  • HYDROTESTHYDROTEST

    SAFETYSAFETY

    ChecklistChecklist

    20 Simple tips on how to carry out 20 Simple tips on how to carry out hydrotesthydrotest safelysafely

  • Why hydrotest is

    HAZARDOUS?

  • 1.5 TIMES design pressure

    Hydrotest involves

    HIGH PRESSURE.

  • Hydrotest could

    INJURE PEOPLE

    and

    DAMAGE PROVERTY

  • So be careful.

    Always follow

    SAFETY STANDARD and

    BEST PRACTICES for hydrotest

  • LEARNING how to carry out

    hydrotest

    SAFELY

    is very important

  • Here are the tips...

  • Only TRAINED and

    AUTHORIZED PERSONNEL

    can take responsibility for

    the test

    11

  • Ensure test condition with

    the DESIGN

    intents

    22

  • All fill piping, hose and

    temporary closures should

    have higher STRENGTH

    than the test pressure

    33

  • All piping, valves and fittings

    tested should of known

    SPECIFICATION

    44

  • NEVER USE susceptible to

    brittle or stress corrosion

    cracking materials

    55

  • All re-used materials have to

    be INSPECTED before used.

    66

  • SUPPORT of piping and

    equipment exposed to the

    hydrotest should have

    proper STRENGTH.

    77

  • Pressure-relief device is

    required to avoid

    OVER PRESSURE.

    88

  • Make sure no AIR trapped in

    the tested pipe or

    equipment. It is very

    DANGEROUS.

    99

  • Only

    AUTHORIZED PERSONNELS

    are allowed to be

    at the test area.

    1010

  • Hydrotest area has to be

    restricted with

    SAFETY LINE and protected

    BARRIER.

    1111

  • Use WARNING SIGNS to

    warn people about the

    hydrotest.

    1212

  • WEAR appropriate PPE for

    the hydrotest.

    1313

  • Use CALIBRATED pressure

    gauge for the test. It must

    be able to cover 1.5 to 2

    times pressure test.

    1414

  • Get SAFETY WORK PERMIT

    prior to hydrotest.

    1515

  • COMMUNICATE the test

    planning prior to execution.

    1616

  • STOP the work if unsafe or

    potential hazardous

    condition found during the

    test.

    1717

  • Never STAND in the front of

    pressure gauge during the

    test.

    1818

  • Enough LIGHTING is

    available for the hydrotest.

    1919

  • After hydrotest finished,

    RELIEF PRESSURE first prior

    to draining water.

    2020

  • It is very essential to know

    how to select proper

    pressure gauge

    for hydrotest, get the guide

    here.

    ChemicalEngineeringMagazine.com