Upload
jessica-kennedy
View
230
Download
5
Tags:
Embed Size (px)
Citation preview
I-95/Route 630 Interchange, Alternative E
FUNDING(Cumulative)
SCHEDULE
JULY2007
JULY2008
JULY2009
JULY2010
JULY2011
JULY2012
JULY2013
JULY2007
JULY2008
JULY2009
JULY2010
JULY2011
JULY2012
JULY2013
$4.5M $7.2M $13.0M $16.2M $22.5M $28.8M
Needed to Complete:
$157M Priorto2007
BeyondJuly 2013
COST IN 2013 DOLLARSPreliminary Engineering $18,000,000Right of Way and Utilities $48,000,000Construction $120,000,000Total $186,000,000
(1994)
Project Funding and Schedule: I-95/Route 630
AUTHOR-IZATION
SCOPING
PRELIM. REVIEW
FIELD INSPECTION
ADVER-TISEMENT
RIGHT OF WAY
I-95/Route 630 Interchange Status Summary
• VDOT will utilize consultants for project development
• VDOT will be seeking a consultant contract in the next few months
• Significant additional funding will be required
• Project will probably be developed in phases
I-95/Route 630 Interchange – additional item
General Discussion:
• Through 2008 and into early 2009 VDOT will be performing additional studies to refine interchange design concepts and right of way footprint.
• An update of the Location Study will follow which will include an the NEPA required Environmental Assessment document and a Public Hearing.
• An interchange modification report will also be developed for FHWA approval to assure adequate performance of the design for future year traffic.
• It is anticipated these activities will be completed by late 2009 or early 2010.