I-395 Reconstruction Project PAG Meeting
January 23, 2013
1
Existing Conditions/Deficiencies • Safety and Operational Issues: poor horizontal and vertical geometry, lane
continuity, etc. • Entrances/Exits Ramps: undesirable left hand entrance/exit ramps • Weaving: competing movements in a very short distance • Access: poor access to and from I-395 • Clearances: low clearance from local streets to I-395
2
Commitments
• Roadway vertical clearance west of FEC should be a minimum of 19 feet and east of FEC a minimum of 25 feet.
• A minimum of 200 feet between the I-395 westbound bridge and the Adrienne Arsht Center for the Performing Arts (AACPA) will be provided.
• A minimum of 225 feet of column span length will be provided. • The Department commits to providing a signature span design. • The Department will provide aesthetics enhancements (e.g.
landscaping) to help maximize the total integration of the project with the adjacent community.
• Reconnect NW 2nd Avenue .
3
Refinements to Alternative
• Approved by FDOT D6 June 2012 • Added additional thru lane in each direction from 2L to 3L. • Eliminated most design exceptions and variations. • Improved interchange at North Miami /NE 1st Aves. with I-395. • Length of “Aesthetic Pleasing Bridge” is approximately 600 feet total length.
Begin Project
End Project
4
Proposed Plan & Profile
5
NW 3 AVE NW 2 AVE FEC RR MIAMI AVE NE 1 AVE NE 2 AVE BISCAYNE
BLVD
METROMOVER
16.5
’
23.4
’
24.0
’
25.3
’
29.6
’
20.2
’
28.5
’
Right-of-Way Plans • Total of 70 Fee
Simple Parcels and 15 Permanent Easements required for project.
• Twenty-six parcels acquired to-date.
• Right-of-way funded thru FY 2015.
6
Visual Quality Process
7
• Objectives: Balance Cost, Engineering, Architecture, Constructibility and Community Expectations
• Steps Taken: Developed Corridor Character Received Input from TAC, PAG and Community Established Selection Criteria Developed Bridge Type Alternatives
Bridge/Structures Design • Main Span ~ 600 ft x 2 = 1,200 FT
• Main Span Length was optimized to manage total project construction cost
• Avoid curved alignment • Main Span Approaches ~ 8,000 ft • Connectors & Ramps ~ 11,000ft
8
Main Span Designs
• Fifteen different design concepts presented to TAC and PAG • TAC- FDOT District 6 and Central Office • PAG- Major Stakeholders within project area
• Based on five TAC and four PAG meetings held, the following four Designs have been recommended: • Infinity Arch • Wishbone Arch • Segmental Box • Aesthetic Viaduct
9
Main Span : Infinity Arch
• Challenges • Complicated construction
sequence • Will require additional
phases to MOT
• Overall Length • Suspended span
approximately 690 ft.
10
Total Cost = $ 740,000,000
Main Span : Wishbone Arch
• Challenges • Arches erected separately • Complicated foundation
• Overall Length • Suspended span
approximately 600 ft.
11
Total Cost = $ 673,000,000
Main Span: Segmental Box • View: Aerial Looking Southeast
Main Span: Segmental Box • View: Northbound Biscayne Boulevard
Main Span : Segmental Box
• Challenges • No Aesthetic Component for
Main Span
• Overall Length • Main Span 300 ft.
14
Total Cost = $ 559,000,000
Main Span: Aesthetic Viaduct • View: Aerial Looking Southeast
Main Span: Aesthetic Viaduct • Eastbound I-395
Main Span: Aesthetic Viaduct • Southwest View
Main Span : Aesthetic Viaduct
• Challenges • Fabrication of tower • Maintaining cables taut
over time
• Overall Length • Main spans approximately
300 ft.
18
Total Cost = $ 604,000,000
Overall Cost Comparison
• Infinity Arch = $740,000,000 • Wishbone Arch = $673,000,000 • Segmental Box = $559,000,000 • Aesthetic Viaduct = $604,000,000
19
Cross Section
Cross Section
21
Pier Renderings •14th St NE
22
Pier Renderings
• 14th St NE
23
Schedule of Milestones
• Survey: Completed • Soil Testing: Completed • Traffic Analysis: Completed • Alignment: Completed • Public Involvement: On-Going • Draft Preliminary Plans: Submitted November 2012
• Bridge Development Report (BDR) • Visual Quality Manual (VQM) • Various Component Sets
• Final Preliminary (15%) Plans: Late February 2013 • Hold Public Meeting: April 2013 • Issue Draft Request For Proposal (RFP): June 2013 • Complete Right of Way Acquisition: Summer 2015
24
Visual Quality Manual
I-395 Reconstruction
25