51
1 Preliminary Report Created For Colorado State University Facilities Management MAKET ENGINEERING APRIL 28 2011 HUGHES STADIUM SEATING EXPANSION

HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

1  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

          Preliminary Report  Created For Colorado State University Facilities Management 

 

MAKET ENGINEERING 

APRIL 28 2011     

HUGHES STADIUM SEATING EXPANSION

Page 2: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado        

 

 

        

This report has been prepared for  Colorado State University Facilities Management 

Fort Collins, Colorado 80523  

 Created By  MAKET Engineering 

Department of Civil Engineering College of Engineering 

Colorado State University Fort Collins, Colorado 80523 

 Spring Semester 2011 

    

      

MAKET ENGINEERING TEAM MATT GOODERUM 

ANNIE SWAN KAITLIN PHENIX EVAN SHICK 

Page 3: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado        

TYLER DUNN DEREK PECK 

Page 4: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado        

Fred Haberecht Colorado State University Facilities Management Facilities Services North 251 Edison Drive Colorado State University Fort Collins, CO 80523‐6030  

April 2011 

Dear Mr. Haberecht,  

MAKET  Engineering  is  honored  to  present  a  preliminary  design  plan  for  the  seating reconfiguration  and  expansion  of  the  east  side  of  Hughes  Stadium  in  Fort  Collins,  CO.  The following  report  includes  additions  such  as  seating  design  plans  for  the  east  side which will maximize revenue, and plans for renovation of the restrooms and concessions to accommodate additional guests.  

A hard copy of the preliminary report follows, and includes: 

• The background of the stadium and statement of problems and objectives • The technical approach for designing the seating expansion • Preliminary design alternatives and descriptions • Preliminary design, analysis, and recommendations • Cost estimate for seating expansion 

After  three  design  alternatives  were  created  and  analyzed,  MAKET  Engineering  has recommended a design which will be built on top of the existing structure and  includes a club level with box suites mirroring the west side of the stadium.  This design also includes a plan to renovate  the  restrooms,  concessions,  and exits  to  accommodate  the  additional  guests.   This design was chosen because it maximizes revenue, maintains an aesthetic appeal and increases seating  capacity  by  approximately  seven  thousand  seats.  The  estimated  preliminary construction cost for the seating expansion and renovation is $ 27.1 million. 

MAKET Engineering  is grateful  for  the opportunity  to work with CSU’s Facilities Management and be able to provide a preliminary design plan for the client.   The experience the team has gained is invaluable and will be used as each member continues into the workforce.  Please feel free to contact us with any questions or concerns at 303‐588‐8389 or the address below. 

Respectfully,  

 

 

Kaitlin Phenix, Project Lead  MAKET Engineering 3444 Riva Ridge Place Fort Collins, Colorado 80526

Page 5: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado        

Table of Contents                     

Background and History                   1 

Purpose and Objectives                   5 

Technical Approach                     6 

Collection of Relevant Information                 7 

Alternative Designs and Evaluation                 8 

  Seating Configuration A                 8 

  Seating Configuration B                 9 

  Seating Configuration C                10 

  Alternative Recommendation               11 

Preliminary Design                     12 

  General Design Description                12 

  Specifications for Design                13 

  Structural Analysis                  16 

Cost Analysis                      19 

Summary                       20 

Appendices                       

  Appendix A:  Additional Figures              A1 

Appendix B:  AutoCAD Drawings              B1 

  Appendix C:  Calculations                C1 

  Appendix D:  References                D1 

Page 6: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      ii  

List of Figures & Tables                            

 

Figures 

Figure 1. Hughes Stadium from the East             1 

Figure 2. Press Box, Club Level Seating and Suites           2 

Figure 3. Location of Potential East Side Stadium Expansion        4 

Figure 4. Technical Approach Flowchart             6 

Figure 5. Design A                   8 

Figure 6. Design B                   9 

Figure 7. Design C                  10 

Figure 8. Geographic Location of Hughes Stadium in Fort Collins, Colorado   A1 

 

Tables 

Table 1. 2004 – 2005 Renovations                3 

Table 2. Loads and Load Combinations             17 

Table 3. Columns                   18 

Table 4. Initial Cost                   19 

  Table 5. Increased Revenue                 19

 

Page 7: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      1  

Background and History                   

Colorado  State University’s  football  team  is  currently  a Division  1  Football  Bowl  Subdivision program. College football currently uses the Bowl Championship Series (BCS), which employs a ranking system to determine which teams will play in the thirty‐five bowl games at the end of the season. These bowl games can generate a large amount of revenue for the teams involved. Each  of  the  five major  BCS  bowls  pay  each  school  $17 million  dollars,  and more money  is generated  through  sponsorship  and  booster  clubs.  There  are  currently  120  Football  Bowl Subdivision  teams  split up  into eleven  conferences and  three  independent  schools. Colorado State University’s  football  team  is currently a part of  the Mountain West Conference  (MWC), which  is  labeled as a non‐automatic qualifier conference. The MWC will be expanding to take on  three new  teams  from  the Western Athletic Conference; Boise State, Nevada and Fresno State.   By  expanding  to  a  total  of  ten  teams,  the MWC  is  closer  to  becoming  an  automatic qualifier conference.  In order to be considered as an automatic qualifier conference in the BCS, the  teams  in  the  conference must have  stadiums  that  seat  enough people. Hughes  stadium currently seats approximately 35,000 people, which is well below the desired requirements. 

Hughes Stadium has been an  important part of the Colorado State University and Fort Collins community  since  its  opening  in  the  fall  of  1968.  The  stadium, which was  constructed  in  a natural oval bowl, is home to the Colorado State University Rams and over the years has been the site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John.  Officially named Sonny Lubick Field at Hughes Stadium, it sits at an elevation of 5,190 feet.  It is located beneath the famous Aggies “A” at the base of Horsetooth Reservoir, about four miles west of the main campus. Figure 1 below  illustrates the current appearance of the stadium as seen from the east side and Figure 8 in Appendix A indicates its geographic location.  

 

Figure 1. Hughes Stadium from the East 

Page 8: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      2  

The initial cost of construction was about three million dollars and took one year to complete.  Originally, seating was only provided on the east and west sides of the stadium, with grass on the north and  south ends. On  the west  side of  the  stadium  the  seating  is  currently  for non‐students and contains approximately 16,000 seats that are a combination of bench seats and individual seats.  Student seating is provided on the east side of the stadium and holds close to 10,000  fans on bench  seating.   After a major  renovation  in 2005, 4,300 bleacher  seats were added  to  the north  end  zone.  The  renovation  also  included  the  replacement of  the  existing press box and club  level seating and the addition of twelve  luxury suites. Figure 2 displays the press box, club level seating area, and the suites.  

 

 

 

 

 

 

 

 

 

Figure 2. Press Box, Club Level Seating, Suites 

 

 

 

 

Currently Hughes Stadium seats a total of 34,400 visitors, but an expansion on the south side is being considered to add approximately 4,000 more seats.  The estimated cost of replacement is about $200 million, thus an expansion is the more practical and economical option.  

 

Page 9: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      3  

Since  the original construction of Hughes Stadium  there have been multiple  renovations and additions. In 2000, permanent lighting was added to reduce long term costs of renting lighting equipment. Table 1 outlines the major renovations that took place throughout 2004 and 2005: 

 

Table 1. 2004‐2005 Renovations 

Phase  Description of Work Done 

I  • Enclosed the north bowl, adding 4,300 bleacher seats • A new video scoreboard and renovated sound system in south end zone 

II  • Installed  new  concrete  pier  foundations  and  a  new  precast  concrete structure 

III  • Demolished existing club and press structures • Club  and  press  structures  were  replaced  by  a  20,000  square  foot  steel 

structure  for  enlarged  club  seating,  twelve  suites,  two  lounges  and  eight restrooms 

IV  • Interior finish work, including new central heating and air conditioning • A complete fire sprinkler and alarm system were added 

 

The  renovated  club  section provides  seating  for 420  spectators and  the  twelve added  suites provide seating for 230 spectators. Improvements to these sections include:  

• Two  new  two‐story  lounges  constructed  on  the west  side with  views  of  Horsetooth Reservoir;  

• Two new elevators for spectators;  

• Renovation of the existing elevator for press, coaches and stadium service personnel;  

• Installation of a fire sprinkler and alarm system;  

• Fiber‐optic and wireless connections for spectators, the press and coaches;  and 

• A broadcast cable system for television and replay.  

In 2006, the natural grass field was replaced by FieldTurf.  Aesthetics were kept in mind during the entire renovation, so the  final product  is a modern and high‐tech stadium with expansive views of the foothills. 

 

 

 

Page 10: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      4  

 

Remaining areas of potential expansion include the construction of additional levels above the existing east side seating  including a renovation of  the existing restrooms and concessions as well as an additional level above the existing north side seating. Figure 3 indicates the location of the potential east side expansion. 

 

Figure 3. Location of Potential East Side Stadium Expansion

Page 11: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      5  

 

Purpose and Objectives                   

Since Hughes Stadium  is  the  smallest  stadium  in  the Mountain West Conference,  the overall goal is to raise its capacity to 50,000 seats. The objective of this proposed project is to develop a preliminary architectural design for an east side seating expansion that maximizes the number of seats that will provide the most increased revenue. This expansion will raise the total seating capacity closer  to 50,000  seats,  therefore becoming closer  to complying with  the conference requirements. The project focuses on expanding the east side of the stadium and includes three design  alternatives  to  increase  seating  capacity. One  alternative  includes  the  design  of  club level seating along with box suites that mirror those found on the west side of the stadium. This expansion  adheres  to  building  codes  and  standards  regarding  seating,  stairwells,  fire  codes, means of  egress,  and disabled  seating. Due  to  increased  seating,  stadium  amenities  such  as restrooms,  concessions,  and  exits  have  be  analyzed  to  provide  adequate  facilities  for  the expanding  fan base. The ultimate goal of  this expansion  is  to provide maximum  revenue  for Colorado  State  University  as  well  as  the Mountain West  Conference  while maintaining  an attractive and enjoyable atmosphere for fans. 

       

Page 12: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      6  

Technical Approach                     

MAKET Engineering worked closely with Colorado State University Facilities Management and the Athletic Department to develop a design that was operationally sufficient while remaining economically  feasible.    This  design  had  to  integrate  the  requests  of  the  clients  with  the structural  analysis  aspects  of  the  seating  expansion.    In  order  to  efficiently  and  effectively complete their objectives, MAKET developed a technical approach that is outlined below in the flowchart labeled Figure 4.  Each heading in the flow chart will be explained in further detail in the following pages of this report. 

 

Figure 4. Technical Approach Flowchart 

Page 13: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      7  

Collection of Relevant Information                

After reaching a full understanding of the objectives, MAKET collected the necessary relevant information to facilitate the project. The following summarizes this stage of the technical approach required to move forward with the preliminary design. 

Plans/Blueprints and Site Visit 

MAKET contacted CSU Facilities Management to obtain detailed plans and blueprints of Hughes Stadium.  The  plans  included measurements  and  elevations  of  the  original  design  from  the 1960’s as well as the newer renovation from 2005. An overhead plan view in AutoCAD was also received  showing  exact  dimensions  and  elevations  of  the  current  stadium.  Finally, MAKET Engineering acquired design plans  compliments of HOK,  for  the east  side of Hughes  stadium composed  of  several  expansion  alternatives.  Each  plan  and  blueprint  was  reviewed  and referenced to gain a greater knowledge of the existing structure and its surroundings. 

MAKET Engineering also contacted Athletic Director, Doug Max, to arrange several site visits to Hughes  Stadium.  The  site  visits  were  conducted  for  multiple  purposes:  first,  to  better understand the expansion area by walking the structure and taking photos. Second, to view the current architecture and existing seating areas (bleachers, club seats, and box suites) with the possibility of mirroring the west side. And lastly, MAKET wanted to have the client explain and show  what  was  considered  essential  to  the  new  expansion  design.  A  final  site  visit  was conducted  to confirm  that all  the  final measurements on  the preliminary design comply with the existing structure. 

Codes and Design Specifications for Stadiums 

In order  for  the preliminary stadium design  to be  in compliance with  the City of Fort Collins, MAKET Engineering has taken into account all appropriate codes and design specifications.  All design  specifications  for  the  seating  configurations  such  as  seat  spacing,  aisle  spacing,  and stairway requirements, as well as design loads were established using ICC 300‐2002.  Codes and specifications  involving  structural design, means of egress, and concrete were obtained  from the  IBC  2009:  International  Building  Code.    For  plumbing  requirements  the  IPC  2009: International  Plumbing  Code was  used  for  the  proposed  restroom  facilities.    The  structural design  loads used  to design structural members were determined  from ASCE 7‐05: Minimum Design  Loads  for  Buildings  and Other  Structures.   Minimum  required  design  loads  for  snow wind and rain were found from the City of Fort Collins Building Services: Codes and Standards. Codes and specifications relating to handicap accessibility requirements were found according to the 2010 ADA Standards for Accessible Design. 

Page 14: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      8  

Design Alternatives and Evaluation               

After  collecting  the  necessary  material  and  information,  three  design  alternatives  were developed, analyzed, and prepared  for presentation  to  the client at an  intermediate meeting where  a  final  design was  chosen  for  further  development.  Considerations  included  ease  of construction, construction cost, number and  type of  increased  seats, aesthetics, accessibility, and increased future revenue. The following outlines the three alternatives: 

DESIGN A 

Design A is a seating configuration in which a large  seating  addition  would  be  added directly onto the existing east side structure.  The structure would attach to the back of the existing  seating  and  continue  upwards, adding  approximately  60  rows  above  the existing  student  section.    In  this design,  the style  of  seating  would  be  bleacher  bench seats;  the  same  as  currently  exists  on  the east side.   The apex of this seating addition would be at the same height as the highest point  on  the  west  side  of  the  stadium.  Finally, the seating addition would continue the  length of  the current seating structure, which would help maintain an aesthetically pleasing look to the stadium. 

The  advantage  of  this  design  is  that  it  is simply constructed; no additional structural supports would  be  necessary.    Based  on  the initial cost estimates,  this would be  the most cost effective design out of the three designs because  less material and  labor would be used.  Additionally,  this design provides approximately 6,000 additional  seats.   The disadvantage of this design is that it provides less revenue than other alternatives because bench seating is the least expensive type of seat to sell.  There would also be demolition of about 2,900 seats in the existing student section to accommodate for the construction of the new seats.   Finally, there are possible congestion  issues that arise due to the current means of egress that are available on the east side. Figure 5 displays the design for Alternative A. 

 

Figure 5: Design A

Page 15: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      9  

 DESIGN B 

This  alternative  provides  additional  seating while  also  taking  into  consideration  the viewing  pleasure  of  disabled  patrons.    This addition is similar to Design A, however there would  be  no  demolition  of  existing  seats.  Instead,  Design  B  would  use  the  current space  at  the  top  of  the  exiting  seating structure  to  create  an  aisle way  that would then  give  rise  to  a  seating  expansion.    The aisle way would attach to a ramp, so disabled patrons  would  be  able  to  access  this  area easily  and  have  designated  viewing  areas.  This  aisle  way  is  separated  from  the  main aisle  way  so  that  people  from  the  existing section  as well  as  the  new  addition  can  all move about without congestion issues.   

The  advantage of  this design  is  that  it does not  require  any  demolition  of  the  existing section.  Design B also provides the most net additional  seats  with  approximately  6,300. 

There  is  easy  access  to  this  addition  for  disabled  patrons  as well  as  for  regular  viewers.  In addition,  this  design  maintains  consistency  with  existing  seating,  making  it  aesthetically pleasing.    The  two  disadvantages  of  this  design  are  that  there  is  less  revenue  generated because  of  the  bench  seating  that  would  be  used,  and  there  would  be  a  higher  cost  of construction because more material would be required and the construction would take longer than Design A. Figure 6 illustrates the layout for Alternative B. 

 

 

 

Figure 6: Design B 

Page 16: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      10  

 

 

Figure 7: Design C

 

DESIGN C 

Design  C  is  the  third  and  final  design alternative.  It  includes  suites  and  club seating  as  well  as  bench  seating  above the suite and club area.   There would be 2  suites  added  on  each  end  of  the addition with  the  club  level  in  between.  This  design  mirrors  the  club  and  suite layout on the west side.  Each suite would hold  approximately  18  people  and  the club  level  in  between  would  contain approximately 1,000 seats.  The addition with  the  suites  and  club  seats  would span the  length of the existing east side seating  structure  and  would  be  built above the  last row of seats.   This design alternative  provides  the  suites  and  the club  level  with  indoor  and  outdoor seating,  as  opposed  to  the  west  side which  only  contains  indoor  seating.  Finally, approximately 4,000 seats would be  added  in  a  structure  that would  be placed atop the suite and club  level.   The seats contained  in this area could be changed from bench to chair‐back style depending on preference of the client.   

The advantage of this design is that it generates the most revenue because of the suite and club seating, which in turn benefits the athletic department and university as a whole.  This design is aesthetically pleasing because  it mirrors the west side club  level and suites and adds an air of luxury to the stadium.  Most importantly, this design contains elements, such as suites and club level seating, which are desirable to the client and their vision of the stadium in the future.  The disadvantage  to  this  option  is  that  it  is  a  complex  construction  and  elements  of  structural support must be considered.    It  is also the highest construction cost while providing the  least amount of overall seating. Design C is illustrated in Figure 7. 

 

 

Page 17: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      11  

Page 18: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      12  

 

RECOMMENDATION 

At an intermediate meeting held with the client, MAKET Engineering recommended Design C as the  superior design  for  the expansion of  the east  side of Hughes Stadium. This option  is  the most  complex  in  terms  of  construction  and  structural  additions  and  is  the most  expensive alternative.  However,  after  considering  the  requests  of  the  client,  the  drawbacks  are outweighed by the advantages of this design. By providing the stadium with 4 more suites and approximately 1,000 more club level seats, the revenue generated will be far greater than any other alternative.  Also, this design contains features such as providing outdoor seating for the suite and club  level, which cannot be  found on  the west  side.   Last, by constructing another seating addition atop the suite and club  level,  it gives this design diversity not offered by any other  alternative.    In  summation,  the  benefits  of  constructing  an  addition with  suites,  club seating, and traditional seating provides patrons with more options for seating and revenue for the university, which are offset by the complexities of such a design. At the conclusion of the presentation of the alternatives, the client chose MAKET’s recommendation of Design C to be further developed. 

   

Page 19: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      13  

 

Preliminary Design____________________             

General Design Description 

Visually, the chosen design will span the length of the current east side student section and will be constructed above the last row of the existing section.  The suite and club level will be one story high and will contain 2 suites on each end, with the club level in between.  Each suite will have a  capacity of 18 people and  contain  indoor and outdoor  seating.   The  club  seating will contain  luxury chair‐back seats that will add about 1,000 additional seats to the stadium.   The club  level will also have the option of sitting outside or  inside and a  lounge  inside can provide additional shelter  in case of  inclement weather as well as a 360° bar.   To access the club and suite level, a patron will take a private elevator up to this level and will be spared the difficulty of dealing with crowds in the student section.  Currently a suite sells for $35,000 a season and a single club seat sells for $1,500 per season.  By adding 4 suites and about 1,000 club seats, this provides  a  generous  increase  in  revenue  for  the  athletic  department  and  university.    The additional  seating  structure will be added  to  the  top of  the  suites and club  level and can be accessed by ramps that will be added to each side of the new addition.  The addition of ramps on each  side of  the new addition will minimize congestion as well as giving disabled patrons ease of access to the upper levels.  Disabled seating will exist at the front of this upper seating addition and will provide almost 100 designated areas for disabled persons, which far exceeds the  required amount  specified  in  the  IBC 2009.   This upper  level addition will  contain about 6,200 bench  seats, bringing  the  total  seating addition of  this alternative  to 7,418. This along with an expansion of the north and south sides can potentially raise the capacity of the stadium to 50,000. Detailed accompanying AutoCAD drawings can be found in Appendix B. 

Page 20: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      14  

 

Specifications for Design 

MAKET Engineering has  researched specifications and codes  that apply  to stadiums and have outlined relevant codes below.   Each specification  is  in keeping with stadium codes as well as city  and  county  codes.    Seating,  disabled  seating,  restrooms,  vendors,  ramp  structures  and means of egress have been outlined below and have been complied with in design of structural additions. 

Bleacher Seating 

Bleacher  seating, aisles and aisle  stairs are designed  in accordance with  ICC 300‐2002 and  IBC  2009.  The  upper  seating  addition will  consist  of  26  rows  of  seating with  a maximum of 25 seats per row between a total of 9 aisles. 

Bleacher  seating will  continue  along  the  length of  the  row  and have  a width of  11.5 inches and depth of 16.5  inches measured from the face of the concrete slab to top of bleacher. Seating has been designed so that one person occupies 18 inches of bleacher length.  

To  preserve  the  line‐of‐sight  for  each  spectator,  rows  have  been  designed  to  form  a slight concave shape in keeping with the existing shape of the structure, with depths of approximately 12  inches measured as a clear vertical distance. The width of the row  is approximately 30 inches as a clear horizontal distance. Aisle widths are designed for 48 inches with aisle stairs continuing the length of the aisle. 

Disabled Seating 

Disabled seating  is provided to accommodate people with physical disabilities and has been designed in accordance with ADA standards. It is required that at least one percent of  the  seating be designed  for wheelchair  locations. MAKET Engineering has  included wheelchair seating  locations at the upper  level addition and has  far exceeded the one percent  requirement.  The  clear  space  allowance  in  the  design  for  single  and  double wheelchairs with a  forward entrance are 34  inches by 48  inches and 68  inches by 48 inches, respectively. 

Restrooms 

MAKET Engineering has researched restroom requirements for the seating configuration alternative  chosen  by  the  client.  A  description  and  recommendations  of  necessary 

Page 21: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      15  

additional  facilities needed  for  the proposed expansion are provided on  the  following page. 

In order to accommodate the  increased capacity of the stadium, the existing restroom will be demolished, relocated, and expanded. The IBC 2006 states that for the first 1,500 males and females, 1 toilet stall is required for every 75 males and every 40 females. For numbers exceeding 1,500, 1  toilet  stall  is  required  for every 120 males  and every 60 females. According to the IPC 2006, urinals can replace a maximum of 67% of male stalls in assembly areas  such as  stadiums. The  following  calculations and  recommendations will use this maximum of 67% and will assume that the spectators consist of an equal number of each sex. 

With the  increase of 7,418 seats, a minimum of 68 additional stalls would be required for the women’s restrooms and a minimum of 35 additional stalls would be required for the men’s restrooms, 23 of which could be replaced with urinals. 

Vendors 

Hughes Stadium currently contains eight permanent concessions on the east and west sides of  the  stadium, each with  two vendors a piece.   The  ratio of vendor  to  seats at current  capacity  is  one  vendor  to  every  2,150  seats.    The  standard  throughout  the Mountain  West  Conference  is  one  vendor  to  every  2,500  seats.    Although  Hughes Stadium meets this standard, MAKET Engineering felt that this ratio could be improved by adding more permanent concessions to the east side of the stadium.  The proposed expansion adds 7,418 seats bringing the total stadium capacity to approximately 42,000 and adding six permanent concessions.  As part of the expansion, two of the permanent concessions will  be  added  to  the  lower  level  concourse  and  four  concessions will  be added to the upper  level concourse.   With the added concessions, this brings the ratio to  one  vendor  to  every  1,500  seats.   MAKET  Engineering  believes  that  these  added permanent  concessions  will  greatly  benefit  patrons  with  easier,  faster  service  and benefit the university with added revenue. 

Ramp Structures 

The  ramp  structures  are  designed  in  compliance  with  IBC  2006,  as  well  as  ADA standards. Ramps at the north and south ends of the stadium are to be provided. Each ramp will be designed identically in order to provide a sense of symmetry and aesthetic appeal. A maximum slope of 1:12, permitted by ADA standards, will be used to provide elevation change. The ramps are to be 10 feet wide having runs being equal to or  less 

Page 22: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      16  

than 60 feet. Areas of the ramps where a change in direction occurs, a level landing of at minimum 10  feet shall be provided. Continuous handrails are  to be present along  the inside and outside of  the  ramps  spanning  the entire  ramp  length. The  recommended dimensions  for handrails are 1.25  to 2  inches  in diameter having a height of 34  to 36 inches.  A minimum  clearance  of  2  inches  from  any wall  shall  be  provided  for  every handrail.  

Means of Egress 

The phrase "means of egress" refers to the ability to exit the structure, primarily in the event  of  an  emergency,  such  as  a  fire.  Specifically,  a means  of  egress  is  broken  into three parts: the path of travel to an exit, the exit itself, and the exit discharge (the path to  a  safe  area  outside).  The  code  also  address  the  number  of  exits  required  for  a structure based on its intended occupancy use and the number of people who could be in the structure at one time as well as their relative locations. 

Means  of  egress  and  emergency  escape  conditions  have  been  verified  in  accordance with IBC 2006. A total of eight exits currently exist at Hughes Stadium for spectators to use  in  the  event  of  an  emergency.  The  addition  of  two  ramp  structures  has  been imposed  to  better  exit  access  and  flow. Aisles  and  stairs  that  connect  the  additional seating have been designed  to maximize pedestrian  flow. A maximum  travel distance from the seating to the provided exits along aisle access way’s has been designed at 120 feet which is well below the maximum allowable distance of 400 feet. 

In addition to the ramp structures three elevators have been designed to provide added ease of access and  functionality of  the  structure. Two passenger elevators have been strategically placed  in the center of the expansion structure to provide optimal service routes for the club and upper  levels. A service elevator has also been added providing access for the  loading and unloading of  larger objects to upper  levels of the structure. Each elevator has been designed with accordance with building codes to ensure safety. 

  

Page 23: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      17  

 

Structural Analysis 

Structural  load  analyses  were  performed  to  determine  the  required  load  capacity  of  the proposed  seating  structure,  as well  as  the  seating  structure’s  compatibility with  the  existing seating  structure.  The  design  loads were  calculated  in  accordance with  ASCE  7‐05: Minimal Design Loads for Buildings and Other Structures which includes dead, live, snow, rain, and wind.  

In  order  to  calculate  the  loads  listed  above,  the  proposed  structure  was  broken  into  five separate sections: upper level bleachers, upper level concourse exposed, upper level concourse beneath  the  bleachers,  club  and  suite  level,  and  club  seating  outdoors.  The  sections were separated based on variations in loads experienced throughout the structure. 

Dead  loads,  according  to ASCE  7‐05  3.1.1,  are  defined  as  consisting  of  "...  the weight  of  all materials of construction incorporated into the building..."  This is generally considered to mean that anything that is a fixed part of the structure is a dead load.  To be considered dead load, an item must be physically  attached  to  the  structure. Additional uniform  loads were  taken  into consideration on certain parts of the structure due to the weight of people and amenities. 

Live loads are defined in ASCE 7‐05 4.2.1 are the maximum loads expected by the intended use or occupancy, but shall  in no case be  less than the minimum uniformly distributed unit  loads required  by  Table  4‐1  in  ASCE  7‐05.  The  live  loads  used  for  the  designed  structure  were determined from that table. 

Snow loads are considered a uniform load due to the accumulation of snow and snow drifts on a  structure.  Snow  loads  for  the  proposed  structure  were  calculated  using  the  procedure indicated in Chapter 7 of ASCE 7‐05. The calculations yielded a snow load of 16.17 psf, however, the City of Fort Collins building codes require a minimum snow  load of 30 psf for design. As a result, a snow load of 30 psf was used for design. 

Rain  loads  involve  the uniform  load due  to  the accumulation of precipitation due  to  intense, short‐duration  rainfall  events.  The  determination  of  these  loads  incorporates  the  type  and location  of  roof  drainage  for  the  structure.  The  proposed  structure  was  designed  for  a maximum 2 in.  of standing water due to the location of the secondary drains. 

Wind  loads are defined as  the uniform air pressure acting on  the  surface of a  structure. The loads were calculated, according to Method 1‐ Simplified Procedure described  in Chapter 6 of ASCE 7‐05. The proposed structure was designed as a main wind force resisting system as well as a  rigid  structure. A basic design wind  speed of 100 mph was  required by  the City of Fort 

Page 24: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      18  

Collins  building  codes. Only windward  forces were  taken  into  account  during  the  structural analysis and design.   

Due to geographic location and relevant statistical data, seismic loading was not considered in the design of the proposed structure. 

There were  five  load combinations calculated  for each segment of  the structure. All  five  load combinations  took  into  account  the  dead,  live,  snow,  rain  and  wind  loads  as  previously specified.  These  values  are  shown  in  Table  2. Using  the  Load  and  Resistance  Factor Design (LRFD) the maximum load combination was determined and is highlighted below in Table 2.   

Table 2: Loads and Load Combinations 

Loads (psf) Loads (psf) Loads (psf) Loads (psf) Loads (psf)

Dead 108.67 Dead 98.67 Dead 163.67 Dead 118.67 Dead 112

Live   100 Live   100 Live   100 Live   100 Live   60

Snow 30 Snow 30 Snow 0 Snow 0 Snow 30

Rain 10.4 Ra in 10.4 Ra in 0 Rain 0 Rain 10.4

Wind 4.32 Wind 16.11 Wind 16.11 Wind 11.6 Wind 3.7

Load Combinations

(psf)Load 

Combinations(psf)

Load Combinations

(psf)Load 

Combinations(psf)

Load Combinations

(psf)

1 152.13 1 138.13 1 229.13 1 166.13 1 156.8

2 305.4 2 293.4 2 356.4 2 302.4 2 245.4

3 278.4 3 266.4 3 296.4 3 242.4 3 242.4

4 252.31 4 259.18 4 322.18 4 260.96 4 215.32

5 236.4 5 224.4 5 296.4 5 242.4 5 200.4

Upper Level Bleachers

Upper Level Concourse (Exposed)

Upper Level Concourse    

(Beneath Bleachers)Club and Suite Level Club Seating

 

The  figures  tabulated  in Table 2 were  calculated using a  step by  step procedure  that  can be found in Appendix C. 

After the maximum load combinations were calculated, this information was used to determine the size and strength of columns that will be required to support each  level of the expansion. Initially,  the  square  footage of  each  section of  the proposed  structure was determined.  The total  required  strength  of  each  section  was  determined  using  the  square  footage  and  the calculated  applied  factored  loads  found  using  LRFD.  Each  segment  was  then  divided  into equivalent  tributary  areas  in  order  to  define  the  number  of  columns  to  be  used.    The breakdown of each section  into smaller tributary areas allowed the required strength of each column to be calculated. The LRFD load factor of 0.9 was used to calculate the design strength 

Page 25: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      19  

of each column.  In order  to be conservative, a  large  factor of safety  (3) was used  to  find  the actual design strength of each column. This  is due to the assumption that stadiums are often exposed to excessive, spontaneous dynamic loading.  

Upon  determining  the  design  strength  of  each  column,  several  column  dimensions  were evaluated to meet the design requirements set forth. Using the optimal column dimensions the allowable  column  strengths  were  determined.  The  structure  was  designed  using  3  ksi reinforced concrete with a unit weight of 148 pcf. The resulting column design for each column type of the proposed structure is shown in Table 3. Each column was designed to aesthetically match the existing columns on the west side of Hughes Stadium.  

Table 3: Columns 

Existing Concourse 

T 5001 278 309 3 926 18" x 24" 1296

Existing Concourse Arched

24845 690 767 3 2301 18" x 44" 2376

Club Level and Suites

17265 480 533 3 1599 24" x 24" 1728

Upper Concourse

7903 439 488 3 1464 18" x 27" 1458

Total Required Strength (kips)

Columns

Required Strength of Each Column 

(kips)

Design Strength of Each Column 

(kips)

Factor of Safety

Design Strength w/ F.S. (kips)

Column Dimensions

Actual Column Strength (kips)

 

All calculations supplying the values found in this table can be found in Appendix C.

Page 26: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      20  

 

Cost Analysis                       

After consulting with industry professionals and the advisor of the project, MAKET Engineering decided  upon  a  base  price  per  seat  for  each  section  with  bleacher  seats  being  the  least expensive and box suite seats being  the most expensive. This  is summarized  in  the  following table: 

Table 4: Initial Cost 

Seating Number of Seats Price Per Seat ($) Price (million $)

Bleacher 6420 3500 22.47

Club 926 4500 4.17

Suite 72 6000 0.43

TOTAL 27.07 

The  same  approach  was  used  when  considering  the  increased  future  revenue,  again  with bleacher  seats being  the  least expensive  and box  suite  seats being  the most expensive.  The following table summarizes the increased future revenue: 

Table 5: Increased Revenue 

Increased Revenue  Increased Revenue Per Seat Per Season 

($)Per Season            (million $)

Bleacher 6420 200 1.28

Club 926 600 0.56

Suite 72 1000 0.07

TOTAL 1.91

Seating Number of Seats

 

As previously mentioned, this alternative has the highest initial cost at about $27.1 million but it makes  the most  increase  in  future  revenue  with  about  $2 million  per  season.  At  100% capacity,  the  stadium would  be  paid  off  in  about  14  years  however;  this  number  has  been calculated without the considered increase from concessions and parking. 

MAKET Engineering estimates that about 250 hours were spent towards this expansion design.

Page 27: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      21  

 

Summary                         

In  order  to  increase  the  capacity  at  Colorado  State  University’s  Hughes  Stadium,  MAKET Engineering  has  developed  a  preliminary  design  for  an  east  side  seating  expansion.  Three alternative  designs  were  created  and  presented  to  the  Colorado  State  University  Facilities Management and Athletic Department where a final preliminary design was chosen. The final preliminary design  for the seating expansion  includes the addition of a suite/club  level above the existing  seating and above  that, 6,300 bleacher  style  seats mirroring  those  found on  the west side. 7,418 total additional seats increases the stadium’s overall capacity to approximately 42,000 seats. If the proposed south side expansion is carried out as well as an expansion of the north side, the new stadium would hold the necessary amount of spectators. These additions would allow spectators to choose from a variety of seating options: suite/box on the east side with views of the mountains or west side with view of the city, indoor club seating on the west side, indoor and outdoor club seating on the east side, chair‐back style seating on the west side, and  bleacher  style  seating  on  the  west,  north,  east,  or  south  sides.  The  aesthetics  of  the addition will be consistent with  the  rest of  the stadium,  imitating already existing sections of the  stadium  as  much  as  possible.  It  is  recommended  to  use  lightweight  concrete  in  the expansion to ensure structural reliability of the existing structure. In order to accommodate the additional  visitors  east  side  restrooms  and  concessions  have  been  added  and  relocated  in accordance with  the  appropriate  codes  and  specifications.  The  total  estimated  cost  for  the expansion  is $27.1 million ($3,650 per seat) but the potential  increased revenue per season  is about $2 million. 

 

Page 28: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      2  

Appendices                       

Appendix A: Additional Figures 

Figure 8. Geographic Location of Hughes Stadium in Fort Collins, Colorado 

Page 29: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      A1  

 

Appendix B: AutoCAD Drawings 

Preliminary architectural drawings  for  the proposed Hughes Stadium Seating Expansion have been  drafted  using  AutoCAD.    These  can  be  found  in  the  drawings  attached  to  this  report.  Section A shows plan views  for  the existing structure, our proposed structure, as well as grid measurements used  in the design.   Section B shows elevation views along three separate grid lines.  Section C includes enlarged plan views of the Club/Suite Level as well as the Upper level.  Section D shows an enlarged elevation cross section view of the Club/Suite Level as well as the Upper Level.  The final section, Section E, shows detailed views of the walkways as well as the bleacher and club seats.  These documents are not for use in construction.   

Page 30: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C1  

 

Appendix C: Calculations 

The procedure used to determine the required, allowable, and design strengths of the structural columns designed for the seating expansion structure is listed below.  These calculations were based on ASCE 7‐05:  Minimum Design Loads for Buildings and Other Structures and ACI 318‐08:  Building Code Requirements for Structural Concrete.  All calculations were used with the Load and Resistance Factor Design method. 

Loads on Proposed Upper Bleacher Seating 

1. Required Loads  Dead Load, D (psf)  

• 8” slabs of reinforced concrete with a unit weight, γ, of 148 pcf 

• Bleacher seating superimposed uniform dead load of 10 psf  

 

Live Load, L (psf)  

• Per ASCE 7‐05, Chapter 4, Table 4‐1, Bleacher seating uniform live load of 100 psf  

 

Snow Load, S (psf)  

• Using ASCE 7‐05, Chapter 6, the snow load was calculated using Eq. 7‐1 

• City of Fort Collins Building Code requires a minimum of 30 psf for design  

• The larger of the two loads was used for design 

• A flat roof snow load was determined based on flat bleacher and step surface areas 

• Occupancy category III, Exposure category B 

•  

 

Page 31: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C2  

        Where:    Flat roof snow load, psf 

 Exposure Factor = 0.7 

  Thermal Factor = 1.0 

  Importance Factor = 1.1 

  Ground snow load = 30 psf 

 

• A snow load of 30 psf was used for design   

Rain Load, R (psf) 

• Using ASCE 7‐05, Chapter 8, the rain load was calculated using Eq. 8‐1 as shown below  

  

        Where:    Rain load, psf 

 Depth of water on undeflected roof up inlet of   secondary drainage system when primary drainage system is blocked = 2 in 

 Additional depth of water on undeflected roof above inlet of secondary drainage system at its design flow = 0 in 

  Wind Load, W (psf)  

• Using ASCE 7‐05, Chapter 6, the wind loads were found using Eq. 15 and Eq. 6‐17 for Main Wind‐Force Resisting Systems: Rigid Buildings of All Heights 

• Calculations were based on factors of region/area, elevation, and the structure’s surface on which the wind contacted 

Page 32: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C3  

• Only windward forces were taken into account  

 

      Where:   Velocity pressure, psf 

 Velocity pressure coefficient = 1.016, for height above the ground surface = 110 ft [from Table 6‐3, Case 2, Exposure Category B] 

 Topographic factor = 1.0 [from Section 6.5.7.2] 

 Wind directionality factor = 0.85 [from Table 6‐4, Buildings: Main Wind Force Resisting Systems] 

 Basic wind speed = 100 mph [from City of Fort Collins Building Codes and Standards] 

 Importance Factor = 1.15 [from Table 6‐1, Non‐Hurricane Prone Regions] 

 

 

 

• Using the velocity pressure, the windward load was determined using Eq. 6‐17 as shown below 

 

Where:   wind load, psf 

  Velocity pressure = 25.41 psf 

 Gust effect factor = 0.85 [from Section 6.5.8.1, Rigid Structures] 

 External pressure coefficient = ±0.2 [from Figure 6‐6 for a 32° slope] 

Page 33: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C4  

 Velocity pressure for internal pressure =   [from Section 6.5.12.2.1] 

 Internal pressure coefficient = 0.0 [from Figure 6‐5, open building] 

 

 

 

2. Load and Resistance Factor Design – Load Combinations  

• The controlling load combination was determined from ASCE 7‐05, Chapter 2, Section 2.3.2, Eq. 2 as shown below  

  

Where:   Required strength, psf 

 Dead load, psf 

 Live load, psf 

 Snow load, psf 

 Rain load, psf 

 

  

Loads on Proposed Upper Concourse (Exposed) 

1. Required Loads  Dead Load, D (psf)  

• 8” slabs of reinforced concrete with a unit weight, γ, of 148 pcf 

Page 34: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C5  

 

 

  Live Load, L (psf)  

• Per ASCE 7‐05, Chapter 4, Table 4‐1, Bleacher seating uniform live load of 100 psf  

 

 

Snow Load, S (psf)  

• Using ASCE 7‐05, Chapter 6, the snow load was calculated using Eq. 7‐1 

• City of Fort Collins Building Code requires a minimum of 30 psf for design  

• The larger of the two loads was used for design 

• A flat roof snow load was determined based on flat bleacher and step surface areas 

• Occupancy category III, Exposure category B  

 

        Where:    Flat roof snow load, psf 

 Exposure Factor = 0.7 

  Thermal Factor = 1.0 

  Importance Factor = 1.1 

  Ground snow load = 30 psf 

 

• A snow load of 30 psf was used for design   

Page 35: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C6  

Rain Load, R (psf) 

• Using ASCE 7‐05, Chapter 8, the rain load was calculated using Eq. 8‐1 as shown below  

  

        Where:    Rain load, psf 

 Depth of water on undeflected roof up inlet of   secondary drainage system when primary drainage system is blocked = 2 in 

 Additional depth of water on undeflected roof above inlet of secondary drainage system at its design flow = 0 in 

  Wind Load, W (psf)  

• Using ASCE 7‐05, Chapter 6, the wind loads were found using Eq. 15 and Eq. 6‐17 for Main Wind‐Force Resisting Systems: Rigid Buildings of All Heights 

• Calculations were based on factors of region/area, elevation, and the structure’s surface on which the wind contacted 

• Only windward forces were taken into account  

 

      Where:   Velocity pressure, psf 

 Velocity pressure coefficient = 0.95, for height above the ground surface = 86 ft [from Table 6‐3, Case 2, Exposure Category B] 

 Topographic factor = 1.0 [from Section 6.5.7.2] 

 Wind directionality factor = 0.85 [from Table 6‐4, Buildings: Main Wind Force Resisting Systems] 

Page 36: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C7  

 Basic wind speed = 100 mph [from City of Fort Collins Building Codes and Standards] 

 Importance Factor = 1.15 [from Table 6‐1, Non‐Hurricane Prone Regions] 

 

 

 

• Using the velocity pressure, the windward load was determined using Eq. 6‐17 as shown below 

 

Where:   wind load, psf 

  Velocity pressure = 23.69 psf 

 Gust effect factor = 0.85 [from Section 6.5.8.1, Rigid Structures] 

 External pressure coefficient = 0.8 [from Figure 6‐6] 

 Velocity pressure for internal pressure =   [from Section 6.5.12.2.1] 

 Internal pressure coefficient = 0.0 [from Figure 6‐5, open building] 

 

 

 

2. Load and Resistance Factor Design – Load Combinations  

Page 37: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C8  

• The controlling load combination was determined from ASCE 7‐05, Chapter 2, Section 2.3.2, Eq. 2 as shown below  

  

Where:   Required strength, psf 

 Dead load, psf 

 Live load, psf 

 Snow load, psf 

 Rain load, psf 

 

  

Loads on Proposed Upper Concourse (Beneath Bleachers) 

1. Required Loads  Dead Load, D (psf)  

• 8” slabs of reinforced concrete with a unit weight, γ, of 148 pcf 

• Amenities  superimposed uniform dead load of 65 psf  

 

 

Live Load, L (psf)  

• Per ASCE 7‐05, Chapter 4, Table 4‐1, Bleacher seating uniform live load of 100 psf  

 

Page 38: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C9  

Wind Load, W (psf)  

• Using ASCE 7‐05, Chapter 6, the wind loads were found using Eq. 15 and Eq. 6‐17 for Main Wind‐Force Resisting Systems: Rigid Buildings of All Heights 

• Calculations were based on factors of region/area, elevation, and the structure’s surface on which the wind contacted 

• Only windward forces were taken into account  

 

      Where:   Velocity pressure, psf 

 Velocity pressure coefficient = 0.95, for height above the ground surface =86 ft [from Table 6‐3, Case 2, Exposure Category B] 

 Topographic factor = 1.0 [from Section 6.5.7.2] 

 Wind directionality factor = 0.85 [from Table 6‐4, Buildings: Main Wind Force Resisting Systems] 

 Basic wind speed = 100 mph [from City of Fort Collins Building Codes and Standards] 

 Importance Factor = 1.15 [from Table 6‐1, Non‐Hurricane Prone Regions] 

 

 

 

• Using the velocity pressure, the windward load was determined using Eq. 6‐17 as shown below  

 

Where:   wind load, psf 

Page 39: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C10  

  Velocity pressure = 23.69 psf 

 Gust effect factor = 0.85 [from Section 6.5.8.1, Rigid Structures] 

 External pressure coefficient = 0.8 [from Figure 6‐6] 

 Velocity pressure for internal pressure =   [from Section 6.5.12.2.1] 

 Internal pressure coefficient = 0.0 [from Figure 6‐5, open building] 

 

 

 

2. Load and Resistance Factor Design – Load Combinations  

• The controlling load combination was determined from ASCE 7‐05, Chapter 2, Section 2.3.2, Eq. 2 as shown below  

  

Where:   Required strength, psf 

 Dead load, psf 

 Live load, psf 

 Snow load, psf 

 Rain load, psf 

 

  

Page 40: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C11  

Loads on Proposed Club and Suite Level 

1. Required Loads  Dead Load, D (psf)  

• 8” slabs of reinforced concrete with a unit weight, γ, of 148 pcf 

• General superimposed uniform dead load of 10 psf  

 

 

Live Load, L (psf)  

• Per ASCE 7‐05, Chapter 4, Table 4‐1, Bleacher seating uniform live load of 100 psf  

 

 Wind Load, W (psf)  

• Using ASCE 7‐05, Chapter 6, the wind loads were found using Eq. 15 and Eq. 6‐17 for Main Wind‐Force Resisting Systems: Rigid Buildings of All Heights 

• Calculations were based on factors of region/area, elevation, and the structure’s surface on which the wind contacted 

• Only windward forces were taken into account  

 

      Where:   Velocity pressure, psf 

 Velocity pressure coefficient = 0.93, for height above the ground surface = 80 ft [from Table 6‐3, Case 2, Exposure Category B] 

 Topographic factor = 1.0 [from Section 6.5.7.2] 

Page 41: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C12  

 Wind directionality factor = 0.85 [from Table 6‐4, Buildings: Main Wind Force Resisting Systems] 

 Basic wind speed = 100 mph [from City of Fort Collins Building Codes and Standards] 

 Importance Factor = 1.15 [from Table 6‐1, Non‐Hurricane Prone Regions] 

 

 

 

• Using the velocity pressure, the windward load was determined using Eq. 6‐17 as shown below 

 

Where:   wind load, psf 

  Velocity pressure = 23.20 psf 

 Gust effect factor = 0.85 [from Section 6.5.8.1, Rigid Structures] 

 External pressure coefficient = 0.8 [from Figure 6‐6] 

 Velocity pressure for internal pressure =   [from Section 6.5.12.2.1] 

 Internal pressure coefficient = 0.18 [from Figure 6‐5, open building] 

 

 

 

2. Load and Resistance Factor Design – Load Combinations 

Page 42: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C13  

 

• The controlling load combination was determined from ASCE 7‐05, Chapter 2, Section 2.3.2, Eq. 2 as shown below  

  

Where:   Required strength, psf 

 Dead load, psf 

 Live load, psf 

 Snow load, psf 

 Rain load, psf 

 

  

Loads on Proposed Outer Club Seating 

1. Required Loads  Dead Load, D (psf)  

• 8.3” slabs of reinforced concrete with a unit weight, γ, of 148 pcf 

• Bleacher seating superimposed uniform dead load of 10 psf  

 

 

Live Load, L (psf)  

• Per ASCE 7‐05, Chapter 4, Table 4‐1, chair‐back bleacher seating uniform live load of 100 psf 

 

Page 43: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C14  

 

Snow Load, S (psf)  

• Using ASCE 7‐05, Chapter 6, the snow load was calculated using Eq. 7‐1 

• City of Fort Collins Building Code requires a minimum of 30 psf for design  

• The larger of the two loads was used for design 

• A flat roof snow load was determined based on flat bleacher and step surface areas 

• Occupancy category III, Exposure category B  

 

        Where:    Flat roof snow load, psf 

 Exposure Factor = 0.7 

  Thermal Factor = 1.0 

  Importance Factor = 1.1 

  Ground snow load = 30 psf 

 

• A snow load of 30 psf was used for design   

Rain Load, R (psf) 

• Using ASCE 7‐05, Chapter 8, the rain load was calculated using Eq. 8‐1 as shown below  

  

        Where:    Rain load, psf 

 Depth of water on undeflected roof up inlet of   secondary drainage system when primary drainage system is blocked = 2 in 

Page 44: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C15  

 Additional depth of water on undeflected roof above inlet of secondary drainage system at its design flow = 0 in 

  Wind Load, W (psf)  

• Using ASCE 7‐05, Chapter 6, the wind loads were found using Eq. 15 and Eq. 6‐17 for Main Wind‐Force Resisting Systems: Rigid Buildings of All Heights 

• Calculations were based on factors of region/area, elevation, and the structure’s surface on which the wind contacted 

• Only windward forces were taken into account  

 

      Where:   Velocity pressure, psf 

 Velocity pressure coefficient = 0.87, for height above the ground surface = 64 ft [from Table 6‐3, Case 2, Exposure Category B] 

 Topographic factor = 1.0 [from Section 6.5.7.2] 

 Wind directionality factor = 0.85 [from Table 6‐4, Buildings: Main Wind Force Resisting Systems] 

 Basic wind speed = 100 mph [from City of Fort Collins Building Codes and Standards] 

 Importance Factor = 1.15 [from Table 6‐1, Non‐Hurricane Prone Regions] 

 

 

 

Page 45: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C16  

• Using the velocity pressure, the windward load was determined using Eq. 6‐17 as shown below 

 

Where:   wind load, psf 

  Velocity pressure = 21.77 psf 

 Gust effect factor = 0.85 [from Section 6.5.8.1, Rigid Structures] 

 External pressure coefficient = ±0.2 [from Figure 6‐6 for a 34° slope] 

 Velocity pressure for internal pressure =   [from Section 6.5.12.2.1] 

 Internal pressure coefficient = 0.0 [from Figure 6‐5, open building] 

 

 

 

2. Load and Resistance Factor Design – Load Combinations  

• The controlling load combination was determined from ASCE 7‐05, Chapter 2, Section 2.3.2, Eq. 2 as shown below  

  

Where:   Required strength, psf 

 Dead load, psf 

 Live load, psf 

 Snow load, psf 

Page 46: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C17  

 Rain load, psf 

 

  

 

Column Design on Proposed Upper Bleacher Seating 

• A total of 18 columns will be used as support members for this section of the structure 

• All columns were designed as vertical, rectangular concrete supports 

• All columns were designed using 3 ksi reinforced concrete 

• A factor of safety of 3 was used for the determination of design strengths  

1. Area Determination (ft2)  

 

 

 

2. Required Strength  

 

 3. Design Strength 

 

 

Page 47: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C18  

4. Column Design 

 

Column Design on Proposed Club and Suite Level 

• A total of 36 columns will be used as support members for this section of the structure 

• All columns were designed as vertical, square concrete supports 

• All columns were designed using 3 ksi reinforced concrete 

• A factor of safety of 3 was used for the determination of design strengths  

5. Area Determination (ft2)  

 

 

 

6. Required Strength  

 

 7. Design Strength 

 

 

 

Page 48: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C19  

8. Column Design 

 

 

Column Design on Proposed Arched Columns 

• A total of 36 columns will be used as support members for this section of the structure 

• All columns were designed as vertical, rectangular concrete supports 

• All columns were designed using 3 ksi reinforced concrete 

• A factor of safety of 3 was used for the determination of design strengths  

9. Area Determination (ft2)  

 

 

 

10. Required Strength  

 

 11. Design Strength 

 

 

Page 49: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C20  

 

12. Column Design 

 

 

Column Design on Proposed T Columns 

• A total of 18 columns will be used as support members for this section of the structure 

• All columns were designed as vertical, rectangular concrete supports 

• All columns were designed using 3 ksi reinforced concrete 

• A factor of safety of 3 was used for the determination of design strengths  

13. Area Determination (ft2)  

 

 

 

14. Required Strength  

 

 15. Design Strength 

 

 

Page 50: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C21  

 

16. Column Design 

 

   

Page 51: HUGHES STADIUM SEATING EXPANSIONthornton/Spring_2013/Old Reports/MAKET_Report.pdfthe site for concerts by such well‐known artists as Bob Dylan, The Rolling Stones and Elton John

HUGHES STADIUM SEATING EXPANSION PRELIMINARY REPORT 

2011 

 

MAKET ENGINEERING | Fort Collins, Colorado      C2  

 

Appendix D. References 

ASCE 7‐05: Minimum Design Loads for Buildings and Other Structures. American Society of Civil Engineers, 2006. 

City of Fort Collins: Codes and Standards. Fort Collins, Colorado: City of Fort Collins, Nov 2005. Accessed Feb 2011. <http://www.fcgov.com/nbs/codes.php>. 

Code of Federal Regulations. 28 CFR Part 36. “ADA Standards for Accessible Design.” Department of Justice, 1994. 

IBC 2006: International Building Code. Country Club Hills, Illinois: International Code Council, Inc., 2006. 

ICC 300‐2002: International Code Council. “Bleachers, Folding and Telescopic Seating, and Grandstands.” Country Club Hills, Illinois: International Code Council, Inc., 2003. 

IPC 2006: International Plumbing Code. Country Club Hills, Illinois: International Code Council, Inc., 2006 

Sonny Lubick Field at Hughes Stadium Renovation Plans: Construction Documents Bid Package #1. Created by HOK, et al. 17 March 2004.