Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
EWFWSuite 5, Level 1
330 Wattle St
Ultimo NSW 2007
ABN: 48 130 395 827
Hydraulic Infrastructure Report Grocon Group Development Application Submission 31 Wheat Rd, Sydney
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
Table of Contents
1. Introduction 31.1. Purpose 31.2. Authority 31.3. Objectives of Study 31.4. Outline 31.5. Terminology 3
2. Technical Information 42.1. Author Details 42.2. Information Sources 42.3. Disclaimer of Liability 42.4. Copyright© 42.5. Revision History 4
3. Area of consideration 54. Existing Infrastructure Services 6
4.1. SWC Water Main 64.2. SWC Sewer Main 64.3. SWC Stormwater Main 64.4. Jemena Gas Main 6
5. Consideration of Authority Infrastructure 85.1. SWC Water Main 85.2. SWC Sewer Main 85.3. SWC Stormwater Main 85.4. Jemena Gas Main 8
6. Appendix 1 – Sydney Water Mains Map 107. Appendix 2 – Jemena Mains Map 128. Appendix 3 – Indicative Infrastructure Location 149. Appendix 4 – Sydney Water Letter of Feasibility 1610. Appendix 5 – Sydney Water – Meeting Minutes 2811. Appendix 6 – Jemema – Meeting Minutes 55
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
1. Introduction
1.1. Purpose This report has been produced by EWFW Pty Ltd in response to the request from Justin Clark from Grocon Group.
The purpose of this report is to provide an assessment of the hydraulic infrastructure within the vicinity of the proposed development at 31 Wheat Rd, Sydney.
This report shall not be relied upon as providing any warranty or guarantee of the building, its services or equipment.
1.2. Authority Authority to undertake this report was provided by Justin Clark of Grocon Group on 20 November 2012.
1.3. Objectives of Study The objectives of the report are to:
Outline the details of the surrounding infrastructure.
Nominate areas of concern.
Outline the steps that will be taken to ensure that the infrastructure is considered.
Provide recommendations.
1.4. Outline The following services have been assessed in this report:
Water services Sewer services Stormwater Gas Services
1.5. Terminology The abbreviations and notations referred to within this report relate to the following:
CICL Cast Iron Concrete Lined
DICL Ductile Iron Concrete Lined
kPa Kilopascals
mm Millimetres
NOR Notice of Requirements (Sydney Water)
SWC Sydney Water Corporation
VC Vitrified Clay
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
2. Technical Information
2.1. Author Details EWFW Pty Ltd Suite 5, Level 1, 330 Wattle St Ultimo NSW 2007 ABN: 48 130 395 827 Phone: + 61 2 9212 1000 Fax: + 61 2 9212 1000 E-mail: [email protected]
Author: Dominic De Gioia Director
Reviewer Luke De Gioia Director
2.2. Information Sources Information provided by Sydney Water as part of the Dial Before you Dig Program.
Information provided by Jemena as part of the Dial Before you Dig Program.
Information provided by Justin Clark of Grocon.
Information obtained during site inspections and from drawings provided on site.
Various manufacturers and suppliers.
2.3. Disclaimer of Liability The information contained in this document is provided for the sole use of the recipient and no reliance should be placed on the information by any other person. In the event that the information is disclosed or furnished to any other person, EWFW accepts no liability for any loss or damage incurred by that person whatsoever as a result of using the information.
2.4. Copyright© All rights reserved. No part of the content of this document may be reproduced, published, transmitted or adapted in any form or by any means without the written permission of EWFW.
2.5. Revision History
Revision Date Issued Comment
A 22 November 2012 Draft
B 4 December 2012 Final Issue
C 11 December 2012 Final Issue – Revised site title
D 21 June 2013 Final Issue – Revised building
E 19 July 2013 For Development Application
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
3. Area of consideration The area of consideration relates to 31 Wheat Rd, Sydney.
The proposed area (bounded approximately by the red square in the picture below) currently consists of the IMAX Theatre and associated retail areas.
Figure 3.1. Proposed site
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
4. Existing Infrastructure Services 4.1. SWC Water Main
The site is flanked by two (2) Sydney Water water mains. These mains are:
A 200mm DICL main located on the western end of the site (See Appendix 1 – Note 1)
A 150mm CICL dead leg capped main located on the eastern end of the site (See Appendix 1 – Note 2)
From the proposed footprint of the development both mains will be within the line of the building construction. It will be proposed to move the line of the water services to ensure they are diverted clear of the proposed building line. In addition to this, it is proposed that the 150mm and 200mm mains will be interconnected to extend the Sydney Water network within this region. This is in line with the requirements put forward by Sydney Water in their Letter of Feasibility for the site (Refer to Appendix 4).
4.2. SWC Sewer Main The site is flanked by several Sydney Water sewer mains and associated equipment. These include:
A 525 VC sewer main located at the eastern end of the site (See Appendix 1 – Note 3)
A 300 VC sewer main located at the southern end of the site (See Appendix 1 – Note 4)
A pump station and a vent shaft adjacent the site. This site pump station is also heritage listed.
Access chambers along both of the sewer mains nominated above
From the proposed footprint of the development both mains will be within the line of the building construction. It will be proposed to move the line of the sewer services to ensure they are diverted clear of the proposed building line. This is in line with the requirements put forward by Sydney Water in their Letter of Feasibility for the site (Refer to Appendix 4).
The Southern Lease Area of the proposed development (See Appendix 3) is located clear of the 750 VC sewer main (See Appendix 1 – Note 5). Further assessment will be conducted in conjunction with Structural Engineers as part of the design process to ensure that the proposed structure will have no impact on the service. This shall also be confirmed with Sydney Water as part of the Sydney Water Notice of Requirements.
4.3. SWC Stormwater Main As there are two significant stormwater mains running below the site there will be a protection requirement as part of the works. These mains include a set of culverts which traverse through the centre of the site in a north-south direction (known as the Hay Lackey Culverts) and a set which are located at the western side of the proposed development site.
The existing development currently sits above culverts and these will continue to be affected by the proposed development. Whilst the building footprint does not directly impinge the culverts at the western end of the site Sydney Water will be consulted in order to ensure all steps are taken to protect their adjacent assets.
Any works will be at the discretion of Sydney Water and their conditions as nominated.
4.4. Jemena Gas Main The site is flanked at the south-eastern corner and along the eastern boundary by Jemena gas infrastructure. This includes:
A 110mm Nylon main located at the eastern end of the site (See Appendix 2 – Note 1)
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
A 50mm Nylon main located at the south-eastern end of the site (See Appendix 2 – Note 2)
A Secondary gas main (1050kPa) and a pressure reduction station located at the south-eastern end of the site (See Appendix 2 – Note 3)
Authority infrastructure to supply the Aquarium located at the south-eastern end of the site (See Appendix 2 – Note 4)
From the proposed footprint of the development both mains will be within the line of the building construction. It will be proposed to move the line of the gas services to ensure they are diverted clear of the proposed building line. These lines will run to the west and then the north of the building line, remaining clear of all adjacent supply authority infrastructure. This will be at the discretion of Jemena and their conditions nominated.
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
5. Consideration of Authority Infrastructure 5.1. SWC Water Main
Sydney Water’s Letter of Feasibility has deemed that the adjacent water mains will be sufficient to satisfy the requirements of the proposed building. Sydney Water has nominated that the 150mm and 200mm water mains need to be relocated clear of the building line and interconnected. These works will be completed as part of the development. Subject to the final requirements set forth by Sydney Water, the building will be connected to the 200mm service.
A Sydney Water Co-ordinator will be engaged once the Development Application has been submitted. The Sydney Water Co-ordinator will provide the submission of a Section 73 Application to Sydney Water in order to obtain the Notice of Requirements for the development.
Works outlined within the Notice of Requirements will be undertaken by the Sydney Water Co-ordinator in accordance with Sydney Water’s Design Guidelines. Any works to the mains will be undertaken by Sydney Water approved contractors as nominated by the Water Co-ordinator.
5.2. SWC Sewer Main Sydney Water’s Letter of Feasibility has deemed that the adjacent sewer mains will be sufficient to satisfy the requirements of the proposed building. Sydney Water has nominated that the 525mm and 300mm sewer mains need to be relocated clear of the building line. These works will be completed as part of the development. Subject to the final requirements set forth by Sydney Water, the building will be connected to the 525 VC service through a connection at one of the adjacent access chambers.
A Sydney Water Co-ordinator will be engaged once the Development Application has been submitted. The Sydney Water Co-ordinator will provide the submission of a Section 73 Application to Sydney Water in order to obtain the Notice of Requirements for the development.
Works outlined within the Notice of Requirements will be undertaken by the Sydney Water Co-ordinator in accordance with Sydney Water’s Design Guidelines. Any works to the sewer mains will be undertaken by Sydney Water approved contractors as nominated by the Water Co-ordinator.
5.3. SWC Stormwater Main Presently we have commenced discussions with Jeya Jeyadevan and Raymond Parsell of the Sydney Water Stormwater Group. Several meetings have been undertaken to date in order to determine the requirements for any works which will affect the stormwater culverts, particularly the Hay Lackey culverts which traverse below the building line. Sydney Water has outlined the information they require which we will provided to Sydney Water as part of the Design Development.
Any direction or requirements provided by Sydney Water’s stormwater group in terms of construction over, or protection of these assets will be undertaken in strict accordance with the requirements nominated.
5.4. Jemena Gas Main Based on the initial site meeting with Anne Westwood and Andrew Lelliott of Jemena, the adjacent gas mains are running close to capacity. Jemena are in the process of reviewing their capabilities within the region and the strategy for supply to this area and the adjacent CBD. This will see additional supply within the region which will satisfy the supply required for the calculated building demand. Presently it is proposed that connection be made to the main located at the rear of the site (pending final gas diversion routes).
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
Any direction or requirements provided by Jemena in terms of construction over, relocation or protection of these assets will be undertaken in strict accordance with the requirements nominated.
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
6. Appendix 1 – Sydney Water Mains Map
SP
0012
ST
ST
PL
DR
UIT
T
DR
UIT
T
KENT
LAN
E
DR
UIT
T
WHEAT
PL
BLA
CK
WA
TTLE
DAY
STSANDS
ST
WE
STE
RN
BA
THU
RS
T
DAY
JAMES
DS
TRS
T
SUSSEX
LANE
JAM
ES
ST
RP
VSE
VSE
VERT
VERT
RP
VSE
VSE
VSE
VSE
DisDis
Dis
Dis
Dis Dis
Dis DisDis
Dis
Dis Dis Dis
Dis
Dis Dis Dis
DisDisDis
Dis
Dis
DisDis
Dis
Dis
Dis
DisDis
Dis
Dis
DisDis
Dis
Dis
Dis
Dis
VERT
BAY
2
B
A
1 20
CP
CP
16
1
11
12
CP
1
8
10C
50 51
4
5
A
BCP 1
1 1CP
2 10010 1
CPCP
101 1 1
11
11
21
C 1
1 1
CP
60
17
60
42
65
40
56
62
10
61
2
4
9
1
20
503
601
504
602
10
1010
60
63
64
402
401
405
404
306
218
4042
403 25
53
800
805
801
CP
3 4 5
A
23 1 1
B
313
313 1 1
100
100
C
10
1
804
802
803
730
58
9
806
901
1
1 12 2 1
CP3
1
3
1
CP
333
CP
1
4
502
200
414-418
222-228
439 439-441
230
234
25245
3-46
348
-58
465-467469
491499-501
503-505
507-509
259-261259-261
263
51 278
265 267 269
477
499-
501
286
493-495
499-
501
70-7
2
70-7
2
286
273-275 277
286 286
289-295
168
299-305
307 309
176-182
311
313-315 317 319 321-325 321-325
188
511 521-527 521-527 529 531
298-304306-318
318A
320-332
333-337327
336-346
533-5
192-
196
447
281-287
201
201
150
1-25
1-25
25G
11
1
3
5
13
1-25
2.04
1.8
2.1
20.2
27.4
10.1
20.4
43.6
29.9
43.0
34.1
3.3
18.6
26.8
36.0
37.2
13.4
21.
6.7
8.2
19.2
40.8
47.5
42.1
42.7
50.0
55.5
56.1
59.7 3.8
2.7
7.6
13.1
18.9
29.3
11.3
8.5
15.2
34.4
34.4 33.2
3.75.5
26.8 25.6
16.5
21.3 19.3
15.2
9.6 5.3
39.6
36.9
38.0
8.7
4.3
26.6
1.3
11.0 2.7
23.7
2.8
41.2
53.9
15.7
38.2
33.
43.3
41.8 30.2 82
.3 71.9
59.1
51.8
6.14.6
6.4
4.54
1.68
1.8
2.57
4.67
4.79
1.52
3.59
3.65
2.63
4.87
5.01
1.0
1.0
7.5 2.49 2.13
2.99
2.52
5.18
2.7
4.76
4.95
4.92
6.27
1.53 5.21
17.7
2.55
3.209
7.2
5.4
2.6
2.9
2.99
2.9
3.16
3.9
3.5
5.25
5.26
1.79
3.8
1.2
3.9
4.56
4.1
MH Chmb
4.019
4.92
6.7
MH Chmb
6.64
5.99
4.53
3.0
3.91
2.9
6.39
5.74
6.331.7
2
1.89
4.29
4.74
5.2
1.95
1.75
1.0
2.22
2.7
2.6
5.4
3.96
3.95
3.86
3.81
3.31
MH C
hmb
5.8
5.1
3.1
7.8
3.64
3.8
2.2
5.3
Conc Encased
In T
unne
l
Conc
Enc
ased
Conc Encased
Conc E
ncased
Conc
Enc
ased
Conc Encased
Conc
Enc
ased
Conc Encased
In Tu
nnel
300 V
C711x1066 CONC
300 VC
300 VC300 PVC
225 VC
300
VC30
0 VC
225 VC
300 P
VC
300 P
VC
300 PVC
300 VC
711x1066 CONC
300 E
W
300 P
VC
711x1066 CONC 711x1066 CONC
225 VC
711x1066 CONC
300 PVC
300 P
VC
300 PVC
300
PVC
225 VC
225 VC
225 V
C30
0 VC
300 VC
300 VC
150 PVC
300 C
ICL
300
CICL
300
CICL
300 VC
300 CICL
300 P
VC
300
VC
219 SCL 300 VC 300 VC
300 PVC
300 VC 300 VC
300 V
C
300
VC
300 CICL 300 V
C
300 VC
525 V
C
300 V
C
525 VC525 VC
300 V
C30
0 VC
300 C
ICL
750 V
C
750 V
C
750 VC
750 V
C
750 VC
1300x1750 Unlined Rock
375 VC 750 VC
750 VC
450 VC
300 PVC
300 PVC
300 VC
300 V
C
300 VC
300 PVC 300 VC
300 V
C
450 VC
750 V
C
450 VC
450 VC
750 V
C
750 V
C
300 V
C52
5 VC 225 VC
711x1066 CONC
150VC
225 VC
300 VC300 VC 300 VC
225
VC
300 VC 400 VC
300 VC
375 VC
3.0
2.9
3.1
2.9
0.5
0.8 6.4 3.8
6.4 4.
1 2.8
4.6 3.
1
3.0
3.0 0.8 2.
9
2.9
2.7
0.4
3.1
1.6
2.9 2.9
3.0
3.5
3.8
2.3
3.2
2.3
3.0
3.0 2.1
1.8
2.9
1.8
3.0
3.0
3.1
3.1
3.02.5 2.3
3.0 3.
0 2.8
2.8
2.9
2.8 3.0
1.8
Conc. Encased
150 CICL
200 CICL200 CICL
300 CICL
200
DICL
200
DICL
250 D
ICL
300
CICL 250 DICL 273 SCL
324 SCL32
4 SCL
200
DICL
250
DICL
273 S
CL
150 CICL
300 DICL
273 SCL
150 oPVC
250 CICL
500 CICL
150 oPVC
273 SCL
250
CICL
250 CICL
500 CICL150 CICL
150 CICL
500 CICL
300 CICL
150
CICL
150
DICL
150 D
ICL
150 CICL
300 CICL
150 CICL
150 CICL
150 S
CL
150 CICL
150 CICL
150 CICL
200
CICL
150 CICL
150 DICL
300 S
CL20
0 SC
L
250
SCL
250 SCL
250 D
ICL
150 C
ICL
250 CICL
150 S
CL15
0 SC
L
150 CICL
200 S
CL
200 DICL
200
DICL
200 SCL
200 D
ICL
200
DICL
200 S
CL
200 DICL
250 SCL
150 D
ICL
150 D
ICL
200 D
ICL
200 DICL
200
DICL
200 DICL
250DICL
250 DICL
300 DICL
300 DICL
300 DICL
200 DICL
200 S
CL
250 C
ICL
300 CICL
250 CICL
200 SCL
200 DICL
250 CICL
200 DICL
200 DICL
200 DICL
200
DICL
200 DICL
200 C
ICL
150 C
ICL
150 C
ICL
150 C
ICL
200 CICL
500 CICL
150 CICL
200 CICL
150 C
ICL
200 DICL
250 CICL
5.45.4
5.85
5.15.
450 VCVC
450 VC
450 VC
450 VC
2.3 2.3
25G25G4.2
9
5.25
450 VC50 VC50 VC
00SC
L0SC
LCL
INFO
RM
ATI
ON
ELS
EWH
ERE:
see
GU
IDE
ref 1
1213
3
3.3333 331
022
805
25G25G
4.53
L CL
RE:
sR
ER
E:R
ER
EE: s
RE
INFO
RM
ATI
ON
ELS
EWH
ERE:
see
GU
IDE
ref 1
1717
8
N0m
9m18
m27
m36
m
Copy
right
Res
erve
d Sy
dney
Wat
er 2
012
Plan
1 o
f 1A3
Date
of P
rodu
ction
: 15/
11/2
012
DBYD
Seq
uenc
e No
: 270
6687
6
DBYD
Add
ress
: 1-
5 W
heat
Rd
Sydn
ey N
SW 2
000
SYDN
EY W
ATER
COR
PORA
TION
No w
arra
nty i
s give
n th
at th
e inf
orm
ation
show
n is
com
plete
or a
ccur
ate.
DBYD
Job
No: 1
1783
7Sc
ale: 1
:150
0
Not
e1
-200
mm
Mai
n
Not
e2
-150
mm
Mai
n
Not
e3
-525
VC
Sew
er
Not
e4
-300
VC
Sew
er
Sto
rmw
ater
Cul
verts
Sto
rmw
ater
Cul
verts
Not
e5
-Bui
ldin
g2
sits
clea
roft
his
750
VC
Sew
er
11
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
7. Appendix 2 – Jemena Mains Map
Not
e1
-110
mm
Mai
n
Not
e2
-50m
mM
ain
Not
e3
-Pre
ssur
eR
educ
tion
Sta
tion
Not
e4
-Aqu
ariu
mIn
frast
ruct
ure
13
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
8. Appendix 3 – Indicative Infrastructure Location
AP
PR
IMA
AI
NS
NA
RS
RM
AR
AP
PR
IMA
AI
NS
NA
RS
RM
AR
AP
PR
IMA
AI
NM
NA
AS
MA
INIS
SN
RA
IN
MP
AP
PR
IMA
AI
NS
NA
RM
AIN
AP
PR
IMA
AI
NS
NA
RS
RM
AIN
AP
PR
IMA
AI
NP
RS
SR
SA
IN
ISS
15
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
9. Appendix 4 – Sydney Water Letter of Feasibility
Case Number: 131752
11 April 2013
GROCON PTY LTDc/- BILLBERGIA PTY LTD
FEASIBILITY LETTER
Developer: GROCON PTY LTDYour reference: 3867Development: Lot 401 DP862501 DARLING HARBOUR Unset, SydneyDevelopment Description: The development comprises a 20 storey building component
of approximately 73,000sqm total Gross Floor Area plus anUrban Renewal / Landscape component of approximately10,000sqm. The total proposed site area for the developmentincluding the building footprint is 15,060sqm on, and adjacentto, the site currently occupied by the IMAX Cinema, DarlingHarbour, Sydney.
Dear Applicant
This Feasibility Letter (Letter) is a guide only. It provides general information about what SydneyWater’s requirements could be if you applied to us for a Section 73 Certificate (Certificate) foryour proposed development. The information is accurate at today’s date only.
If you obtain development consent for that development from your consent authority (this isusually your local Council) they will require you to apply to us for a Section 73 Certificate. Youwill need to submit a new application (and pay another application fee) to us for that Certificateby using your current or another Water Servicing Coordinator (Coordinator).
Sydney Water will then send you either a:• Notice of Requirements (Notice) and Developer Works Deed (Deed); or• Certificate.
These documents will be the definitive statement of Sydney Water’s requirements.
There may be changes in Sydney Water’s requirements between the issue dates of this Letterand the Notice or Certificate. The changes may be:
• if you change your proposed development, e.g. the development description or the plan/
17
SYDNEY WATER CORPORATION 2 Case No: 131752
site layout, after today, the requirements in this Letter could change when you submityour new application; and
• if you decide to do your development in stages then you must submit a new application(and pay another application fee) for each stage.
No warranties or assurances can be given about the suitability of this document orany of its provisions for any specific transaction. It does not constitute an approvalfrom Sydney Water and to the extent that it is able, Sydney Water limits its liability tothe reissue of this Letter or the return of your application fee. You should rely on yourown independent professional advice.
18
SYDNEY WATER CORPORATION 3 Case No: 131752
What You Must Do To Get A Section 73 CertificateTo get a Section 73 Certificate you must do the following things. You can also find out about thisprocess by visiting www.sydneywater.com.au > Building and Developing > Developing YourLand.
1. Obtain Development Consent from the consent authority for your developmentproposal.
2. Engage a Water Servicing Coordinator (Coordinator).
You must engage your current or another authorised Coordinator to manage the designand construction of works that you must provide, at your cost, to service your development.If you wish to engage another Coordinator (at any point in this process) you must write andtell Sydney Water.
For a list of authorised Coordinators, either visit www.sydneywater.com.au > Building andDeveloping > Developing Your Land or call 13 20 92.
The Coordinator will be your point of contact with Sydney Water. They can answer mostquestions that you might have about the process and developer charges and can give you aquote or information about costs for services/works (including Sydney Water costs).
3. Developer Works Deed
After the Coordinator has submitted your new application, they will receive the SydneyWater Notice and Developer Works Deed. You and your accredited DeveloperInfrastructure Providers (Providers) will need to sign and lodge both copies of the Deed withyour nominated Coordinator. After Sydney Water has signed the documents, one copy willbe returned to the Coordinator.
The Deed sets out for this project:
• your responsibilities;
• Sydney Water’s responsibilities; and
• the Provider’s responsibilities.
You must do all the things that we ask you to do in that Deed. This is because yourdevelopment will have an impact on existing water, sewer and storm water services and youmay be required to adjust/deviate these assets and pay for the following works under thisDeed to provide these services.
Note: The Coordinator must be fully authorised by us for the whole time of the agreement.
4. Water and Sewer Works
4.1 Water
Your development must have a frontage to a water main that is the right size and can be
19
SYDNEY WATER CORPORATION 4 Case No: 131752
used for connection.
Sydney Water has assessed your application and found that:
There is sufficient trunk capacity to service your development.
Adjustments will be required to the existing DN150 water main currently supplying the IMAXTheatre and the DN 200 water main that loops through Tumberlong Park to accommodatethe proposed development footprint.
A link main will need to be constructed between the two existing aforementioned DN150 andDN200 water mains to provide a point of connection with adequate capacity for domestic andcommercial services.
Fire services have not been assessed as part of this application. Sydney Water provides noguarantee that the proposed infrastructure will have sufficient capacity for fire services –Refer to Fire Fighting in ‘Other Things You Need to Do or Know’ below.
These works must be constructed by a constructor with the appropriate capability. YourCoordinator will be able to provide further advice about this.
4.2 Sewer
Your development must have a sewer main that is the right size and can be used forconnection. That sewer must also have a connection point within your development'sboundaries.
Sydney Water has assessed your application and found that:
There is sufficient trunk capacity for the proposed development.
Adjustments to the existing DN525 & DN300 sewer mains will be required to accommodatethe proposed development footprint.
A Sewer main extension will be required if the point of connection is remote from theproperty boundary.
The terms of the Deed define this extension as ‘Major Works’.
4.3 Stormwater Requirements.
Sydney Water has assessed your application and found that indicatively:
• The proposed development is in close proximity to existing Sydney Water stormwaterassets.
• There is insufficient information / clarity within the submitted documentation to facilitate aclear understanding of the potential impacts of the proposed development on SydneyWater stormwater assets or the potential impacts of the proposed development on local
20
SYDNEY WATER CORPORATION 5 Case No: 131752
flooding.
• The applicant is requested to provide a Stormwater Impacts Report to assist SydneyWater in the assessment of the proposed development and the formulation of furtherrequirements related to Stormwater.
o The Stormwater Impacts Report is to be prepared by a suitably qualified andexperienced person (Water Servicing Coordinator to verify) with access to thecurrent Sydney Water GIS Asset Database (Hydra) via the lodging WaterServicing Coordinator.
o Any component of the proposed development within 10 metres of an existingSydney Water stormwater asset is to be clearly identified by the Water ServicingCoordinator in plan and described / itemised in the report.
On receipt of a suitable Stormwater Impacts Report, as part of either a new feasibility applicationor Section 73 Compliance application, Sydney Water shall issue further requirements related tostormwater.
Approval for any element of the proposed development that is within 10 metres of an existingSydney Water stormwater asset shall not be inferred, notwithstanding the content of anydocumentation provided to date, unless specifically approved in writing by Sydney Waterfollowing receipt and review of a suitable Stormwater Impacts Report.
• In general terms the proposed development is required to meet the followingrequirements:
o Where an existing structure is already placed in, on or near the stormwater assetin a manner that interferes with the operation of or accessibility to the asset andthe structure is to be demolished then any replacement structure shall generallynot be installed in a similar configuration / footprint without the writtenconcurrence of Sydney Water.
o Sydney Water will consider on merit any proposal to reinstate a replacementbuilding or structure in a similar configuration / footprint.
o No new structure is to be placed in, on or near the stormwater asset in a mannerthat interferes with the operation of or accessibility to the asset.
o Sydney Water would consider a proposal to deviate / relocate an existing SydneyWater stormwater asset to facilitate an improved development outcome.
o The development is to be configured and include any necessary design elementsor works to ensure that local flood risks are suitably managed and appropriatelymitigated. The proposed development shall incorporate sufficient floodmanagement elements to ensure that the development shall not increase floodrisks to the community nor shall there be any potential for increased communityexpectation or demand for stormwater asset amplification to be undertaken bySydney Water in the future.
21
SYDNEY WATER CORPORATION 6 Case No: 131752
o A detailed 2D flood study will be submitted describing flood extents, velocities anddepths for a range of events (5yr, 20yr, 100yr) and provisional hydraulic andhazard categories (low and high).
o The proposed development will need to demonstrate a best practice approach tomanaging people and property in high flood hazard areas.
If the proposed development is required to discharge stormwater into Sydney Water’sstormwater channel, then a separate application is to be forwarded to Sydney Water.
All stormwater connections should comply with Sydney Water’s On-Site Detention policy andconnection requirements. For further details please contact Sydney Water’s StormwaterTeam on (02) 8849 4459 (or fax (02) 8849 3063)
5. Ancillary Matters
5.1 Asset adjustments
After Sydney Water issues this Notice (and more detailed designs are available), SydneyWater may require that the water main/sewer main/stormwater located in the footway/yourproperty needs to be adjusted/deviated. If this happens, you will need to do this work as wellas the extension we have detailed above at your cost. The work must meet the conditions ofthis Notice and you will need to complete it before we can issue the Certificate. SydneyWater will need to see the completed designs for the work and we will require you to lodge asecurity. The security will be refunded once the work is completed.
5.2 Entry onto neighbouring property
If you need to enter a neighbouring property, you must have the written permission of therelevant property owners and tenants. You must use Sydney Water’s Permission to Enterform(s) for this. You can get copies of these forms from your Coordinator or the SydneyWater website. Your Coordinator can also negotiate on your behalf. Please make sure thatyou address all the items on the form(s) including payment of compensation and whetherthere are other ways of designing and constructing that could avoid or reduce their impacts.You will be responsible for all costs of mediation involved in resolving any disputes. Pleaseallow enough time for entry issues to be resolved.
5.3 Costs
Construction of these future works will require you to pay project management, survey,design and construction costs directly to your suppliers. Additional costs payable toSydney Water may include:• water main shutdown and disinfection;• connection of new water mains to Sydney Water system(s);• design and construction audit fees;• contract administration, Operations Area Charge & Customer Redress prior to project
finalisation;
22
SYDNEY WATER CORPORATION 7 Case No: 131752
• creation or alteration of easements etc; and• water usage charges where water has been supplied for building activity purposes prior
to disinfection of a newly constructed water main.
Note: Payment for any Goods and Services (including Customer Redress) provided bySydney Water will be required prior to the issue of the Section 73 Certificate orrelease of the Bank Guarantee or Cash Bond.
Your Coordinator can tell you about these costs.
6. Stamping and Approval of your Building Plans
You must have your building plans stamped and approved before the Certificate can beissued. Building construction work MUST NOT commence until Sydney Water hasgranted approval. Approval is needed because construction/building works may affectSydney Water’s assets (e.g. water and sewer mains).
Your Coordinator can tell you about the approval process including:• Your provision, if required, of a “Services Protection Report” (also known as a “peg-out”).
This is needed to check whether the building and engineering plans show accuratelywhere Sydney Water’s assets are located in relation to your proposed building work.Your Coordinator will then either approve the plans or make requirements to protectthose assets before approving the plans;
• Possible requirements;• Costs; and• Timeframes.
You can also find information about this process (including technical specifications) if youeither:• visit www.sydneywater.com.au > Building and Developing > Building and Renovating.
Here you can find Sydney Water’s Guidelines for Building Over/Adjacent to SydneyWater Assets; or
• call 13 20 92.
Notes:• The Certificate will not be issued until the plans have been approved and, if
required, Sydney Water’s assets are altered or deviated;• You can only remove, deviate or replace any of Sydney Water’s pipes using
temporary pipework if you have written approval from Sydney Water’s UrbanGrowth Business. You must engage your Coordinator to arrange this approval;and
• You must obtain our written approval before you do any work on Sydney Water’ssystems. Sydney Water will take action to have work stopped on the site if you donot have that approval. We will apply Section 44 of the Sydney Water Act 1994.
23
SYDNEY WATER CORPORATION 8 Case No: 131752
OTHER THINGS YOU MAY NEED TO DO OR KNOWShown below are other things you need to do that are NOT a requirement for the Certificate.They may well be a requirement of Sydney Water in the future because of the impact of yourdevelopment on our assets. You must read them before you go any further.
Individual metering of units
All multi-level unit developments now have the option (not mandatory) to prepare their building’splumbing for individual unit metering. For more information visit www.sydneywater.com.au >Plumbing > Meters and look at our �ulti�level�individual��etering�guide� It is important that youunderstand that this will become mandatory from late 2013 and that you should consider this inplanning your development.
Disused Sewerage Service Sealing
Please do not forget that you must pay to disconnect all disused private sewerage services andseal them at the point of connection to a Sydney Water sewer main. This work must meetSydney Water’s standards in the NSW Code of Practice for Plumbing and Drainage (the Code)and be done by a licensed drainer. The licensed drainer must arrange for an inspection of thework by a NSW Fair Trading Plumbing Inspection Assurance Services (PIAS) officer. After thatofficer has looked at the work, the drainer can issue the Certificate of Compliance. The Coderequires this.
Soffit Requirements
Please be aware that floor levels must be able to meet Sydney Water’s soffit requirements forproperty connection and drainage.
Requirements for Business Customers for Commercial and Industrial PropertyDevelopments
If this property is to be developed for Industrial or Commercial operations, it may need to meetthe following requirements:
Trade Wastewater Requirements
If this development is going to generate trade wastewater, the property owner must submit anapplication requesting permission to discharge trade wastewater to Sydney Water’s seweragesystem. You must wait for approval of this permit before any business activities can commence.
The permit application should be emailed to Sydney Water’s Business Customer Services [email protected]
It is illegal to discharge Trade Wastewater into the Sydney Water sewerage system withoutpermission.
A Boundary Trap is required for all developments that discharge trade wastewater wherearrestors and special units are installed for trade wastewater pre-treatment.
24
SYDNEY WATER CORPORATION 9 Case No: 131752
If the property development is for Industrial operations, the wastewater may discharge into asewerage area that is subject to wastewater reuse. Find out from Business Customer Services ifthis is applicable to your development.
Backflow Prevention Requirements
Backflow is when there is unintentional flow of water in the wrong direction from a potentiallypolluted source into the drinking water supply.
All properties connected to Sydney Water's supply must install a testable Backflow PreventionContainment Device appropriate to the property's hazard rating. Property with a high ormedium hazard rating must have the backflow prevention containment device tested annually.Properties identified as having a low hazard rating must install a non-testable device, as aminimum.
Separate hydrant and sprinkler fire services on non-residential properties, require the installationof a testable double check detector assembly. The device is to be located at the boundary of theproperty.
Before you install a backflow prevention device:1. Get your hydraulic consultant or plumber to check the available water pressure versus
the property’s required pressure and flow requirements.2. Conduct a site assessment to confirm the hazard rating of the property and its services.
Contact PIAS at NSW Fair Trading on 1300 889 099.
For installation you will need to engage a licensed plumber with backflow accreditation who canbe found on the Sydney Water website:http://www.sydneywater.com.au/Plumbing/BackflowPrevention/
Water Efficiency Recommendations
Water is our most precious resource and every customer can play a role in its conservation. Byworking together with Sydney Water, business customers are able to reduce their waterconsumption. This will help your business save money, improve productivity and protect theenvironment.
Some water efficiency measures that can be easily implemented in your business are:• Install water efficiency fixtures to help increase your water efficiency, refer to WELS
(Water Efficiency Labelling and Standards (WELS) Scheme, http://www.waterrating.gov.au/
• Consider installing rainwater tanks to capture rainwater runoff, and reusing it, where costeffective. Refer to http://www.sydneywater.com.au/Water4Life/InYourBusiness/RWTCalculator.cfm
• Install water-monitoring devices on your meter to identify water usage patterns and leaks.• Develop a water efficiency plan for your business.
It is cheaper to install water efficiency appliances while you are developing than retrofitting themlater.
25
SYDNEY WATER CORPORATION 10 Case No: 131752
Contingency Plan Recommendations
Under Sydney Water's customer contract Sydney Water aims to provide Business Customerswith a continuous supply of clean water at a minimum pressure of 15meters head at the maintap. This is equivalent to 146.8kpa or 21.29psi to meet reasonable business usage needs.
Sometimes Sydney Water may need to interrupt, postpone or limit the supply of water servicesto your property for maintenance or other reasons. These interruptions can be planned orunplanned.
Water supply is critical to some businesses and Sydney Water will treat vulnerable customers,such as hospitals, as a high priority.
Have you thought about a contingency plan for your business? Your Business CustomerRepresentative will help you to develop a plan that is tailored to your business and minimisesproductivity losses in the event of a water service disruption.
For further information please visit the Sydney Water website at: http://www.sydneywater.com.au/OurSystemsandOperations/TradeWaste/ or contact BusinessCustomer Services on 1300 985 227 or [email protected]
Fire Fighting
Definition of fire fighting systems is the responsibility of the developer and is not part of theSection 73 process. It is recommended that a consultant should advise the developer regardingthe fire fighting flow of the development and the ability of Sydney Water’s system to provide thatflow in an emergency. Sydney Water’s Operating Licence directs that Sydney Water’s mains areonly required to provide domestic supply at a minimum pressure of 15 m head.
A report supplying modelled pressures called the Statement of Available pressure can bepurchased through any Quickcheck agent and may be of some assistance when defining the firefighting system. The Statement of Available pressure, may advise flow limits that relate tosystem capacity or diameter of the main and pressure limits according to pressure managementinitiatives. If mains are required for fire fighting purposes, the mains shall be arranged throughthe water main extension process and not the Section 73 process.
Large Water Service Connection
A water main will be available, once you have completed your drinking water main constructionto provide your development with a domestic supply. The size of your development means thatyou will need a connection larger than the standard domestic 20 mm size.
To get approval for your connection, you will need to lodge an application with a Quick CheckAgent. You, or your hydraulic consultant, may need to supply the following:
• A plan of the hydraulic layout;• A list of all the fixtures/fittings within the property;• A copy of the fire flow pressure inquiry issued by Sydney Water;
26
SYDNEY WATER CORPORATION 11 Case No: 131752
• A pump application form (if a pump is required);• All pump details (if a pump is required).
You will have to pay an application fee.
Sydney Water does not consider whether a water main is adequate for fire fighting purposes foryour development. We cannot guarantee that this water supply will meet your Council’s firefighting requirements. The Council and your hydraulic consultant can help.
Disused Water Service Sealing
You must pay to disconnect all disused private water services and seal them at the point ofconnection to a Sydney Water water main. This work must meet Sydney Water’s standards inthe NSW Code of Practice for Plumbing and Drainage (the Code) and be done by a licensedplumber. The licensed plumber must arrange for an inspection of the work by a NSW FairTrading Plumbing Inspection Assurance Services (PIAS) officer. After that officer has looked atthe work, the drainer can issue the Certificate of Compliance. The Code requires this.
Other fees and requirementsThe requirements in this Notice relate to your Certificate application only. Sydney Water may beinvolved with other aspects of your development and there may be other fees or requirements.These include:
• plumbing and drainage inspection costs;• the installation of backflow prevention devices;• trade waste requirements;• large water connections and• council fire fighting requirements. (It will help you to know what the fire fighting
requirements are for your development as soon as possible. Your hydraulic consultantcan help you here.)
No warranties or assurances can be given about the suitability of this document or any ofits provisions for any specific transaction. It does not constitute an approval fromSydney Water and to the extent that it is able, Sydney Water limits its liability to thereissue of this Letter or the return of your application fee. You should rely on your ownindependent professional advice.
END
27
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
10. Appendix 5 – Sydney Water – Meeting Minutes
Meet
Held wit
Location
Regardi
In attend
Comme
RR
JRpRd
ting Mi
th: Syd
n: Syd
ng: Hay
dance: Ray
Jey
Geo
Luk
Dom
nts:
RP initially noRP outlined t
o It is aexist
o If theachie
o Legaautobeyo
JJ noted thatRP noted thaprotected if bRP outlined tdecision on w
o A De- If th- If th- The- Anyinfras
o A Se- Siz- Zon- Pro
nutes
dney Water (
dney Water -
y-Lackey Cu
y Persell (RP
ya Jeyadevan
off Briggs (G
ke De Gioia (
minic De Gio
oted that SWthat consideramending anting building e lease area eved by any acy developmmatic justifica
ond the existit the culvertsat it is up to thbuilt overthe requiremworks over theviation Repohe services che building cae reasons any potential fostructure
ervices Proteze, depth, locne of influencoposed const
(SW)
- Parramatta
lverts
P)
n (JJ)
GB)
(LDG)
oia (DDG)
W’s first preferation will be n existing builinehas assets rother means
ments, such aation for futuing boundarys are approximhe developm
ents that neehe culvert. Tort outlining:can be relocaan be relocat
nd issues as tor amendmen
ction Report cation etc of tce of the surrtruction and p
Da
Pa
Me
Co
rence is not tmade if: lding which e
unning throusas the existinre works, es
ymately 80 ye
ment team to
ed to be provhese include
atedted to why the bunt of the build
outlining: he existing srounding struprotection of
ate:
ages:
eeting #:
ompany:
to build over
exists over an
gh the site a
ng IMAX Cinepecially whe
ears old and tdemonstrate
vided to Sydne:
uilding must ding to be sym
services ucture the assets b
27 Novembe
2
1
Sydney Wat
Sydney Wat
Grocon Grou
EWFW (EW
EWFW (EW
the stormwa
n asset but o
nd developm
ema would nore the develo
their age will e how the SW
ney Water in
be located ampathetic to
below
er 2012 – 11
ter (SW)
ter (SW)
up (GG)
WFW)
WFW)
ater
only to the ex
ment cannot b
ot generally opment would
be a consideW asset will b
order to mak
s nominatedthe surround
.15am
xtent of the
be
be an d extend
eration. e
ke a
ding
29
Meeting Minutes EWFW
- Dilapidation reporting - Maintenance and access requirements and potential methods for replacing the stormwater in the future
o A Flood Study outlining: - Overland flow paths for existing and proposed - Capacity assessments - Impacts associated with the stormwater and the proposed buildings
JJ noted that the existing culverts are 3.9m x 2.2m and 3.0m x 2.2m and they have been sized using the rational method for a 100 year capacity
JJ is happy to allow access to any information SW has available and copies can be made of existing information. There may be a condition report for the culverts. JJ can be approached to find further information however the SW contact who would be aware of this information is currently on holidays for 2 weeks
RP noted that the main issues in which SW would not allow any construction is if there are overland flow path and flooding issues that can’t be rectified or if the assets could not be cost effectively renewed in the future
RP noted that a decision would be made a couple of weeks after all of the above information was available to SW
Issues for Resolution
EWFW to provide information on Dilapidation Contractor used for previous project to GG GB to confirm if these works are covered under Bonacci Contract In the event that Bonacci are not providing Flood Study EWFW to provide details to have Flood
Study conducted All services will be required to provide information for the Deviation Report as required
30
Meet
Held wit
Location
Regardi
In attend
Comme
RoRoRtSh
SRpRwRr
Attached
DB
ting Mi
th: Syd
n: Syd
ng: Hay
dance: Ray
Jey
Ste
Dom
nts:
RP & JJ provor adjacent toRP & JJ provover or adjacRP & JJ provthe informatioSN requestehe will requir
o 2D mo Inforo SW a
and o RP n
SW iSN requesteRP noted thaprovide a gooRP suggestewith access tRP suggestereview and re
d documents
Darling HarbBuilding over
nutes
dney Water (
dney Water -
y-Lackey Cu
y Persell (RP
ya Jeyadevan
ephen Naugh
minic De Gio
vided the newo stormwatervided the newcent to stormvided a Termon discussedd the scope o
re:model rmation to share looking focall out requ
nominated thin order to prd design flow
at the informaod starting p
ed that we neto the buildined that we proecommend a
:
bour IMAX Thr or adjacent
(SW)
- Parramatta
lverts
P)
n (JJ)
hton (SN)
oia (DDG)
w guidelines r.w policy docuwater.
ms of Reply dod at the previof informatio
ow that the por confirmatioirements at SN shouldrevent BG unw informationation is basedoint but it sho
eed to look atng if they are ovide a “Drafany additiona
heatre – Feasto Sydney W
Da
Pa
Me
Co
that have be
ument that ha
ocument in rious meetingn required fo
proposed syson of a syste
d provide higndertaking con which was pd on capacityould not be tht their mainteperforming mft Report” for
al information
sibility CN113Water stormw
ate:
ages:
eeting #:
ompany:
een released
as been relea
relation to the.
or the overlan
stem will adhem that will he
h level informostly work forprovided on Cy estimates uhe fundamen
enance requirmaintenancer all sections n requirement
31752 water assets -
25 March 20
2 + Attachm
2
Sydney Wat
Sydney Wat
Bonacci Gro
EWFW (EW
by SW in rel
ased by SW
e site. This d
nd flow inform
ere to “Best elp to reduce
mation at firstr no reason CD by JJ. using the Ratntal basis of trements so t.before submts.
- Policy
013 – 11.00a
ments
ter (SW)
ter (SW)
oup (BG)
WFW)
lation to build
in relation to
document is i
mation. RP n
Practice” e maintenanc
t for a “Draft
tional Methodthe calculatiohat there are
mission in ord
am
ding over
o building
n line with
noted that
ce issues
review” by
d. This will ons. e no issues
der to
31
Meeting Minutes EWFW
Building over or adjacent to Sydney Water stormwater assets - Guidelines
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
EWFW
Wheat Rd, Sydney Revision E
Hydraulic Infrastructure Report 19 July 2013
11. Appendix 6 – Jemema – Meeting Minutes Note: The initial meeting was undertaken during the development of the first iteration of the building. As such the plans as included in the minutes were for the previous scheme. Whilst the building shape has changed in subsequent iterations it will have no impact on the gas services proposed nor will it vary the works as per the discussions held in this meeting.
Meet
Held wit
Location
Regardi
In attend
Comme
AJAtDsAcAiGAIbIGAeAo
Issues f
EE
ting Mi
th: Jem
n: On
ng: Jem
dance: Ann
And
Geo
Dom
nts:
AL outlined tJemena servAL noted thathat requires DDG noted tsite. AW noted thaclose to capaAW nominateinvolved as pGB informedAL nominateIt was discusboundary lineIt is unlikely tGB questioneAL confirmedextended thrAL suggesteoption. They
for Resolutio
EWFW to proEWFW to pro
nutes
mena (JE)
site – Darlin
mena Gas Ma
ne Woodwar
drew Lelliott
off Briggs (G
minic De Gio
he location ovices runningat there is an
upgrade. hat there will
at the increasacity at preseed that due topart of the pro Jemena tha
ed that any pissed that re-de) is problemthat there wiled if there wed that the nexrough the CBd that re-divey will explore
on
ovide all Dialovide a draw
g Harbour
ains
rd (AW)
(AL)
GB)
oia (DDG)
of the existingg under the ex
existing regu
l be a co-gen
sed load will ent. o the nature ocess.
at demolition pework needdiverting the
matic due to thll be an acceere other netxt closest line
BD. erting the pipthis further.
l Before you wing nominati
Da
Pa
Me
Co
g main. He axisting IMAXulator station
n plant in add
need to be c
of the projec
is likely to cods to be provpipework in the adjacent rss corridor otwork lines ine was severa
pework (North
Dig informating proposed
ate:
ages:
eeting #:
ompany:
also confirmeX building.
located on t
dition to retail
considered a
ct that severa
ommence midvided with excthe vicinity ofroadways an
of sufficient sin the vicinity wal blocks awa
hern side of t
ion to Jemend relocation ru
18 Decembe
5
1
Jemena (JE
Jemena (JE
Grocon Grou
EWFW (EW
ed that there
the Southern
l and plant an
as the Sydney
al divisions in
d 2013. cavation accf its current lo
nd the adjaceize. which could aay and would
the site) is lik
na (AL/AW) un to Jemena
er 2012 – 8.3
)
)
up (GG)
WFW)
are currently
boundary of
nd equipmen
y CBD feed i
n Jemena wil
ess.ocation (Sou
ent electrical s
act as the feed require pipe
kely to be the
a (AL/AW)
30am
y no
f the site
nt for the
s running
l be
thern services.
ed line. ework to be
e best
56
Meeting Minutes EWFW
JE will provide details on their proposed relocations once they have reviewed the documentation provided
Drawings Attached
Sydney Water Mains Maps Hassell Existing Services Overlay EWFW Existing Services Overlay including proposed relocation Electrical Mains Maps from Dial Before You Dig
57
58
SP
0012
ST
ST
PL
DR
UIT
T
DR
UIT
T
KENT
LAN
E
DR
UIT
T
WHEAT
PL
BLA
CK
WA
TT
LE
DAY
STSANDS
ST
WE
ST
ER
N
BA
TH
UR
ST
DAY
JAMES
DS
TRS
T
SUSSEX
LANE
JAM
ES
ST
RP
VSE
VSE
VERT
VERT
RP
VSE
VSE
VSE
VSE
DisDis
Dis
Dis
Dis Dis
Dis
DisDis
Dis
Dis Dis Dis
Dis
Dis Dis Dis
DisDisDis
Dis
Dis
Dis
Dis
Dis
Dis
Dis
DisDis
Dis
Dis
Dis
Dis
Dis
Dis
Dis
Dis
VERT
BAY
2
B
A
1 20
CP
CP
16
1
11
12
CP
1
8
10C
50 51
4
5
A
BCP 1
1 1CP
2 10010 1
CPCP
101 1 1
11
11
21
C 1
1 1
CP
60
17
60
42
65
40
56
62
10
61
2
4
9
1
20
503
601
504
602
10
1010
60
63
64
402
401
405
404
306
218
4042
403 25
53
800
805
801
CP
34 5
A
23 1 1
B
313
313 1 1
100
100
C
10
1
804
802
803
730
58
9
806
901
1
1 12 2
1
CP3
1
3
1
CP
333
CP
1
4
502
200
414-418
222-228
439 439-441
230
234
25245
3-46
348
-58
465-467469
491499-501
503-505
507-509
259-261259-261
263
51 278
265 267 269
477
499-
501
286
493-495
499-
501
70-7
2
70-7
2
286
273-275 277
286 286
289-295
168
299-305
307 309
176-182
311
313-315 317 319 321-325 321-325
188
511 521-527 521-527 529 531
298-304306-318
318A
320-332
333-337327
336-346
533-5
192-
196
447
281-287
201
201
150
1-25
1-25
25G
11
1
3
5
13
1-25
2.04
1.8
2.1
20.2
27.4
10.1
20.4
43.6
29.9
43.0
34.1
3.3
18.6
26.8
36.0
37.2
13.4
21.
6.7
8.2
19.2
40.8
47.5
42.1
42.7
50.0
55.5
56.1
59.7 3.
8
2.7
7.6
13.1
18.9
29.3
11.3
8.5
15.2
34.4
34.4 33.2
3.75.5
26.8 25.6
16.5
21.3 19.3
15.2
9.6 5.3
39.6
36.9
38.0
8.7
4.3
26.6
1.3
11.0 2.7
23.7
2.8
41.2
53.9
15.7
38.2
33.
43.3
41.8 30.2 82
.3 71.9
59.1
51.8
6.14.6
6.4
4.54
1.68
1.8
2.57
4.67
4.79
1.52
3.59
3.65
2.63
4.87
5.01
1.0
1.0
7.5 2.49 2.13
2.99
2.52 5.18
2.7
4.76
4.95
4.92
6.27
1.53 5.21
17.7
2.55
3.20
9
7.2
5.4
2.6
2.9
2.99
2.9
3.16
3.9
3.5
5.25
5.26
1.79
3.8
1.2
3.9
4.56
4.1
MH Chmb
4.01
9
4.92
6.7
MH Chmb
6.64
5.99
4.53
3.0
3.91
2.9
6.39
5.74
6.331.7
2
1.89
4.29
4.74
5.2
1.95
1.75
1.0
2.22
2.7
2.6
5.4
3.96
3.95
3.86
3.81
3.31
MH C
hmb
5.8
5.1
3.1
7.8
3.64
3.8
2.2
5.3
Conc Encased
In T
unne
l
Conc
Enc
ased
Conc Encased
Conc E
ncas
ed
Conc
Enc
ased
Conc Encased
Conc
Enc
ased
Conc Encased
In T
unne
l
300 V
C711x1066 CONC
300 VC
300 VC300 PVC
225 VC
300
VC30
0 VC
225 VC
300 P
VC
300
PVC
300 PVC
300 VC
711x1066 CONC
300
EW
300
PVC
711x1066 CONC 711x1066 CONC
225 VC
711x1066 CONC
300 PVC
300 P
VC
300 PVC
300
PVC
225 VC
225 VC
225
VC30
0 VC
300 VC
300 VC
150 PVC
300
CICL
300
CICL
300
CICL
300 VC
300 CICL
300
PVC
300
VC
219 SCL 300 VC 300 VC
300 PVC
300 VC 300 VC
300 V
C
300
VC
300 CICL 300
VC
300 VC
525
VC
300 V
C
525 VC525 VC
300 V
C30
0 VC
300
CICL
750 V
C
750 V
C
750 V
C
750 V
C
750 V
C
1300x1750 Unlined Rock
375 VC 750 VC
750 VC
450 VC
300 PVC
300 PVC
300 VC
300
VC
300 VC
300 PVC 300 VC
300
VC
450 VC
750 V
C
450 V
C
450 VC
750
VC
750
VC
300
VC52
5 VC 225 VC
711x1066 CONC
150VC
225 VC
300 VC300 VC 300 VC
225
VC
300 VC 400 VC
300 VC
375 VC
3.0
2.9
3.1
2.9
0.5
0.8 6.4 3.8
6.4 4.
1 2.8
4.6 3.
1
3.0
3.0 0.8 2.
9
2.9
2.7
0.4
3.1
1.6
2.9 2.9
3.0
3.5
3.8
2.3
3.2
2.3
3.0
3.0 2.1
1.8
2.9
1.8
3.0
3.0
3.1
3.1
3.02.52.3
3.0 3.
0 2.8
2.8
2.9
2.8 3.0
1.8
Conc. Encased
150 CICL
200 CICL200 CICL
300 CICL
200
DICL
200
DICL
250
DICL
300
CICL 250 DICL 273 SCL
324 SCL32
4 SC
L20
0 DI
CL
250
DICL
273
SCL
150 CICL
300 DICL
273 S
CL
150 oPVC
250 CICL
500 CICL
150 oPVC
273 SCL
250
CICL
250 CICL
500 CICL150 CICL
150 CICL
500 CICL
300 CICL
150
CICL
150
DICL
150
DICL
150 CICL
300 CICL
150 CICL
150 CICL
150 S
CL
150 CICL
150 CICL
150 CICL
200
CICL
150 CICL
150 DICL
300
SCL
200
SCL
250
SCL
250 SCL
250 D
ICL
150
CICL
250 CICL
150
SCL
150
SCL
150 CICL
200
SCL
200 DICL
200
DICL
200 SCL
200 D
ICL
200
DICL
200 S
CL
200 DICL
250 SCL
150
DICL
150
DICL
200
DICL
200 DICL
200
DICL
200 DICL
250DICL
250 DICL
300 DICL
300 DICL
300 DICL
200 DICL
200 S
CL
250
CICL
300 CICL
250 CICL
200 SCL
200 DICL
250 CICL
200 DICL
200 DICL
200 DICL
200
DICL
200 DICL
200
CICL
150
CICL
150
CICL
150
CICL
200 CICL
500 CICL
150 CICL
200 CICL
150
CICL
200 DICL
250 CICL
5.45.4
5.85
5.15.
450 VCVC
450 V
C45
0 VC
450 VC
2.3 2.3
25G25G4.
29
5.25
450 VC50 VC50 VC
00SC
L0SC
LCL
INFO
RM
ATI
ON
ELS
EW
HE
RE
: see
GU
IDE
ref
112
133
3.33
33331
022
805
25G25G
4.53
L CL
RE
: sR
ER
E:
RE
REE
: sR
EIN
FOR
MA
TIO
N E
LSE
WH
ER
E: s
ee G
UID
E r
ef 1
1717
8
N0m
9m18
m27
m36
m
Copy
right
Res
erve
d Sy
dney
Wat
er 2
012
Plan
1 o
f 1A3
Date
of P
rodu
ction
: 15/
11/2
012
DBYD
Seq
uenc
e No
: 270
6687
6
DBYD
Add
ress
: 1-
5 W
heat
Rd
Sydn
ey N
SW 2
000
SYDN
EY W
ATER
COR
PORA
TION
No w
arra
nty i
s give
n th
at th
e inf
orm
ation
show
n is
com
plete
or a
ccur
ate.
DBYD
Job
No: 1
1783
7Sc
ale: 1
:150
0
59
60