60
EWFW Suite 5, Level 1 330 Wattle St Ultimo NSW 2007 ABN: 48 130 395 827 Hydraulic Infrastructure Report Grocon Group Development Application Submission 31 Wheat Rd, Sydney

Hydraulic Infrastructure Report Grocon Group Development

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Hydraulic Infrastructure Report Grocon Group Development

EWFWSuite 5, Level 1

330 Wattle St

Ultimo NSW 2007

ABN: 48 130 395 827

Hydraulic Infrastructure Report Grocon Group Development Application Submission 31 Wheat Rd, Sydney

Page 2: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

Table of Contents

1. Introduction 31.1. Purpose 31.2. Authority 31.3. Objectives of Study 31.4. Outline 31.5. Terminology 3

2. Technical Information 42.1. Author Details 42.2. Information Sources 42.3. Disclaimer of Liability 42.4. Copyright© 42.5. Revision History 4

3. Area of consideration 54. Existing Infrastructure Services 6

4.1. SWC Water Main 64.2. SWC Sewer Main 64.3. SWC Stormwater Main 64.4. Jemena Gas Main 6

5. Consideration of Authority Infrastructure 85.1. SWC Water Main 85.2. SWC Sewer Main 85.3. SWC Stormwater Main 85.4. Jemena Gas Main 8

6. Appendix 1 – Sydney Water Mains Map 107. Appendix 2 – Jemena Mains Map 128. Appendix 3 – Indicative Infrastructure Location 149. Appendix 4 – Sydney Water Letter of Feasibility 1610. Appendix 5 – Sydney Water – Meeting Minutes 2811. Appendix 6 – Jemema – Meeting Minutes 55

Page 3: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

1. Introduction

1.1. Purpose This report has been produced by EWFW Pty Ltd in response to the request from Justin Clark from Grocon Group.

The purpose of this report is to provide an assessment of the hydraulic infrastructure within the vicinity of the proposed development at 31 Wheat Rd, Sydney.

This report shall not be relied upon as providing any warranty or guarantee of the building, its services or equipment.

1.2. Authority Authority to undertake this report was provided by Justin Clark of Grocon Group on 20 November 2012.

1.3. Objectives of Study The objectives of the report are to:

Outline the details of the surrounding infrastructure.

Nominate areas of concern.

Outline the steps that will be taken to ensure that the infrastructure is considered.

Provide recommendations.

1.4. Outline The following services have been assessed in this report:

Water services Sewer services Stormwater Gas Services

1.5. Terminology The abbreviations and notations referred to within this report relate to the following:

CICL Cast Iron Concrete Lined

DICL Ductile Iron Concrete Lined

kPa Kilopascals

mm Millimetres

NOR Notice of Requirements (Sydney Water)

SWC Sydney Water Corporation

VC Vitrified Clay

Page 4: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

2. Technical Information

2.1. Author Details EWFW Pty Ltd Suite 5, Level 1, 330 Wattle St Ultimo NSW 2007 ABN: 48 130 395 827 Phone: + 61 2 9212 1000 Fax: + 61 2 9212 1000 E-mail: [email protected]

Author: Dominic De Gioia Director

Reviewer Luke De Gioia Director

2.2. Information Sources Information provided by Sydney Water as part of the Dial Before you Dig Program.

Information provided by Jemena as part of the Dial Before you Dig Program.

Information provided by Justin Clark of Grocon.

Information obtained during site inspections and from drawings provided on site.

Various manufacturers and suppliers.

2.3. Disclaimer of Liability The information contained in this document is provided for the sole use of the recipient and no reliance should be placed on the information by any other person. In the event that the information is disclosed or furnished to any other person, EWFW accepts no liability for any loss or damage incurred by that person whatsoever as a result of using the information.

2.4. Copyright© All rights reserved. No part of the content of this document may be reproduced, published, transmitted or adapted in any form or by any means without the written permission of EWFW.

2.5. Revision History

Revision Date Issued Comment

A 22 November 2012 Draft

B 4 December 2012 Final Issue

C 11 December 2012 Final Issue – Revised site title

D 21 June 2013 Final Issue – Revised building

E 19 July 2013 For Development Application

Page 5: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

3. Area of consideration The area of consideration relates to 31 Wheat Rd, Sydney.

The proposed area (bounded approximately by the red square in the picture below) currently consists of the IMAX Theatre and associated retail areas.

Figure 3.1. Proposed site

Page 6: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

4. Existing Infrastructure Services 4.1. SWC Water Main

The site is flanked by two (2) Sydney Water water mains. These mains are:

A 200mm DICL main located on the western end of the site (See Appendix 1 – Note 1)

A 150mm CICL dead leg capped main located on the eastern end of the site (See Appendix 1 – Note 2)

From the proposed footprint of the development both mains will be within the line of the building construction. It will be proposed to move the line of the water services to ensure they are diverted clear of the proposed building line. In addition to this, it is proposed that the 150mm and 200mm mains will be interconnected to extend the Sydney Water network within this region. This is in line with the requirements put forward by Sydney Water in their Letter of Feasibility for the site (Refer to Appendix 4).

4.2. SWC Sewer Main The site is flanked by several Sydney Water sewer mains and associated equipment. These include:

A 525 VC sewer main located at the eastern end of the site (See Appendix 1 – Note 3)

A 300 VC sewer main located at the southern end of the site (See Appendix 1 – Note 4)

A pump station and a vent shaft adjacent the site. This site pump station is also heritage listed.

Access chambers along both of the sewer mains nominated above

From the proposed footprint of the development both mains will be within the line of the building construction. It will be proposed to move the line of the sewer services to ensure they are diverted clear of the proposed building line. This is in line with the requirements put forward by Sydney Water in their Letter of Feasibility for the site (Refer to Appendix 4).

The Southern Lease Area of the proposed development (See Appendix 3) is located clear of the 750 VC sewer main (See Appendix 1 – Note 5). Further assessment will be conducted in conjunction with Structural Engineers as part of the design process to ensure that the proposed structure will have no impact on the service. This shall also be confirmed with Sydney Water as part of the Sydney Water Notice of Requirements.

4.3. SWC Stormwater Main As there are two significant stormwater mains running below the site there will be a protection requirement as part of the works. These mains include a set of culverts which traverse through the centre of the site in a north-south direction (known as the Hay Lackey Culverts) and a set which are located at the western side of the proposed development site.

The existing development currently sits above culverts and these will continue to be affected by the proposed development. Whilst the building footprint does not directly impinge the culverts at the western end of the site Sydney Water will be consulted in order to ensure all steps are taken to protect their adjacent assets.

Any works will be at the discretion of Sydney Water and their conditions as nominated.

4.4. Jemena Gas Main The site is flanked at the south-eastern corner and along the eastern boundary by Jemena gas infrastructure. This includes:

A 110mm Nylon main located at the eastern end of the site (See Appendix 2 – Note 1)

Page 7: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

A 50mm Nylon main located at the south-eastern end of the site (See Appendix 2 – Note 2)

A Secondary gas main (1050kPa) and a pressure reduction station located at the south-eastern end of the site (See Appendix 2 – Note 3)

Authority infrastructure to supply the Aquarium located at the south-eastern end of the site (See Appendix 2 – Note 4)

From the proposed footprint of the development both mains will be within the line of the building construction. It will be proposed to move the line of the gas services to ensure they are diverted clear of the proposed building line. These lines will run to the west and then the north of the building line, remaining clear of all adjacent supply authority infrastructure. This will be at the discretion of Jemena and their conditions nominated.

Page 8: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

5. Consideration of Authority Infrastructure 5.1. SWC Water Main

Sydney Water’s Letter of Feasibility has deemed that the adjacent water mains will be sufficient to satisfy the requirements of the proposed building. Sydney Water has nominated that the 150mm and 200mm water mains need to be relocated clear of the building line and interconnected. These works will be completed as part of the development. Subject to the final requirements set forth by Sydney Water, the building will be connected to the 200mm service.

A Sydney Water Co-ordinator will be engaged once the Development Application has been submitted. The Sydney Water Co-ordinator will provide the submission of a Section 73 Application to Sydney Water in order to obtain the Notice of Requirements for the development.

Works outlined within the Notice of Requirements will be undertaken by the Sydney Water Co-ordinator in accordance with Sydney Water’s Design Guidelines. Any works to the mains will be undertaken by Sydney Water approved contractors as nominated by the Water Co-ordinator.

5.2. SWC Sewer Main Sydney Water’s Letter of Feasibility has deemed that the adjacent sewer mains will be sufficient to satisfy the requirements of the proposed building. Sydney Water has nominated that the 525mm and 300mm sewer mains need to be relocated clear of the building line. These works will be completed as part of the development. Subject to the final requirements set forth by Sydney Water, the building will be connected to the 525 VC service through a connection at one of the adjacent access chambers.

A Sydney Water Co-ordinator will be engaged once the Development Application has been submitted. The Sydney Water Co-ordinator will provide the submission of a Section 73 Application to Sydney Water in order to obtain the Notice of Requirements for the development.

Works outlined within the Notice of Requirements will be undertaken by the Sydney Water Co-ordinator in accordance with Sydney Water’s Design Guidelines. Any works to the sewer mains will be undertaken by Sydney Water approved contractors as nominated by the Water Co-ordinator.

5.3. SWC Stormwater Main Presently we have commenced discussions with Jeya Jeyadevan and Raymond Parsell of the Sydney Water Stormwater Group. Several meetings have been undertaken to date in order to determine the requirements for any works which will affect the stormwater culverts, particularly the Hay Lackey culverts which traverse below the building line. Sydney Water has outlined the information they require which we will provided to Sydney Water as part of the Design Development.

Any direction or requirements provided by Sydney Water’s stormwater group in terms of construction over, or protection of these assets will be undertaken in strict accordance with the requirements nominated.

5.4. Jemena Gas Main Based on the initial site meeting with Anne Westwood and Andrew Lelliott of Jemena, the adjacent gas mains are running close to capacity. Jemena are in the process of reviewing their capabilities within the region and the strategy for supply to this area and the adjacent CBD. This will see additional supply within the region which will satisfy the supply required for the calculated building demand. Presently it is proposed that connection be made to the main located at the rear of the site (pending final gas diversion routes).

Page 9: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

Any direction or requirements provided by Jemena in terms of construction over, relocation or protection of these assets will be undertaken in strict accordance with the requirements nominated.

Page 10: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

6. Appendix 1 – Sydney Water Mains Map

Page 11: Hydraulic Infrastructure Report Grocon Group Development

SP

0012

ST

ST

PL

DR

UIT

T

DR

UIT

T

KENT

LAN

E

DR

UIT

T

WHEAT

PL

BLA

CK

WA

TTLE

DAY

STSANDS

ST

WE

STE

RN

BA

THU

RS

T

DAY

JAMES

DS

TRS

T

SUSSEX

LANE

JAM

ES

ST

RP

VSE

VSE

VERT

VERT

RP

VSE

VSE

VSE

VSE

DisDis

Dis

Dis

Dis Dis

Dis DisDis

Dis

Dis Dis Dis

Dis

Dis Dis Dis

DisDisDis

Dis

Dis

DisDis

Dis

Dis

Dis

DisDis

Dis

Dis

DisDis

Dis

Dis

Dis

Dis

VERT

BAY

2

B

A

1 20

CP

CP

16

1

11

12

CP

1

8

10C

50 51

4

5

A

BCP 1

1 1CP

2 10010 1

CPCP

101 1 1

11

11

21

C 1

1 1

CP

60

17

60

42

65

40

56

62

10

61

2

4

9

1

20

503

601

504

602

10

1010

60

63

64

402

401

405

404

306

218

4042

403 25

53

800

805

801

CP

3 4 5

A

23 1 1

B

313

313 1 1

100

100

C

10

1

804

802

803

730

58

9

806

901

1

1 12 2 1

CP3

1

3

1

CP

333

CP

1

4

502

200

414-418

222-228

439 439-441

230

234

25245

3-46

348

-58

465-467469

491499-501

503-505

507-509

259-261259-261

263

51 278

265 267 269

477

499-

501

286

493-495

499-

501

70-7

2

70-7

2

286

273-275 277

286 286

289-295

168

299-305

307 309

176-182

311

313-315 317 319 321-325 321-325

188

511 521-527 521-527 529 531

298-304306-318

318A

320-332

333-337327

336-346

533-5

192-

196

447

281-287

201

201

150

1-25

1-25

25G

11

1

3

5

13

1-25

2.04

1.8

2.1

20.2

27.4

10.1

20.4

43.6

29.9

43.0

34.1

3.3

18.6

26.8

36.0

37.2

13.4

21.

6.7

8.2

19.2

40.8

47.5

42.1

42.7

50.0

55.5

56.1

59.7 3.8

2.7

7.6

13.1

18.9

29.3

11.3

8.5

15.2

34.4

34.4 33.2

3.75.5

26.8 25.6

16.5

21.3 19.3

15.2

9.6 5.3

39.6

36.9

38.0

8.7

4.3

26.6

1.3

11.0 2.7

23.7

2.8

41.2

53.9

15.7

38.2

33.

43.3

41.8 30.2 82

.3 71.9

59.1

51.8

6.14.6

6.4

4.54

1.68

1.8

2.57

4.67

4.79

1.52

3.59

3.65

2.63

4.87

5.01

1.0

1.0

7.5 2.49 2.13

2.99

2.52

5.18

2.7

4.76

4.95

4.92

6.27

1.53 5.21

17.7

2.55

3.209

7.2

5.4

2.6

2.9

2.99

2.9

3.16

3.9

3.5

5.25

5.26

1.79

3.8

1.2

3.9

4.56

4.1

MH Chmb

4.019

4.92

6.7

MH Chmb

6.64

5.99

4.53

3.0

3.91

2.9

6.39

5.74

6.331.7

2

1.89

4.29

4.74

5.2

1.95

1.75

1.0

2.22

2.7

2.6

5.4

3.96

3.95

3.86

3.81

3.31

MH C

hmb

5.8

5.1

3.1

7.8

3.64

3.8

2.2

5.3

Conc Encased

In T

unne

l

Conc

Enc

ased

Conc Encased

Conc E

ncased

Conc

Enc

ased

Conc Encased

Conc

Enc

ased

Conc Encased

In Tu

nnel

300 V

C711x1066 CONC

300 VC

300 VC300 PVC

225 VC

300

VC30

0 VC

225 VC

300 P

VC

300 P

VC

300 PVC

300 VC

711x1066 CONC

300 E

W

300 P

VC

711x1066 CONC 711x1066 CONC

225 VC

711x1066 CONC

300 PVC

300 P

VC

300 PVC

300

PVC

225 VC

225 VC

225 V

C30

0 VC

300 VC

300 VC

150 PVC

300 C

ICL

300

CICL

300

CICL

300 VC

300 CICL

300 P

VC

300

VC

219 SCL 300 VC 300 VC

300 PVC

300 VC 300 VC

300 V

C

300

VC

300 CICL 300 V

C

300 VC

525 V

C

300 V

C

525 VC525 VC

300 V

C30

0 VC

300 C

ICL

750 V

C

750 V

C

750 VC

750 V

C

750 VC

1300x1750 Unlined Rock

375 VC 750 VC

750 VC

450 VC

300 PVC

300 PVC

300 VC

300 V

C

300 VC

300 PVC 300 VC

300 V

C

450 VC

750 V

C

450 VC

450 VC

750 V

C

750 V

C

300 V

C52

5 VC 225 VC

711x1066 CONC

150VC

225 VC

300 VC300 VC 300 VC

225

VC

300 VC 400 VC

300 VC

375 VC

3.0

2.9

3.1

2.9

0.5

0.8 6.4 3.8

6.4 4.

1 2.8

4.6 3.

1

3.0

3.0 0.8 2.

9

2.9

2.7

0.4

3.1

1.6

2.9 2.9

3.0

3.5

3.8

2.3

3.2

2.3

3.0

3.0 2.1

1.8

2.9

1.8

3.0

3.0

3.1

3.1

3.02.5 2.3

3.0 3.

0 2.8

2.8

2.9

2.8 3.0

1.8

Conc. Encased

150 CICL

200 CICL200 CICL

300 CICL

200

DICL

200

DICL

250 D

ICL

300

CICL 250 DICL 273 SCL

324 SCL32

4 SCL

200

DICL

250

DICL

273 S

CL

150 CICL

300 DICL

273 SCL

150 oPVC

250 CICL

500 CICL

150 oPVC

273 SCL

250

CICL

250 CICL

500 CICL150 CICL

150 CICL

500 CICL

300 CICL

150

CICL

150

DICL

150 D

ICL

150 CICL

300 CICL

150 CICL

150 CICL

150 S

CL

150 CICL

150 CICL

150 CICL

200

CICL

150 CICL

150 DICL

300 S

CL20

0 SC

L

250

SCL

250 SCL

250 D

ICL

150 C

ICL

250 CICL

150 S

CL15

0 SC

L

150 CICL

200 S

CL

200 DICL

200

DICL

200 SCL

200 D

ICL

200

DICL

200 S

CL

200 DICL

250 SCL

150 D

ICL

150 D

ICL

200 D

ICL

200 DICL

200

DICL

200 DICL

250DICL

250 DICL

300 DICL

300 DICL

300 DICL

200 DICL

200 S

CL

250 C

ICL

300 CICL

250 CICL

200 SCL

200 DICL

250 CICL

200 DICL

200 DICL

200 DICL

200

DICL

200 DICL

200 C

ICL

150 C

ICL

150 C

ICL

150 C

ICL

200 CICL

500 CICL

150 CICL

200 CICL

150 C

ICL

200 DICL

250 CICL

5.45.4

5.85

5.15.

450 VCVC

450 VC

450 VC

450 VC

2.3 2.3

25G25G4.2

9

5.25

450 VC50 VC50 VC

00SC

L0SC

LCL

INFO

RM

ATI

ON

ELS

EWH

ERE:

see

GU

IDE

ref 1

1213

3

3.3333 331

022

805

25G25G

4.53

L CL

RE:

sR

ER

E:R

ER

EE: s

RE

INFO

RM

ATI

ON

ELS

EWH

ERE:

see

GU

IDE

ref 1

1717

8

N0m

9m18

m27

m36

m

Copy

right

Res

erve

d Sy

dney

Wat

er 2

012

Plan

1 o

f 1A3

Date

of P

rodu

ction

: 15/

11/2

012

DBYD

Seq

uenc

e No

: 270

6687

6

DBYD

Add

ress

: 1-

5 W

heat

Rd

Sydn

ey N

SW 2

000

SYDN

EY W

ATER

COR

PORA

TION

No w

arra

nty i

s give

n th

at th

e inf

orm

ation

show

n is

com

plete

or a

ccur

ate.

DBYD

Job

No: 1

1783

7Sc

ale: 1

:150

0

Not

e1

-200

mm

Mai

n

Not

e2

-150

mm

Mai

n

Not

e3

-525

VC

Sew

er

Not

e4

-300

VC

Sew

er

Sto

rmw

ater

Cul

verts

Sto

rmw

ater

Cul

verts

Not

e5

-Bui

ldin

g2

sits

clea

roft

his

750

VC

Sew

er

11

Page 12: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

7. Appendix 2 – Jemena Mains Map

Page 13: Hydraulic Infrastructure Report Grocon Group Development

Not

e1

-110

mm

Mai

n

Not

e2

-50m

mM

ain

Not

e3

-Pre

ssur

eR

educ

tion

Sta

tion

Not

e4

-Aqu

ariu

mIn

frast

ruct

ure

13

Page 14: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

8. Appendix 3 – Indicative Infrastructure Location

Page 15: Hydraulic Infrastructure Report Grocon Group Development

AP

PR

IMA

AI

NS

NA

RS

RM

AR

AP

PR

IMA

AI

NS

NA

RS

RM

AR

AP

PR

IMA

AI

NM

NA

AS

MA

INIS

SN

RA

IN

MP

AP

PR

IMA

AI

NS

NA

RM

AIN

AP

PR

IMA

AI

NS

NA

RS

RM

AIN

AP

PR

IMA

AI

NP

RS

SR

SA

IN

ISS

15

Page 16: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

9. Appendix 4 – Sydney Water Letter of Feasibility

Page 17: Hydraulic Infrastructure Report Grocon Group Development

Case Number: 131752

11 April 2013

GROCON PTY LTDc/- BILLBERGIA PTY LTD

FEASIBILITY LETTER

Developer: GROCON PTY LTDYour reference: 3867Development: Lot 401 DP862501 DARLING HARBOUR Unset, SydneyDevelopment Description: The development comprises a 20 storey building component

of approximately 73,000sqm total Gross Floor Area plus anUrban Renewal / Landscape component of approximately10,000sqm. The total proposed site area for the developmentincluding the building footprint is 15,060sqm on, and adjacentto, the site currently occupied by the IMAX Cinema, DarlingHarbour, Sydney.

Dear Applicant

This Feasibility Letter (Letter) is a guide only. It provides general information about what SydneyWater’s requirements could be if you applied to us for a Section 73 Certificate (Certificate) foryour proposed development. The information is accurate at today’s date only.

If you obtain development consent for that development from your consent authority (this isusually your local Council) they will require you to apply to us for a Section 73 Certificate. Youwill need to submit a new application (and pay another application fee) to us for that Certificateby using your current or another Water Servicing Coordinator (Coordinator).

Sydney Water will then send you either a:• Notice of Requirements (Notice) and Developer Works Deed (Deed); or• Certificate.

These documents will be the definitive statement of Sydney Water’s requirements.

There may be changes in Sydney Water’s requirements between the issue dates of this Letterand the Notice or Certificate. The changes may be:

• if you change your proposed development, e.g. the development description or the plan/

17

Page 18: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 2 Case No: 131752

site layout, after today, the requirements in this Letter could change when you submityour new application; and

• if you decide to do your development in stages then you must submit a new application(and pay another application fee) for each stage.

No warranties or assurances can be given about the suitability of this document orany of its provisions for any specific transaction. It does not constitute an approvalfrom Sydney Water and to the extent that it is able, Sydney Water limits its liability tothe reissue of this Letter or the return of your application fee. You should rely on yourown independent professional advice.

18

Page 19: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 3 Case No: 131752

What You Must Do To Get A Section 73 CertificateTo get a Section 73 Certificate you must do the following things. You can also find out about thisprocess by visiting www.sydneywater.com.au > Building and Developing > Developing YourLand.

1. Obtain Development Consent from the consent authority for your developmentproposal.

2. Engage a Water Servicing Coordinator (Coordinator).

You must engage your current or another authorised Coordinator to manage the designand construction of works that you must provide, at your cost, to service your development.If you wish to engage another Coordinator (at any point in this process) you must write andtell Sydney Water.

For a list of authorised Coordinators, either visit www.sydneywater.com.au > Building andDeveloping > Developing Your Land or call 13 20 92.

The Coordinator will be your point of contact with Sydney Water. They can answer mostquestions that you might have about the process and developer charges and can give you aquote or information about costs for services/works (including Sydney Water costs).

3. Developer Works Deed

After the Coordinator has submitted your new application, they will receive the SydneyWater Notice and Developer Works Deed. You and your accredited DeveloperInfrastructure Providers (Providers) will need to sign and lodge both copies of the Deed withyour nominated Coordinator. After Sydney Water has signed the documents, one copy willbe returned to the Coordinator.

The Deed sets out for this project:

• your responsibilities;

• Sydney Water’s responsibilities; and

• the Provider’s responsibilities.

You must do all the things that we ask you to do in that Deed. This is because yourdevelopment will have an impact on existing water, sewer and storm water services and youmay be required to adjust/deviate these assets and pay for the following works under thisDeed to provide these services.

Note: The Coordinator must be fully authorised by us for the whole time of the agreement.

4. Water and Sewer Works

4.1 Water

Your development must have a frontage to a water main that is the right size and can be

19

Page 20: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 4 Case No: 131752

used for connection.

Sydney Water has assessed your application and found that:

There is sufficient trunk capacity to service your development.

Adjustments will be required to the existing DN150 water main currently supplying the IMAXTheatre and the DN 200 water main that loops through Tumberlong Park to accommodatethe proposed development footprint.

A link main will need to be constructed between the two existing aforementioned DN150 andDN200 water mains to provide a point of connection with adequate capacity for domestic andcommercial services.

Fire services have not been assessed as part of this application. Sydney Water provides noguarantee that the proposed infrastructure will have sufficient capacity for fire services –Refer to Fire Fighting in ‘Other Things You Need to Do or Know’ below.

These works must be constructed by a constructor with the appropriate capability. YourCoordinator will be able to provide further advice about this.

4.2 Sewer

Your development must have a sewer main that is the right size and can be used forconnection. That sewer must also have a connection point within your development'sboundaries.

Sydney Water has assessed your application and found that:

There is sufficient trunk capacity for the proposed development.

Adjustments to the existing DN525 & DN300 sewer mains will be required to accommodatethe proposed development footprint.

A Sewer main extension will be required if the point of connection is remote from theproperty boundary.

The terms of the Deed define this extension as ‘Major Works’.

4.3 Stormwater Requirements.

Sydney Water has assessed your application and found that indicatively:

• The proposed development is in close proximity to existing Sydney Water stormwaterassets.

• There is insufficient information / clarity within the submitted documentation to facilitate aclear understanding of the potential impacts of the proposed development on SydneyWater stormwater assets or the potential impacts of the proposed development on local

20

Page 21: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 5 Case No: 131752

flooding.

• The applicant is requested to provide a Stormwater Impacts Report to assist SydneyWater in the assessment of the proposed development and the formulation of furtherrequirements related to Stormwater.

o The Stormwater Impacts Report is to be prepared by a suitably qualified andexperienced person (Water Servicing Coordinator to verify) with access to thecurrent Sydney Water GIS Asset Database (Hydra) via the lodging WaterServicing Coordinator.

o Any component of the proposed development within 10 metres of an existingSydney Water stormwater asset is to be clearly identified by the Water ServicingCoordinator in plan and described / itemised in the report.

On receipt of a suitable Stormwater Impacts Report, as part of either a new feasibility applicationor Section 73 Compliance application, Sydney Water shall issue further requirements related tostormwater.

Approval for any element of the proposed development that is within 10 metres of an existingSydney Water stormwater asset shall not be inferred, notwithstanding the content of anydocumentation provided to date, unless specifically approved in writing by Sydney Waterfollowing receipt and review of a suitable Stormwater Impacts Report.

• In general terms the proposed development is required to meet the followingrequirements:

o Where an existing structure is already placed in, on or near the stormwater assetin a manner that interferes with the operation of or accessibility to the asset andthe structure is to be demolished then any replacement structure shall generallynot be installed in a similar configuration / footprint without the writtenconcurrence of Sydney Water.

o Sydney Water will consider on merit any proposal to reinstate a replacementbuilding or structure in a similar configuration / footprint.

o No new structure is to be placed in, on or near the stormwater asset in a mannerthat interferes with the operation of or accessibility to the asset.

o Sydney Water would consider a proposal to deviate / relocate an existing SydneyWater stormwater asset to facilitate an improved development outcome.

o The development is to be configured and include any necessary design elementsor works to ensure that local flood risks are suitably managed and appropriatelymitigated. The proposed development shall incorporate sufficient floodmanagement elements to ensure that the development shall not increase floodrisks to the community nor shall there be any potential for increased communityexpectation or demand for stormwater asset amplification to be undertaken bySydney Water in the future.

21

Page 22: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 6 Case No: 131752

o A detailed 2D flood study will be submitted describing flood extents, velocities anddepths for a range of events (5yr, 20yr, 100yr) and provisional hydraulic andhazard categories (low and high).

o The proposed development will need to demonstrate a best practice approach tomanaging people and property in high flood hazard areas.

If the proposed development is required to discharge stormwater into Sydney Water’sstormwater channel, then a separate application is to be forwarded to Sydney Water.

All stormwater connections should comply with Sydney Water’s On-Site Detention policy andconnection requirements. For further details please contact Sydney Water’s StormwaterTeam on (02) 8849 4459 (or fax (02) 8849 3063)

5. Ancillary Matters

5.1 Asset adjustments

After Sydney Water issues this Notice (and more detailed designs are available), SydneyWater may require that the water main/sewer main/stormwater located in the footway/yourproperty needs to be adjusted/deviated. If this happens, you will need to do this work as wellas the extension we have detailed above at your cost. The work must meet the conditions ofthis Notice and you will need to complete it before we can issue the Certificate. SydneyWater will need to see the completed designs for the work and we will require you to lodge asecurity. The security will be refunded once the work is completed.

5.2 Entry onto neighbouring property

If you need to enter a neighbouring property, you must have the written permission of therelevant property owners and tenants. You must use Sydney Water’s Permission to Enterform(s) for this. You can get copies of these forms from your Coordinator or the SydneyWater website. Your Coordinator can also negotiate on your behalf. Please make sure thatyou address all the items on the form(s) including payment of compensation and whetherthere are other ways of designing and constructing that could avoid or reduce their impacts.You will be responsible for all costs of mediation involved in resolving any disputes. Pleaseallow enough time for entry issues to be resolved.

5.3 Costs

Construction of these future works will require you to pay project management, survey,design and construction costs directly to your suppliers. Additional costs payable toSydney Water may include:• water main shutdown and disinfection;• connection of new water mains to Sydney Water system(s);• design and construction audit fees;• contract administration, Operations Area Charge & Customer Redress prior to project

finalisation;

22

Page 23: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 7 Case No: 131752

• creation or alteration of easements etc; and• water usage charges where water has been supplied for building activity purposes prior

to disinfection of a newly constructed water main.

Note: Payment for any Goods and Services (including Customer Redress) provided bySydney Water will be required prior to the issue of the Section 73 Certificate orrelease of the Bank Guarantee or Cash Bond.

Your Coordinator can tell you about these costs.

6. Stamping and Approval of your Building Plans

You must have your building plans stamped and approved before the Certificate can beissued. Building construction work MUST NOT commence until Sydney Water hasgranted approval. Approval is needed because construction/building works may affectSydney Water’s assets (e.g. water and sewer mains).

Your Coordinator can tell you about the approval process including:• Your provision, if required, of a “Services Protection Report” (also known as a “peg-out”).

This is needed to check whether the building and engineering plans show accuratelywhere Sydney Water’s assets are located in relation to your proposed building work.Your Coordinator will then either approve the plans or make requirements to protectthose assets before approving the plans;

• Possible requirements;• Costs; and• Timeframes.

You can also find information about this process (including technical specifications) if youeither:• visit www.sydneywater.com.au > Building and Developing > Building and Renovating.

Here you can find Sydney Water’s Guidelines for Building Over/Adjacent to SydneyWater Assets; or

• call 13 20 92.

Notes:• The Certificate will not be issued until the plans have been approved and, if

required, Sydney Water’s assets are altered or deviated;• You can only remove, deviate or replace any of Sydney Water’s pipes using

temporary pipework if you have written approval from Sydney Water’s UrbanGrowth Business. You must engage your Coordinator to arrange this approval;and

• You must obtain our written approval before you do any work on Sydney Water’ssystems. Sydney Water will take action to have work stopped on the site if you donot have that approval. We will apply Section 44 of the Sydney Water Act 1994.

23

Page 24: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 8 Case No: 131752

OTHER THINGS YOU MAY NEED TO DO OR KNOWShown below are other things you need to do that are NOT a requirement for the Certificate.They may well be a requirement of Sydney Water in the future because of the impact of yourdevelopment on our assets. You must read them before you go any further.

Individual metering of units

All multi-level unit developments now have the option (not mandatory) to prepare their building’splumbing for individual unit metering. For more information visit www.sydneywater.com.au >Plumbing > Meters and look at our �ulti�level�individual��etering�guide� It is important that youunderstand that this will become mandatory from late 2013 and that you should consider this inplanning your development.

Disused Sewerage Service Sealing

Please do not forget that you must pay to disconnect all disused private sewerage services andseal them at the point of connection to a Sydney Water sewer main. This work must meetSydney Water’s standards in the NSW Code of Practice for Plumbing and Drainage (the Code)and be done by a licensed drainer. The licensed drainer must arrange for an inspection of thework by a NSW Fair Trading Plumbing Inspection Assurance Services (PIAS) officer. After thatofficer has looked at the work, the drainer can issue the Certificate of Compliance. The Coderequires this.

Soffit Requirements

Please be aware that floor levels must be able to meet Sydney Water’s soffit requirements forproperty connection and drainage.

Requirements for Business Customers for Commercial and Industrial PropertyDevelopments

If this property is to be developed for Industrial or Commercial operations, it may need to meetthe following requirements:

Trade Wastewater Requirements

If this development is going to generate trade wastewater, the property owner must submit anapplication requesting permission to discharge trade wastewater to Sydney Water’s seweragesystem. You must wait for approval of this permit before any business activities can commence.

The permit application should be emailed to Sydney Water’s Business Customer Services [email protected]

It is illegal to discharge Trade Wastewater into the Sydney Water sewerage system withoutpermission.

A Boundary Trap is required for all developments that discharge trade wastewater wherearrestors and special units are installed for trade wastewater pre-treatment.

24

Page 25: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 9 Case No: 131752

If the property development is for Industrial operations, the wastewater may discharge into asewerage area that is subject to wastewater reuse. Find out from Business Customer Services ifthis is applicable to your development.

Backflow Prevention Requirements

Backflow is when there is unintentional flow of water in the wrong direction from a potentiallypolluted source into the drinking water supply.

All properties connected to Sydney Water's supply must install a testable Backflow PreventionContainment Device appropriate to the property's hazard rating. Property with a high ormedium hazard rating must have the backflow prevention containment device tested annually.Properties identified as having a low hazard rating must install a non-testable device, as aminimum.

Separate hydrant and sprinkler fire services on non-residential properties, require the installationof a testable double check detector assembly. The device is to be located at the boundary of theproperty.

Before you install a backflow prevention device:1. Get your hydraulic consultant or plumber to check the available water pressure versus

the property’s required pressure and flow requirements.2. Conduct a site assessment to confirm the hazard rating of the property and its services.

Contact PIAS at NSW Fair Trading on 1300 889 099.

For installation you will need to engage a licensed plumber with backflow accreditation who canbe found on the Sydney Water website:http://www.sydneywater.com.au/Plumbing/BackflowPrevention/

Water Efficiency Recommendations

Water is our most precious resource and every customer can play a role in its conservation. Byworking together with Sydney Water, business customers are able to reduce their waterconsumption. This will help your business save money, improve productivity and protect theenvironment.

Some water efficiency measures that can be easily implemented in your business are:• Install water efficiency fixtures to help increase your water efficiency, refer to WELS

(Water Efficiency Labelling and Standards (WELS) Scheme, http://www.waterrating.gov.au/

• Consider installing rainwater tanks to capture rainwater runoff, and reusing it, where costeffective. Refer to http://www.sydneywater.com.au/Water4Life/InYourBusiness/RWTCalculator.cfm

• Install water-monitoring devices on your meter to identify water usage patterns and leaks.• Develop a water efficiency plan for your business.

It is cheaper to install water efficiency appliances while you are developing than retrofitting themlater.

25

Page 26: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 10 Case No: 131752

Contingency Plan Recommendations

Under Sydney Water's customer contract Sydney Water aims to provide Business Customerswith a continuous supply of clean water at a minimum pressure of 15meters head at the maintap. This is equivalent to 146.8kpa or 21.29psi to meet reasonable business usage needs.

Sometimes Sydney Water may need to interrupt, postpone or limit the supply of water servicesto your property for maintenance or other reasons. These interruptions can be planned orunplanned.

Water supply is critical to some businesses and Sydney Water will treat vulnerable customers,such as hospitals, as a high priority.

Have you thought about a contingency plan for your business? Your Business CustomerRepresentative will help you to develop a plan that is tailored to your business and minimisesproductivity losses in the event of a water service disruption.

For further information please visit the Sydney Water website at: http://www.sydneywater.com.au/OurSystemsandOperations/TradeWaste/ or contact BusinessCustomer Services on 1300 985 227 or [email protected]

Fire Fighting

Definition of fire fighting systems is the responsibility of the developer and is not part of theSection 73 process. It is recommended that a consultant should advise the developer regardingthe fire fighting flow of the development and the ability of Sydney Water’s system to provide thatflow in an emergency. Sydney Water’s Operating Licence directs that Sydney Water’s mains areonly required to provide domestic supply at a minimum pressure of 15 m head.

A report supplying modelled pressures called the Statement of Available pressure can bepurchased through any Quickcheck agent and may be of some assistance when defining the firefighting system. The Statement of Available pressure, may advise flow limits that relate tosystem capacity or diameter of the main and pressure limits according to pressure managementinitiatives. If mains are required for fire fighting purposes, the mains shall be arranged throughthe water main extension process and not the Section 73 process.

Large Water Service Connection

A water main will be available, once you have completed your drinking water main constructionto provide your development with a domestic supply. The size of your development means thatyou will need a connection larger than the standard domestic 20 mm size.

To get approval for your connection, you will need to lodge an application with a Quick CheckAgent. You, or your hydraulic consultant, may need to supply the following:

• A plan of the hydraulic layout;• A list of all the fixtures/fittings within the property;• A copy of the fire flow pressure inquiry issued by Sydney Water;

26

Page 27: Hydraulic Infrastructure Report Grocon Group Development

SYDNEY WATER CORPORATION 11 Case No: 131752

• A pump application form (if a pump is required);• All pump details (if a pump is required).

You will have to pay an application fee.

Sydney Water does not consider whether a water main is adequate for fire fighting purposes foryour development. We cannot guarantee that this water supply will meet your Council’s firefighting requirements. The Council and your hydraulic consultant can help.

Disused Water Service Sealing

You must pay to disconnect all disused private water services and seal them at the point ofconnection to a Sydney Water water main. This work must meet Sydney Water’s standards inthe NSW Code of Practice for Plumbing and Drainage (the Code) and be done by a licensedplumber. The licensed plumber must arrange for an inspection of the work by a NSW FairTrading Plumbing Inspection Assurance Services (PIAS) officer. After that officer has looked atthe work, the drainer can issue the Certificate of Compliance. The Code requires this.

Other fees and requirementsThe requirements in this Notice relate to your Certificate application only. Sydney Water may beinvolved with other aspects of your development and there may be other fees or requirements.These include:

• plumbing and drainage inspection costs;• the installation of backflow prevention devices;• trade waste requirements;• large water connections and• council fire fighting requirements. (It will help you to know what the fire fighting

requirements are for your development as soon as possible. Your hydraulic consultantcan help you here.)

No warranties or assurances can be given about the suitability of this document or any ofits provisions for any specific transaction. It does not constitute an approval fromSydney Water and to the extent that it is able, Sydney Water limits its liability to thereissue of this Letter or the return of your application fee. You should rely on your ownindependent professional advice.

END

27

Page 28: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

10. Appendix 5 – Sydney Water – Meeting Minutes

Page 29: Hydraulic Infrastructure Report Grocon Group Development

Meet

Held wit

Location

Regardi

In attend

Comme

RR

JRpRd

ting Mi

th: Syd

n: Syd

ng: Hay

dance: Ray

Jey

Geo

Luk

Dom

nts:

RP initially noRP outlined t

o It is aexist

o If theachie

o Legaautobeyo

JJ noted thatRP noted thaprotected if bRP outlined tdecision on w

o A De- If th- If th- The- Anyinfras

o A Se- Siz- Zon- Pro

nutes

dney Water (

dney Water -

y-Lackey Cu

y Persell (RP

ya Jeyadevan

off Briggs (G

ke De Gioia (

minic De Gio

oted that SWthat consideramending anting building e lease area eved by any acy developmmatic justifica

ond the existit the culvertsat it is up to thbuilt overthe requiremworks over theviation Repohe services che building cae reasons any potential fostructure

ervices Proteze, depth, locne of influencoposed const

(SW)

- Parramatta

lverts

P)

n (JJ)

GB)

(LDG)

oia (DDG)

W’s first preferation will be n existing builinehas assets rother means

ments, such aation for futuing boundarys are approximhe developm

ents that neehe culvert. Tort outlining:can be relocaan be relocat

nd issues as tor amendmen

ction Report cation etc of tce of the surrtruction and p

Da

Pa

Me

Co

rence is not tmade if: lding which e

unning throusas the existinre works, es

ymately 80 ye

ment team to

ed to be provhese include

atedted to why the bunt of the build

outlining: he existing srounding struprotection of

ate:

ages:

eeting #:

ompany:

to build over

exists over an

gh the site a

ng IMAX Cinepecially whe

ears old and tdemonstrate

vided to Sydne:

uilding must ding to be sym

services ucture the assets b

27 Novembe

2

1

Sydney Wat

Sydney Wat

Grocon Grou

EWFW (EW

EWFW (EW

the stormwa

n asset but o

nd developm

ema would nore the develo

their age will e how the SW

ney Water in

be located ampathetic to

below

er 2012 – 11

ter (SW)

ter (SW)

up (GG)

WFW)

WFW)

ater

only to the ex

ment cannot b

ot generally opment would

be a consideW asset will b

order to mak

s nominatedthe surround

.15am

xtent of the

be

be an d extend

eration. e

ke a

ding

29

Page 30: Hydraulic Infrastructure Report Grocon Group Development

Meeting Minutes EWFW

- Dilapidation reporting - Maintenance and access requirements and potential methods for replacing the stormwater in the future

o A Flood Study outlining: - Overland flow paths for existing and proposed - Capacity assessments - Impacts associated with the stormwater and the proposed buildings

JJ noted that the existing culverts are 3.9m x 2.2m and 3.0m x 2.2m and they have been sized using the rational method for a 100 year capacity

JJ is happy to allow access to any information SW has available and copies can be made of existing information. There may be a condition report for the culverts. JJ can be approached to find further information however the SW contact who would be aware of this information is currently on holidays for 2 weeks

RP noted that the main issues in which SW would not allow any construction is if there are overland flow path and flooding issues that can’t be rectified or if the assets could not be cost effectively renewed in the future

RP noted that a decision would be made a couple of weeks after all of the above information was available to SW

Issues for Resolution

EWFW to provide information on Dilapidation Contractor used for previous project to GG GB to confirm if these works are covered under Bonacci Contract In the event that Bonacci are not providing Flood Study EWFW to provide details to have Flood

Study conducted All services will be required to provide information for the Deviation Report as required

30

Page 31: Hydraulic Infrastructure Report Grocon Group Development

Meet

Held wit

Location

Regardi

In attend

Comme

RoRoRtSh

SRpRwRr

Attached

DB

ting Mi

th: Syd

n: Syd

ng: Hay

dance: Ray

Jey

Ste

Dom

nts:

RP & JJ provor adjacent toRP & JJ provover or adjacRP & JJ provthe informatioSN requestehe will requir

o 2D mo Inforo SW a

and o RP n

SW iSN requesteRP noted thaprovide a gooRP suggestewith access tRP suggestereview and re

d documents

Darling HarbBuilding over

nutes

dney Water (

dney Water -

y-Lackey Cu

y Persell (RP

ya Jeyadevan

ephen Naugh

minic De Gio

vided the newo stormwatervided the newcent to stormvided a Termon discussedd the scope o

re:model rmation to share looking focall out requ

nominated thin order to prd design flow

at the informaod starting p

ed that we neto the buildined that we proecommend a

:

bour IMAX Thr or adjacent

(SW)

- Parramatta

lverts

P)

n (JJ)

hton (SN)

oia (DDG)

w guidelines r.w policy docuwater.

ms of Reply dod at the previof informatio

ow that the por confirmatioirements at SN shouldrevent BG unw informationation is basedoint but it sho

eed to look atng if they are ovide a “Drafany additiona

heatre – Feasto Sydney W

Da

Pa

Me

Co

that have be

ument that ha

ocument in rious meetingn required fo

proposed syson of a syste

d provide higndertaking con which was pd on capacityould not be tht their mainteperforming mft Report” for

al information

sibility CN113Water stormw

ate:

ages:

eeting #:

ompany:

een released

as been relea

relation to the.

or the overlan

stem will adhem that will he

h level informostly work forprovided on Cy estimates uhe fundamen

enance requirmaintenancer all sections n requirement

31752 water assets -

25 March 20

2 + Attachm

2

Sydney Wat

Sydney Wat

Bonacci Gro

EWFW (EW

by SW in rel

ased by SW

e site. This d

nd flow inform

ere to “Best elp to reduce

mation at firstr no reason CD by JJ. using the Ratntal basis of trements so t.before submts.

- Policy

013 – 11.00a

ments

ter (SW)

ter (SW)

oup (BG)

WFW)

lation to build

in relation to

document is i

mation. RP n

Practice” e maintenanc

t for a “Draft

tional Methodthe calculatiohat there are

mission in ord

am

ding over

o building

n line with

noted that

ce issues

review” by

d. This will ons. e no issues

der to

31

Page 32: Hydraulic Infrastructure Report Grocon Group Development

Meeting Minutes EWFW

Building over or adjacent to Sydney Water stormwater assets - Guidelines

32

Page 33: Hydraulic Infrastructure Report Grocon Group Development

33

Page 34: Hydraulic Infrastructure Report Grocon Group Development

34

Page 35: Hydraulic Infrastructure Report Grocon Group Development

35

Page 36: Hydraulic Infrastructure Report Grocon Group Development

36

Page 37: Hydraulic Infrastructure Report Grocon Group Development

37

Page 38: Hydraulic Infrastructure Report Grocon Group Development

38

Page 39: Hydraulic Infrastructure Report Grocon Group Development

39

Page 40: Hydraulic Infrastructure Report Grocon Group Development

40

Page 41: Hydraulic Infrastructure Report Grocon Group Development

41

Page 42: Hydraulic Infrastructure Report Grocon Group Development

42

Page 43: Hydraulic Infrastructure Report Grocon Group Development

43

Page 44: Hydraulic Infrastructure Report Grocon Group Development

44

Page 45: Hydraulic Infrastructure Report Grocon Group Development

45

Page 46: Hydraulic Infrastructure Report Grocon Group Development

46

Page 47: Hydraulic Infrastructure Report Grocon Group Development

47

Page 48: Hydraulic Infrastructure Report Grocon Group Development

48

Page 49: Hydraulic Infrastructure Report Grocon Group Development

49

Page 50: Hydraulic Infrastructure Report Grocon Group Development

50

Page 51: Hydraulic Infrastructure Report Grocon Group Development

51

Page 52: Hydraulic Infrastructure Report Grocon Group Development

52

Page 53: Hydraulic Infrastructure Report Grocon Group Development

53

Page 54: Hydraulic Infrastructure Report Grocon Group Development

54

Page 55: Hydraulic Infrastructure Report Grocon Group Development

EWFW

Wheat Rd, Sydney Revision E

Hydraulic Infrastructure Report 19 July 2013

11. Appendix 6 – Jemema – Meeting Minutes Note: The initial meeting was undertaken during the development of the first iteration of the building. As such the plans as included in the minutes were for the previous scheme. Whilst the building shape has changed in subsequent iterations it will have no impact on the gas services proposed nor will it vary the works as per the discussions held in this meeting.

Page 56: Hydraulic Infrastructure Report Grocon Group Development

Meet

Held wit

Location

Regardi

In attend

Comme

AJAtDsAcAiGAIbIGAeAo

Issues f

EE

ting Mi

th: Jem

n: On

ng: Jem

dance: Ann

And

Geo

Dom

nts:

AL outlined tJemena servAL noted thathat requires DDG noted tsite. AW noted thaclose to capaAW nominateinvolved as pGB informedAL nominateIt was discusboundary lineIt is unlikely tGB questioneAL confirmedextended thrAL suggesteoption. They

for Resolutio

EWFW to proEWFW to pro

nutes

mena (JE)

site – Darlin

mena Gas Ma

ne Woodwar

drew Lelliott

off Briggs (G

minic De Gio

he location ovices runningat there is an

upgrade. hat there will

at the increasacity at preseed that due topart of the pro Jemena tha

ed that any pissed that re-de) is problemthat there wiled if there wed that the nexrough the CBd that re-divey will explore

on

ovide all Dialovide a draw

g Harbour

ains

rd (AW)

(AL)

GB)

oia (DDG)

of the existingg under the ex

existing regu

l be a co-gen

sed load will ent. o the nature ocess.

at demolition pework needdiverting the

matic due to thll be an acceere other netxt closest line

BD. erting the pipthis further.

l Before you wing nominati

Da

Pa

Me

Co

g main. He axisting IMAXulator station

n plant in add

need to be c

of the projec

is likely to cods to be provpipework in the adjacent rss corridor otwork lines ine was severa

pework (North

Dig informating proposed

ate:

ages:

eeting #:

ompany:

also confirmeX building.

located on t

dition to retail

considered a

ct that severa

ommence midvided with excthe vicinity ofroadways an

of sufficient sin the vicinity wal blocks awa

hern side of t

ion to Jemend relocation ru

18 Decembe

5

1

Jemena (JE

Jemena (JE

Grocon Grou

EWFW (EW

ed that there

the Southern

l and plant an

as the Sydney

al divisions in

d 2013. cavation accf its current lo

nd the adjaceize. which could aay and would

the site) is lik

na (AL/AW) un to Jemena

er 2012 – 8.3

)

)

up (GG)

WFW)

are currently

boundary of

nd equipmen

y CBD feed i

n Jemena wil

ess.ocation (Sou

ent electrical s

act as the feed require pipe

kely to be the

a (AL/AW)

30am

y no

f the site

nt for the

s running

l be

thern services.

ed line. ework to be

e best

56

Page 57: Hydraulic Infrastructure Report Grocon Group Development

Meeting Minutes EWFW

JE will provide details on their proposed relocations once they have reviewed the documentation provided

Drawings Attached

Sydney Water Mains Maps Hassell Existing Services Overlay EWFW Existing Services Overlay including proposed relocation Electrical Mains Maps from Dial Before You Dig

57

Page 58: Hydraulic Infrastructure Report Grocon Group Development

58

Page 59: Hydraulic Infrastructure Report Grocon Group Development

SP

0012

ST

ST

PL

DR

UIT

T

DR

UIT

T

KENT

LAN

E

DR

UIT

T

WHEAT

PL

BLA

CK

WA

TT

LE

DAY

STSANDS

ST

WE

ST

ER

N

BA

TH

UR

ST

DAY

JAMES

DS

TRS

T

SUSSEX

LANE

JAM

ES

ST

RP

VSE

VSE

VERT

VERT

RP

VSE

VSE

VSE

VSE

DisDis

Dis

Dis

Dis Dis

Dis

DisDis

Dis

Dis Dis Dis

Dis

Dis Dis Dis

DisDisDis

Dis

Dis

Dis

Dis

Dis

Dis

Dis

DisDis

Dis

Dis

Dis

Dis

Dis

Dis

Dis

Dis

VERT

BAY

2

B

A

1 20

CP

CP

16

1

11

12

CP

1

8

10C

50 51

4

5

A

BCP 1

1 1CP

2 10010 1

CPCP

101 1 1

11

11

21

C 1

1 1

CP

60

17

60

42

65

40

56

62

10

61

2

4

9

1

20

503

601

504

602

10

1010

60

63

64

402

401

405

404

306

218

4042

403 25

53

800

805

801

CP

34 5

A

23 1 1

B

313

313 1 1

100

100

C

10

1

804

802

803

730

58

9

806

901

1

1 12 2

1

CP3

1

3

1

CP

333

CP

1

4

502

200

414-418

222-228

439 439-441

230

234

25245

3-46

348

-58

465-467469

491499-501

503-505

507-509

259-261259-261

263

51 278

265 267 269

477

499-

501

286

493-495

499-

501

70-7

2

70-7

2

286

273-275 277

286 286

289-295

168

299-305

307 309

176-182

311

313-315 317 319 321-325 321-325

188

511 521-527 521-527 529 531

298-304306-318

318A

320-332

333-337327

336-346

533-5

192-

196

447

281-287

201

201

150

1-25

1-25

25G

11

1

3

5

13

1-25

2.04

1.8

2.1

20.2

27.4

10.1

20.4

43.6

29.9

43.0

34.1

3.3

18.6

26.8

36.0

37.2

13.4

21.

6.7

8.2

19.2

40.8

47.5

42.1

42.7

50.0

55.5

56.1

59.7 3.

8

2.7

7.6

13.1

18.9

29.3

11.3

8.5

15.2

34.4

34.4 33.2

3.75.5

26.8 25.6

16.5

21.3 19.3

15.2

9.6 5.3

39.6

36.9

38.0

8.7

4.3

26.6

1.3

11.0 2.7

23.7

2.8

41.2

53.9

15.7

38.2

33.

43.3

41.8 30.2 82

.3 71.9

59.1

51.8

6.14.6

6.4

4.54

1.68

1.8

2.57

4.67

4.79

1.52

3.59

3.65

2.63

4.87

5.01

1.0

1.0

7.5 2.49 2.13

2.99

2.52 5.18

2.7

4.76

4.95

4.92

6.27

1.53 5.21

17.7

2.55

3.20

9

7.2

5.4

2.6

2.9

2.99

2.9

3.16

3.9

3.5

5.25

5.26

1.79

3.8

1.2

3.9

4.56

4.1

MH Chmb

4.01

9

4.92

6.7

MH Chmb

6.64

5.99

4.53

3.0

3.91

2.9

6.39

5.74

6.331.7

2

1.89

4.29

4.74

5.2

1.95

1.75

1.0

2.22

2.7

2.6

5.4

3.96

3.95

3.86

3.81

3.31

MH C

hmb

5.8

5.1

3.1

7.8

3.64

3.8

2.2

5.3

Conc Encased

In T

unne

l

Conc

Enc

ased

Conc Encased

Conc E

ncas

ed

Conc

Enc

ased

Conc Encased

Conc

Enc

ased

Conc Encased

In T

unne

l

300 V

C711x1066 CONC

300 VC

300 VC300 PVC

225 VC

300

VC30

0 VC

225 VC

300 P

VC

300

PVC

300 PVC

300 VC

711x1066 CONC

300

EW

300

PVC

711x1066 CONC 711x1066 CONC

225 VC

711x1066 CONC

300 PVC

300 P

VC

300 PVC

300

PVC

225 VC

225 VC

225

VC30

0 VC

300 VC

300 VC

150 PVC

300

CICL

300

CICL

300

CICL

300 VC

300 CICL

300

PVC

300

VC

219 SCL 300 VC 300 VC

300 PVC

300 VC 300 VC

300 V

C

300

VC

300 CICL 300

VC

300 VC

525

VC

300 V

C

525 VC525 VC

300 V

C30

0 VC

300

CICL

750 V

C

750 V

C

750 V

C

750 V

C

750 V

C

1300x1750 Unlined Rock

375 VC 750 VC

750 VC

450 VC

300 PVC

300 PVC

300 VC

300

VC

300 VC

300 PVC 300 VC

300

VC

450 VC

750 V

C

450 V

C

450 VC

750

VC

750

VC

300

VC52

5 VC 225 VC

711x1066 CONC

150VC

225 VC

300 VC300 VC 300 VC

225

VC

300 VC 400 VC

300 VC

375 VC

3.0

2.9

3.1

2.9

0.5

0.8 6.4 3.8

6.4 4.

1 2.8

4.6 3.

1

3.0

3.0 0.8 2.

9

2.9

2.7

0.4

3.1

1.6

2.9 2.9

3.0

3.5

3.8

2.3

3.2

2.3

3.0

3.0 2.1

1.8

2.9

1.8

3.0

3.0

3.1

3.1

3.02.52.3

3.0 3.

0 2.8

2.8

2.9

2.8 3.0

1.8

Conc. Encased

150 CICL

200 CICL200 CICL

300 CICL

200

DICL

200

DICL

250

DICL

300

CICL 250 DICL 273 SCL

324 SCL32

4 SC

L20

0 DI

CL

250

DICL

273

SCL

150 CICL

300 DICL

273 S

CL

150 oPVC

250 CICL

500 CICL

150 oPVC

273 SCL

250

CICL

250 CICL

500 CICL150 CICL

150 CICL

500 CICL

300 CICL

150

CICL

150

DICL

150

DICL

150 CICL

300 CICL

150 CICL

150 CICL

150 S

CL

150 CICL

150 CICL

150 CICL

200

CICL

150 CICL

150 DICL

300

SCL

200

SCL

250

SCL

250 SCL

250 D

ICL

150

CICL

250 CICL

150

SCL

150

SCL

150 CICL

200

SCL

200 DICL

200

DICL

200 SCL

200 D

ICL

200

DICL

200 S

CL

200 DICL

250 SCL

150

DICL

150

DICL

200

DICL

200 DICL

200

DICL

200 DICL

250DICL

250 DICL

300 DICL

300 DICL

300 DICL

200 DICL

200 S

CL

250

CICL

300 CICL

250 CICL

200 SCL

200 DICL

250 CICL

200 DICL

200 DICL

200 DICL

200

DICL

200 DICL

200

CICL

150

CICL

150

CICL

150

CICL

200 CICL

500 CICL

150 CICL

200 CICL

150

CICL

200 DICL

250 CICL

5.45.4

5.85

5.15.

450 VCVC

450 V

C45

0 VC

450 VC

2.3 2.3

25G25G4.

29

5.25

450 VC50 VC50 VC

00SC

L0SC

LCL

INFO

RM

ATI

ON

ELS

EW

HE

RE

: see

GU

IDE

ref

112

133

3.33

33331

022

805

25G25G

4.53

L CL

RE

: sR

ER

E:

RE

REE

: sR

EIN

FOR

MA

TIO

N E

LSE

WH

ER

E: s

ee G

UID

E r

ef 1

1717

8

N0m

9m18

m27

m36

m

Copy

right

Res

erve

d Sy

dney

Wat

er 2

012

Plan

1 o

f 1A3

Date

of P

rodu

ction

: 15/

11/2

012

DBYD

Seq

uenc

e No

: 270

6687

6

DBYD

Add

ress

: 1-

5 W

heat

Rd

Sydn

ey N

SW 2

000

SYDN

EY W

ATER

COR

PORA

TION

No w

arra

nty i

s give

n th

at th

e inf

orm

ation

show

n is

com

plete

or a

ccur

ate.

DBYD

Job

No: 1

1783

7Sc

ale: 1

:150

0

59

Page 60: Hydraulic Infrastructure Report Grocon Group Development

60