39

I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside
Page 2: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

I-64 Southside Widening and

High Rise Bridge Phase 1 Project

Presentation for WTS

Rick Correa, PE, Senior Project Manager

VDOT Hampton Roads District Major Projects

June 17, 2019

Page 3: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

I-64 Southside Widening and High Rise Bridge Phase 1

Hampton Roads District 3

Page 4: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Introduction

• Project Location

• Existing and New

High Rise Bridges

• Project History

• Project Goals

• Project Scope

• Design-Build Contract

and Team

• Design-Build Schedule

• Design-Build Progress

• Design and Construction

Details

• Questions

4

Agenda

Hampton Roads District

Page 5: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Project Location

Hampton Roads District 5

Page 6: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

6

Project Location

Begin Project

End Project

City of Chesapeake:

From: Rotunda Avenue, 0.3 mile east of I-264 interchange at Bowers Hill

To: Battlefield Blvd, 1.0 mile east of the I-464 Interchange

Hampton Roads District

Page 7: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Existing High Rise Bridge

Existing bridge built in 1966

Hampton Roads District 7

Page 8: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Rendering of New High Rise Bridge

Hampton Roads District 8

Page 9: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Construction is Underway!

Hampton Roads District 9

Page 10: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Construction is Underway!

Hampton Roads District 10

Page 11: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• 1995: Hampton Roads Congestion Management System planning

study recommended adding a General Purpose lane in each direction

• 1996: Major Investment Study (MIS) for I-64 Corridor Improvements

from Route 168 (Battlefield Blvd) to Interstate I-264 (Bowers Hill)

• 1997: FHWA issued a Finding of No Significant Impact (FONSI)

• 2007: VDOT and FHWA drafted a Revised EA as part of design

project that advanced to the preliminary design level before it was

canceled due to lack of construction funds

• 2013: VA legislation created the HRTF, which would be administered

by the HRTAC

• 2013: Hampton Roads 2034 Long-Range Transportation Plan

included an environmental study for the I-64 corridor from I-464 to

I-664/264

• Oct 2014: Draft Environmental Assessment approved by FHWA

• Nov 2014: Location Public Hearing was held

Project History

Hampton Roads District 11

Page 12: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Mar 2015: CTB approved location of project (Alternative 2):

Widen I-64 from 4 to 8 lanes, adding 2 managed lanes in each direction

Replace High Rise Bridge with high-level, fixed-span bridge

• Jul 2015: VDOT began phasing study, endorsed by HRTPO

• Jan 2016: HRTPO gave approval to build the project in 2 phases:

Phase 1 Project: Widen I-64 from 4 lanes to 6 lanes; new High Rise

Bridge south of the existing bridge.

Phase 2 Project: Widen I-64 from 6 lanes to 8 lanes; replace existing

High Rise Bridge; I-264, Military Hwy, Rte. 17 and I-464 Interchanges.

• Feb 2016: Started preliminary design and development of design-

build (DB) contract

• Aug 2016: FHWA issued a FONSI

• Aug 2016: Advertised RFQ for DB contractors

• Oct 2016: Design Public Hearing

• Dec 2016: Issued RFP to shortlisted DB contractors

• Nov 2017: NTP to Granite/Parsons/Corman, a JV (GPC)

Project History

Hampton Roads District 12

Page 13: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Increase capacity

• Improve safety

• Enhanced emergency evacuation route

Project Goals

Hampton Roads District 13

Page 14: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Widen 9 miles of I-64 in Chesapeake from 4 lanes to 6 lanes

• Add one HOT lane in each direction

• Add one shoulder lane in each direction from Rte 17 (George

Washington Highway) to Rte 190 (Great Bridge Blvd)

(Adds 4th lane in each direction during peak congestion periods)

• New High Rise Bridge

• Retrofit existing High Rise Bridge for 1-way traffic

• Replace Great Bridge Blvd Bridge

• Widen 6 bridges on I-64

Project Scope

Hampton Roads District 14

Page 15: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Project Scope

0.3 miles east

of I-264

1.0 miles east

of I-464

Hampton Roads District 15

Page 16: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Original Project Budget: $598 Million

Preliminary Engineering

Right-of-Way, Utilities

Final Design and Construction (estimated at $490 Million)

• DB Contract: $410 Million ($80 Million less than estimate)

Largest DB contract in VDOT history (Prior to recent HRBT contract)

Design-Builder – GPC, JV – Granite Construction Co.,

Parsons Construction Co., Corman Kokosing Construction Co.

• Revised Project Budget:

PE $ 12,200,000

RW $ 18,726,000

CN $493,687,765 (Includes $9.6 Million early completion incentive)

$524,613,765

• Funding:

HRTAC: $431,956,220

SMART SCALE (Fed/State): $ 92,657,545

Design-Build Contract and Team

Hampton Roads District 16

Page 17: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Design-Bid-Build Delivery

• Design-Build Project Delivery

Design-Build Contract and Team

Hampton Roads District 17

Page 18: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Design-Build Schedule

Start Prelim. Design

02/19/2016

DB Notice to Proceed

11/17/2017

Start Construction

09/18/2018

Open New HRB

11/21/2020

Final Completion

07/30/2021

- - - - - - - - - - - - - -

Incentive Date

05/07/2021

Hampton Roads District 18

Page 19: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Design-Build Schedule

Hampton Roads District 19

Page 20: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Current Design/Build Progress (Approximation)

• Geotechnical Exploration (927 borings): Completed

• Design (Bridges and Structures): 98%

• Design (Roadway): 100%

• Permits (USACE, DEQ, VMRC, USCG, VPDES): Completed

• Utility Relocations: 60%

• ROW: 80%

• Construction: 10%

Hampton Roads District 20

Page 21: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Roadway Typical Sections

Median > 30’ = Grass, west of Rte. 17

Median < 30’ = Concrete Barrier, east of Rte. 17

Hampton Roads District 21

Page 22: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

HOT Lane Features

I-495 (Capital Beltway) in Northern Virginia

Hampton Roads District 22

Page 23: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Noise Barriers

Project includes about 8 miles of noise barriers

Hampton Roads District 23

Page 24: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Great Bridge Blvd Bridge Replacement

Existing Great Bridge Blvd Bridge (Looking East)

Current View of Great Bridge Blvd Bridge (Looking East)

Proposed Great Bridge Blvd Bridge (Looking East)

Hampton Roads District 24

Page 25: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

I-64 Bridge Widenings

Hampton Roads District 25

Page 26: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Existing and Proposed High Rise Bridges

Hampton Roads District 26

Page 27: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

High Rise Bridge Typical Section

Wide enough for 6 lanes during construction of Phase 2 project

Hampton Roads District 27

Page 28: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

High Rise Bridge Typical Pier

Pier Cap Data:

Width 6 ft

Height 8 ft

Length 85 ft

Volume 150 CY

Weight 300 Tons

Hampton Roads District 28

Page 29: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Channel Unit of High Rise Bridge

Hampton Roads District 29

Page 30: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Channel Unit of High Rise Bridge

Hampton Roads District 30

Steel Girder Erection Sequence of Construction

Page 31: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Fender SystemExisting Fender (Timber) New Fender (FRP and SP)

Hampton Roads District 31

Page 32: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Piles on New High Rise Bridge

• Abutment A: 18” square PS concrete piles – 18 total

• Abutment B: 24” square PS concrete piles – 18 total

• Land & River Piers: 36” square PS concrete piles – 230 total

• River Piers: 66” diam. PS concrete cylinder piles – 86 total

Hampton Roads District 32

Page 33: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

66” Diameter Cylinder Piles

Pile Data:

Diameter 66 inch

Thickness 6.75 inch

Length 90 feet

Volume 30 CY

Weight 60 Tons

Hampton Roads District 33

Page 34: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

Access for High Rise Bridge Construction

• Spans 1-4: Built from land

• Spans 5-8: Built from 700 ft long west temporary trestle

• Spans 9-18: Built from floating barges

• Span 19: Built from 200 ft long east temporary trestle

(trestle also used for material delivery to river)

• Spans 20-37: Built from 2000 ft long temporary access road

Hampton Roads District 34

Page 35: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Total Length 6110 LF (1.2 Miles)

• Width 85 LF

• Total Area 519,350 SF (= area of 11 football fields)

• Maximum Height 113 feet (100 feet clearance over river)

• Number of Spans 37 (Span lengths vary from 140’ to 250’ long)

• Number of Prestr. Concrete Piles 352 (Total length of 25,000 LF, or 4.7 Miles)

• Number of Prestr. Concrete Beams 296 (Total length of 53,580 LF, or 10.1 Miles)(140’ to 196’ long Bulb-Ts)

• Structural Steel 3 Million LBS(3 spans over navigation channel)

• Concrete 70,000 CY

• Rebar 13 Million LBS

High Rise Bridge by the Numbers

Hampton Roads District 35

Page 36: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Total Length of Roadway 41,000 LF (7.8 Miles)

• Asphalt 266,500 Tons

• CTA 68,000 Tons

• Flexible Pavement Planing 301,000 SY

• Excavation 230,000 CY

• Embankment 129,000 CY

• Select Backfill 39,000 CY

• Drainage Pipe 48,000 LF

• Drainage Structures 475 EA

• Noise Wall 750,000 SF

• Major Sign Structures 42 EA

• Sign Panels 14,000 SF

• Guard Rail 92,000 LF

• Barrier 49,000 LF

Roadway by the Numbers

Hampton Roads District 36

Page 37: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Visit the project website – www.64highrise.org

Traffic alerts

Past presentations

Upcoming presentations

Project cameras showing real time activity

FAQs

Sign up for e-blasts

• VDOT Facebook Page/Group

• Quarterly Community/Public Meetings

• Contact Information:

Ricardo Correa, VDOT Project Manager

o [email protected]

o 757-635-2162

Shelby Frank, GPC Public Information Officer

o [email protected]

o 757-744-9636

37

Stay Informed

Hampton Roads District

Page 38: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

• Project Website – www.64highrise.org

38

Stay Informed

Hampton Roads District

Page 39: I-64 Southside Widening and · 2019. 6. 17. · Presentation for WTS Rick Correa, PE, Senior Project Manager VDOT Hampton Roads District Major Projects June 17, 2019. I-64 Southside

I-64 Southside Widening and High Rise Bridge Phase 1

Questions?

Hampton Roads District 39