23
Hydropower Good Practice Guide Dr John Aldrick HO Water Resources Regulation manager

Hydropower Good Practice Guide - Lancaster

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Hydropower Good Practice Guide - Lancaster

HydropowerGood Practice Guide

Dr John Aldrick

HO Water Resources Regulation manager

Page 2: Hydropower Good Practice Guide - Lancaster

Environment Agency Policy on Hydropower

h The Agency strongly supports the Government’s

targets for the use of renewable energy. (10% - 2010

20% - 2020)

BUT

h The Agency recognises both potential benefits &

environmental impacts of small-scale hydropower

h The Agency’s duty is to balance the benefits/impacts

of hydropower

Page 3: Hydropower Good Practice Guide - Lancaster

We’re only borrowing the water, so what’s the big deal”

Page 4: Hydropower Good Practice Guide - Lancaster

Agency regulatory regime

Range of matters to take into accounth e.g. water resources, fisheries, flood risk, water quality, navigation, Na

Water Resources permit

h Quantity that can be abstracted

h Residual flows in deprived reach

h Operating/control agreement

h Time limited licence (normally 12 years to CAMS Common EndDate)

h Fish Screening requirements

h Fish Pass requirements

Page 5: Hydropower Good Practice Guide - Lancaster

Hydropower issues

Location

h environmental sensitivity

Volume/timing

h local impact

Residual flows

h deprived reaches

h flow measurement

Fisheries

h turbines

h screens

Page 6: Hydropower Good Practice Guide - Lancaster

Environmental site list audit

Water Resources

Conservation

Chemical/physical water quality

Biological Water quality

Fisheries

Flood Defence

Red boxes need further work

Notes provide

Is there an EA gauging station in the depleted reach or nearby that is likely to be

affected by the scheme?

Do surveys reveal any existing abstractions, including unlicensed ones, which will

be derogated by the proposal? (1)

Is it intended to increase the height of the impoundment?

Is there a flow-depleted weir?

Is there a flow-depleted channel?

Will the turbine be placed directly within the weir / water course rather than in a

separate channel?

Is the scheme being built on existing infrastructure?

Is the scheme non-consumptive i.e. will 100% of any water abstracted be returned to

the water course from which it was taken?

NOYES

A Water Resources Checklisttick box

h Checklist indicates factors that need to be considered

Page 7: Hydropower Good Practice Guide - Lancaster

Hydropowersite layout

Turbine / waterwheel installed in leat

a) control device at offtake (b) no control at offtake)

weir

Deprived reach of River

Leatsystem

Length of/and controls on leatsystem are site specific

Turbine /waterwheeinstalled in weir

Page 8: Hydropower Good Practice Guide - Lancaster

Deprived reach Flow

h Flow to be left in deprived reach between intake

and discharge - (how much?)

h To meet fisheries, ecological, amenity, riparian,

navigation needs

h Dependant on environmental sensitivity

h May depend on the length of the deprived reach

h May vary with flow or season (eg migratory fish)

h Flow measurement or control

h Decisions impact on economics/viability of scheme

Page 9: Hydropower Good Practice Guide - Lancaster

Hydrological analysis

h Flow for hydropower

h Flow in the depleted reach

More flow for energy = less flow for environment

(in depleted reach)

Can examine hydrology using

h daily hydrographs

h Flow duration curves

Page 10: Hydropower Good Practice Guide - Lancaster

HydropowerLarge Chalk river Q30 & flow split Q50/Q95 1.75

Large Chalk river - flow depleted reach

0

100

200

300

400

500

600

Oct-

89

Dec-8

9

Feb

-90

Apr-

90

Jun

-90

Aug

-90

Oct-

90

Dec-9

0

Feb

-91

Apr-

91

Jun

-91

Aug

-91

Oct-

91

Dec-9

1

Feb

-92

Apr-

92

Jun

-92

Aug

-92

Oct-

92

Dec-9

2

Feb

-93

Apr-

93

Jun

-93

Aug

-93

Oct-

93

Dec-9

3

Feb

-94

Apr-

94

Jun

-94

Aug

-94

Itchen datahantsQ50

Q95

50/50 split

50/50 gen

Q30-Q90

30-90gen

Q30-Q95

30-95 gen

Page 11: Hydropower Good Practice Guide - Lancaster

FDC – Large chalk river

Depleted reach Flow duration curves

Large Chalk river

0.0

200.0

400.0

600.0

800.0

1000.0

1200.0

Natural flow

Q50-95

Q50

Q30-95

Q30-90

75% flow

50%flow

Page 12: Hydropower Good Practice Guide - Lancaster

HydropowerDecision tree

Obtain flow data from nearest gauging station or LF2000 and establish Flow

Duration Curve for the HEP site.

Determine the 30,50, 95,100th percentile

Is site in Salmonid spawning reach?

yes

no

Is site in Salmon migration river?

yes

50/50 flow splitQ30 to Q90

4 week no HEP

Depleted reach<10m

Depleted reach 10-100m

Depleted reach

Q30 - Q90Or Q50 - Q95HOF Q90 or Q95

Q30 - Q90HOF Q90

Q50 - Q90HOF Q90

Is Q50/95<3High baseflow

UseQ50 - Q100Or flow ove

no Maximum quantityavailable for HEP

Fish pass required

Fish pass required

Page 13: Hydropower Good Practice Guide - Lancaster

Hydrological conclusions

Q30 - HOF for hydro has major impact on flow in depletedreach.

Acceptable for very short reach <100m

Longer reach/salmon spawning needs more flow variabilit

Turbine in weir – most advantageous esp High baseflowrivers if very short depleted reach

(1.2 to 1.8 times more power) may allow more hydro

Salmonid spawning rivers – flow split

Salmon migratory rivers – month no hydro

Page 14: Hydropower Good Practice Guide - Lancaster

Hydropowersite layout

Turbine / waterwheel installed in leat

a) control device at offtake (b) no control at offtake)

weir

Deprived reach of River

Leatsystem

Length of/and controls on leatsystem are site specific

<10m<10m<10m<10m

Q30Q30Q30Q30----90909090

or flow over or flow over or flow over or flow over

weirweirweirweir

10m 10m 10m 10m –––– 100m100m100m100m

Q30Q30Q30Q30----90909090

100m 100m 100m 100m –––– 500m500m500m500m

Q50Q50Q50Q50----90909090

>500m>500m>500m>500m

50/50 split50/50 split50/50 split50/50 split

Page 15: Hydropower Good Practice Guide - Lancaster

Turbine type/Fish screen requirements

h Fish friendliness of turbine will determine screen

requirements

Must also consider

h Water approach velocity

h Escape & by-wash

Page 16: Hydropower Good Practice Guide - Lancaster

Fish friendly turbines?

Crossflow

Francis

Kaplan

Archimedean screw

Waterwheel

Page 17: Hydropower Good Practice Guide - Lancaster

Fish Screens

Crossflow turbine 6mm screenAll regions

Drop through Coanda screens 1

Water wheel

Archimedes screw

Trash screen

As appropriate (100mm)

Kaplan

Farncis turbines

10mm screen -North-East, North-West, Wales, Southwest (devon/Cornwall)

12.5mm screen –Midlands, Anglian, Southern, Thames, Southwest (Wessex)

TURBINE TYPE SCREEN REQUIREMENTS

Page 18: Hydropower Good Practice Guide - Lancaster

Fish screens

Mostly physical

h wedge wire, mesh,bar

Fish screens are expensive

Recent R&D

h Mesh size

h flow velocities

Page 19: Hydropower Good Practice Guide - Lancaster

Fish Screen - principles

h Inlet velocity – ideally 0.25-0.3m/sec (at an angle to

the flow) – leading to a

h By-wash – to enable fish to escape

h Tail race screens on salmonid rivers?

Page 20: Hydropower Good Practice Guide - Lancaster

Fish migration

Fish passes

h may involve retro-fit

h also likely to be costly

h New weirs

h Salmonid rivers first

Page 21: Hydropower Good Practice Guide - Lancaster

Applicants should expect the Agency to:

h Provide clear guidance on the licensing process

h Highlight key issues for environmental assessment

h Have an understanding of hydropower

h Provide information it has available

h Be consistent

h Provide timely responses, with explanations

Page 22: Hydropower Good Practice Guide - Lancaster

Applicants should notexpect the Agency to:

h collect and analyse supporting data

h carry out the environmental assessment

h accept inadequate data or assessments

h give a binding view based on incomplete information

h design the scheme

h contravene its statutory duties

Page 23: Hydropower Good Practice Guide - Lancaster

The Agency expectsthe applicants to:

h to know their site, its environment and their objectives for

the scheme (background)

h consider and design their proposals carefully

h consider options/alternatives

h make early contact with the Agency and continue such

throughout the process

h appreciate the legislative and other constraints

h provide quality, focused environmental assessments

h provide appropriately detailed plans and drawings to

support any applications