1
DESIGN CONSTRUCTION JULY 30, 2019 Project let for construction FEBRUARY 2019 Public Meeting MAY 17, 2019 PS&E submission received by Engineering Division I-70 BRIDGES Project Timeline 2019 FEB DEC OCT SEP MAR JUNE JULY AUG OCT DEC FEB OCT 2020 2021 2022 OCTOBER 28,2022 PROJECT COMPLETED UPDATED JUNE 2019 Federal Project Number NFA-2317(008) State Project Number S335-70-0.01 00 Stakeholder Advisory Group Meetings SEPTEMBER 1, 2018 Design-Build Bids rejected FEB OCT JUNE 10, 2019 Project Advertised on Bid Express JUNE 3, 2019 PS&E submission received by Contract Administration Fulton WB Bridge Closure Fulton EB Bridge Closure 2018 MAY OCTOBER 16, 2018 Design Kickoff Meeting SEPTEMBER 26, 2018 Design Team received NTP

I-70 BRIDGES Project Timeline...DESIGN CONSTRUCTION JULY 30, 2019 Project let for construction FEBRUARY 2019 Public Meeting MAY 17, 2019 PS&E submission received by Engineering Division

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: I-70 BRIDGES Project Timeline...DESIGN CONSTRUCTION JULY 30, 2019 Project let for construction FEBRUARY 2019 Public Meeting MAY 17, 2019 PS&E submission received by Engineering Division

DESIGN CONSTRUCTION

JULY 30, 2019

Project let for construction FEBRUARY 2019

Public Meeting

MAY 17, 2019

PS&E submission received by Engineering Division

I-70 BRIDGES

Project Timeline

2019

FEBDECOCTSEP MAR JUNE JULY AUG OCT DEC FEB OCT

2020 2021 2022

OCTOBER 28,2022

PROJECT COMPLETED

UPDATED JUNE 2019

Federal Project NumberNFA-2317(008)

State Project Number S335-70-0.01 00

Stakeholder Advisory Group Meetings

SEPTEMBER 1, 2018

Design-Build Bids rejected

FEB OCT

JUNE 10, 2019

Project Advertised on Bid Express

JUNE 3, 2019

PS&E submission received by Contract Administration

Fulton WB Bridge Closure

Fulton EB Bridge Closure

2018

MAY

OCTOBER 16, 2018

Design Kicko� Meeting

SEPTEMBER 26, 2018

Design Team received NTP