Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Manila Third Sewerage Project
Hypothetical SWMM Application in San Juan River Watershed
Henry Manguerra
GEF-MTSP Consultant
August 3-4, 2011
EW-2
EW-2 Subcatchment as defined in the MWSS 2005 Master Plan
Source:MWSS 2005Master Plan
Source:MTSP BoundaryDelineation Team
EW-2 was arbitrarilydelineated
Source: MWSS 2005 Master Plan, MWSS 2009 Preparatory Survey ReportNote: Estimates were calculated followingprocedures described in the reports.
STPUpperSF River(3,150m)
Hypothetical Future Management Scenario◦ STP design capacity =
0.25 m3/s or 5.7 million GPD (approx. 25% of the total domestic/ commercial wastewater flow
◦ Remaining 75% stays on septic systems but are well maintained/ managed (e.g., SpTP)
◦ STP Permit BOD Limit = 50 mg/lSevilla Bridge
WQ Station
Largest in the world
Rated average day capacity = 370 millions GPD
Wet weather capacity = 1.076 billion GPD
Discharges to Potomac River (Part of Chesapeake Bay Watershed)
Stringent NPDES Permit Limit Requirements (See Table Below)
STPUpperSF River(3,150m)
A SWMM input file was already created for this exercise.
To start the hands-on exercise, open project file c:\SWMMTraining\SWMMData\Example_EW2.inp.
Sevilla BridgeWQ Station
Specify point source discharges and other external inflows
Perform model calibration
Estimate load reduction and resulting in-stream BOD concentration impacts of STP and improved septic maintenance/management
Evaluation of simulated in-stream concentrations against water quality standards both during dry and rainfall event
The input file represents “current” conditions prior to the hypothetical future management scenario◦ Questions: How is “current” domestic/commercial wastewater flow and
BOD loads represented in the model? Q = _____; C = ______ What does the dry weather inflow represent? ____________
Upper SF River was divided into 4 segments/conduits: C1, C2, C3, C4◦ Questions: What is the channel shape? ___________ What are the cross-sectional dimensions? _________ What is the longitudinal slope? _________ (Tip: slope is not
directly an input value but is calculated from the invert elevations of the nodes)
Run the model and quickly view results by clicking Report >> Status from main menu.◦ Confirm that no rainfall event occurred during the
simulation (TIP: Rainfall Gage1 is associated with PPTNO time series which is a dummy time series of zero precipitation)
◦ Question: What is the total BOD loading at the outfall? Answer: 351,011 kg.
◦ Question: What are the inflow – outflow BOD amounts?
Dry Weather Inflow? ____ (baseflow contribution)
External Inflow? ________ (domestic/commercial)
Mass Reacted? _________ (BOD removed due to decay)
Sevilla Bridge Water Quality Monitoring Station◦ 2009 PRUMS report: BOD conc. = 43.4 mg/l (average dry
weather condition) with 1st quarter = 70.2 mg/l
◦ No flow monitoring data available. 2009 PRUMS report showed flow velocity information ranging between 0.1 –0.3 m/s.
◦ PRRC wq of selected esteros showed 125 mg/l for Ermitano, 123 mg/l for Diliman, and 133 mg/l for Mariabolo
For the purposes of illustrating model calibration, use the following:◦ BOD = 70 mg/l
◦ Velocity = 0.1 m/s
Calibration Parameter = channel roughness coefficient (N)◦ Question: What is currently the N value? ________◦ Question: What are the current flow velocities in
the following channels (Tip: Click Report >> Table >> By Variable from main menu): C1: _______ C3: _______
C2: _______ C4 :_______
Adjust the current N value to reduce flow velocities to about 0.1 m/s.◦ Question: What is the new value of N? _______◦ Question: What is the new total BOD loading at the
outfall? _________ What did it change?
Calibration Parameter = BOD decay coefficient (k)◦ Question: What is currently the BOD k value? ________
◦ Question: What are the current in-stream concentration (Tip: Click Report >> Table >> By Variable from main menu):
C1: _______ C3: _______
C2: _______ C4 :_______
Adjust the current BOD k value to obtain in-stream BOD concentrations of about 70 mg/l ◦ Question: What is the new value of k? _______
◦ Question: What is the new total BOD loading at the outfall? _________
Calibrated k = 4.5
Corresponding total BOD loading at the outfall = 121,368 kg about 1/3 of the original estimate value of 351,011 kg.
Analysis: ◦ The resulting BOD removal due to decay is highly
unrealistic.
◦ Typical literature values of k range from 0.05 – 0.5
◦ Therefore, the calibrated k = 4.5 incorporates an additional adjustment factor that significantly removes BOD at the source before it reaches the main streams. What would that be?
HANDS-ON EXERCISE STOPPING POINT
EW-2 Catchment
Q
Direct inflowC = 269 mg/l
Observed C= 70 mg/l
Wet-weatherDriven InflowC << 269 mg/l
Ponds, depressions,stagnant esteros, storage, etc.
Options to model this scenario in SWMM:• Reduce direct inflow Q• Model additional BOD removal due to ponds,
depressions, etc. using a treatment function• Provide network details to include ponds,
esteros, etc.
Section 3.3.10 User‟s Manual – Assign a node a treatment function
Use a first-order decay expression◦ C = BOD * exp (-0.05 * HRT) where
HRT = hydraulic resistance time (hrs) assumed equal to 20 hours for this hands-on exercise.
Assign k = 0.25 (consistent with literature values)
Enter treatment function at node J1 (Tip: see figure next slide)◦ Question: What are the current in-stream
concentration (Tip: Click Report >> Table >> By Variable from main menu): C1: _______ C3: _______
C2: _______ C4 :_______
◦ Question: What is the new total BOD loading at the outfall? Answer: 123,769 kg. Note that this value corresponds to the calibrated „current‟ total BOD loading during dry days prior to the hypothetical future management scenario.
Steps:1. Click Node J12. Click Treatment Field3. Enter Expression
1
23
• Results correspond to average steady state conditions
A fully calibrated model is “almost” essential Model should be calibrated for seasonality
(low flow, high flow) at several stream locations◦ Time series of flow and in-stream concentrations
are required
Other measurements can be used for calibration (Section 5.7, p81, User‟s Manual)◦ Runoff◦ Pollutant Washoff◦ Groundwater inflow/baseflow◦ Water Surface Depth
Scenario
◦ STP design capacity = 0.25 m3/s or 5.7 million GPD (approx. 25% of the total domestic/ commercial wastewater flow
◦ Remaining 75% stays septicsystems but are well maintained/ managed (e.g., SpTP)
◦ STP Permit BOD Limit = 50 mg/l
Steps: 1. Save current project file2. Create new project file for new
scenario by Saving As the current project file to Example_EW2_Future.inp
3. Remove treatment function in node J1 (from the previous scenario)
4. Change direct inflowQ = 0.25 m3/sBOD conc. = 50 mg/l
5. Run model
Tip: Run model 2-3 times to stabilize the run since the model is setup to assign initial conditions with model results (Chapter 11.7, User‟s Manual.
Confirm that resulting in-stream BOD concentrations are in the 20-25 mg/l (see Figure below) higher than the BOD standard of 7 mg/l for class C waters.
What is the maximum BOD concentration can the STP discharge so the BOD standard is not exceeded? Answer: 13 mg/l
Graph below shows resulting in-stream concentration (prepared in MS Excel)
Distance Downstream From STP (m)
Conc.,
mg/l)
Question: What is the total BOD loading at the outfall? Answer: 4,404 kg.
This corresponds to a 96.4 percent reduction of the “current” BOD loading = 123,769 kg.
Note that the previous exercises involved running the model in Steady State (i.e., constant inflows)
Question: What are resulting in-stream concentration if effluent discharges are intermittent (e.g., discharging only during Mondays, Wednesdays, and Fridays) at a flow rate equal to twice the previous constant flow (new Q = 0.50 m3/s, BOD = 13 mg/l)
Options: External Inflow TS Use of Baseline Pattern
Step 1. Create Time Series PatternsStep 2. Specify Inflow to Follow a
Pattern
Exceedance ofBOD Standard
Objective: Determine impact of a rainfall event to in-stream BOD concentration
Step 1: Change effluent discharge back to constant Q = 0.25 m3/s and BOD = 13 mg/l
Step 2: Specify Gage1 to be associated with rainfall time series IDF (see Figure)◦ Note that this time series contains a 1-
hr duration rainfall event with a return period of 1 year for NAIA, Philippines (Source: Daniell and Tabios, 2008)
Step 3: Examine catchment attributes including landuse◦ Question: What pollutant buildup and
washoff functions were used?
Step 4: Run the model (see continuity errors in the Figure -numbers might be slightly different)
Step 5: Rerun the model as Dynamic Wave (see continuity errors in the Figure – numbers might be slightly different)
Save project: Click File >> Save from the main menu
Exceedance ofBOD Standard
Tip: The SWMM5 input filefor this Wet Weather Modelinghands-on exercise can be foundat c:\SWMMTraining\SWMMData\Example_EW2_WetWeather.inp
Tip: The SWMM5 input filefor the Wet Weather Modelinghands-On exercise can be foundat c:\SWMMTraining\SWMMData\Example_EW2_WetWeather.inp
Station: Science Garden, Quezon City, 6 hour rainfall interval, 1/1/2003 – 12/31- 2003
Filename: science_swmm.dat
Steps (See Figure):
◦ Change Data Source field = File
◦ Specify FilePath\FileName(C:\SWMMTraining\SWMMData\science_Swmm.data)
◦ Enter Station ID = Science
◦ Enter Rain Units = MM
◦ Enter Time Interval = 6
◦ Specify Simulation Period from 1/1/2003 – 12/31/2003
◦ Run the Simulation
◦ Save project: Click File >> Savefrom the main menu
Click Report >> Statistics from Main Menu
Days
BODmg/l
RunoffCMS
Note: SWMM output exported to and graph produced in MS Excel.
Tip: The SWMM5 input filefor the Rainfall Time Series hands-on exercise can be foundat c:\SWMMTraining\SWMMData\Example_EW2_Continuous.inp
END OF HANDS-ON EXERCISES
Manila Third Sewerage Project
Henry Manguerra
GEF-MTSP Consultant
August 3-4, 2011
EPA SWMM5 has a lot more to offer◦ Groundwater module◦ Other drainage control structures (regulators, storage units,
flow dividers, pumps) in more detailed and complex drainage network
◦ Best management practices (ponds, and low impact development)
◦ Integration with other models
EPA SWMM5 is (relatively) easy to learn, versatile and has wide-ranging applications to many agencies◦ Pollution load allocation/TMDL ◦ Flood modeling◦ Stormwater/Sanitary sewer/Combine Sewer Capacity
Modeling and Design
Don‟t lose what you learned here◦ Continuously find opportunities to apply the model◦ Designate/mentor/empower others◦ Keep building internal capacity for modeling – Model, Data,
Computer Infrastructure, People, Budget
Modeling Workgroup will meet to discuss EPA SWMM5 application in San Juan River Watershed and eventually in Manila Bay watershed