60
i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION MODEL FOR CONSTRUCTION PROJECT DESIGN STAGE SUZILA BINTI MOHD A thesis submitted in fulfilment of the requirement for the award of the Degree of Master of Science in Technology Management Faculty of Technology Management and Business Universiti Tun Hussein Onn Malaysia SEPTEMBER 2015

i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

Embed Size (px)

Citation preview

Page 1: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

i

BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION MODEL

FOR CONSTRUCTION PROJECT DESIGN STAGE

SUZILA BINTI MOHD

A thesis submitted in

fulfilment of the requirement for the award of the

Degree of Master of Science in Technology Management

Faculty of Technology Management and Business

Universiti Tun Hussein Onn Malaysia

SEPTEMBER 2015

Page 2: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

v

ABSTRACT

Building Information Modelling (BIM) provides significant benefits to construction

players. However, BIM in construction projects seem not fully been implemented. This

is due to lack effective strategy of implementing BIM in project design stage. Added

to the matters, most of the construction players fail to get benefits using BIM because

they are facing difficulty to implement BIM. This research aims to assist construction

players to implement BIM in construction project design stage. Literature review was

carried out to discover BIM implementation in construction project design stage and

examples of models in construction field, which the research model has similar

purposes with the models. Semi-structured interviews have been done with design

team, which currently involved and have been involved in projects using BIM for

residential and commercial projects in Malaysia. All data obtained from the interviews

were analysed using content analysis technique. The findings from the interviews

revealed that, construction players need an assistance in a form of model to implement

BIM in construction project design stage. Therefore, both data from literature review

and the interviews were used to develop a model, which has been named as ‘BIM

Implementation Model for design team’. The model is one of the ways to assist design

team to implement BIM in construction project design stage. Apart from that, the

model would assist design team a place to start and follow with several elements in

each level of the model. Thus, the model could increase BIM implementation in project

design stage.

Page 3: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

vi

ABSTRAK

Pemodelan Maklumat Bangunan (Building Information Modelling (BIM)) memberi

manfaat dan kebaikan kepada pemain industri pembinaan. Walau bagaimanapun,

pelaksanaannya di dalam projek-projek pembinaan tidak dilaksanakan secara

menyeluruh. Perkara ini berlaku disebabkan oleh kekurangan strategi yang berkesan

untuk melaksanakan BIM di peringkat reka bentuk projek pembinaan. Disebabkan

oleh perkara tersebut, kebanyakan pemain industri pembinaan gagal untuk

mendapatkan manfaat dari BIM. Penyelidikan ini dijalankan untuk membantu pasukan

reka bentuk projek pembinaan melaksanakan BIM di peringkat reka bentuk projek

pembinaan. Kajian literatur dilaksanakan untuk memperolehi maklumat mengenai

penggunaan BIM di peringkat reka bentuk projek pembinaan dan contoh-contoh

model yang berkaitan bidang pembinaan, di mana model penyelidikan mempunyai

tujuan yang sama dengan contoh-contoh model tersebut. Tambahan pula, temubual

secara separa struktur telah dilakukan ke atas pasukan reka bentuk projek pembinaan

yang telah menggunakan dan sedang menggunakan BIM dalam projek-projek

kediaman dan komersial di Malaysia. Data yang diperolehi daripada temubual tersebut

telah dianalisis menggunakan teknik analisis kandungan. Hasil daripada temubual

mendapati bahawa, pasukan reka bentuk projek pembinaan memerlukan bantuan

dalam bentuk model untuk melaksanakan BIM di peringkat reka bentuk projek

pembinaan. Oleh itu, kedua-dua data dari kajian literatur dan temubual telah digunakan

untuk membangunkan sebuah model yang dinamakan sebagai Model Pelaksanaan

BIM untuk pasukan reka bentuk projek pembinaan. Model ini merupakan salah satu

cara untuk membantu pasukan reka bentuk projek pembinaan melaksanakan BIM di

peringkat reka bentuk projek pembinaan. Selain itu, model ini juga menyediakan

langkah-langkah yang jelas serta beberapa elemen untuk melaksanakan BIM di

peringkat reka bentuk projek pembinaan. Oleh itu, model ini dapat meningkatkan

pelaksanaan BIM pada peringkat reka bentuk projek pembinaan.

Page 4: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

vii

CONTENTS

TITLE i

DECLARATION ii

DEDICATION iii

ACKNOWLEDGEMENT iv

ABSTRACT v

ABSTRAK vi

CONTENTS vii

LIST OF TABLES xiv

LIST OF FIGURES xvi

LIST OF ABBREVIATIONS xviii

LIST OF APPENDICES xx

CHAPTER 1 INTRODUCTION 1

1.1 Introduction 1

1.2 Research Background 2

1.3 Problem Statement 4

1.4 Research Questions 7

1.5 Research Aim and Objectives 7

1.6 Scope of Research 7

1.7 Significant of Research 8

1.8 Research Methodology 8

1.9 Research Organisation 10

1.10 Summary 12

CHAPTER 2 LITERATURE REVIEW 13

2.1 Introduction 13

2.2 Construction Project Design Stage 13

2.3 Building Information Modelling (BIM) 24

Page 5: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

viii

2.3.1 BIM in the Malaysian Construction Industry 25

2.3.2 Definition of BIM 26

2.4 BIM Application in Project Design Stage 29

2.4.1 Visualise Project Models 29

2.4.2 Generate Fabrication or Shop Drawing for Various

Building Systems

32

2.4.3 Utilise Project Model Parameters by Using Code

Review

34

2.4.4 Preview Design Clashes Analysis 35

2.4.5 Assist in Preparing Cost Estimating 35

2.4.6 Assist in Preparing Project Scheduling 36

2.5 BIM Adaptation in Project Design Stage 37

2.6 BIM Tools in Design Stage 38

2.7 Benefits of Implementing BIM in Project Design

Stage

41

2.8 Challenges in Implementing BIM 42

2.8.1 Legal or Contractual Issues Relating to BIM 43

2.8.2 Cost Issues 43

2.8.3 Skill and Knowledge Issues 44

2.8.4 Lack of Effective Strategy to Implement BIM 44

2.9 Potential Improvement of BIM Implementation in

the Construction Industry

45

2.10 Model Related to BIM and Construction Field 46

2.10.1 Capability Maturity Model (CMM) for Software 46

2.10.2 The Business Process Operation (BPO) Maturity

Model

48

2.10.3 The STEPS Model 49

2.10.4 The People Capability Maturity Model

(People CMM)

49

2.10.5 The Bew-Richards BIM Maturity Model 51

2.10.6 BIM Maturity Matrix (BIm3) 52

2.10.7 Performance Measurement (PM) Migration Path

Model

53

Page 6: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

ix

2.10.8 Similarities Between the Models 54

2.10.9 Selection of Maturity Levels for the Research

Model

55

2.11 Theoretical Framework 59

2.12 Summary 61

CHAPTER 3 RESEARCH METHODOLOGY 62

3.1 Introduction 62

3.2 Research Purposes 62

3.3 Research Approaches 64

3.4 Research Strategies 67

3.5 Data Collection 71

3.5.1 Literature Review Related to BIM, Project

Design Stage and Model Related to BIM and

Construction Field

75

3.5.2 Semi-Structured Interview with Design Team 76

3.5.2.1 Respondent Selection 77

3.5.2.2 Development of Interview Questions 77

3.5.2.3 Pilot Study 78

3.6 Data Analysis Technique 80

3.6.1 Development of BIM Implementation Model for

Design Team

81

3.6.2 Evaluation of Research Model 82

3.7 Summary 83

CHAPTER 4 DATA ANALYSIS AND FINDINGS 84

4.1 Introduction 84

4.2 Objectives of Interviews 84

4.3 Discussion on the Data from Interviews 85

4.3.1 Respondent’s Background 85

4.3.2 Current Practices of BIM Implementation in

Project Design Stage

87

4.3.2.1 Understanding on BIM 88

4.3.2.2 Design Process for Construction Projects 93

Page 7: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

x

4.3.2.3 Design Process for Construction Project Using

BIM

98

4.3.3 The Effects of BIM Implementation in Project

Design Stage

106

4.3.3.1 Issues Related to Project Design 106

4.3.3.2 Benefits of BIM Implementation in Project

Design Stage

110

4.3.4 Challenges of BIM Implementation in Project

Design Stage

114

4.3.4.1 Challenges Faced by Design Team

to Implement in Project Design Stage

114

4.3.4.2 Potential Improvement on BIM Implementation 120

4.4 Key Finding From Interviews 125

4.5 Summary 128

CHAPTER 5 BIM IMPLEMENTATION MODEL FOR DESIGN

TEAM

129

5.1 Introduction 129

5.2 The Model: BIM Implementation for Design

Team

129

5.3 Model Development Process 130

5.3.1 Step 1: Research Model Purposes 131

5.3.2 Step 2: Concept of Research Model 132

5.3.3 Step 3: Procedure of Research Model

Development

132

5.3.4 Step 4: Details of the Model Elements 133

5.4 Evaluation of the Research Model 140

5.4.2 Evaluator’s Background 141

5.4.2 Evaluation on BIM Implementation Model for

Design Team Model Elements

142

5.4.3 Benefits of Using BIM Implementation Model for

Design Team

145

5.4.4 Barriers to Use BIM Implementation Model for

Design Team

146

Page 8: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xi

5.4.5 Improvements of BIM Implementation Model for

Design Team

147

5.5 Summary 149

CHAPTER 6 CONCLUSIONS AND RECOMMENDATIONS 150

6.1 Introduction 150

6.2 Research Overview 150

6.3 Conclusion 154

6.4 Contribution of Research 155

6.5 Limitations of Research 156

6.6 Recommendations for Further Research 157

6.7 Concluding Remark 157

REFERENCES 158

APPENDICES

LIST OF PUBLICATIONS

VITA

Page 9: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xiv

LIST OF TABLES

2.1 Definition of BIM. 26

2.2 Types of BIM Tools in Project Design Stage. 41

2.3 Summary of Models Similarities 55

2.4 Selection of Maturity Levels for Research Model. 56

3.1 Respondents Feedback on Interview Questions. 79

4.1 Respondents’ Backgrounds. 86

4.2 Understanding on BIM. 88

4.3 Purpose of BIM Implementation in Project Design. 90

4.4 Design Stage Activities. 94

4.5 Construction Players Involved in Project Design Stage. 95

4.6 Design Process for Project Using BIM. 98

4.7 Level of Development (LOD). 102

4.8 The use of LOD. 104

4.9 Types of BIM Tools. 104

4.10 Summary of the BIM Tools Used by Respondents. 106

4.11 Project Design Issues. 107

4.12 Benefits of BIM Implementation in Project Design Stage. 110

4.13 ‘People’ Factor. 115

4.14 ‘Process’ Factor. 117

4.15 ‘Technology’ Factor. 118

4.16 Potential Improvement to Increase BIM Implementation in

Project Design Stage.

121

5.1 Details of Key Aspects of BIM Implementation Model for

Design Team.

135

5.2 Evaluator’s Information. 141

5.3 Model Contents. 142

Page 10: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xv

5.4 Model Capability. 143

5.5 Model Usability. 144

5.6 Summary of Model Elements Evaluation. 145

5.7 Benefits of Using BIM Implementation Model for Design Team. 146

5.8 Benefits of Using the Model 146

5.9 Barriers to Use the BIM Implementation Model for Design

Team.

147

5.10 Barriers of Using the Model 147

5.11 Potential Improvements to Improve BIM Implementation Model

for Design Team.

148

5.12 Summary of Potential Improvements to Improve the Model 148

Page 11: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xvi

LIST OF FIGURES

1.1 Research Methodology Process. 9

2.1 Construction Project Process (Adopted from: Cooper et al.,

2005; Kazi, 2005; NCCER, 2008; CIOB, 2010).

14

2.2 Activities in Project Design Stage 14

2.3 Design Team (Adopted from: Klinger and Susong, 2006;

Winch, 2010; Levy, 2010).

17

2.4 Project Design Issues (Adopted from: Sambasivan and

Soon, 2007; Forbes and Ahmed, 2011; Kikwasi, 2013).

22

2.5 Example of 2D Design and 3D Model. 30

2.6 Visual simulation of 4D Model for Scheduling (HSE

Contractor Inc, 2013).

31

2.7 Example of 5D Model for Project Estimating (Construction

Management Software (CMS), 2008).

32

2.8 General Instruction of Structural Steel Connections

(Autodesk, 2007).

33

2.9 4D Structure Steel Design (Cadalyst, 2013). 34

2.10 Example of Design Clashes (Logiseek, 2013). 35

2.11 BIM Throughout a Building Life-cycle (PWD, 2011). 37

2.12 Capability Maturity Model (CMM) for Software (Paulk et

al., 1993).

47

2.13 The BPO Maturity Model (Lockamy III and McCormack,

2004).

48

2.14 The STEPS Model (Robinson et al., 2005). 49

2.15 The People Capability Maturity Model (Curtis et al., 2009). 50

2.16 The Bew-Richards BIM Maturity Model (Jayasena and

Chitra, 2013).

51

Page 12: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xvii

2.17 Performance Measurement Migration Path Model (Ahmad

Latiffi et al., 2012).

53

2.18 Suggestion of Research Model 59

2.19 Theoretical Framework. 60

3.1 Research Approaches (Creswell, 2003). 64

3.2 Types of Research Strategies (Adopted from: Creswell,

2007; Saunders et al., 2007).

68

3.3 Data Collection Methods (Adopted from: Fellows and Lui,

2008; Athanasiou et al., 2010).

72

3.4 Steps of Research Model Development 82

4.1 The Sequences of Project Design Stage Activities. 95

4.2 Challenges to Implementing BIM in Project Design Stage. 120

5.1 BIM Implementation Model for Design Team. 134

Page 13: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xviii

LIST OF ABBREVIATIONS

USA - United States of America

UK - United Kingdom

ICT - Information and Communication Technology

RFI - Request for Information

PWD - Public Work of Department

BIM - Building Information Modelling

AEC - Architecture, Engineering and Construction

FM - Facilities Management

HK - Hong Kong

UTHM - Universiti Tun Hussein Onn Malaysia

NCI - National Cancer Institute

O&M - Operations and Maintenance

2D - 2-dimensional

3D - 3-dimensional

4D - 4-dimensional

5D - 5-dimensional

6D - 6-dimensional

7D - 7-dimensional

n-D - n dimensional

M&E - Mechanical and Electrical

ROI - Return on Investment

MEP - Mechanical, Electrical and Plumbing

QS - Quantity Surveyor

MoE - Ministry of Education

CIDB - Construction Industry Development Board

BOE - Board of Engineers

Page 14: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xix

HVAC - Ventilation and Air-Conditioning

CAD - Computer Aided Design

BDS - Building Description System

GLIDE - Graphical Language for Interactive Design

AEC-FM - Architectural, Engineering and Construction-Facilities

Management

IBC - International Building Code

ADA - America with Disabilities Act guideline

IT - Information Technology

BOA - Board of Architect

CMM - Capability Maturity Model

BPO - Business Process Operation

BIm3 - BIM Maturity Model

SEI - Software Engineering Institute

KM - Knowledge Management

IPD - Integrated Project Delivery

PM - Performance Measurement

SWOT - Strength, Weaknesses, Opportunities and Threats

Page 15: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

xx

LIST OF APPENDICES

APPENDIX TITLE

A BIM Maturity Matrix Model

B Interview Questions

C Evaluation Questions

Page 16: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

CHAPTER 1

INTRODUCTION

1.1 Introduction

Construction industry is one of the contributor to the economy of Malaysia. It has

contributed a total worth of MYR 194 billion to the Malaysian gross domestic product

in year 2011 to 2015 (Unit Perancang Ekonomi, 2015). Other than that, it is also

important in supporting social development through the provision of basic

infrastructure in Malaysia (Construction Industry Development Board (CIDB), 2007).

According to Unit Perancangan Ekonomi (2015), the uses of technology in the

construction industry has increased the rate of Malaysia economy.

In order to manage the construction industry efficiently, information and

communication technology (ICT) has provided better management solution to the

construction industry. The implementation of ICT in the construction industry has

become a norm since year 1990 (Forbes and Ahmed, 2011). Moreover, Forbes and

Ahmed (2011) stated that ICT is a technology that encompasses computer hardware,

software and communication devices of sharing and accessing information

conveniently. It has been used widely to avoid construction project problems such as

low productivity of construction projects, low quality of end projects, project delaying,

construction cost overrun and disputes among construction players (Kadir et al., 2005;

Arayici et al., 2009; Khosnava et al., 2012; Haron, 2013).

Thus, ICT has introduced a new technology, namely building information

modelling (BIM) in order to overcome the construction problems (CIDB, 2007; Forbes

and Ahmed, 2011; Public Work Department (PWD), 2013). The implementation of

Page 17: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

2

new technology such as BIM in construction projects has reduced issues on project

delay, construction cost overrun, disputes among construction players; and it has

increased project quality as well as productivity of construction projects (Azhar, 2011;

Eastman et al., 2011; Zakaria et al., 2013).

BIM has been used widely by the architecture, engineering, construction and

facilities management (AEC-FM) industry for the purpose of managing construction

project life-cycle (Levy, 2010). It has also been introduced to the construction industry

in many countries such as United States of America (USA), Australia, Hong Kong

(HK) (Monteiro and Martins, 2013; Ahmad Latiffi and Mohd, 2014), Finland,

Denmark and Norway (Eastman et al., 2011; Crotty, 2012). In Malaysia, the idea to

implement BIM was introduced by the Director of Public Works of Department

(PWD) in year 2007. The idea was proposed when Malaysian government are aware

about the potential of BIM in avoiding construction cost overrun and project delay as

well as to avoid design problems at early stage of construction project (PWD, 2013;

Ahmad Latiffi et al., 2013; Zakaria et al., 2013). Since then, PWD has encouraged all

construction players to implement BIM in construction projects (PWD, 2013).

Correspondingly, the implementation of BIM in construction projects need to be

explored in order to identify the capabilities of BIM in managing construction projects

effectively.

1.2 Research Background

Adaptation of technology in the construction industry is moving rapidly towards the

era of modernisation and globalisation. ICT has played a significant role in this

transformation. The use of ICT permeates in various industries including in the

construction industry and it is seen as a major driver for improving performance of the

industry (CIDB, 2007; Eastman et al., 2011; Hosseini et al., 2012; Zhang, 2013).

According to Forbes and Ahmed (2011), ICT has introduced BIM as a tool to manage

construction projects effectively by reducing construction problems such as project

delay, construction cost overrun and disputes among construction players.

BIM is seen as a concerted action to ensure collaboration among construction

players such as architect, engineers, project manager and contractors (Furneaux and

Kivvits, 2008; PWD, 2013). The positive effects from the implementation of BIM in

Page 18: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

3

construction projects have been highlighted by many construction players as a need in

managing construction projects in order to reduce construction problems (Bryde,

Broquetas and Volm, 2013). According to Bryde et al. (2013), there are thirty five (35)

examples of BIM projects in USA, UK and France, which had been contributed

positive effects to construction projects. The positive effects can be traced in terms of

construction cost, project duration, project quality, communication and collaboration

among construction players (Bryde et al., 2013).

Moreover, the successful of BIM in managing construction projects can be seen

through several successful erected projects. These projects are the Freedom Tower in

New York City, USA; Birmingham City University in UK; One Island East project in

HK, and Sydney Opera House in Australia (Furneaux and Kivvits, 2008; Winch, 2010;

Royal Institution of Charted Surveyor (RICS), 2013). Apart from that, there are also

several construction projects in the construction industry of Malaysia were identified

to be employing BIM. These projects are Sultan Ibrahim Hall (formerly known as

Multipurpose Hall of Universiti Tun Hussein Onn Malaysia, UTHM) in Batu Pahat,

Johor (Construction Research Institute of Malaysia (CREAM), 2012; Mohd and

Ahmad Latiffi, 2013); National Cancer Institute (NCI) of Malaysia in Putrajaya

(Ahmad Latiffi, Mohd and Brahim, 2014); Educity Sports Complex in Nusajaya,

Johor; and Ancasa Hotel in Pekan, Pahang (PWD, 2011; Ahmad Latiffi et al., 2013;

Mohd and Ahmad Latiffi, 2013).

BIM has capabilities in managing construction projects starting from pre-

construction stage to post-construction stage (Levy, 2010; Eastman et al., 2011;

Crotty, 2012). It has to be implemented in each of the stages in order to manage all

activities in construction projects especially in project design (Yan and Damian, 2008;

Weygant, 2011; Newman, 2013). Project design has been considered as an important

activity in construction projects (Eastman et al., 2011; Memon et al., 2011) because

other activities such as cost estimating and project scheduling can only be started and

refined after the completion of project design (Eastman et al., 2011; Memon et al.,

2011). Therefore, it is crucial to implement BIM in the stage of project design in order

to increase accuracy in preparing cost estimating, project scheduling, site analysis, and

project productivity (Fallon and Palmer, 2007; Eastman et al., 2011). The ability of

BIM in visualising project design and detect design clashes during design stage can

reduce request for information (RFI), design changes and incomplete design

specification during construction stage. The possibilities of those problems occur

Page 19: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

4

during construction stage can be avoided earlier in pre-construction stage (Kymmell,

2008; NCCER, 2008).

Moreover, BIM can also be integrated with post-construction activities such as

facilities management (FM), operations and maintenance (O&M) (Newman, 2013;

Abdullah et al., 2014). The implementation of BIM in project design helps facility

manager to manage FM by visualising all information in 3D model. In addition, all

information in the model can be easily shared and to be used by the contractor (Sabol,

2008; Abdullah et al., 2014). BIM can also improve space management, where facility

managers can use the 3D model to visualise project plan and configure space more

efficiently (Sabol, 2008; Abdullah et al., 2014).

Correspondingly, the main importance of BIM implementation in project design

stage lies on the use of three dimensional (3D) parametric authoring tools as object

based modelling software (Mohamad Kamar, 2012). There are several types of

modelling software or also known as BIM tools are used to manage project design in

construction projects. These tools are such as Revit (architecture, structural,

mechanical and electrical (M&E)), Bentley System (architecture, structural and M&E)

and Tekla structure. The tools are capable to visualise project model, preview design

clashes and generate fabrication drawing for various building systems (Azhar, 2011;

Eastman et al., 2011; Ahmad Latiffi et al., 2013; Monteiro and Martins, 2013; PWD,

2013).

Utilising BIM technology allows effective and better plan for construction

projects activities, which can overcome the potential errors in design, disputes among

construction players, construction cost overrun and project delay (Eastman et al.,

2011). BIM also has potential for improving communication, collaboration between

construction players, reducing cost at every stage in construction projects and reduce

safety issues in construction projects (Smith and Tardif, 2009; Cheng and Ma, 2012;

Sunindijo and Zou, 2013).

1.3 Problem Statement

Low productivity of construction projects, low quality of end projects, project delay

and construction cost overrun are the four main construction problems lead to

construction project failure (Arayici et al., 2009; Forbes and Ahmed, 2011; Khosnava

Page 20: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

5

et al., 2012 and Haron, 2013). Most of the problems that were identified by Arayici et

al. (2009), Forbes and Ahmed (2011), Khosnava et al. (2012) and Haron (2013)

occurred due to weakness in managing project design. This shows that, project design

is one of important element lead to the success of managing construction projects

(Eastman et al., 2011; Memon et al., 2011). Therefore, many attempts were done by

construction players especially by the design team (client, architect, structural

engineer, M & E engineer and contractor) to improve quality of project design by

implementing BIM (Kymmell, 2008: Forbes and Ahmed, 2011).

Nowadays, the implementation of BIM in project design stage is seen as one of

the effective ways to reduce construction problems. Even though BIM implementation

gives positive effects to construction projects, most of the design team is facing

difficulty to implement BIM. In addition to that, some were failed to obtain the benefits

of using BIM (Cheung et al., 2012; CREAM, 2014). According to Zakaria et al.

(2013), most of the construction players are having difficulty to implement BIM as

they do not know what, how, where, who and when to begin with BIM in construction

projects especially in the Malaysia construction industry. This matters happened due

to several factors, such as lack of knowledge as well as skill on BIM; cost to adopt

BIM tools as well as training are expensive and lack of effective strategy to implement

BIM (Furneaux and Kivvits, 2008; Arayici et al., 2012, Zakaria et al., 2013).

One of the main setbacks for the implementation of BIM in construction projects

is due to lack of knowledge and skill on BIM. Construction players are required to

dominate knowledge and skill on BIM before deciding to implement BIM (Eastman

et al., 2011: Azhar, 2011; Ahmad Latiffi et al., 2013). Apparently, possessing relevant

knowledge on BIM is important to lead construction players to the right way of

implementing BIM. It will also increase awareness among construction players

regarding the benefits of implementing in construction projects (Gu and London, 2010;

MH Government, 2012; Zakaria et al., 2013). Meanwhile, possessing relevant skill on

BIM will also guide construction players on how to manage project design, cost

estimating, project scheduling, site coordination and facilities management by using

BIM tools such as Revit families (Azhar, 2011; Newman, 2013).

The second factor that explained about the slow adoption of BIM in construction

projects is due to cost of implementing BIM tools (revit families), new hardware

(computer) and BIM training. The cost for these tools are expensive and it could be a

barrier for small and medium construction companies to implement BIM in their work

Page 21: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

6

(Furneaux and Kivvits, 2008; Eastman et al., 2011; Forbes and Ahmed, 2011).

Therefore, in order to manage construction projects using BIM, construction players

must ensure to gain benefits from using BIM or else all the investment on BIM will be

wasted and useless.

Another factor that lead to slow adoption of BIM among construction players is

due to lack of effective strategy of implementing BIM in an organisation (Arayici et

al., 2012); for example: absent of a comprehensive BIM standard guideline (Zakaria

et al., 2013; CREAM, 2014) and adoption model to implement BIM (Zakaria et al.,

2013). Literally, there is no clear consensus on how to implement BIM in construction

projects (Azhar, 2011). On top of this, there is no single BIM document that provides

instruction on its application and implementation (Azhar, 2011; Zakaria et al., 2013).

Continuation from the matters, many construction players have developed their own

version of BIM implementation guideline. However, the informal guideline somehow

has resulted in confusion among construction players, which render the construction

players to feel doubted to implement BIM (Zakaria et al., 2013; CREAM, 2014).

Additionally, the role of effective strategy such as BIM standard guideline and

adoption model is important to answer all questions and enquiries from the

construction players, which are where they to start, how is the BIM process work, what

can BIM produces and who are responsible towards the process (Arayici et al., 2012;

Building and Construction Authority (BCA), 2013). The guideline will help

construction players to achieve all benefits of BIM implementation in construction

project in a right way. Since BIM implementation in project design could reduce

construction problems during construction stage, this research has develop a model

that could assist design team to implement BIM in project design stage. The model

could assist design team in a proper way to implement BIM, so they could gain all

benefits of using BIM and increase efficiency in managing construction project life-

cycle.

Page 22: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

7

1.4 Research Questions

The research questions are as follows:

(i) To what extent did construction players use BIM in project design stage?

(ii) How BIM implementation in project design stage gives effect to construction

players?

(iii) What are challenges of BIM implementation in project design stage?

(iv) How to assist construction players to implement BIM in project design stage?

1.5 Research Aim and Objectives

The aim of this research is to assist construction players to implement BIM in project

design stage. In order to achieve the aim, the following research objectives are

established:

(i) To determine the extent to which construction players use BIM in project design

stage.

(ii) To identify the effects cause from BIM implementation in project design stage

to construction players.

(iii) To identify the challenges of BIM implementation in project design stage.

(iv) To develop a model that could assist construction players to implement BIM in

project design stage.

1.6 Scope of Research

The scope of this research is focused on construction projects in Malaysia, which have

used and currently using BIM. The projects are residential and commercial projects.

Therefore, all information regarding implementing BIM in design stage were obtained

from design team, which are client, architect, structural engineer, Mechanical,

Electrical and Plumbing (MEP) engineers as well as contractors. The contractor are

involved in this research because most of the projects using BIM in Malaysia is using

design and build (D&B) as project delivery method. According to Chappell (2007),

contractor is involved in managing project design in design and build project.

Page 23: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

8

Moreover, all respondents involved in this research must have been involved and

currently involved in projects using BIM. This is important in order to gain their

understanding and experiences in managing projects using BIM. Moreover, the

information also important to discover current BIM practices in Malaysian

construction projects. The information is very useful to identify level of BIM

implementation in Malaysian construction projects.

1.7 Significance of Research

This research is expected to contribute to design team and the construction industry

with:

(i) giving recommendation to design team on how to implement BIM in project

design stage in a construction project. This could increase BIM implementation

in construction projects.

(ii) producing a model that could assist design team to implement BIM and get

benefits of using BIM in managing construction projects.

1.8 Research Methodology

Research methodology is one of the approaches in doing research. It is an approach to

plan, to review and to control research process (Fellows and Liu, 2008). Figure 1.1

shows research methodology process for this research in order to achieve research aim

and objectives.

Page 24: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

9

Formulation of

Problem Statement

Determine Research

Aim and Objectives

Identification of

Research Scope

Identifying Types of Research Strategy and

Data Collection Technique:

1) Research Strategy:

Survey

2) Data Collection Technique:

i) Literature Review:

Books, journal articles, international

conference papers, and materials available

on the internet.

ii) Semi-structured interview:

Semi-structured interviews with design team

(client, architect, structural engineer, MEP

engineer and contractor)

Data Analysis:

Content analysis

Results and Findings

Conclusion and

Recommendations

Model Development

First StageSecond

StageThird Stage

Figure 1.1: Research Methodology Process

Based on Figure 1.1, the research methodology process is divided into three (3)

stages. The first stage is the process to identify research issues, topic selection, problem

statement and research objectives. The researcher had brainstormed for research topic

and had identified current issues on BIM implementation in construction projects.

Moreover, the researcher has identified which construction projects in Malaysia are

using BIM for the purpose of data collection.

The second stage shows types of research strategy and data collection technique

used in this research. Survey is adopted in this study as the research strategy.

Meanwhile, literature review and semi-structured interview were used in this study as

data collection technique. The literature review is made to gain information on BIM

implementation in project design stage and types of model, which related to BIM and

construction field. All information on BIM and project design stage was gathered from

books, journal articles, international conference papers, and materials available on the

internet. Moreover, semi-structured interviews are conducted as data collection in this

study to gain information from the design team on current BIM implementation in

project design stage.

The final stage, stage three is divided into four (4), which are data analysis,

results and findings, model development, conclusion and recommendations. All data

gained from semi-structured interviews with design team are analysed using content

Page 25: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

10

analysis. Both data from literature review and semi-structured interview were used for

the purpose of model development. The content analysis view data representation

through texts, images and expressions (Krippendorff, 2012).

Microsoft excel is used to assist researchers in analysing all the data.

Conclusion and recommendation are the last chapter in this thesis. The conclusion

summarised all chapters in this thesis. Meanwhile, recommendations are produced

based on limitation to fulfil this study and recommendations made by the researcher

in order to improve this research in the future. Details of research methodology process

were discussed in Chapter 3.

1.9 Research Organisation

The research consists of six (6) main chapters. The chapters are as follows:

(i) Chapter 1: Introduction

This chapter consisted of introduction to research, background of research,

problem statement, research questions, research objectives, scope of research,

significance of research, research methodology, research organisation and

summary of the chapter.

(ii) Chapter 2: Literature Review

Chapter 2 contained of literature reviews on construction project design stage

and BIM. All information in this chapter consisted of introduction to

construction project design stage; construction players in project design stage

and issues on project design. This chapter also discussed on BIM in construction

projects; definitions of BIM; implementation of BIM in the Malaysia

construction industry; application of BIM in project design; tools; benefits;

challenges to implementing BIM; future development of BIM in the construction

industry and BIM adaptation in project design stage. Apart from that, this chapter

also discussed about model development technique, which are related to BIM

and construction field. The discussion contained of examples of model related

to research model, similarities between the model and selection of maturity level

Page 26: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

11

for the research model. This chapter end with explanations on theoretical

framework and summary.

(iii) Chapter 3: Research Methodology

Chapter 3 discussed on research approaches, research strategies and data

collection method. This is followed by methodology adopted for the research

and discussion on each adopted approaches, methods used for data collection

and data analysis.

(iv) Chapter 4: Results and Findings

This chapter consisted of findings from semi-structured interviews with the

design team. Moreover, this chapter focused on current BIM practices in project

design stage among design team. The trends of BIM implementation in project

design stage are explored, which include BIM implementation in project design

stage, effects of BIM implementation in project design stage, challenges of BIM

implementation in project design stage and potential improvements of BIM

implementation in project design stage.

(v) Chapter 5: BIM Implementation Model For Design Team

This chapter presented the establishment of the proposed model for this research.

The establishment of the model was developed based on data gained from

literature review and semi-structured interviews with design team. It discussed

the model development process, starting from its design and followed by a

description of the model. This chapter also explained the main features and

content of the model.

(vi) Chapter 6: Conclusion and Recommendations

The main conclusion is drawn out in this chapter and the limitations of the

research are highlighted. It revealed the finding and suggested recommendations

for future research and it ended with a concluding remark.

Page 27: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

12

1.10 Summary

This chapter has presented the main issues of BIM implementation in project design

stage and justification for the need of research on BIM in project design stage. The

aim and objectives of the research are stated in this chapter. This chapter also explored

about the research planning and methodology used in this study. The structure of this

study is presented at the end of the chapter.

The next chapter focused on literature review related to project design stage,

BIM and model related to BIM and construction field.

Page 28: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

CHAPTER 2

LITERATURE REVIEW

2.1 Introduction

This chapter discussed on application of BIM in project design stage. It consisted of

introduction to construction project design stage, BIM in construction projects; its

definitions, history and the implementation in the Malaysia construction industry.

Furthermore, this chapter also explained on BIM application, BIM tools, it benefits to

construction projects, challenges to implementing BIM, future of BIM in the

construction industry and adaptation of BIM in project design stage. Moreover, models

development technique, which related to BIM and construction field are also discussed

in this chapter. Discussion on those elements is important to identify current practices

of BIM implementation in project design stage and development of model that could

assist construction players to implement BIM in project design stage.

2.2 Construction Project Design Stage

Construction project is symbolising social, cultural and technological development. It

consists of numerous people, activities and requirements to fulfil client goals (NCCER,

2008; Jackson, 2010). A construction project can be divided into three (3) main stages,

which are pre-construction, construction and post-construction (Cooper et al., 2005;

Kazi, 2005; NCCER, 2008; Charted Institute of Building (CIOB), 2010). Figure 2.1

shows the construction project process.

Page 29: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

14

Pre-construction StageConstruction

Project Stage

Activity

· Project Design

· Project scheduling

· Cost Estimating

· Site Coordination

· Managing Materials

and Machineries

Construction Stage

· Excavation of

Foundation

· Framing

· Roofing and Siding

· Plumbing and

Heating

· Electrical Work

· Interior Finishes

Post-construction Stage

· Final Inspection and

Acceptance

· Project Close Out

· Owner Move In

· Warranty

· Project Evaluation

Figure 2.1: Construction Project Process (Adopted from: Cooper et al., 2005; Kazi,

2005; NCCER, 2008; CIOB, 2010)

Based on the figure, project design is the first activity in pre-construction stage.

According to Eastman et al. (2011) and Memon et al. (2011), project design is

considered as an important activity in construction projects. Project design has been

produced by construction players in project design stage. Eastman et al., (2011) also

mentioned that, project design is an activity, which consists of all information

regarding a construction project. The information are such as project size, cost and

building elements. Figure 2.2 shows the main activities in project design stage.

Figure 2.2: Activities in Project Design Stage (Adopted from: Klinger and Susong,

2006; Autodesk, 2008; Jackson, 2010; Crotty, 2012)

There are four (4) main activities in project design stage shown in Figure 2.2,

which are programming and feasibility which also known as conceptual design,

schematic design, design development as well as construction document or also known

as detail design (Klinger and Susong, 2006; Autodesk, 2008; Jackson, 2010; Crotty,

2012). Details on each activity are as follows:

(i) Programming and Feasibility Study

Programming and feasibility study are usually done prior to the design process. It also

known as conceptual design process (Weiler and Scholz-Barth, 2009). The

Programming and Feasibility

Study

Schematic Design

Design Development

Construction Document

Page 30: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

15

information that comes out during this stage is the project size, number of rooms, the

use of each space and requirement for each function (Autodesk, 2008; Jackson, 2010).

According to Jackson (2010), client is responsible to brief the architect regarding his

or her needs and expectation to the project. Moreover, client also needs to clarify about

his or her project’s budget to architect (Autodesk, 2008; Jackson, 2010). The

information on project budget is important because architect is responsible to carry out

the project design based on client needs and budget (McCarthy, 2007; Jackson, 2010).

(ii) Schematic Design

Schematic design also called as preliminary design, serves to establish the general

scope of project, conceptual design, scale and relationships among the component of

a project (Klinger and Susong, 2006; American Institute of Architect (AIA), 2009).

Moreover, the objective of schematic design is to arrive at a clearly defined, feasible

concept and to present all the information in a form that achieve client understanding

and acceptance (Hess et al., 2007; AIA, 2009; Autodesk, 2008).

Furthermore, schematic design information can be used to demonstrate basic

spaces, scale and relationship of each building components (AIA, 2009; Autodesk,

2008). Typically documentation at the end of schematic design will include several

important items such as site plan, plans for each level, all elevations, key sections,

outline specification, statistical summary of design area as well as other characteristics

in comparison to the programme, a preliminary construction cost estimate, and

illustrative of materials (Hess et al., 2007; AIA, 2009; Autodesk, 2008).

An architect will develop project design, which consist of several information

such as a preliminary site plan, exterior elevation, floor plan and building sections

(Klinger and Susong, 2006; Hess et al., 2007). The project design will contain only

approximate dimensions. As part of schematic design process, architect may agree to

provide services such as lifecycle cost analysis, energy studies, economic feasibilities

studies, special rendering, models, brochures and promotional materials for the client.

However, it is depends on client-architect agreement on ‘additional services’ where

stated in American Institute of Architects (AIA) B201 form client-architect agreement

form (AIA, 2009). AIA B201 is a document, which defines the architect’s traditional

scope of services for design and construction contract administration in a standard

form that client and architect can modify to suit the needs of the projects (AIA, 2009).

Page 31: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

16

According to Klinger and Susong (2006), schematic design is only present 20

per cent of design effort. Client has to review and leave comments toward the design

produced by architect after completion of this stage. The architect needs to obtain

formal client approval in writing as prove or evidence that the client had agreed with

the design (AIA, 2009).

(iii) Design Development

Design development is a third activity in design stage. The main objective in design

development is to provide final design of project together with building systems in the

project (AIA, 2009; Autodesk, 2008). Basically, the design development activity will

be continued based on client comment and approval in schematic design. The architect

will develop a detailed site plans, floor plans and building sections. In this stage, others

design team which are structural and MEP engineers will collaborate to complete the

design development. Structural engineer will produce detail drawings regarding

building structural, building specifications, type of materials, and design sections.

Meanwhile, MEP engineer will produce detail drawing regarding electrical,

mechanical and plumbing system for a building. All the detailed drawing will be

referred to drawings, which have been produced by architect. The architect drawing is

the baseline to structural and MEP engineer detail drawings (Klinger and Susong,

2006; AIA, 2009).

The deliverables of the design development stage is similar to those of schematic

design (AIA, 2009). This stage is important to allow the preparation of a preliminary

construction estimate. Apart from that, the primary purposes of design development is

to further define and describe all important aspects of the project so that what remains

is the final step of creating construction documents (AIA, 2009). Klinger and Susong

(2006) stated that design development only present 50per cent of design effort. The

client will review and leave he or her comments regarding the project design (AIA,

2009).

(iv) Construction Document

Construction document stage starts after obtained the client approval on design

development. The approved design development will become a firm foundation for the

construction document stage (Reiling, 2007). Construction document stage is the stage

Page 32: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

17

which the architect, structural and MEP engineers focus on the preparation of

throughout drawings and specifications that will issue for bidding and construction of

project (Reiling, 2007; AIA, 2009).

At this stage, design team has to finalise the project design (Hess et al., 2007;

AIA, 2009; Autodesk, 2008). A construction document consist a set of complete

drawing and accurate dimension of site plan, floor plan and elevations. The elevations

also include complete information regarding detail selection of materials, complete

mechanical, electrical, lighting, foundation, as well as structural drawings (Klinger and

Susong, 2006; AIA, 2009; Jackson, 2010).

The construction document also needs to be reviewed and approved by the client.

After obtained client’s approval, the bidding tender will begin. Construction document

is important to contractor in preparing accurate cost estimate for the project. Moreover,

construction project will be constructed by the contractor based on information in in

construction document. According to Klinger and Susong (2006), construction

documents are the 100 per cent drawings for a project.

Basically, there are several construction players involved in managing project

design, which are client, architect, structural engineer, MEP engineers and contractor.

They are also known as design team (Klinger and Susong, 2006; Winch, 2010; Levy,

2010). Figure 2.3 shows the design team.

Figure 2.3: Design Team (Adopted from: Klinger and Susong, 2006; Winch, 2010;

Levy, 2010)

According to Klinger and Susong (2006), Winch (2010) and Levy (2010), client

can be divided into two (2), which are public sector and private sector. Meanwhile,

Design Team

Client

Architect

Structural Engineer

Mechanical, Electrical and Plumbing (MEP) Engineers

Contractor

Page 33: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

18

contractor consists of main contractor and sub-contractor. The design team is

responsible to manage project design in order to increase project quality and avoid

construction problems. Details on each design team are now discussed.

(i) Client

Client is the driving force behind the construction industry. According to Lock (2003)

and Winch (2010), client is a person who has capital and desire to execute a project.

Client is divided into two (2) different sectors, which are public and private sectors.

Public sector consists of ministries, local authorities and statutory boards. The

examples of ministries are Ministry of Education (MoE), and Ministry of Public Work.

Local authorities are Public Work Department (PWD), and Urban Utilities. Examples

of statutory board are Construction Industry Development Board (CIDB), and Board

of Engineers (BOE). Public sector is responsible to provide free services to citizen.

The examples of free services are such as road, hospitals, post-offices and schools

(Kamara, Anumba and Evbuomwan, 2002; Winch, 2010).

Private sector or also known as non-government sector is a client that uses its

own capital to develop own projects (Jackson, 2010). Basically, this type of client will

rent their building to obtain capital and profits.

The roles of client in construction projects are to identify project needs, monitor

project progress and prepare project cost. Basically, client will appoint consultants

(architect, structural engineer and MEP engineer) to manage he or her construction

projects. However, client also deserves to monitor the entire project progress to ensure

the project runs smoothly (Abdullah, 2001; Winch, 2010).

(ii) Architect

Architect is a licensed professional trained in the art and science of project design. An

architect is responsible to transform client’s programme into concept and develop the

concept into building images and plans that can be constructed by contractor (Jackson,

2010). Architect also responsibles to prepare design documentations and monitor

design team works progress (Gahlot, 2002; Uher and Loosemore, 2004; Winkler and

Chiumento, 2009). An architect also serves as client representative to monitor

construction process during construction and post-construction stage (AIA, 2009).

Other roles of an architect are to:

Page 34: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

19

(a) develop schematic, preliminary and final designs (Gahlot, 2002; Uher and

Loosemore, 2004; Winkler and Chiumento, 2009).

(b) coordinate design activities of other designers (structural engineer and MEP

engineers). (Gahlot, 2002; Uher and Loosemore, 2004; Winkler and

Chiumento, 2009).

(c) prepare tender documentation in the form of working drawings and

specification (AIA, 2009).

(d) revise contract documentation (AIA, 2009).

(e) assist in resolving design-related problems (AIA, 2009).

(f) assist in controlling quality of construction projects (AIA, 2009).

(iii) Structural Engineer

Structural engineer is responsible to plan and prepare structural design for a project

(Levy, 2010). Structural engineer is responsible to prepare structural working drawing

or details design based on architect drawing (Gahlot, 2002; Levy, 2010). The roles of

structural engineer are as follows:

(a) A design structure was created to withstand stresses and pressures such as

weather and human use. A structural engineer needs to ensure that building

structures are not bending, twist and collapse because it can cause to project

delay, increase construction cost, and accident on site (Gahlot, 2002; Levy,

2010).

(b) Choose the appropriate materials, such as bricks, concrete and steels to meet

the design specification (Gahlot, 2002; Levy, 2010).

(c) Collaborate with other construction players such as architect to discuss on

safety design and aesthetic concepts of construction (Gahlot, 2002; Levy,

2010).

(iv) Mechanical, Electrical and Plumbing (MEP) Engineers

MEP engineers are responsible to prepare mechanical, electrical and plumbing design.

However, MEP engineers will produce their design based on their discipline.

Mechanical engineer is responsible to design the heating, ventilation, and air-

conditioning (HVAC) system within a building (Gahlot, 2002; Jackson, 2010; Levy

Page 35: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

20

2010). Other roles of mechanical engineer are as the following (Gahlot, 2002; Jackson,

2010; Levy 2010):

(a) Provide structural engineer with the layout of underground utilities, which

include pipe sizes, types and specifications.

(b) Confer with structural engineer to ensure that building structure and roof will

have sufficient structural integrity to support the weight of equipment being

designed.

(c) Confer with architect to ensure that sufficient spaces are allocated for

equipment installation and for routine maintenance to take place.

(d) Provide structural engineer with size and location of floor penetrations required

for HVAC, plumbing, electrical ductwork, and conduit that extends from floor

to floor.

An electrical engineer is in-charge to design and prepare working drawing or

details design for electrical power and distribution systems during and after

construction process (Gahlot, 2002; Levy 2010). Other roles of electrical engineer

mentioned by Gahlot (2002) and Levy (2010) are as follows:

(a) Supervise electrician in handling electrical works and considering the safety

and quality requirement.

(b) Involve in preparing electrical design starting from concept and detail design,

implementation, testing and handover.

(c) Researching suitable solutions for electrical ducting and estimating costs for

whole electrical projects and timescale of a project.

(d) Collaborate with other construction players such as clients, architect, QS and

contractor to detect design clashes between electrical, structural, and

mechanical designs.

A plumbing engineer is in-charge to perform calculations on each size of

plumbing equipment, prepare plumbing design, and construction document related to

plumbing installation (Gahlot, 2002; Levy 2010). A plumbing engineer works under

the supervision of mechanical, fire protection, and professional engineers. The role of

plumbing engineer is to design the building primary plumbing equipment such as water

tank, pumps, and fixtures (Boswell, 2013). According to Gahlot (2002), Levy (2010),

Page 36: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

21

and Whole Building Design Guide (WBDG) (2013), other roles of plumbing engineer

are as the following:

(a) Prepare design process of fluid flow system. The process is important to

facilitate piping installation during construction stage.

(b) Design plumbing system. Plumbing system requires proper design and follows

official plumbing code and ensuring code compliance.

(c) Advice on ideal location and capacity for treatment plan, septic tank, sump,

and general direction in which waste is to be disposed depending on

topography of the land, road and public sewer location.

(d) Prepare a schematic plumbing layout and details specification for the entire

plumbing works.

(v) Contractor

Contractor is a party who perform and complete a project based on tender contract. A

contractor is responsible to plan, control, manage, and coordinate construction works

to make sure that risks such as project delay and cost overrun could be avoided (Mosey,

2009; Health and Safety Execution (HSE), 2013). There are two (2) types of

contractor, which are main contractor and subcontractor. The role of main contractor

is to provide the total scope of works required in the contract. The main contractor

must also control and coordinate all necessary production activities during

construction stage. Subcontractor is responsible to manage tasks given by the main

contractor (Boyle, 2003; Towey, 2012). Other roles of contractor in a construction

project are as the following (Mosey, 2009; HSE, 2013):

(a) Plan, manage, and monitor the entire project process to avoid construction

problems during construction stage.

(b) Provide labours and subcontractors to accomplish construction works. Labour

need to accomplish construction works according to project drawing.

Subcontractors need to accomplish construction works according to main

contractor instruction.

(c) Supervise labours and provide materials and equipments for construction

works.

Page 37: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

22

As a conclusion, design team are responsible to manage project design. The

cooperation among them is important in order to avoid construction problems.

According to Sambasivan and Soon (2007), Forbes and Ahmed (2011) and Kikwasi

(2013), low design constructability is one of factors contribute to several construction

problems such as low of construction productivity, low of project quality, project

delay, construction cost overrun and disputes among construction players (Sambasivan

and Soon, 2007; Forbes and Ahmed, 2011; Kikwasi, 2013). The factor contributes to

construction problems need to be explored in order to avoid it during managing

construction projects. Other factors contribute to construction problems, which are

related to project design, are specified in Figure 2.4.

Contribute to construction problems such as:

· Low of construction

productivity · Project delay

· Low of project

quality

· Construction cost

overrun

· Disputes among

construction players

Project Design Issues

· Design changes · Design clashes · Poor design constructability · Poor 2-dimensional (2D)

drawing

Solution

· Building Information Modelling (BIM) implementation in project design stage

Figure 2.4: Project Design Issues (Adopted from: Sambasivan and Soon, 2007;

Forbes and Ahmed, 2011; Kikwasi, 2013)

Based on Figure 2.4, there are four (4) factors that contribute to construction

problems which are changes in project design, design clashes, poor design

constructability and poor 2D drawings. Details on each factor are as follows:

(i) Changes in project design

(a) Changes mean modifications of an original contract that effectively change

the provision of contract, changes in design specifications, method of

performance, facilities, equipment, materials, site and completion of work.

All changes made must be recorded through letter confirming and

approved by client, architect as well as engineers. Any changes in design

during construction stage will effect to project delay, construction cost

Page 38: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

23

overrun and disputes among construction players (Emmitt and Yeomans,

2008; Emmitt and Ruikar, 2013).

(ii) Design clashes

(a) Basically, design clashes occur between architectural, structural and MEP

designs. It happened when one of the designs has not been monitored

properly after the designs changes. The design errors or clashes were high

risk and only can be detected by contractor during the construction stage

of the project (Wang et al., 2013). The contractor will seek any solution,

direction and resolution from the architect or engineers with RFI. The

architect and engineer will provide a response that may or may not affect

the project cost or schedule (McCarthy, 2010). However, late respond to

RFI issues by contractor can cause to project delay.

(iii) Poor design constructability

(a) Constructability means prime use of construction knowledge and

experiences in planning, design, procurement and field operation in order

to achieve construction project objectives. Lack of design constructability

is caused to construction cost overrun and quality of end product issues

faced by the construction industry (Gambatese, Pocock and Dunston,

2007). Moreover, design clashes among the design disciplines (architect,

structural and MEP designs) are difficult to identify and analyse. This

problem can cause to low construction productivity and low of project

quality (Haron, 2013).

(iv) Poor of 2D drawing

(a) Traditionally, project design will be produced by using computer aided

design (CAD) system. The drawing will come out in 2D concept where the

use of 2D drawing was difficult to be understood (Lee et al., 2003; Haron,

2013). These problems also lead to insufficient drawing and specification.

In order to avoid all the construction problems, ICT has introduced building

information modelling (BIM) to overcome construction problems (Forbes and Ahmed,

2011; Crotty, 2012). BIM is an emerging technology, which can improve

Page 39: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

24

performances and productivities of design, construction, operation and maintenance

process (Love et al., 2013). It can be applied in construction projects to manage

construction projects stages appropriately especially project design stage. Moreover,

the use of BIM in project design stage increases accuracy in preparing schematic

design, design development and construction documentation.

2.3 Building Information Modelling (BIM)

Building Information Modelling (BIM) is used by construction players to increase

efficiency and effectiveness in managing construction projects. It is known as an

approach to manage construction projects with relief from several set of tools such as

Autodesk Revit, Tekla, Vico Office, ArchiCAD and Bentley System (Robinson, 2007:

Forbes and Ahmed, 2011; Monteiro and Martins, 2013). The used of the tools help

construction players to manage construction projects by detecting common problems

occur during construction stage such as design clashes, design changes and incomplete

design specifications (Kymmell, 2008).

BIM has been utilised in construction projects to manage the continuous and

availability of construction projects activities. The activities are design, cost

estimating, project scheduling, site coordination and facilities management

(Barrington, 2010; Eastman et al., 2011; Succar, 2013). Moreover, BIM

implementation in construction projects can avoid project delay, construction cost

overrun and disputes among construction players, which are client, consultants and

contractors (Smith and Tardif, 2009; Forbes and Ahmed, 2011).

The AEC industry in USA, Australia, Finland and HK have expressed their

interest in adopting BIM as a tool to manage construction projects (Azhar, 2011;

Forbes and Ahmed, 2011; Eastman et al., 2011; Levy, 201). The first impression of

BIM implementation can be seen through project design stage where BIM has

improved design management tools in the AEC industry from 2D to 3-dimensional

(3D) (Yan and Damian, 2008). Others than that, BIM provides many benefits to

construction players. The benefits are detecting design clashing, increases accuracy in

cost estimating, project scheduling, and improves communication as well as

collaboration between construction players (Forbes and Ahmed, 2011; Reddy, 2012).

Page 40: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

REFERENCES

Abdul-Rahman, H., Berawi, M. A., Berawi, A. R., Mohamed, O., Othman, M., &

Yahya, I. A. (2006). Delay mitigation in the Malaysian construction industry.

Journal of Construction Engineering and Management, 132(2), 125-133.

Abdul Azis, A. A., Memon, A. H., Rahman, I. A., Latif, Q. B. A. I., & Nagapan, S.

(2012, September). Cost management of large construction projects in South

Malaysia. In Business, Engineering and Industrial Applications (ISBEIA), 2012

IEEE Symposium on (pp. 625-629). IEEE.

Abdullah, S. A., Sulaiman, N., Ahmad Latiffi, A., & David, B. (2014). Building

information modeling (BIM) from the perspective of facilities management

(FM) in Malaysia.

Abdullah, N. A. (2001). Pengenalan kepada Kontrak Pembinaan. Malaysia. Universiti

Teknologi Mara.

Ahmad Latiffi, A., Carrillo, P. M., Ruikar, K., & Anumba, C. J. (2010). Improving

performance measurement practices in construction organisations. Retrieved

July 7, 2015 from https://dspace.lboro.ac.uk/2134/11305.

Ahmad Latiffi, A., Carrillo, P. M., Ruikar, K., & Anumba, C. J. (2012). Development

of Performance Measurement Migration Path For Construction Organisations.

Third International Conference on Construction In Developing Countries

(ICCIDC–III) “Advancing Civil, Architectural and Construction Engineering &

Management” July 4-6, 2012 Bangkok, Thailand.

Ahmad Latiffi, A., Mohd, S., Kasim, N. & Fathi, M. S. (2013). Building Information

Modeling (BIM) Application in Malaysian Construction Industry. International

Journal of Construction Engineering and Management 2(4A), pp.1-6.

Page 41: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

159

Ahmad Latiffi, A., & Mohd, S. (2014). Building Information Modeling (BIM)

Technology In The Sultan Ibrahim Hall of UTHM. 2014 IEEE Colloquium on

Humanities, Science and Engineering (CHUSER 2014).

Ahmad Latiffi, A., Brahim, J., & Fathi, M. S. (2014). The Development of Building

Information Modelling (BIM) Definition. Applied Mechanics and Materials Vol.

567 (2014) pp 625-630. Online available since 2014/Jun/06 at

www.scientific.net © (2014) Trans Tech Publications, Switzerland

doi:10.4028/www.scientific.net/AMM.567.625.

Ahmad Latiffi, A., Mohd, S., & Brahim, J. (2014). Application of Building

Information (BIM) in the Malaysian Construction Industry: A story of the First

Government Project. Applied Mechanics and Materials, ISSN: 1660-9336.

Ahmad Latiffi, A., Brahim, J., Mohd, S., & Fathi, M. S. (2014). Building Information

Modelling (BIM): Exploring Level of Development (LOD) in Construction

Projects. Applied Mechanics and Materials, ISSN: 1660-9336.

Alaghbari, W. E., Kadir, M. R. A., & Salim, A. (2007). The significant factors causing

delay of building construction projects in Malaysia. Engineering, Construction

and Architectural Management, 14(2), 192-206.

America with Disabilities Act guidelines (ADA), (2010). Guidance on the 2012 ADA

Standards for Accessible Design. Retrieved July 20, 2013 from

http://www.ada.gov/regs2010/2010ADAStandards/Guidance2010ADAstandar

ds.htm

American Institute of Architects (AIA). (2009). The American Institute of Architects

Official Guide to the 2007 AIA Contract Documents. John Wiley & Sons.

Anfara, V. A. & Mertz, N. T. (2014). Theoretical Framework in Qualitative Research.

United States of America: SAGE Publications, Inc.

Aouad, G., Lee, A. & Wu, S. (2007). Constructing the Future nD Modelling. New

York: Taylor & Francis.

Page 42: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

160

Architectural Research Lab (ARL). (2012). History of BIM. Retrieved March 11,

2013, from http://www.architectureresearchlab.com/arl/2011/08/21/bim-

history/.

Arayici, Y., Khosrowshahi, F., Ponting, A. M. & Mihindu, S. (2009). Towards

Implementation of Building Information Modelling in the Construction Industry.

International Conference on Construction, pp. 29-34.

Arayici, Y., Egbu, C. O., & Coates, P. (2012). Building information modelling (BIM)

implementation and remote construction projects: issues, challenges, and

critiques. Journal of Information Technology in Construction, 17, 75-92.

Appa, G. M., Pitsoulis, L. & Williams, H. P. (2006), Handbook on Modelling for

Discrete Optimization. POME.

Autodesk. (2007). BIM Communication, Specification. United States of America:

Autodesk, Inc.

Autodesk (2008). Autodesk BIM Communication Specification. United stated

America. Autodesk, Inc. Retrieved March 28, 2013,

fromhttp://au.autodesk.com/?autodownload=../orig/class_questions/thread__13

56/AutodeskAEC---Communication-Sp ecification-FINAL.pdf.

Autodesk. (2013). 3D Design, Engineering and Entertainment Software. Retrieved

August 2, 2013, from http://www.autodesk.com.my/.

Ashcraft, H. W. (2008). Building Information Modelling: A Framework for

Collaboration. Construction Lawyer, vol. 28.

Athanasiou, T., Debas, H. & Darzi, A. (2010). Key Topic in Surgical Research and

Methodology. New York: Springer.

Azhar, S., Hein, M., & Sketo, B. (2008, April). Building information modeling (BIM):

Benefits, risks and challenges. In Proceedings of the 44th ASC National

Conference.

Page 43: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

161

Azhar, S., Nadeem, A., Mok, J. Y. N. and Leung, B. H. Y. (2008) Building Information

Modeling (BIM): A new paradigm for visual interactive modeling and

simulation for construction projects. In Proc., First International Conference on

Construction in Developing Countries, pp. 435-446.

Azhar, S. (2011). Building Information Modeling (BIM): Trends, Benefits, Risks, and

Challenges for the ACE Industry. Leadership and Management in Engineering,

11, pp. 241-252.

Azhar, S., Khalfan, M., & Maqsood, T. (2012). Building information modelling

(BIM): now and beyond. Australasian Journal of Construction Economics and

Building, 12(4), 15-28.

Azis, A. A. A., Memon, A. H., Rahman, I. A., Latif, Q. B. A. I., & Nagapan, S. (2012,

September). Cost management of large construction projects in South Malaysia.

In Business, Engineering and Industrial Applications (ISBEIA), 2012 IEEE

Symposium on (pp. 625-629). IEEE.

Babbie, E. (2013). The basics of social research. Cengage Learning.

Barbour, R. (2007). Introducing Qualitative Research: A Student’s Guide to the Craft

of Doing Qualitative Research. Sage Publications.

Barrington, S. (2010) “Guide to BIM,” Barringtonarc, Barrington Architecture and

Design Ltd, 2010.

Barlish, K., & Sullivan, K. (2012). How to measure the benefits of BIM: A case study

approach. Automation in construction, 24, 149-159.

Becker, J., Knackstedt, R., & Pöppelbuß, D. W. I. J. (2009). Developing maturity

models for IT management. Business & Information Systems Engineering, 1(3),

213-222.

Becerik-Gerber, B., & Rice, S. (2010). The perceived value of building information

modeling in the US building industry. Journal of information technology in

Construction, 15(2), 185-201.

Bethlehem, J. & Biffignandi, S. (2011). Handbook of Websurvey. New Jersey: John

Wiley & Son, Inc.

Page 44: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

162

Bentley System (2013). Building Information Modelling. Retreived April 29, 2013,

from http://www.exactal.com/.

Bentley System. (2015). Building Information Modelling. Retreived April 29, 2015,

from http://www.bentley.com/en-US/.

Bloomberg, M. R., Burney, D. J. & Resnick, D. (2012). BIM Guidelines. New York:

New York Department of Design and Construction.

Boswell, K. (2013). Exterior Building Enclosures: Design Process and Composition

for Innovative Facades. John Wiley & Sons.

Boyle, T. (2003). Design principles for authoring dynamic, reusable learning objects.

Australian Journal of Educational Technology, 19(1), 46-58.

Brown, T., Suter, T., & Churchill, G. (2012). Basic Marketing Research. Cengage

Learning.

Bryde, D., Broquetas, M., & Volm, J. M. (2013). The project benefits of building

information modelling (BIM). International Journal of Project Management,

31(7), 971-980.

Bryman, A. (2004). Social Research Methods. 2nd edition. Oxford: Oxford University

Press.

Bryman, A. & Bell, E. (2007). Business Research Methods. 2nd edition. Oxford:

Oxford University Press.

Bryman, A., & Bell, E. (2011). Business Research Methods 3e. Oxford university

press.

Bryman, A. (2012). Social Research Methods. 4th edition. Oxford: Oxford University

Press.

Building and Construction Authority (BCA). (2013). Technology Adoption: Building

Information Model (BIM) Fund (ENHANCED). Retrieved March 10, 2013 from

http://www.bca.gov.sg/BIM/bimfund.html

Page 45: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

163

Butcher, D. C. A. and Sheehan, M. J. (2010), “Excellent contractor performance inthe

UK construction industry”, Engineering, Construction and

Architectural Management, 17(1), 35-45.

Cadalyst. (2013). Computer Aided Design and Related Software. Retrieved August

13, 2013, from http://www.cadalyst.com/aec.

Carter, G., & Smith, S. D. (2006). Safety hazard identification on construction projects.

Journal of Construction Engineering and Management, 132(2), 197-205.

Chambliss, D. F., & Schutt, R. K. (2012). Making sense of the social world: Methods

of investigation. Sage.

Chappell, D. (2007). The JCT Minor Works Building Contractor 2005. 4th edition. UK:

Blackwell Publishing.

Charted Institute of Building (CIOB), (2010). Guide to Good Practice in the

management of Time in Complex Projects. United Kingdom: Blackwell

Publishing.

Chen, Y., Dib, H., & Cox, R. F. (2014). A measurement model of building information

modelling maturity. Construction Innovation: Information, Process,

Management, 14(2), 186-209.

Cheng, J., & Ma, L. (2012). A BIM-based system for demolition and renovation waste

quantification and planning. In Proceedings of the 14th International Conference

on computing in Civil and Building Engineering (ICCCBE 2012), Moskow.

Cheung, F. K., Rihan, J., Tah, J., Duce, D., & Kurul, E. (2012). Early stage multi-level

cost estimation for schematic BIM models. Automation in Construction, 27, 67-

77.

Cho, H., Lee, K.H., Lee, S.H., Lee, T., Cho, H.J., Kim, S.H. & Nam, S.H. (2011).

Introduction of Construction management integrated system using BIM in the

Honam High-speed railway lot No.4-2. Proceedings of the 28th ISARC, Seoul,

Korea.

Page 46: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

164

Construction Management Software (CMS). (2008). Construction Estimating and

Tendering Software–Corporate. Retrieved April 5, 2013 from

http://www.cmscontractor.com/ConstructionSoftware/Estimating.asp

Construction Industry Development Board (CIDB), (2007). Construction Industry

Master Plan Malaysia 2006-2015 (CIMP). Malaysia: Construction Industry

Development.

Construction Industry Development Board (CIDB), (2013a). BIM Portal: Building

Information Modelling. Retrieved November 12, 2013 from

http://bimcenter.com.my/index.php/bim-news.

Construction Industry Development Board (CIDB), (2013b). Retrieved April 5, 2014

from:http://www.cidb.gov.my/index.php?option=com_content&view=article&i

d=553:keynote-address-y-bhg-dato-sri-ir-dr-judin-bin-abdul-karim-chief

executive-cidb-malaysia-for-international-construction-conference-2013&c

tid=50:highlights&Itemid=388&lang=en.

Construction Research Institute of Malaysia, (CREAM). (2012). A Case Study of BIM

Implementation in Malaysia. Retrieved March 10, 2013, from

http://www.myconstructionresearch.com/index.php/publication/integrated-

design-delivery-solution/file/12-bim-implementation-in-malaysia.

Construction Research Institute of Malaysia, (CREAM). (2014). Issues and

Challenges in Implementing Building Information Modeling (BIM) by SME’s

in the Construction Industry. Retrieved February 2, 2014 from

https://www.cidb.gov.my/cidbv3/images/pdf/announcement/BIM/bim%20semi

nar%20%20workshop%20for%20malaysia%20construction%20industry.pdf.

Construction Research Centre (CRC). (2007). Adopting BIM for Facilities

Management: Solutions for Managing the Sydney Opera House. Brisbane,

Australia: Cooperative Research Centre for Construction Innovation.

Construction Users Round Table (CURT, 2010). BIM Implementation: An Owner's

Guide to Getting Started. American Institute of Architects. Retrieved March 16,

2013 from http://www.aia.org/aiaucmp/groups/aia/documents/pdf/

aiab085571.pdf.

Page 47: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

165

Computer Integrated Construction (CIC). (2010). BIM Execution Planning Guide

Version 2.1. Pennsylvania states University.

Cooke, B. & Williams, P. (2009). Construction Planning, Programming and Control.

3rd ed. New Jersey: John Wiley and Son, Inc.

Cooper, R., Aouad, G., Lee, A., Wu, S., Fleming, A. & Kagioglou, M. (2005). Process

Management in Design and Construction. United Kingdom: Blackwell

Publishing.

Cooper, D & Schindler, P. (2008). Business research Method. McGraw-Hill Higher

Education.

Corbin, J. & Strauss, A. (2008). Basic of Quantitative Research 3e. California, USA:

Sage Publications, Inc.

Crawford, J. K. (2007). Project management maturity model. New York: Auerbach

Publications.

Creswell, J. W. (2003). Research Design: Qualitative, Quantitative, and Mixed

Methods Approaches. 2nd edition. California, USA: Sage Publications.

Creswell, J. W. (2007). Qualitative Inquiry and Research Design: Choosing among

Five Approaches. 2nd edition. California, USA: Sage Publications.

Creswell, J. W. (2009). Research Design: Qualitative, Quantitative, and Mixed

Methods Approaches. 3rd edition. California, USA: Sage Publications.

Creswell, J. W. (2012). Qualitative inquiry and research design: Choosing among five

approaches. Sage publications.

Crotty, R. (2012). The Impact of Building Information Modelling: Transforming

Construction. London: SPON Press.

Curtis, B., Hefley, B., & Miller, S. (2009). People Capability Maturity Model (P-

CMM) Version 2.0 (No. CMU/SEI-2009-TR-003). Carnegie-Mellon Univ

Pittsburgh Pa Software Engineering Inst.

Denscombe, M. (2010). The Good Research Guide: For Small-Scale Social Research

Projects: For small-scale social research projects. McGraw-Hill International.

Page 48: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

166

Dore, C. & Murphy, M. (2012). Integration of Historic Building Information Modeling

(HBIM) and 3D GIS for recording and managing cultural heritage sites. In

Virtual Systems and Multimedia (VSMM), 2012 18th International Conference

on (pp. 369-376). IEEE.

Eastman, C. & Henrion, M. (1977). GLIDE: A Language For Design Information

Systems. ACM SIGGRAPH Computer Graphics 11.2 (1977): 24-33.

Eastman, C., Teicholz, P., Sacks, R. & Liston, K. (2008). BIM Handbook: A Guide to

Building Information Modeling for Owners, Managers, Designers, Engineers

and Constructions. 1st ed. New Jersey: John Wiley & Son Inc.

Eastman, C., Teicholz, P., Sacks, R. & Liston, K. (2011). BIM Handbook: A Guide to

Building Information Modeling for Owners, Managers, Designers, Engineers

and Constructions. 2nd ed. New Jersey: John Wiley & Son Inc.

Emmitt, S., & Yeomans, D. T. (2008). Specifying Buildings: A Design Manangement

Perspective. New York. Routledge.

Emmitt, S., & Ruikar, K. (2013). Collaborative Design Management. New York.

Routledge.

Eisenhardt, K. M., & Graebner, M. E. (2007). Theory building from cases:

opportunities and challenges. Academy of management journal, 50(1), 25-32.

Exactal (2013). Cost X your Estimating Solution. Retreived April 29, 2013, from

http://www.exactal.com/

Fallon, K. K. & Palmer, M. E. (2007). General Building Information Handover Guide:

Principles, Methodology and Case Study Studies. United States of America: The

National Institute of Standards and Technology (NIST).

Fallon, K. K. & Palmer, M. E. (2007). General Building Information Handover Guide:

Principles, Methodology and Case Study Studies. United States of America: The

National Institute of Standards and Technology (NIST).

Fellows, R. F. & Lui, A. M. M. (2008). Research Methods for Construction. United

States of America: Blackwell Publishing Ltd.

Page 49: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

167

Fellows, R. F., & Liu, A. M. (2009). Research methods for construction. John Wiley

& Sons.

Fischer, M. & Kunz, F. (2006). The Scope and Role of Information Technology in

Construction. Stanford University: Centre for Integrated Facility Engineering.

Forbes, L. H. & Ahmed, S. M. (2011). Modern Construction Lean Project Delivery

and Integrated Practices. United States of America: Taylor and Francis Group,

LLC.

Furneaux, C. & Kivit, R. (2008). BIM: Implications for Government. CRC for

Construction Innovation. Brisbane Australia: Net Pty Ltd.

Gahlot, P. S. (2002). Construction Planning and Management. India: New Age

International (P) Ltd.

Gambatese, J. A., Pocock, J. B., & Dunston, P. S. (Eds.). (2007). Constructability

concepts and practice. ASCE Publications.

Gould, F. E. (2010). Managing the Construction Process: Estimating, Scheduling and

Project Control. 4th ed. United States of America: Pearson Prentice Hall.

Gould, F. E. & Joyce, N. (2009). Construction Project Management. 3rd ed. New

Jersey: Pearson Education Hall.

Graphisoft. (2013). ArchiCAD. Retrieved August 17, 2013 from

http://www.graphisoft.com/archicad/

Grigg, N. S. (2010). Infrastructure Finance: The Business of Infrastructure for a

Sustainable Future. New Jersey: John Wiley and Son, Inc.

Gill, J. & Johnson, P. (2010). Research Methods for Managers. 4th edition. London:

Sage Publications, Ltd.

Gravetter, F. J. & Forzano, L. B. (2012). Research Methods for the Behavioural

Sciences. 4th edition. USA: Linda Scheiber-Ganster.

Gu, N., & London, K. (2010). Understanding and facilitating BIM adoption in the AEC

industry. Automation in construction, 19(8), 988-999.

Page 50: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

168

Hair, J. F., Sarstedt, M., Ringle, C. M., & Mena, J. A. (2012). An assessment of the

use of partial least squares structural equation modeling in marketing

research. Journal of the Academy of Marketing Science, 40(3), 414-433.

Haron, A. T. (2013). Organisational readiness to implement building information

modelling: A framework for design consultants in Malysia (Doctoral

dissertation, University of Salford).

Health and Safety Execution (HSE). (2013). Using contractors: A brief guide.

Retrieved April 21, 2013, from http://www.hse.gov.uk/pubns/indg368.pdf

Hennink, M., Hutter, I., & Bailey, A. (2010). Qualitative research methods. Sage

Publication.

Hess, S. A., Jerome, V. B., Folk, P. D., & Holt, L. T. (2007). Design professional and

construction manager law. American Bar Association.

Hosseini, M.R., Chileshe, N., Zuo, J. and Baroudi, B. (2012). Approaches for

implementing ICT technologies within construction industry. Australasian

Journal of Construction Economics and Building, Conference Series, 1 (2), pp.

1-12.

Hennink, M., Hutter, I. & Bailey, A. (2011).Qualitative Research Methods. London:

SAGE Publications, Ltd.

HSE Contractors Inc. (2014). BIM Modelling Services. Retrieved June 12, 2013, from

http://www.hsecontractors.com/services/bim-modeling-services

Illingworth, J.R. (2001). Cosntruction Methods and Planning. United States of

America: Taylor & Francis Group, LLC.

International Code Council (ICC), (2007).International Code Council Online Library.

Retrieved June 12, 2013, from http://publicecodes.cyberregs.com/icod/

Isikdag, U. (2012). Design patterns for BIM-based service-oriented architectures.

Automation in Construction, 25, 59-71.

Page 51: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

169

Ishak, I. S & Alias, R. A. (2005).Designing Strategic Information Systems Planning

Methodology for Malaysian Institutes of Higher Learning (ISP-IPTA).

http://iacis.org/iis/2005/Ishak_Alias.pdf

Jabatan Kerja Raya (JKR) (2011). Laporan Tahunan JKR 2011. Retrieved

March 12, 2013, from http://www.jkr.gov.my/var/files/File/dokumen

/laporan_tahunan_jkr_2011.pdf

Jackson, B. J. (2010). Construction Management JumpStart: The Best First Step

Toward a Career in Construction Management. 2nd edition. Canada: Wiley

Publishing, Inc.

Jackson, B. J. (2004). Construction Management JumpStart. Canada: Wiley

Publishing, Inc.

Jayasena, H. S., & Weddikkara, C. (2013, June). Assessing the BIM maturity in a BIM

infant industry. In Proceedings of the Second World Construction Symposium

2013: Socio-Economic Sustainability in Construction (pp. 14-15).

Johnson, R. B. & Onwuegbuzie, A. J. (2004). Mixed Methods Research: A Research

Paradigm Whose Time Has Come. American Educational Research Association.

Johnson, B. & Christensen, L. (2012). Educational Research: Quantitative.

Qualitative, and Mixed Approaches. 4th edition. California, USA: Sage

Publications.

Kadir M. R. A, Lee W. P., Jaafar M. S., Sapuan S. M. & Ali A. A. A. (2005). Factors

affecting construction labour productivity for Malaysian residential projects.

Structural Survey 23 (1), 42-54.

Kazi, A. S. (2005). Knowledge Management in the Construction Industry: A Socio-

technical Perspective. United States of America: Idea Group Publishing.

Klinger, M., & Susong, M. (2006). The construction project: phases, people, terms,

paperwork, processes. American Bar Association.

Kikwasi, G. (2013, February). Causes and effects of delays and disruptions in

construction projects in Tanzania. In Australasian Journal of Construction

Economics and Building-Conference Series (Vol. 1, No. 2, pp. 52-59).

Page 52: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

170

Kymmell, W. (2008). Building Information Modeling: Planning and Managing

Construction Projects with 4D CAD and Simulations. United States of America:

Mc Graw Hill.

Kamara, J. M., Anumba, C. J. & Evbuomwan, N. F. O. (2002). Capturing Client

Requirement in Construction Projects. London: Thomas Telford Publishing.

Khoshnava, S.M., Ahankoob, A., Preece, C. & Rostami, R. (2012). Potential

Application of BIM in Construction Disputes and Conflict. Management in

Construction Research Association (MiCRA) conference. Retrieved March 21,

2013 from http://www.academia.edu/2948039/Potential_Application

_of_BIM_in_Construction_Dispute_and_Conflict

King, W. R. (2009). Knowledge management and organizational learning.US.

Springer US.

Kiviniemi, A., Tarandi, V., Karlshoj, J., Bell, H. & Karud, O. J. (2008). Review of the

Development and Implementation of IFC Compatible BIM. Report for

Government R & D funding organization in the Nordic Countries and the

Netherlands. Retrieved April 20, 2013 from

http://www.sintef.no/upload/Byggforsk/Bygninger/Erabuild%20BIM%20Repo

rt%20January%202008%20-%20Executive%20Summary.pdf.

Kubba. S. (2012). Handbook of Green Building Design and Construction: LEED,

BREEAM, and GREEN GLOBES. United Kingdom: Elsevier Inc.

Krippendorff, K. (2004) Content Analysis: An Introduction to Its Methodology. 2nd

edition. United Kingdom: Sage Publications, Inc.

Krippendorff, K. (2012). Content analysis: An introduction to its methodology. New

York. Sage.

Kumar, R. (2011). Research Methodology: A Step by Step Guide for Beginners. Third

edition. California: SAGE Publication, Inc.

Lee, K. Y., Kim, I. I., Cho, D. Y., & Kim, T. W. (2003). An algorithm for automatic

2D quadrilateral mesh generation with line constraints. Computer-Aided Design,

35(12), 1055-1068.

Page 53: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

171

Levy, S. M. (2010). Construction Process Planning and Management: An Owners

Guide to Successful Projects. America: Elsevier, Inc.

Lock, G. (2003). Using Computers in Archaeology: Toward Virtual Pasts. New York:

Taylor & Francis.

Logiseek. (2013). BIM Clash Detection. Retrieved April 20, 2013 from

http://www.logiseek.com/BIM_clash_detection.php

Love, P. E. D., Simpson, I., Hill, A. & Standing, C. (2013). From Justification to

Evaluation: Building Information Modeling for Asset Owners. Automation in

Construction, In Press.

Lu, W., Peng, Yi., Shen, Q., ASCE, M. & Li, H. (2013). Generic Model for Measuring

Benefits of BIM as a Learning Tool in Construction Tasks. Journal of

Construction Engineering and Management, vol, 139, pp. 195-203.

Lee, G., Sacks, R., & Eastman, C. M. (2006). Specifying parametric building object

behavior (BOB) for a building information modeling system. Automation in

construction, 15(6), 758-776.

Lancaster, G. (2005). Research Methods in Management: A Concise Introduction to

Research in Management and Business Consultancy. Oxford: Elsevier Ltd.

Lehman, C. M. & Dufrene, D. D. (2011). Business Communication. United States of

America: South-Western, Cengage Learning.

Leedy, P. D. & Ormrod, J. E. (2012). Practical Research: Planning and Design.

Pearson Collage Division.

Lockamy III, A., & McCormack, K. (2004). The development of a supply chain

management process maturity model using the concepts of business process

orientation. Supply Chain Management: An International Journal, 9(4), 272-278.

Marrelli, A. F. (2005). The performance technologist's toolbox: Literature

reviews. Performance Improvement, 44(7), 40-44.

McCarthy, R. C. (2007). Managing your library construction project: a step-by-step

guide. American Library Association.

Page 54: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

172

McCarthy, J. F. (2010). Construction Project Management: A Managerial Approach.

USA. Pareto.

Memon, A. H., Abdul Rahman, I., Abdullah, M. R., Aziz, A., & Asmi, A. (2011). Time

overrun in construction projects from the perspective of Project Management

Consultant (PMC). Journal of Surveying, Construction and Property (JSCP),

2(1).

Meng, X., Sun, M., & Jones, M. (2011). Maturity model for supply chain relationships

in construction. Journal of Management in Engineering, 27(2), 97-105.

Mendenhall, M. E., Oddou, G. R., & Osland, J. (2013). Global leadership: Research,

practice, and development. Routledge. Taylor and Francis Group.

MH Government, (2012). Industrial strategy: government and industry in partnership

on BIM. Retrieved December 24, 2013 from

https://www.gov.uk/government/uploads/system /uploads/attachment_data

/file/34710/1 2-1327-building-information-modelling.pdf

Mohamad Kamar, K.A.M, (2012). 8th IBS Roundtable: Mechanisation through

Building Information Modelling (BIM). Retrieved December 20, 2013 from

http://ibsresearch.blogspot.com/2012/01/8th-ibs-rountable-mechanisation-

through.html

Monteiro, A. & Martins, J. P. (2013). A Survey on Modeling Guidelines for Quantity

Takeoff-oriented BIM-based Design. Automation in Construction, pp. 1-16.

Mosey, D. (2009). Early Contractor Involvement in Building Procurement: Contracts,

Partnering, and Project Management. United Kingdom: John Wiley & Son.

Ministry of Urban Wellbeing, Housing and Local Government, (2013). Abandoned

Housing Project. Retrieved July 31, 2013, from

http://www.kpkt.gov.my/kpkt_bi_2013/

Mubarak, S. A. (2010). Construction Project Scheduling and Control. John Wiley &

Sons.

Mujis, D. (2011). Doing Quantitative Research in Education with SPSS.Second

editions. London: SAGE Publication Ltd.

Page 55: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

173

McKenzie, G., Powell, J. & Usher, R. (2005). Understanding Social Research:

Perspective on Methodology and Practice. London: Taylor & Francis e-Library.

Mohd Tobi, S. U. (2012). Research methodological Cage: Understanding the

Qualitative Viewpoint. Malaysia: Aras Publisher.

Mohd, S. & Ahmad Latiffi, A (2013). Building Information Modeling (BIM)

Application in Construction Planning. Seventh International Conference on

Construction in the 21st Century (CITC-VII) “Challenges in Innovation,

Integration and Collaboration in Construction & Engineering” December 19-21,

2013, Bangkok, Thailand.

National Center for Construction Education and Research (NCCER), (2008). Project

Management. New Jersey: Pearson Education, Inc.

National Institute of Building Sciences (NIBS), (2007). United States National

Building Information Model Standard, Version 1. Retrieved May 29, 2013 from

http://www.wbdg.org/pdfs/NBIMSv1_p1.pdf.

National Institute of Building Science (NIBS). (2008). National Building Information

Modeling Standard. Version 1: Overview, Principles and Methodologies.

National Institute of Building Sciences.

Newman, S. L. (2013). Building Information Modeling: Enabling Smart Design,

Construction Facilities Management. Real Estate Institute, Baruch College New

York.

Neville, C. (2007). Introduction to Research and Research Method. University of

Brandford School of Management: Effective Learning Service.

Neuman, W. L. (2004). Basic of Social Research: Qualitative and Quantitative

Approaches. United States of America: Pearson Education, Inc.

Neuman, (2007). Social Research Methods: Qualitative and Quantitative Approaches.

6th edition. Pearson Education.

Naoum, S. G. (2002). Dissertation Research Writing for Construction Students.

Second editions. United Kingdom (UK): Butterworth-Heinemann.

Page 56: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

174

Parasuraman, A., Grewal, D., & Krishnan, R. (2007). Marketing research. Cengage

Learning.

Parmenter, D. (2015). Key performance indicators: developing, implementing, and

using winning KPIs. John Wiley & Sons.

Public Work Department (PWD), (2011). Unit Building Information Modelling

(BIM). Retrieved on December 25, 2013 from:

https://www.jkr.gov.my/prokom/index.php?option=com_content&view=article

&id=84&Itemid=435&lang=ms

Public Work Department (PWD), (2013). BIM Introduction. Retrieved March 12,

2013 from http://www.jkr.gov.my/prokom/index.php?option=com_

content&view=article&id=310&Itemid=476&lang=ms

Patton, M. Q. (2002).Qualitative Research and Evaluation Methods. 3rd edition.

California, USA: Sage Publication.

Polonsky, M. J. & Waller, D. S. (2011). Designing and Managing a Research Project:

A Business Student’s Guide. 2nd edition. California, USA: Sage Publications.

Paulk, M. (1993). Capability maturity model for software. John Wiley & Sons, Inc..

Reddy, K. P. (2012). BIM for Building Owners and Developers: Making a Business

Case for Using BIM on Projects. United States of America: John Wiley & Son,

Inc.

Reiling, J. (2007). Safe By Design: Designing safety in health care facilities, processes,

and culture. Joint Commission Resources.

Robinson, H. S., Carrillo, P. M., Anumba, C. J., & Al-Ghassani, A. M. (2005).

Knowledge management practices in large construction organisations.

Engineering, Construction and Architectural Management, 12(5), 431-445.

Robinson, C. (2007). Structural BIM: Discussion, Case Studies and Latest

Developments. Struct. Design Tall Spec. Build. 16, 519-533. Wiley Interscience.

Retrieved from April 2nd 2013, from http://www.intersciences.willey.com.

Page 57: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

175

Royal Institution of Charted Surveyor (RICS), (2013). RICS Diploma Presentation

Ceremony and CPD Seminar: Current Level of BIM Development in Selected

Counties How Does Malaysia Stack Up? Retrieved December 13, 2013 from:

http://www.ricsasia.org/eventDetail.php?id=630&regionID=0

Royse, D., Thyer, B. & Padgett, D. (2010). Program Evaluation: An Introduction. 5th

edition. Cengage Learning.

Richey, R. C & Klein, J. D. (2007). Design and Development Research: Methods,

Strategies and Issues. United States of America: Lawrence Erlbaum Associates,

Inc. Saunders et al., (2007).

Robson, C. (2002). Real world research: A Resource for Social Scientists and

Pactitioner-researchers. Vol. 2. Oxford: Blackwell Publishing.

Sabol, L. (2008). Building Information Modeling & Facility Management. IFMA

World Workplace, Dallas, Tex., USA.

Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian

construction industry. International Journal of project management, 25(5), 517-

526.

Sears, S. K., Sears, G. A. & Clough, R. H. (2008). Construction Project Management:

A Practical Guide to Field Construction Management. New Jersey: John Wiley

& Son, Inc.

Schmuck, R. A. (2006). Practical action research for change. Corwin Press.

Smith, D. K. & Tardif, M. (2009). Building Information Modeling: A Strategic

Implementation Guide for Architects, Engineers, Constructors, and Real Estate

Asset Managers. United States of America: John Wiley & Son, Inc.

Singh, K. (2009). Organizational Behaviour: Text and Cases. India: Dorling

Kindersley Pvt, Ltd.

Sarcar, M. M. M., Mallikarjuna, K. R. & Narayan, K. L. (2008). Computer Aided

Design and Manufacturing. India: Prentice-Hall.

Page 58: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

176

Steel, J., Drogemuller, R. & Toth, B. (2012). Model Interoperability in Building

Information Modelling. Software System Model (2012) 11:99-109. DOI

10.1007/s10270-010-0178-4.

Succar, B. (2009). Building information Modelling Framework: A Research and

Delivery Foundation for Industry Stakeholders. Automation in Construction.

Vol.18, pp. 357-375.

Succar, B. (2010). Building information modelling maturity matrix. Handbook of

research on building information modelling and construction informatics:

Concepts and technologies, J. Underwood and U. Isikdag, eds., IGI Publishing,

65-103.

Succar, B. (2013). Building Information Modelling: conceptual constructs and

performance improvement tools (Doctoral dissertation, Ph. D. Dissertation,

School of Architecture and Built Environment Faculty of Engineering and Built

Environment, University of Newcastle).

Succar, B., Sher, W. & Williams, A. (2013). An Integrated Approach to BIM

Competency Assessment, Acquisition and Application. Journal of Automation

in Construction.

Saunders, M., Lewis, P. & Thornhill, A. (2007). Research Methods for Business

Students. United Kingdom: Pearson Education.

Sunindijo, R. Y., & Zou, P. X. (2013). Conceptualizing safety management in

construction projects. Journal of Construction Engineering and Management,

139(9), 1144-1153.

Swanborn, P.G. (2010). Case Study Research. London: Sage Publications, Ltd.

Towey, D. (2012). Construction Quantity Surveying: A Practical Guide for the

Contractor’s QS. United Kingdom: Blackwell Publishing.

Tekla (2013). Tekla BIM Software. Retrieved April 29, 2013, from

http://www.tekla.com/international/products/teklatructures/Pages/Default.asp

Tekla Cooperation. (2015). Company Information. Retrieved April 29, 2015, from

http://www.tekla.com/sg/company/about

Page 59: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

177

Trochim, W.M.K. (2006) Research Methods Knowledge Base [online]. Available at

http://www.socialresearchmethods.net/kb/intreval.htm [Retrieved September

29, 2013].

Uher, T. E. & Loosemore, M. (2004). Essentials of Construction Project Management.

Australia: University of New South Wales Press Ltd.

Unit Perancang Ekonomi (2013). Rancangan Malaysia Kesebelas 2016-2020.

Malaysia. Percetakan Nasional Malaysia Berhad.

Vico Software (2013). 5D BIM Construction Software, Virtual Construction.

Retrieved April 23, 2013, from www.vicosoftware.com.

Wang, X., Love, P. E., Kim, M. J., Park, C. S., Sing, C. P., & Hou, L. (2013). A

conceptual framework for integrating building information modeling with

augmented reality. Automation in Construction, 34, 37-44.

Winch, G. M. (2010). Managing Construction Projects. 2nd ed. United States of

America: Blackwell Publishing Ltd.

Winkler, G. & Chiumento, G. (2009). Construction Administration for Architects.

McGraw Hill Professional.

Weiler, S., & Scholz-Barth, K. (2009). Green roof systems: a guide to the planning,

design, and construction of landscapes over structure. John Wiley & Sons.

Weygant, R. S. (2011). BIM Content Development: standard, Strategies, and Best

Practices. New Jersey: John Wiley & Son, Inc.

Whole Building Design Guide (WBDG). (2013). Information Resources and

Technology. Retrieved August 12, 2013 from http://www.wbdg.org/

Yan, H. & Damian, P. (2008). Benefits and Barriers of Building Information

modelling. In 12th International Conference on Computing in Civil and Building

Engineering 2008.

Yusof, A. M., Ismail, S., & Chin, L. S. (2011). Procurement Method as Conflict and

Dispute Reduction Mechanism for Construction Industry in Malaysia. In 2nd

Page 60: i BUILDING INFORMATION MODELLING (BIM) IMPLEMENTATION

178

International Conference on Construction and Project Management.

2011IACSIT Press, Singapore.

Yin, R. K. (2003).Case Study Research Design and Methods.Third editions. United

Kingdom (UK): SAGE Publication, Inc.

Yin, R. K. (2009). Case Study Research: Design and Methods. California, USA: Sage

Publication.

Yin, R. K. (2014). Case study research: Design and methods. Sage publications.

Zakaria, Z., Mohamed-Ali, N., Haron, A. T., Marshall-Ponting, A. & Abd- Hamid, Z.

(2013). Exploring the adoption of Building Information Modelling (BIM) in the

Malaysian construction industry: A qualitative approach. International Journal

of Research in Engineering and Technology, 2(8), 384-395.

Zakaria, Z., Mohamed-Ali, N., Haron, A. T., Marshall-Ponting, A. & Abd- Hamid, Z.

(2014). Exploring the barriers and driving factors in implementing building

Information Modelling (BIM) in the Malaysian construction industry- A

preliminary study. International Journal of The Institution of Engineers,

Malaysia (Vol. 75, No. 1, June 2014).

Zhang, P. (2013). The affective response model: a theoretical framework of affective

concepts and their relationships in the ICT context. MIS Quarterly, 37(1), 247-

274.

Zhang, S., Teizer, J., Lee, J. K., Eastman, C. M., & Venugopal, M. (2013). Building

information modeling (BIM) and safety: Automatic safety checking of

construction models and schedules. Automation in Construction, 29, 183-195.

Zwikael, O. (2009). The relative importance of the PMBOK® Guide's nine Knowledge

Areas during project planning. Project Management Journal, 40(4), 94-103.

Zikmund, W. G. (2003). Business Research Methods. Indiana University: Thomson

South-Western.