19
P. Paolucci - I.N.F.N. di Napoli 1 30-01-2006 / Joint RPC-Trigger meeting HV-LV-DCS Status DCS barrel: G. Polese and P. Paolucci DCS endcap: A. Cimmino and P. Paolucci HV & LV: D. Lomidze and P. Paolucci NEWS DCS Endcap Integration DCS Barrel Integration see Giovanni talk 1 PC with barrel project working at 904 1 PC with endcap project at 904 asap HV-LV test setup is going on at BLG 904

HV-LV-DCS Status

  • Upload
    azia

  • View
    51

  • Download
    0

Embed Size (px)

DESCRIPTION

HV-LV-DCS Status. DCS barrel: G. Polese and P. Paolucci DCS endcap: A. Cimmino and P. Paolucci HV & LV: D. Lomidze and P. Paolucci NEWS DCS Endcap Integration DCS Barrel Integration see Giovanni talk 1 PC with barrel project working at 904 1 PC with endcap project at 904 asap - PowerPoint PPT Presentation

Citation preview

Page 1: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli1

30-01-2006 / Joint RPC-Trigger meeting

HV-LV-DCS Status DCS barrel:G. Polese and P. Paolucci DCS endcap: A. Cimmino and P. Paolucci HV & LV: D. Lomidze and P. Paolucci

NEWS DCS Endcap Integration DCS Barrel Integration see Giovanni talk 1 PC with barrel project working at 904 1 PC with endcap project at 904 asap HV-LV test setup is going on at BLG 904

Page 2: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli2

30-01-2006 / Joint RPC-Trigger meeting

EASY Crate

board/crate channel/crate (max power)

power/crate # crate/rack power/rack # A3486

LV 3 36 (11 watt/ch) < 900* 1 < 900 1ch/rack

HV 4-5 24-30 (10 watt/ch) < 600** 3 < 1800 2ch/rack

A3486 AC/DC has 2 channels of 2 KW each

* 3 boards with safety factor 2** 6 boards with safety factor 2

Page 3: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli3

30-01-2006 / Joint RPC-Trigger meeting

EASY crate back schema

Page 4: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli4

30-01-2006 / Joint RPC-Trigger meeting

EASY crate connection schema

Connector Cost Cable cost

48V power APP - 75A red/black + pin (14-8 awg) (2.1-8.2 mm2)

2.46 + 1.5 1 KW 2.5 (black) + 2.5 (red) + 3.0 (2 pins) = 8.0

48V service APP - 30A red/black + pin (16-12 awg) (1.5-4 mm2)

0.52 + 0.27

0.1 KW 0.52(black) + 0.52(red) + 0.54 (2 pins) = 1.58

EASY bus 50 pins flat cable 8.39 Flat 50 wires

Earth Fork 7mm 0.10

Page 5: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli5

30-01-2006 / Joint RPC-Trigger meeting

NEW USC55 barrel HV system

General Information• max HV EASY board: 7 ch.• max EASY crate: 42 ch.• HV distributor:

• 32 input ch (2 sectors)• 16 output ch.

• Rack height tot: 56 U• turbine 4 U• air defl. 2 U

• Rack available height 50 U

Total:72/96 ch.

We need (per wheel/rack)• 72 ch 12 HV boards (reduced*)• 96 ch 16 HV boards (final)• 3 EASY crate (4-4-4) (6-6-4) • 3 FAN crates + heat exchange • 6 distributors + 1 RB4-sect4 join* RB3 and RB4 joint together (12 + 12)

8UEASY

1 2 3 4 5 6 -fan tary

heat exchange

EASY1 2 3 4 5 6 -

fan taryheat exchange

8U

EASY1 2 3 4 - - -

fan taryheat exchange

8U

44 U

36 input ch.

36 input ch.

24 input ch.

48 output ch.

36 ch.

24 ch.

12 ch.

24 ch.

HV distributorsect 11-12

HV distributorHV distributor

sect 09-10

sect 08-07

48 output ch.HV distributorsect 05-06

HV distributorHV distributor

sect 03-04

sect 01-02

HV distributorspare

turbine4U

air deflector2U

S1H02-06

Page 6: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli6

30-01-2006 / Joint RPC-Trigger meeting

34U

AC/DC 48Vpower3U 2x2 KW

S1H07turbine

air deflector2U

4U

NEW USC55 HV barrel racks composition

SY1527HV

SY1527LV8U

8U

AC/DC 48Vpower3U 2x2 KW

AC/DC 48Vservice3U 2x2 KW

HW numbers • 15 EASY crates• 60-80 HV boards A3512• 360-480 HV channel• 30+4 HV distributors• 2 SY1527 mainframes• 3 or 4 AC/DC 48 V - A3486 (or A3485)

CABLE numbers • EASY power (direct) 5• EASY power (daisy) 10• EASY service (direct) 2• EASY service (daisy) 14• Branch Contr. (direct) 2• Branch Contr. (daisy) 14• Fan unit contr. 15• EASY Ground - 15• SY1527 ground - 2 • 480 HV input + 240 HV out

AC/DC 48Vpower3U 2x2 KW (spare ?)

136 components

800 cables

Page 7: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli7

30-01-2006 / Joint RPC-Trigger meeting

HV-LV status

Setup at 904 is finished. MTCC setup is almost ready

Setup ready for Cosmic Challenge in March 06 Move from 904 to SX5 in April 06

Page 8: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli8

30-01-2006 / Joint RPC-Trigger meeting

LV MTCC setup

2 LV EASY crates OK 2 LV boards A3009 (2 sectors) 1 LV board A3009 (1 sector) Short cables and connections are OK Waiting for lengths for long cables.

2 Control cables

Page 9: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli9

30-01-2006 / Joint RPC-Trigger meeting

HV MTCC setup

1 HV EASY crates OK 4 HV boards A3512 (3 sectors) Short cables and connections are OK Waiting for lengths for long cables.

3 multi-conductors cables

Page 10: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli10

30-01-2006 / Joint RPC-Trigger meeting

RPC DCS status

Barrel and Endcap projects are readyTwo PCs running the projects are at 904 Integration with CMS DCS is almost ready, some common problems still to fix

RPC DCS will be ready for May 2006

Page 11: HV-LV-DCS  Status

P. Paolucci - I.N.F.N. di Napoli11

30-01-2006 / Joint RPC-Trigger meeting

Next Steps

Define the hardware of the endcap system Install the system at SX5 Build and install long cables Test it in April-May to be ready for CC

Page 12: HV-LV-DCS  Status

HW schema for CC

BCLV

BCLV

BCHV

RPC - SY1527

HV – EASY – 24 ch.

HV HV HV HV

AC/DC

HV – MAO – 2 ch.

Balcony Barack

48 V – service LV

Control LV

Detector

PWR HV

Control HV

W+2

W+1

LV – EASY – 12 ch.

LV

LV – MAO – 1 ch.

LV – EASY – 24 ch.

LV LV

LV – MAO – 1 ch.

PWR HV

PWR HVAC/DC

AC/DC

380 3-phase 380 3-phase

HV multicond. 10 ch.

Page 13: HV-LV-DCS  Status

30-01-2006 / Joint RPC-30-01-2006 / Joint RPC-Trigger meetingTrigger meeting

P. Paolucci - I.N.F.N. di NapoliP. Paolucci - I.N.F.N. di Napoli 1313

RPC FSM RPC FSM HierarchyHierarchy

Endcap RPC Endcap Supervisor

Disc

Ring

Chamber

Barrel RPC

Barre

l Sup

ervi

sor

Devi

ce

leve

l

Wheel

Sector

Chamber

ChannelHV/LV Sys

CMS_RPCSince the last meeting:• The endcap is up to date with the barrel and the two systems are proceeding in parallel• Tests on CPU and RAM usage have brought us to reduce the number of CUs. Limiting to the top two levels. Possibility of using only wheels or disks in standalone mode as lower nodes.• Introduction of a new level in the hierarchy. This will allows a better partitioning of the system.• The two systems are under a single top node as required by the CMS DCS Integration guidelines. The two systems can also work standalone.

Device levelChannelHV/LV SysNEW LEVEL

CU

LU

Page 14: HV-LV-DCS  Status

30-01-2006 / Joint RPC-30-01-2006 / Joint RPC-Trigger meetingTrigger meeting

P. Paolucci - I.N.F.N. di NapoliP. Paolucci - I.N.F.N. di Napoli 1414

RPC DCS for RPC DCS for MTCCMTCC

Endcap RPC

Disc

Ring

Chamber

Barrel RPC

Devi

ce

leve

l

Wheel

Sector

Chamber

Channel

HV/LV Sys

CMS_RPCSince the last meeting:• Intensive (2 weeks) test with HW at 904 building induced us to perform Minor changes to the FSM schema• Redesign Hierarchy and distribution on more PCs. • We are investigating How distribute the HW component on more PCs and the resources needed. Device

level

Channel

HV/LV Sys

PC01Supervisor

PC02

PC03.. PC04..

DATABASE• We are able to receive and upload the HW setup into the project from Oracle DB• We are able to download different configuration setup from DB for ON and StandBy states

Conf.DB

Page 15: HV-LV-DCS  Status

30-01-2006 / Joint RPC-30-01-2006 / Joint RPC-Trigger meetingTrigger meeting

P. Paolucci - I.N.F.N. di NapoliP. Paolucci - I.N.F.N. di Napoli 1515

RPC DCS RPC DCS Integration Integration StatusStatus

• We were successful in creating a first version of the CMS RPC sub-detector SUPERVISOR component using the tool provided by the JCOP framework. The RPC component contains both Endcap and Barrel trees, but it has been designed has two components that can work on different PCs. • We accessed the Configuration DB . We are able to read from and write in it (in a private Oracle DB) using custom scripts with Framework functions. We still need to

- know the coordinates of the DB we are going to use for the CC and test the best way to access the DB (different solutions are possible)- finish to prepare the hardware component (march 06)- work on the condition DB- temperature monitoring (waiting for JCOP FW)

Page 16: HV-LV-DCS  Status

1616

CMS RPC Gas Monitor CMS RPC Gas Monitor Frascati GroupFrascati Group

• A monitoring system of the RPC work point A monitoring system of the RPC work point which is able to provide much faster and which is able to provide much faster and sensitive response than the CMS RPC system. sensitive response than the CMS RPC system.

• Monitor efficiency and charge continuouslyMonitor efficiency and charge continuously• If work point changes, alarm goes off and If work point changes, alarm goes off and

DSC systems (GC,probes, etc) verify what the DSC systems (GC,probes, etc) verify what the change of work point is due to. change of work point is due to.

Page 17: HV-LV-DCS  Status

1717

RPC Gas Monitor RPC Gas Monitor v.1v.1

C 2H 2

F 4/S

F 6 /i

-C4H

10 /H

2O

Slow CtrlGC, p/T/RH/Ph

RPC PADRPC PADRPC PAD

RPC PADRPC PADRPC PAD

source

MONITOR

RPC PADRPC PADRPC PAD

RPC PADRPC PADRPC PAD

source

CMS

RPC PADRPC PADRPC PAD

RPC PADRPC PADRPC PAD

source

REFERENCE

Page 18: HV-LV-DCS  Status

1818

DAQ system for the CMS RPC Gas MonitorDAQ system for the CMS RPC Gas Monitor

• The system must be integrated in the Slow Control (SC) of CMS The system must be integrated in the Slow Control (SC) of CMS RPC. This implies to follow the CMS standards for DAQ: PVSS or RPC. This implies to follow the CMS standards for DAQ: PVSS or xDAQ xDAQ • We are evaluating different solutions in order to minimize the We are evaluating different solutions in order to minimize the effort in the integration with CMS Slow Controlseffort in the integration with CMS Slow Controls• Our present option is to use a system fully based on PVSS both Our present option is to use a system fully based on PVSS both for P,T, RH and HV, and both for ADC, (+TDC...+ other VME for P,T, RH and HV, and both for ADC, (+TDC...+ other VME module) readout based on VME standardmodule) readout based on VME standard• Standalone systems (PICO, ACQIRIS, etc) do not seem to offer the Standalone systems (PICO, ACQIRIS, etc) do not seem to offer the same versatility of a VME system and comparable performancessame versatility of a VME system and comparable performances• VME readout via PVSS ? VME readout via PVSS ?

Page 19: HV-LV-DCS  Status

1919

Temptative DAQ Temptative DAQ architecture architecture

for the CMS RPC Gas for the CMS RPC Gas MonitorMonitor

Pressure,temperature& humidity

sensors

VME modules for RPC pads readout

●Controller VME CAEN

●ADC V1724A - 8CH 14BIT 100MHZ

●Scaler V830AC - 32 Channel 32 Bit

●Crate VME8002 MINI VME64 09 SLOT

●TDC V1290A - 32 Ch /25 psec

CAEN HV system

PVSSPVSS

CMS SlowControl

?