I-29 Pembina Border Crossing Project Development Process Justin Schlosser, P.E. NDDOT – Design Division

I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

I-29 Pembina Border CrossingProject Development Process

Justin Schlosser, P.E.NDDOT – Design Division

Page 2: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

COORDINATION

Consultant

• KLJ – Kadrmas, Lee, & Jackson

Canadian Agencies

• CBSA – Canadian Border Services Agency

• MIT – Manitoba Infrastructure and Transportation

• PWGSC – Public Works and Government Services Canada

United States Agencies & Stakeholders

• CBP – US Customs and Border Protection

• DFA – Duty Free America

• FHWA- Federal Highway Administration

• GSA – General Services Administration

• USACE – U.S. Army Corps of Engineers

• USDOS – U.S. Department of State

Page 3: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

ENVIRONMENTAL PHASE

• Project environmental document started as a Documented Catex

• Presidential Permit was needed from the United States Department of State (USDOS) since we were penetrating the border at a new location

• After discussion with USDOS environmental document switched to an environmental assessment (EA)

• EA signed February of 2016

• FONSI received April of 2016

Page 4: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

PRESIDENTIAL PERMIT

• Required Permit from U.S. Department of State since we substantially modified an existing border crossing

• Long Process (1.5 years once submitted)

• Submitted permit application May of 2016

– EA

– FONSI

• Federal Agency Review Period on Federal Registry

Page 5: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

SECTION 508 COMPLIANCE

Page 6: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017

Page 7: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

UNIQUE DESIGN CHALLENGESPRE-PROJECT

Page 8: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

FINAL DESIGN

Page 9: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN
Page 10: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

OTHER PROJECT COMPONENTS

Highway Advisory Radio

High Mast Lighting

FAST

Page 11: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

OTHER PROJECT COMPONENTS – ELECTRONIC PLAQUES

Page 12: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

RIGHT OF WAY• Permanent Acquisition

– BNSF railroad

– Private landowner

• Temporary Easementfrom GSA

• Working on Transferring land to GSA

– Land in the new median (can be seen highlighted on picture)

Page 13: I-29 Pembina Border Crossing Project Development Process...SECTION 508 COMPLIANCE. RECEIVED PRESIDENTIAL PERMIT OCTOBER OF 2017. UNIQUE DESIGN CHALLENGES PRE-PROJECT. FINAL DESIGN

Questions?

Justin Schlosser, P.E.NDDOT – Design Division