disciplines.

    Under The Institution of Surveyors Malaysia (ISM),the

    surveying profession in Malaysia is divided into 4 maindivisions :

    Land Surveying (LS)

    Quantity Surveying (QS)

    Building Surveying (BS)

    Property Management, Valuation & Estate

    Agency Surveying (PMVS)

    6

    INTRODUCTION TO SURVEYING

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    7/44

    QS

    a)Who

    b)What

    c) How

    d)Where

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    8/44

    ~ QUANTITY SURVEYING~

    QUANTITY SURVEYOR (QS) is a construction professional

    QSis qualifiedand adequately trained to

    adviseon all aspects of construction

    costs, financial and contractualadministration

    Advises the client on appropriate contract

    arrangement as well as the legal

    contract and conditions under which the

    building will be constructed.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    9/44

    ~ QUANTITY SURVEYING~ QS: Acting on behalf of the CLIENT Advises the Architect and

    Engineer on the cost implications such as:

    (i) different construction methods

    (ii) alternative choice of materials and size

    (iii) quality of the project.

    To ensure that each element is reconciled with the cost plan

    allowanceoverall project cost remains within the budget.

    An experton thecostandmanagement of construction projects(a)building, (b) civil or (c) heavy engineering

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    10/44

    ~ QUANTITY SURVEYING~ Whenever any building project is proposed, it is important that

    the cost involved is known in advance.

    These include :

    Site preparation cost

    Construction

    Labour

    Material and plant costs

    Professional fees, taxes andother charges

    Running and maintenance

    costs for the new building.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    11/44

    ~ QUANTITY SURVEYING~

    QSmust be able to assess

    (i) Implications of changes in design,

    (ii) Site conditions and working arrangements and

    (iii) Give the client accurate budget and time estimates.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    12/44

    ~ QUANTITY SURVEYING~

    SCOPE

    OF

    SERVICES

    a) Basic Serviceb)Supplementary

    Service

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    13/44

    ~ QUANTITY SURVEYING~

    a) BASICSERVICE

    i) Estimation

    ii)Measurement iii) Procurement

    iv) Payment

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    14/44

    ~ QUANTITY SURVEYING~ i) ESTIMATION:

    ESTIMATION The process of calculation the quantities ofvarious items of work, and the expenses likelyto be incurred.

    The estimated cost of a work is a close approximation of its

    actual cost (by measuring)

    Purpose to give the owner a reasonably accurate idea of

    the cost to help him decide whether the work can be

    undertaken as proposed or needs to be curtailed or abandoned,depending upon the availability of funds and prospective direct

    and indirect benefits.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    15/44

    ~ QUANTITY SURVEYING~

    i) ESTIMATION (Contd):

    Under-estimating client getting an unpleasant shock when

    tenders are opened and drastically modifying or abandoning

    the work at that stage

    Over-estimating estimator will lose his client or his job, or in

    any case his confidence.

    This knowledge is usedconstruction

    of new building with new design

    Also based on Estimatorsexperienced

    & knowledgesince it based on

    architectural drawing

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    16/44

    ~ QUANTITY SURVEYING~

    i) ESTIMATION (Contd):

    Example: The cost of brickwork in a building would be determined asbelow:

    (i) Cost of Material RM

    (a) Brick

    (b) Cement

    (c ) sand

    (d) Water

    (ii) Labor Cost RM

    (a) skilled

    (b) Unskilled

    (iii) Total of Material & Labor Cost RM

    (iv) Cost of plant RM

    (v) Cost of handling & transportation RM

    (vi) Overhead & profit

    TOTAL COST OF BRICKWORK RM

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    17/44

    ~ QUANTITY SURVEYING~

    i) ESTIMATION(Contd):

    By using this estimating knowledge, a QS will be able:

    Preparation of preliminary cost estimates and cost plans

    of the development project.

    Advise on cost estimates in relation to design

    development of a project.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    18/44

    ~ QUANTITY SURVEYING~

    ii) MEASUREMENT:

    MEASUREMENT The process of controlling the construction

    costby accurate measurement of the work required

    MeasurementAlso known as TAKING-OFF

    The quantities are measured from drawings

    and specifications prepared by architects

    and engineersknown as Billof

    Quantities(BQs)

    Purpose in order to prepare tender@ contract documents

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    19/44

    ~ QUANTITY SURVEYING~

    ii) MEASUREMENT(Contd):

    By using this measurementknowledge, a QS will be able:

    To prepare the Bill of Quantities or Specification

    document for tendering purposes.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    20/44

    ~ QUANTITY SURVEYING~

    ii) MEASUREMENT(Contd):

    BQs are prepared in accordance to:

    (a) Malaysian Standard Method of Measurement of Building Works

    (SMM 2)

    (b) Malaysian Standard Method of Measurement of Civil Engineering

    Works(CESMM)

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    21/44

    ~ QUANTITY SURVEYING~

    iii) PROCUREMENT:

    Generally PROCUREMENT refer to The action or process ofacquiring or obtaining material, property, or services at the

    operational level for example, purchasing, contracting, and

    negotiating directly with the source of supply

    BUT, the term PROCUREMENT is widely used in different context

    such as:

    (i) Commerce

    (ii) Defence

    (iii) Construction

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    22/44

    ~ QUANTITY SURVEYING~

    iii) PROCUREMENT (Contd):

    CONSTRUCTION PROCUREMENTThe process of acquiring theconstruction project

    7 main element of the process of construction procurement &

    may be divided into 2 broad categories:

    (a) Pre-Construction Stage (Before the Construction)

    Initiation

    Funding

    DesignSchematic, Detailed, Specialist Statutory approval

    TenderingOpen, Selective, Negotiated

    5

    E

    L

    EM

    E

    N

    T

    S

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    23/44

    ~ QUANTITY SURVEYING~

    iii) PROCUREMENT (Contd):

    (b) Construction Stage(During the Construction)

    Constructioninvolved Management

    & physical construction process

    Risk allocation

    2

    E

    L

    E

    M

    E

    N

    T

    S

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    24/44

    ~ QUANTITY SURVEYING~

    iii) PROCUREMENT (Contd):

    There are 2 main types of system of CONSTRUCTION

    PROCUREMENT in Malaysia such as:

    (a) Traditional system

    (b) Design & Build @ Turnkey system

    Apart from that there are also a few newSystem like Management Based system

    ( Built, Operate, Transfer) and Innovative

    System(PFI, Partnering, Privatisation)

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    25/44

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    26/44

    ~ QUANTITY SURVEYING~

    iii) PROCUREMENT (Contd):

    Advantages :

    Allow price to be fixed in advance construction

    Designerfull control of design process

    Disadvantages:

    Longer development periodClient delay in making decision

    May encourage adversary between the parties

    many peopleinvolved

    Traditional system:

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    27/44

    iii) PROCUREMENT (Contd):

    (b) Design & Build System:

    Client

    D & B ContSuppliers

    Sub-Cont

    Diagram 3 : Contractual relationship

    Brief Tender Design

    Construction

    Diagram 4 : Sequence of operation

    ~ QUANTITY SURVEYING~

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    28/44

    ~ QUANTITY SURVEYING~

    iii) PROCUREMENT (Contd):

    Advantages:

    Price is fixed in advance construction

    Overlapping of design & construction process shorter

    development process

    Disadvantages:

    Project cost

    higher than traditional

    Project often lacks of aesthetic values

    Design & Build system:

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    29/44

    ~ QUANTITY SURVEYING~iii) PROCUREMENT (Contd):

    By using this procurementknowledge, a QS will be able:

    Advise on procurement, tendering and contractual

    procedures and arrangement. Organize the calling of tenders

    Evaluation of tenders received in the form of tender

    reports.

    Preparation and execution of the formal contract.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    30/44

    ~ QUANTITY SURVEYING~

    iv) PAYMENT:

    CONSTRUCTION PAYMENT The process of paying /transfer ofmoney or goods for the construction works done.

    A QS will be able to:

    Prepare the Interim valuation of works in progress on sitefor purposes of interim payments.

    Prepare the financial statement of regular intervals during

    the construction period.

    Do a settlement of the final accounts of the project.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    31/44

    ~ QUANTITY SURVEYING~

    b) Supplementary services may also be provided by the

    Professional Quantity Surveyor if required:

    Preparation of feasibility studies of a project.

    Projection of estimated project or development expenditure

    and anticipated income cash flows.

    Evaluation of contractorsregistered for prequalification.

    Comparative cost studies on the economics of the project

    during design stage.

    Project management of construction project.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    32/44

    ~ QUANTITY SURVEYING~

    Supplementary services (Contd):

    Life-cycle costing and studies on economics of alternativedesign.

    Pricing of Bills of Quantities or negotiating and agreeingSchedule of Rates.

    Valuation or auditing of contractual claims for arbitrationslitigation cases.

    Valuation or auditing of insurance claims for fire damagedbuildings.

    Auditing of contracts and their related budgets and

    expenditure. Application of the full scope of quantity surveying services in

    Turnkey or Privatisation Contracts.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    33/44

    QUANTITY SURVEYING

    BQSM

    (Board of QuantitySurveyor Malaysia)

    ISM( The

    Institution ofSurveyor Malaysia)

    PROFESSIONAL

    BODY

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    34/44

    ~ QUANTITY SURVEYING~

    BQSM:

    The Board of Quantity Surveyors Malaysia was set up by an Actof Parliament, i.e. Registration of Quantity Surveyors Act 1967,

    Act 487 (revised 1992).

    The Board consists of a President, a Registrar and sixteen (16)

    members appointed by the Minister of Works, Malaysia. To keep and maintain a register of quantity surveyors in Malaysia

    To keep and maintain a register of firms and bodies corporate practicing as

    consulting quantity surveyors in Malaysia.

    To hear and determine disputes relating to professional conduct or ethics

    of quantity surveyors.

    To determine and regulate the professional conduct

    and ethics of the quantity surveying profession

    in Malaysia.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    35/44

    ~ QUANTITY SURVEYING~

    ISM:

    The Institution of Surveyors, Malaysia (ISM) is the professional

    institution representing the surveying profession in Malaysia

    and consists of four main divisions, namely :

    - Property Consultancy Valuation Surveying Division

    - Geomatic and Land Surveying Division

    - Quantity Surveying Division

    - Building Surveying Division

    http://www.ism.org.my/1_public/p_bsindex.asphttp://www.ism.org.my/1_public/p_bsindex.asp
  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    36/44

    ~ QUANTITY SURVEYING~

    ISM:

    Then known as TheMalayan Institution of Surveyors, and theFirst Council Meeting of the Institution was held on 14

    December 1961.

    At the E.G.M held on 19 June, 1966, the name of the Institution

    was changed to the Institutionof Surveyors, Malaysia (ISM)

    To continuously improve the standards of professional practice and ethics

    To promote the welfare and professional development of members

    To expand by incorporating related disciplines into the profession

    BACK

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    37/44

    ~ QUANTITY SURVEYING~

    Quantity Surveyorsmay work in a variety of sectors such as :Private consultancies

    Government agencies

    Educational institutions

    Construction companies

    Property developers

    Banks

    Financial institutions

    Commercial organizations

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    38/44

    ~ QUANTITY SURVEYING~

    ~With all these skills place QUANTITY SURVEYORS in a strong positionto take a leading

    managerial role throughout the development of a project~

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    39/44

    OTHER SURVEYINGPROFESSION

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    40/44

    ~ LAND SURVEYING~

    The role of a Land Surveyor (LS) can be summarized by its

    definition "A surveyor is a professional person with theacademic qualifications and technical expertise to:

    Assemble and assess land and geographic

    related information

    Use that information for the purpose of

    planning and implementing the efficient

    administration of the land, the sea and

    structures

    Instigate the advancement and developmentof such practices

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    41/44

    ~ BUILDING SURVEYING~ The role of a Building Surveyor (BS) offers specialist services on

    matters relating to building and property development such as :

    Project and construction management

    Maintenance and repair of building

    Refurbishment and restoration of old propertiesBuilding law and regulation

    Demolition works

    Property development.

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    42/44

    ~ PROPERTY MANAGEMENT,VALUATION & ESTATE AGENCY

    SURVEYING~

    The range of services that the PMVSmembers provide include:

    Property Valuation

    Estate Agency

    Property Management

    Market Research/Feasibility Studies

    Consultancy

  • 8/13/2019 ibequantitysurveyor2013-130909035857-

    43/44

    ~REFERENCES~

    Khairuddin Abdul Rashid (2002).Construction Procurement in Malaysia.

    Malaysia.Research Centre,IIUM

    Mokhtar Puteh (2000). Malaysia Standard Method of Measurement of Building Works.

    Malaysia.Institute of Surveyor Malaysia

    Mohd Fauzi Abdul Hamid (2005).Malaysia Standard Method of Measurement of CivilEngineering Works. CIDB

    Paul Sanghera (2010).PMP Exam in Depth. USA. Course Technology