7/13/2016
1
Meeting with FHWA and WisDOT BTO
July 22, 2016
I‐39/90 Expansion Project
• Interstate expansion and overview
• 2016 construction schedule
• Improvements to area interchanges
• Rock River bridge project
• How to stay informed and involved
Overview
7/13/2016
2
• Reconstruct and expand 45 miles of I‐39/90 from four to six lanes.
• Reconfigure 11 interchanges.
• Four to eight lanes from WIS 11 (Avalon Rd.) to the WIS 26 interchange in Janesville.
Interstate Improvements
North
• Design schedule: 2012 – 2016
• Construction schedule: 2015 – 2022
• Early LETs: 2013 ITS and WIS 73 (alternate route) reconstruction in 2014
Central
• Design schedule: 2012 – 2017
• Construction schedule: 2014 – 2020
• Early LETs: 2013 ITS and WIS 11 (Racine St.) interchange and US 14 and US 51 alternate route improvements in 2015
South
• Design schedule: 2012 – 2016
• Construction schedule: 2015 – 2020
• Early LETs: 2013 ITS, temporary widening and County G and County BT construction, near Beloit, in 2015
Project Segments
7/13/2016
3
2016 Construction Schedule• I‐39/90 southbound temporary widening, north of Edgerton.
o Replacement of I‐39/90 southbound bridge over E. Church Road.
• Three interchange reconstruction projects:
o US 51 interchange (southbound side), near Stoughton
o WIS 11 (Avalon Road) interchange, south of Janesville
o WIS 59 interchange near Newville
• Rock River bridges, just south of the WIS 59 interchange
• I‐39/90 expansion between the Rock County line and Knutson Road.
• Temporary widening of I‐39/90 southbound through Janesville area, including WIS 26 and US 14 southbound bridges.
• US 14 and WIS 140 intersection improvements; WIS 140 safety enhancements.
• Hart Road alternate route improvements and Hart Road bridge replacement over I‐39/90.
• Numerous bridge replacements over I‐39/90 in Dane and Rock counties.
• Bridge rehabilitation:
o I‐39/90 northbound bridge over Newville Road, south of the WIS 59 interchange.
o I‐39/90 southbound bridge over Turtle Creek, near County S interchange.
Note: More projects may be added to the 2016 construction schedule.
I‐43/WIS 81 interchangeConstruction: 2019‐2022
7/13/2016
4
County S (Shopiere Road) interchangeCompleted in November 2015
First Diverging Diamond Interchange (DDI) in Wisconsin… set to open November 2016!
WIS 11 (Avalon Road) interchange
7/13/2016
5
WIS 11 (Avalon Road) interchangeConstruction: September 2015 to November 2016
DDI movements at the WIS 11 (Avalon Road) interchange
7/13/2016
6
WIS 11 (Racine St.) interchangeCompleted November 2013
Construction: 2019‐2021
7/13/2016
7
Construction: 2019‐2021
WIS 26 interchange
7/13/2016
8
I‐39/90 and Rock River bridges
• Construction: spring 2016 to fall 2018
• LET cost: $48.4 million– Includes two miles of I‐39/90 mainline,
WIS 59 interchange and Rock River bridges
• Staged construction
• Pilot project for Queue Warning System
• Prime contractor: Rock Road Companies, Inc.
• Bridge contractor: Lunda Construction, Inc.
I‐39/90 and Rock River bridges• Extensive outreach and communication to
boaters and water enthusiasts.
• 13 public/private boat launches along Rock River and Lake Koshkonong with boater safety awareness signs and free informational flyers.
7/13/2016
9
I-39/90 and WIS 59 interchangeConstruction: March – Nov. 2016
Narrated animation video for this interchange at www.i39-90.wi.gov under Resources → Roundabouts.
7/13/2016
10
7/13/2016
11
WIS 59 interchangeConstruction: March 2016 to November 2016
7/13/2016
12
WIS 73/US 51 interchangeCompleted in November 2015
7/13/2016
13
US 51 interchangeConstruction: 2016‐2017
County N interchangeConstruction: 2017
7/13/2016
14
Stay informed and involved!
Sign up for project email updates at www.i39‐90.wi.gov.
John Vesperman, P.E.
Project Chief
Katrina Feltes, P.E.
Project Supervisor
Wayne Chase, P.E.
Project Supervisor
Kim Schauder, P.E.
Project Supervisor
Steven Theisen
Project Communications Manager
Project Field Office
111 Interstate Blvd.
Edgerton, WI 53534
Project contacts
7/13/2016
15
Questions?
www.i39‐90.wi.gov
Facebook.com/WisconsinI3990Project
(608) 884‐1234