I-95/Route 630 Interchange, Alternative E FUNDING (Cumulative) SCHEDULE JULY 2007 JULY 2008 JULY 2009 JULY 2010 JULY 2011 JULY 2012 JULY 2013 JULY 2007

Embed Size (px)

Citation preview

Page 1: I-95/Route 630 Interchange, Alternative E FUNDING (Cumulative) SCHEDULE JULY 2007 JULY 2008 JULY 2009 JULY 2010 JULY 2011 JULY 2012 JULY 2013 JULY 2007
Page 2: I-95/Route 630 Interchange, Alternative E FUNDING (Cumulative) SCHEDULE JULY 2007 JULY 2008 JULY 2009 JULY 2010 JULY 2011 JULY 2012 JULY 2013 JULY 2007

I-95/Route 630 Interchange, Alternative E

Page 3: I-95/Route 630 Interchange, Alternative E FUNDING (Cumulative) SCHEDULE JULY 2007 JULY 2008 JULY 2009 JULY 2010 JULY 2011 JULY 2012 JULY 2013 JULY 2007

FUNDING(Cumulative)

SCHEDULE

JULY2007

JULY2008

JULY2009

JULY2010

JULY2011

JULY2012

JULY2013

JULY2007

JULY2008

JULY2009

JULY2010

JULY2011

JULY2012

JULY2013

$4.5M $7.2M $13.0M $16.2M $22.5M $28.8M

Needed to Complete:

$157M Priorto2007

BeyondJuly 2013

COST IN 2013 DOLLARSPreliminary Engineering $18,000,000Right of Way and Utilities $48,000,000Construction $120,000,000Total $186,000,000

(1994)

Project Funding and Schedule: I-95/Route 630

AUTHOR-IZATION

SCOPING

PRELIM. REVIEW

FIELD INSPECTION

ADVER-TISEMENT

RIGHT OF WAY

Page 4: I-95/Route 630 Interchange, Alternative E FUNDING (Cumulative) SCHEDULE JULY 2007 JULY 2008 JULY 2009 JULY 2010 JULY 2011 JULY 2012 JULY 2013 JULY 2007

I-95/Route 630 Interchange Status Summary

• VDOT will utilize consultants for project development

• VDOT will be seeking a consultant contract in the next few months

• Significant additional funding will be required

• Project will probably be developed in phases

Page 5: I-95/Route 630 Interchange, Alternative E FUNDING (Cumulative) SCHEDULE JULY 2007 JULY 2008 JULY 2009 JULY 2010 JULY 2011 JULY 2012 JULY 2013 JULY 2007

I-95/Route 630 Interchange – additional item

General Discussion:

• Through 2008 and into early 2009 VDOT will be performing additional studies to refine interchange design concepts and right of way footprint.

• An update of the Location Study will follow which will include an the NEPA required Environmental Assessment document and a Public Hearing.

• An interchange modification report will also be developed for FHWA approval to assure adequate performance of the design for future year traffic.

• It is anticipated these activities will be completed by late 2009 or early 2010.