Upload
gerald-stafford
View
216
Download
0
Embed Size (px)
Citation preview
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
Installation, Commissioning and Schedule
Marco Oriunno
CERN, PH TOT
TOTEM Collaboration
http://totem.web.cern.ch/Totem/
ROMAN POT
Engineering Design Review, CERN 14 February 2006
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
TOTEM Geography @ LSS5
220 m, C6.L5145 m, C4.L5
220 m, C6.R5145 m, C4.R5
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
Integration of services•Trigger latency critical for the station at 220 m
•Optimized cable routing of the trigger cable to the CMS counting room
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
2 Racks in the USC55Tunnel
Motors and Controls cabling
Accessible area with circulating beam
Not Accessible area with circulating beam
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
The installation procedure
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
Deliverables from previous tasks : Roman pot stations installed and aligned, cooling plant installed, cables and patch panels electrically tested and connected
Infrastructures : In addition to the permanent specified services, Power supply 220V/50Hz for test equipments, Internet connection
Access requirements: Standard access mode to the tunnel, since no dangerous materials or tests are foreseen. Access granted to a team of ~4 people minimum plus tools per sub-system to be commissioned
1st assumption -> The Roman Pot are vacuum equipments of the LSSs. They must be included in the planning of the vacuum commissioning of the LSS, namely:Sectorization valves, bake out, NEGs activation, pure gas filling if required.
2nd assumption -> At the commissioning the pots are under secondary vacuum, but without the detectors.
1. Motors & controls commissioning2. Cooling System Commissioning3. Interlocks & Signals Commissioning 4. Detectors connectivity and cooling
Commissioning of the Roman Pot(Discussed at the LHC Hardware Commissioning Working Group, 3 march 2005)
https://edms.cern.ch/document/566502/1
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
Tasks: Movements sequence of each independent motor Garage position->Data taking position->Garage positionValidation of Encoders readingValidation of LVDTs readingBeam Position Monitor calibration
Crew : 1 Sub –system supervisor1 technicians in the tunnel1 technicians in the counting room1 operator in the control room
Timing: 24 pot & motors to be checked~ 8 hours for 1 crew FTE
Remarks: The primary vacuum is required
Motors & controls commissioning sequences
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
Tasks :Check the logic of the interlocks signals with the Control RoomTo be included in the interlock commissioning of the machine
Crew : 1 Sub –system supervisor1 technician in the tunnel1 operator in the Control room
Timing: ~ 4 hours for 1 crew FTE
Remarks : Non need of the machine vacuum
Interlocks & Signals Commissioning sequences
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
Tasks : Electrical connection of a test assembly detector (warm system)Checking of: readout system
low voltagebias voltagetemperatures
Crew : 1 Sub –system supervisor1 technicians in the tunnel1 technicians in the counting room
Timing: 24 detector assemblies to check~ 12 hours for 1 crew FTE
Remarks : Non need of the machine vacuum
Detectors connectivity
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
High population density in the region between the TAN and D2 (C4.R5 & C4.L5) : Roman Pot, BI, Collimators, Vacuum components -> conflicts during the commissioning of the different items
Possible interferences :
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
• Preparation on Surface January-October 2006
1. Roman Pot equipment assembled on surface without detector
2. UHV Test of the system
3. Commissioning of the full system on surface (detectors, cooling, vacuum)
4. Relative alignment by metrology of the moving components Calibration of motors and encoders
5. Test beam on a fixed target (only for one or two units)
• Underground access through the PM56 shaft October-February 2007
1. Installation of the cooling system
2. Installation at the defined locations along the tunnel
3. Check of the cabling (motors, controls interlocks)
4. Vacuum Chambers connection
5. Alignment on the beam
• Roman Pot Commissioning
• After the LHC commissioning and just before the pilot runs
1. Installation of the detectors assembly in the pots
2. Connection to the patch panels and to the cooling plant
Installation phases break down
http://totem.web.cern.ch/Totem/
Roman Pot Engineering Design Review CERN, 14 February 2006M.Oriunno, CERN PH-TOT
ID Task Name
48 Roman Pot Installation
49 LHC Vacuum Installation sector 4-5
50 Roman Pot Installation sector 4-5
51 Vacuum Commissioning Sector 4-5
52 LHC Vacuum installation Sector 5-6
53 Roman Pot Installation sector 5-6
54 Vacuum Commissioning Sector 5-6
55 LHC Cabling
LHC Vacuum Installation sector 4-5
Roman Pot Installation sector 4-5
Vacuum Commissioning Sector 4-58 weeks
LHC Vacuum installation Sector 5-6
Roman Pot Installation sector 5-6
Vacuum Commissioning Sector 5-68 weeks
LHC Cabling
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J2005 2006 2007 2008 2009
Installation vs. the LHC machine