HSBC Power Utilities

Embed Size (px)

Citation preview

  • 8/1/2019 HSBC Power Utilities

    1/37

    abcGlobal Research

    Equipment ordering for the 11th Plan

    completed; focus turns to executionWe examine the status of current

    projects; firms with operating experience

    and financial stability emerge as winnersReiterate OW(V) on CESC and Tata

    Power, N(V) on Lanco; downgrade NTPC

    to UW(V) from N(V)Focus to shift on execution. Equipment ordering is now

    complete for the 11th Plan, achieving a critical milestone in

    project execution. Now, the focus will shift towards project

    developers in terms of project completion. We have looked at

    the status of projects under construction for stocks we cover.

    We prefer developers with operating experience, financial

    stability and projects that have achieved financial closure.

    CESC: OW(V), TP = INR345. We like CESC primarily

    because of its gradual capacity addition plan, which prevents

    it from spreading itself too thin. We ascribe no value to the

    real estate and retail businesses and retain our estimates,target price, and rating.

    Tata Power: OW(V), TP = INR1,000. Its 5.6GW of capacity

    addition is supported by fuel sourcing and funding strategy. We

    reduce our FY10e profit estimates by 21% to incorporate lower

    coal realisation; we lower our target price to INR1,000.

    Lanco Infratech: N(V), TP = INR132. 3.9GW of power

    projects are in advanced stages of execution, with 600MW to be

    operational by FY10e. However, real estate and infrastructure

    development continue to drag. We reduce our FY10e estimates

    by 18% and lower the target price to INR132.

    NTPC: UW(V), TP = INR142. NTPC enjoys the best

    positioning in terms of access to funds and fuels, but the market

    is ignoring delays in project execution (HSBC estimates

    11.9GW vs companys guidance of 22GW). Maintain our

    estimates and target, but downgade to UW(V).

    Natural Resources & Energy

    Indian Utilities

    Indian UtilitiesFocus on project execution

    14 January 2009

    Sumeet Agrawal*

    Analyst

    HSBC Securities and Capital Markets (India) Private Limited

    +91 22 2268 1243 [email protected]

    Sumit Agarwal*

    Associate

    Bangalore

    View HSBC Global Research at: http://www.research.hsbc.com*Employed by a non-US affiliate of HSBC Securities (USA) Inc,and is not registered/qualified pursuant to NYSE and/or NASDregulations

    Issuer of report: HSBC Securities and Capital Markets (India)Private Limited

    Disclaimer & DisclosuresThis report must be read with thedisclosures and the analyst certificationsin the Disclosure appendix, and with theDisclaimer, which forms part of it

    Valuation summary (INR)

    Name Curr.

    price

    Ticker New

    rating

    Sales

    (bn)

    EBITDA

    (bn)

    PAT

    (bn)

    New

    TP

    Old

    TP

    Potl

    Return

    CESC 242 CESC OW(V) 30.50 7.03 3.53 345 345 45%Lanco 111 LANCI N(V) 34.01 7.54 4.09 132 335 19%NTPC 171 NATP UW(V) 418.19 131.41 82.10 142 142 -15%Tata Power 727 TPWR OW(V) 146.19 38.52 20.97 1,000 1,244 41%

    Source: HSBC estimates

    http://www.research.hsbc.com/http://www.research.hsbc.com/http://www.research.hsbc.com/http://www.research.hsbc.com/
  • 8/1/2019 HSBC Power Utilities

    2/37

    2

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Focus turns to execution 3From orders to execution 3

    Potential winners 3

    BHEL to benefit from capacity addition 5

    NTPC capacity addition plan 5

    We prefer Tata Power among private-sector utilities 7

    CESC Ltd (CESC) 12Key triggers 13

    Valuation 14

    Risks 14

    Financials & valuation 15

    Lanco Infratech (LANCI) 16De-risking the power portfolio 16

    Valuation 18

    Risks 19

    Financials & valuation 20

    NTPC Ltd (NATP) 21Strong project pipeline, but poor execution 21

    Should continue to trade at a premium 22

    Valuation 22

    Risks 23

    Financials & valuation 24

    Tata Power (TPWR) 25Best-placed Indian utility 25

    Fuel and funds well tied up 26

    Valuation 27

    Risks 28

    Financials & valuation 29

    Annexure 30Hectic equipment ordering in 2008 30

    Why were targets not met? 30

    Disclosure appendix 32

    Disclaimer 36

    Contents

  • 8/1/2019 HSBC Power Utilities

    3/37

    3

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    From orders to execution

    The size of power equipment orders formed a

    large part of news flow in 2008 for Indian utilities

    equipment for power projects worth 15GW wasordered during the year. The Ministry of Power

    pushed for power projects financial closure to

    achieve the 11th Five-Year Plan (2007-2012)

    target (c79GW power projects).

    The order flow is over; it is now time to get down to

    brass tacks and focus on execution. We contend that

    this will be the big driver over the next three years.

    We examine the order flows of utilities companies

    under our coverage and maintain that the winners

    will be those with operating experience, financial

    stability, and projects that have achieved

    financial closure.

    Potential winners

    Central utilities to dominate capacity

    addition

    We remain positive in terms of capacity addition

    by central utilities. We expect central utilities to

    dominate capacity addition with c21.7GW (45%

    of total capacity). Central utilities like NTPC and

    Damodar Valley Corporation should be front-

    runners in terms of this capacity addition.

    Private sector: who will win?

    The exuberance in the power sector resulted in a

    host of announcements by private players in terms

    of capacity addition plan. c150GW of new

    capacity addition, almost equivalent to Indias

    current installed base, was announced by different

    private-sector entities.

    We remain cautious in terms of these capacities

    finally coming on stream over the next decade.

    We maintain that it is difficult for the entire

    c150GW to be operational, given the funding

    requirement as well as execution risk. After our

    ground reality check, we believe only 17GW of

    the expected 20GW of the 11th Plan private-

    sector capacity addition has achieved financial

    closure.

    Key projects awaiting financial closure

    600MW Reliance Power Rosa II

    3960MW Reliance Power Sasan UMPP (2

    units of 660MW each, expected for

    commissioning in the 11th Plan)

    540MW Goindwal Sahib by GVK Power(equipment order placed)

    2400MW Sterlite Energy power project

    Focus turns to execution

    With the crucial milestone of equipment ordering for the 11th Plan

    complete, the focus will now shift of project execution

    Delays likely unavoidable due to on-the-ground issues, which will

    result in demand outstripping supply

    We expect central and state utilities to dominate capacity addition

    as the private sector scales back its capacity addition

  • 8/1/2019 HSBC Power Utilities

    4/37

    4

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Private power projects in the 11th Plan (MW)

    Plant name State Agency Ultimatecapacity

    Capacity in11th Plan

    Coal linkagestatus

    Equipment vendor Financialclosure

    Expected dateof commission

    Thermal coalAmarkantak Pathadi (Lanco) U2 Chattisgarh Lanco 300 300 Linkage Zelan, Malaysia Achieved 2009-10Amarkantak Pathadi (Lanco) U1 Chattisgarh Lanco 300 300 Linkage Zelan, Malaysia Achieved 2008-09Anpara C Uttar Pr Lanco 1,000 1,000 Linkage Dong Fang, China Achieved 2011-12Budge Budge Ext. West Bengal CESC 250 250 Block BHEL Achieved 2009-10Goindwal Sahib Punjab GVK 540 540 Block BHEL Not achieved 2011-12Jalipa/ Kapurdi-Lignite Rajasthan IPP 1,080 1,080 Shanghai Electric, China Achieved 2009-11JSW Ratnagiri Maharashtra JSW 1,200 1,200 Imported coal Shanghai Electric, China Achieved 2010-12Trombay TPS Maharashtra Tata Power 250 250 Imported coal BHEL Achieved 2008-09Sasan UMPP U1,2 Madhya Pr Reliance Energy 3,960 1,320 Block REL (main equipment by

    Shanghai Electric, China)Not achieved 2011-12

    Lanco-Nagarjuna Karnataka Lanco 1,015 1,015 Imported coal Dongfang, China Achieved 2010-11Maithan Jharkhand Tata Power 1,050 1,050 Linkage BHEL Achieved 2010-12Mundra TPP Adani Gujarat Adani 1,320 1,320 Imported coal Sepco III, China Achieved 2011-12Mundra TPP Adani Gujarat Adani 1,320 1,320 Imported coal SCMEC, China Achieved 2009-11Raigarh Chatt isgarh Jin. Power 750 750 Block BHEL Achieved 2007-08Raigarh Chatt isgarh Jin. Power 250 250 Block BHEL Achieved 2008-09Rosa St I Uttar Pr Reliance Power 600 600 Linkage Shanghai Electric, China Achieved 2010-11Rosa ST II Uttar Pradesh Reliance Power 600 600 Linkage Shanghai Electric, China Not achieved 2011-12Sterlite Energy Orissa Sterlite 2,400 600 SEPCO, China Not achieved 2009-10Mundra UMPP Gujarat IPP 4,000 1,600 Imported coal Doosan, Korea + Toshiba Achieved 2011-12Torangallu Karnataka JSW 600 600 Imported coal China Achieved 2008-10

    Thermal Gas/LNGGautami Andhra Pr Gautami Power 464 464 Alstom Achieved 2008-09Konaseema Andhra Pr Oakwell 445 445 Larsen & Toubro Achieved 2008-09Kondapall i CCPP II Andhra Pr Lanco 366 366 Gas/LNG GE Achieved 2009-10Rithala CCPP Delhi NDPL 108 108 Gas/LNG China Not achieved 2009-10

    Sugen Torrent Gujarat Torrent 1,128 1,128 Siemens Achieved 2008-10HydroAllain Duhangan Himachal Pr RSWML 192 192 BHEL Achieved 2009-10Budhi l Himachal Pr Lanco 70 70 Dongfang, China Achieved 2009-10Chujachen Sikkim Gati 99 99 Alstom Achieved 2009-10Karcham Wangtoo Himachal Pr JPKHCL 1,000 1,000 Voith Siemens Achieved 2011-12Maheshwar Madhya Pr IPP 400 400 BHEL Achieved 2011-12Malana II Himachal Pr Everest Power Co 100 100 Dongfang, Hong

    Kong+Aviera IndiaAchieved 2009-10

    Sorang Himachal Pr Sorand PowerCo

    100 100 Voith Siemens Not achieved 2011-12

    Srinagar Uttarakhand GVK 330 330 BHEL Achieved 2011-12Teesta III Sikkim Teesta Urja 1,200 1,200 Consortium including SEW

    & ABIRAchieved 2011-12

    Notes: SEW=SEW Infrastructure Limited; ABIR: ABIR I nfrastructure Private Limited; SEPCO=Shandong Electric Power Construction Corp.; RSWML=Rajasthan Spinning and Weaving Mills Limited; JPKHCL=Jaiprakash KarchamWangtoo Hydroelectric Project; NDPL=North Delhi Power Project Limited

    TPP=thermal power projects; CCPP=combined cycle power projects; IPP=independent power producerSource: CEA, HSBC

  • 8/1/2019 HSBC Power Utilities

    5/37

    5

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Impact of credit crisisGiven the current credit crisis, we expect debt

    financing to private-sector projects based on

    merchant or aggressive competitive tariff will be

    difficult. Lending institutions have also been

    reluctant to lend at 80:20 debt to equity. We

    expect debt to equity to be 70:30.

    We believe the recent credit crisis will be

    beneficial to the private sector in long term. Non-

    availability of funds has forced the private sectorto bid for projects at a more reasonable tariff. In

    recent bidding invited by the Punjab State

    Electricity Board, a sole private developer quoted

    a levelised tariff of cINR3.38 per unit. This is

    somewhat higher than bids of less than cINR2.0

    per unit for earlier thermal power projects. Thus,

    aggressive bidding by the private sector has taken

    a back seat, and projects are bid for at prices that

    make economic sense.

    We believe this financial crunch will help

    companies with strong balance sheets and the

    ability to raise funds emerge as the clear winners.

    We prefer such companies.

    Developers with projects in advanced

    stages of development

    We maintain a positive view on projects that have

    achieved financial closure and significant progress

    in terms of execution.

    In this scenario, private utilities will be a mixed

    bag; developers like Tata Power and CESC should

    be better placed in term of achieving their

    capacity addition target.

    BHEL to benefit from capacityaddition

    BHEL was a major beneficiary of this rush toward

    equipment order placement. Quality concerns of

    imported equipment as well as currencymovement helped BHEL to secure c60% market

    share for projects awarded for 11th Plan.

    BHELs success in term of maintaining its

    leadership position has put to rest concerns of

    global competition. In the recent past, BHEL has

    been able to gain some of its lost ground in

    private-sector utilities. It has been able to secure

    equipment orders from developers like Jindal

    Power (2,400MW, INR50bn) and Jaiprakash

    Power (500MW, INR11.75bn).

    Equipment vendors for thermal based power projects (MW)

    FY08a FY09e FY10e FY11e FY12e TotalCentral BHEL 1,250 1,750 1,990 5,765 5,501 16,256Central Others 740 0 1,320 1,260 1,920 5,240State BHEL 2,680 870 4,192 5,202 5,291 18,235State Others 1,200 392 374 1,200 600 3,766Private BHEL 750 500 250 0 540 2,040Private Others 0 2,261 3,520 3,145 6,440 15,366Total BHEL 4,680 3,120 6,432 10,967 11,332 36,531

    Others 1,940 2,653 5,214 5,605 8,960 24,372Total Overall 6,620 5,773 11,646 16,572 20,292 60,903

    Source: CEA, HSBC estimates

    NTPC capacity addition plan

    NTPC has targeted for 22GW of capacity additionplan. However, some projects are facing

    significant delays. Central Electricity Authority

    (CEA), in its recent report, has indicated

    c15.4GW of capacity addition by NTPC in the

    11th Plan.

    NTPCs capacity addition status

    Status MW

    Capacity commissioned 2,740Under implementation 15,930

    Yet to be awarded 3,760Source: Company, HSBC estimates

    We do not think there is concern regarding

    funding at NTPC, which has cINR170bn in cash

    on its balance sheet and a cINR150bn line of

    credit. Its debt-to-equity ratio of c0.5:1 provides

    scope for future domestic bond issuances, or even

    raising ECBs after a few months, once the global

    credit scenario improves.

  • 8/1/2019 HSBC Power Utilities

    6/37

    6

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Key reason for delays

    c3.76 GW of capacity from 11th Plan projects

    yet to be awarded to equipment vendors

    Ongoing negotiation between its international

    vendor, Technoprom Exports (TPE) and

    Power Machines of Russia for increase in

    project cost for 1320MW Bahr project

    Delay in deployment of EPC contractors by

    BHEL and other equipment manufacturers

    Hydro power project affected due to non-

    availability of regulatory clearance

    To mitigate any delays/lapses in capacity addition,

    NTPC has identified c3GW of brown field

    capacity addition and is looking at awarding these

    projects by FY09-10e.

    NTPC additional capacity addition plan

    Project/Location Capacity

    Vindhyachal 1,000Rihand 1,000Vallur 500Muzaffarpur 500

    Source: Company, HSBC

    Despite all these efforts, we expect NTPCscapacity addition to fall short of the plan. We

    expect NTPCs capacity addition to lag behind its

    NTPCs generation capacity addition plans

    Plant Name Ultimatecapacity

    Capacity to beoperational in 11thPlan

    Ordered to Expected date ofcommissioning

    Status

    Thermal ProjectsBarh-I 1,980 1,320 Technoprom,

    Russia2011-12 Various units likely to be commissioned by June 11, Dec 11 and March

    12. Civil and structural work for main plant in progressVallur Ennore JV 1,000 1,000 BHEL 2011-12 Scheduled for commissioning in November 2010Bhilai JV 500 BHEL 2008-09 U 1 commissioned. U 2 synchronisation of turbine expected,

    synchronisation on designated fuel due in Jan 09. Coal handling plantcompleted & ash handling plant to be ready by Jan 09

    Bongaigaon 750 750 BHEL 2010-12 Units expected to go on steam in October 2010 and November 2010.Boiler piling is in progress

    Dadri Ext. 980 980 BHEL 2009-11 U 5 scheduled for commissioning in Sep 09. Turbine generator (TG)erection under way. TG deck testing for U 6 also done. Hydro testcompleted in Nov 08. Unit 6 boiler erection in progress

    Farakka Stage-III 500 500 BHEL 2010-11 Commissioning likely August 2010. Work on the steam generator (SG) inprogress; Boiler erection in progress

    Kahalgaon II Units (U) 6 & 7 1,000 1,000 BHEL 2007-09 Expected to slip to the 4Q09 vs 3Q09 earlier. Coal firing already complete;delay as coal bunker to be ready only by Jan 09

    Indira Gandhi TPP (Jhajjar)JV

    1,500 1,500 BHEL 2010-11

    Korba III 500 500 BHEL 2010-11 Anticipated date of commissioning Feb 10. Unit hydro test likely in Feb09; TG deck casting complete

    Nabinagar 1,000 750 BHEL 2011-12Ratnagiri (Dhobol) JV 740 740 GE 2007-08Simhadri-Ext. U 3 & 4 1,000 1,000 BHEL 2011-12 U 3 scheduled for commissioning in Nov 10. SG work in progressSipat I 1,980 1,980 Doosan,

    Korea+PowerMachines,

    Russia

    2009-11 Under implementation. Anticipated dates of commissioning the two units:Sep 09 and Mar 10 slipped to FY10, against its original target of 3Q09

    Sipat II U 4 & 5 1,000 1,000 BHEL 2007-09 Original target 1Q09; now scheduled for 3Q09Hydro ProjectsKol Dam 800 800 BHEL 2009-10 Various units anticipated to be commissioned in Dec 10, Jan 11, Feb 11

    and Mar 11. Dam filling work in progressLohari Nagpala 600 600 2011-12 3x150MW units targeted for commissioning in 2012-13. Work on head

    race tunnel (HRT), barrage, desilting chambers and power house underway

    Tapovan Vishnugarh 520 520 2011-12 All 4 units targeted for commissioning during 2011-12. Work related toHRT, barrage, desilting chambers and power house in progress

    Source: Industry, HSBC

  • 8/1/2019 HSBC Power Utilities

    7/37

    7

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    plan and expect it to add c11.9GW of new

    capacity between FY08 and FY13e. We have

    extended the project execution timeline for c10

    GW projects and expect these to be operational

    during the 12th Plan.

    We believe there is a significant risk in terms of

    NTPC achieving its capacity target, given the fact

    that 63% of expected capacity is scheduled for

    commissioning in FY11-12.

    We prefer Tata Power amongprivate-sector utilities

    We expect Tata Power to be well placed with its

    5.6GW capacity under construction on track.

    Funding tie-up

    Tata Power has completed financing for two of its

    largest power plants under construction i.e., the

    1050MW Maithon project, for which the debt

    component of cINR30bn is being funded by a

    consortium led by the State Bank of India. For its

    Mundra project, the company has tied up to raise

    USD1.8bn in foreign exchange loans and

    USD1.4bn in INR loans with several multilateral

    and domestic financial institutions. With these

    two big projects, most of the groups funding for

    plants under construction has been tied up.

    Funding for remaining smaller projects, such as

    captive projects at Jojbera and Jamshedpur, is at

    advanced stages of reaching financial closure. Of

    the total funding requirement of INR240bn during

    the next four years, Tata Power proposes to raise

    the amount through its own contribution and debt

    (INR180bn), a large portion of which is already

    tied up (INR60bn).

    Equity funding of INR66bnTata Power requires INR60bn of equity funds for

    its projects under construction. Sources to meet its

    own funding requirement have been identified as

    INR29bn from internal accruals, with INR12bn to

    be obtained through sales of investments in

    various group companies. Any shortfall should be

    met through short-term borrowing in the interim.

    We expect that given the weak equity market

    scenario, fund raising through sales ofinvestments and warrants will be a challenge. The

    warrant conversion price was cINR1,357 per

    share, which was above the prevailing market

    price. Hence, Tata Powers management had not

    subscribed to the warrant.

    We expect Tata Power to raise short-term debt to

    fund balance equity. However, we do not expect

    this to affect its capacity addition. It has already

    invested cINR20bn of its equity contribution in

    projects. We expect that, given the credit rating

    and developer support, raising short-term debt

    will not be an issue, and that Tata Power can raise

    sufficient funds for its expansion plan. Hence, we

    maintain that there is no significant risk to its

    5.6GW of projects under construction.

  • 8/1/2019 HSBC Power Utilities

    8/37

    8

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    However, we expect the projects in the pipeline to

    be delayed, given the equity fund constraints.

    Hence, we believe this will put projects under

    pipeline at risk. Hence, there can be uncertainty

    around 5.7GW of power capacity addition plan.

    The NPV of these five projects (Dehrand, Naraj

    IPP, Naraj CPP, Tubed IPP, Jharkhand CPP)

    based on Tata Powers ownership is cINR15.6bn,translating into INR71 per share. We assign no

    value to these projects, as against 50% earlier.

    CESC: Gradual capacity addition a

    positive

    What we like about CESC is its gradual

    generation capacity addition plan, which prevents

    it from spreading itself too thin.

    It has an installed capacity base of 975MW,

    including the 100MW New Cossipore Generating

    Station, which is to be decommissioned in the

    next two years. The company expects to add

    Tata Powers generation capacity addition plans

    Project Capacity(MW)

    Projectcost(INRbn)

    Debttoequity

    Debt(INRbn)

    Equity(INRbn)

    Developerstake (%)

    Developerequity (INRbn)

    Status of fundingclosure

    Fuel type Fuel source

    UnderconstructionMundra 4,000 170.00 75:25 127.5 42.5 100% 42.5 Done, with USD1.8bn

    forex loan andUSD1.4bn rupee loan

    Imported coal 10mtpa offtake agreement withKPC*/Arutmin, pricing part fixedand part linked to CERC Index

    Maithon (74%stake)

    1,050 44.50 70:30 31.2 13.4 74% 9.9 Done; funded byState Bank of India

    Domestic coal Fuel linkage from Bharat CokingCoal mines

    Jamshedpur andJojobera

    240 11.10 70:30 7.8 3.3 74% 2.5 In advanced stage ofcompletion

    Tollingarrangement

    Coke oven gases of Tata Steel,and linkage from West Bokaroand Mahanadi coal fields

    Trombay Expansion 250 10.66 70:30 7.5 3.2 100% 3.2 In advanced stage ofcompletion

    Imported coal Imported coal, cost pass-through

    Haldia 120 6.05 70:30 4.2 1.8 100% 1.8 In advanced stage ofcompletion

    Tollingarrangement

    Hot flue gases from HooglyMetcoke

    Sub-total 5,660 242 178 64 60In the pipelineCoastalMaharashtra

    2,400 101 70:30 75.6 25.2 100% 25.2 Imported Coal Coal from Bumi Resourcesofftake

    Naraj MarthapurIPP

    1,000 42.0 70:30 29.4 12.6 100% 12.6 Domestic coal Mandakini Coal Block

    Naraj MarthapurCPP

    1,270 53.3 70:30 37.3 16.0 74% 11.8 Tollingarrangement

    Supply by procurers

    Tubed IPP 500 21.0 70:30 14.7 6.3 100% 6.3 Domestic coal Captive coal blockJharkhand CPP 500 21.0 70:30 14.7 6.3 74% 4.7 Tolling

    arrangementSupply by Tata Steel

    Sub-total 5,670 238 172 66.4 60.6Total 11,330 480 350 131 120

    * KPC= Kaltim Prima CoalSource: Company, HSBC estimates

    CESCs generation capacity addition plans

    Location Businessmodel

    Size Cost (INRbn) COD Remarks

    Budge Budge Regulated 250 12 2009-10 Under implementation, commissioning in September 2009Haldia I Regulated 600 26 2010-11 70% land acquired, long-term coal linkage obtained, evacuation and railways

    feasibility study completed, no-objection certificate obtained for water drawalDhumka, Jharkhand Merchant 1,000 40 2012-13 110m tonnes coal block allocated, memorandum of understanding (MoU) signed

    with Jharkhand Govt., land acquisition process initiated

    Dhenkanal, Orissa Merchant 1,000 40 2013-14 MoU signed, land acquisition process initiated, coal allocation being pursued

    Thermal/hydel power plantsin West Bengal/other states

    Merchant 1,300-1,500MW 60 2013-14 Cabinet approval received for 1800 MW power plant at Pirpainti, Bihar

    Source: Company, HSBC estimates

  • 8/1/2019 HSBC Power Utilities

    9/37

    9

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    c1.85GW capacity by FY12-13e and an additional

    2.3GW by FY14-15e, thus increasing its existing

    capacity by 5x. It has already secured fuel for the

    new 1.8GW power generation capacity and has

    achieved financial closure for 50% of the new

    projects, thus providing good visibility and

    reducing execution risk. However, we have not

    factored into our valuation the 2.3GW of capacity

    to come by FY14-15e, as not much action has

    been taken yet.

    The status of the 1.85GW capacity under

    development is as follows:

    250MW Budge Budge expansion under

    construction; to be operational by FY10

    600MW Haldia phase I: Land acquisition in

    progress. Received coal linkage from

    Mahanadi coal mine, looking at awarding the

    equipment contract; project cost cINR26bn

    1000MW Dumka, Jharkhand to be a merchant

    power plant. Received coal linkage from

    Mahugadi coal block; land acquisition in

    progress

    We have extended project execution timelines for

    CESCs Haldia and Dumka projects. We expect

    Haldia to be commissioned in FY13. We have not

    considered Dumka for valuation purposes.

    Lanco InfratechLanco has undertaken an aggressive capacity

    addition plan. It has a pipeline of c4GW of

    capacity under construction and another c4GW in

    the pipeline.

    Financial closure has been achieved for projects

    under construction, and execution activity started.

    It has incurred INR50bn capex on these projects

    so far, including INR22bn equity contribution.

    We expect 600MW of Amarkantak I and II

    thermal power plants to be operational by

    1HFY10. In terms of other capacity, 1015MW

    Nagarjuna Power project and Anpara C are major

    contributors and we expect them to be operational

    by April 2012 and January 2012 respectively.

    Hence, we believe the risk to these capacity

    additions is not significant.

    However, we expect delay in capacity addition of

    3.9GW projects in the pipeline (2.64GW Babandhand 1.3GW Amarkantak). We expect them to be

    extended beyond FY12e and hence have not

    factored in these in our estimates.

  • 8/1/2019 HSBC Power Utilities

    10/37

    10

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Lancos generation capacity addition plans

    Projects Location Fuel Capacity(MW)

    Est. projectcost (USDm)

    Holding(%)

    PPA(years)

    Powerofftaker

    Capexspent so

    far (INRm)

    Est.COD

    Status

    Projects under executionAmarkantak I Chhattisgarh Coal 300 284 76% 25 PTC India 20,118 Feb-09 Boiler hydro test completed Dec 07, switchyard

    charged, switchyard connected to gridAmarkantak I I Chhat tisgarh Coal 300 296 76% 25 PTC India Sep-09 Boi ler drum l if ting completed Dec07, hydro testing

    completed, turbine generator (TG) erectedVamshiHydro

    HimachalPradesh

    Hydro 10 12 91% 35 PunjabSEB

    1,234 Dec-09 Under commissioning

    VamshiIndustrial

    HimachalPradesh

    Hydro 10 12 91% 35 PunjabSEB

    Dec-09

    Lanco Green HimachalPradesh

    Hydro 70 92 90% 35 PTC India 1,992 Apr-11 River divers ion completed in Oct 07, river bedexcavation of dam completed. Commissioningexpected in Dec 09 by company

    Kondpalli-II AndhraPradesh

    Gas 400 300 59% Merchant NA 904 Apr-10 Piling completed, erection of columns in ECB started

    Udupi(Nagarjuna)

    Karnataka Imported Coal

    1,015 955 74% 25 KarnatakaSEB

    14,534 Apr-12 Boiler drum lifting, TG casting done. TG erection tostart soon. For U 2, boiler erection completed

    Lanco Energy Sikkim Hydro 500 660 74% 35 PTC Ind ia 5,704 Jul-12 Civ il work for tunnel in progressLancoUttaranchal

    Uttarakhand Hydro 152 220 90% Merchant NA 577 Apr-12 Techno-economic clearance received, infrastructuredevelopment under way

    Anpara C U ttar Pradesh Coal 1,200 1,100 100% 29 UttarPradesh

    SEB

    5,411 Jan-12 U 1: Boiler foundation done, boiler erection to begin.U 2: construction of boiler foundation in progress

    Total 3,957 3,931 50,474

    Power projects under developmentBabandh Orissa Coal

    (partly

    owned)

    2,640 2,970 100% 25 yearsand

    Merchant

    MP, Orissaand

    HaryanaSEBs

    Apr-14 Captive mine allocated, land acquisition initiated,PPAs secured. Financial closure in process

    AmarkantakIII & IV

    Chatt isgarh Coal 1,320 1,300 76% Merchant NA Apr-13 Financial c losure process under way

    Total 3,960 4,270

    Source: Company, HSBC

  • 8/1/2019 HSBC Power Utilities

    11/37

    11

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Company profiles CESC Lanco Infratech

    NTPC

    Tata Power

  • 8/1/2019 HSBC Power Utilities

    12/37

    12

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    CESC is an integrated utility player under the

    flagship of RPG Enterprises. With installed

    capacity of 975MW and a customer base of 2m, the

    company accounts for c13% of installed generation

    in the state of West Bengal and c90% share of

    installed capacity by the private sector in the state.

    Gradual capacity addition plans

    What we like about CESC is its gradual generation

    capacity addition plan, which prevents it from

    spreading itself too thin. It has an installed capacity

    base of 975MW, including the 100MW New

    Cossipore Generating Station, which is to be

    decommissioned in the next two years. The

    company expects to add c1.85GW capacity by

    FY12-13e and an additional 2.3GW plant by FY14-

    15e, thus increasing its existing capacity by 5x. It

    has already secured fuel for the new 1.8GW and has

    achieved financial closure for 50% of the new

    projects, thus providing good visibility and reducing

    execution risk. However, we have not factored into

    our valuation the 2.3GW of capacity to come by

    FY14-15e, as not much action has been taken yet.

    Excellent operating performance at

    existing generation plants

    During the year ended March 2008 (FY08), all

    three power plant stations achieved a combined

    PLF of c97%, the highest levels ever recorded by

    those stations. These projects also featured in the

    list of top generating stations with highest

    capacity utilisation factors in the country.

    CESC Ltd (CESC)

    Integrated utilities player with gradual capacity addition plans

    Current market cap 1.36x of regulated equity base, indicating little

    value ascribed by the market for upcoming projects, retail and real

    estate businesses

    Reiterate Overweight (V) and INR345 target. Catalysts include

    turnaround of retail business and financial closure on some projects

    CESCs generation capacity addition plans

    Location Purpose Size Cost(INRbn)

    COD Remark

    Budge Budge Regulated 250 12 2009-10 Under implementation, commissioning in September 2009

    Haldia I Regulated 600 26 2010-11 70% land acquired, long-term coal linkage obtained, evacuation & railways feasibility studycompleted, no-objection certificate obtained for water drawal

    Dhumka, Jharkhand Merchant 1000 40 2012-13 110m tonnes coal block allocated, memorandum of understanding (MoU) signed withJharkhand Govt., land acquisition process initiated

    Dhenkanal, Orissa Merchant 1000 40 2013-14 MoU signed, land acquisition process initiated, coal allocation being pursued

    Thermal/hydel power plantin West Bengal/other states

    Merchant 1300-1500MW 60 2013-14 Cabinet approval received for 1800 MW power plant at Pirpainti, Bihar

    Source: Company, HSBC estimates

  • 8/1/2019 HSBC Power Utilities

    13/37

    13

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    The Budge Budge plant, with a PLF of 100.4%, had

    the second highest thermal power plant PLF in India

    during FY08. It has also received INR115m of

    carbon credit this year, for the last four years

    performance. The steady performance of all the

    generation units helped the company achieve a

    combined PLF of 93.4% for FY08, which was

    better than the national average of 78.6% and the

    private-sector average of 90.8%.

    In the T&D division, it has considerably reducedlosses through reduction of pilferage and better

    collection efficiency.

    Fuel tied up, financial closures

    awaited

    Capex plan for future projects

    Project Capacity(MW)

    Projectcost

    (INRbn)

    Debt/equity

    Debt(INRbn)

    Equity(INRbn)

    Haldia I 600 26 70:30 18.2 7.8Dumka Jharkhand 1,000 40 70:30 32 12

    Sub-total 1,600 66 46.2 19.8

    Capex in T&D (fornext three years)

    13.5 70:30 9.45 4.05

    Fund for SpencersRetail (till FY10e)

    4.5 70:30 3.15 1.35

    Sub-total 84 58.8 25.2

    Dhenkanal Orissa 1,000 40 70:30 28 12Haldia II 1,800 60 70:30 42 18Total 184 129 55.2

    Source: Company, HSBC estimates

    CESC has already tied up the fuel requirement for

    these projects. It has achieved financial closure for

    the 250MW Budge Budge expansion and is

    looking at financial closure for its projects at

    Haldia (West Bengal) and Dumka (Jharkhand). We

    expect financial closure for Haldia soon because (a)

    land acquisition is at an advanced stage, (b) fuel

    supply has been assured, and (c) Haldia is based on

    a regulated model, thus ensuring its ROE.

    We expect CESC to fund the equity contribution

    (cINR21.2bn) through (a) INR10bn cash and cash

    equivalents, including INR5.8bn in qualifiedinstitutional placement (QIP) money, and (b)

    internal accrual of INR10bn. We expect CESC to

    be able to fund its Haldia project once required

    land acquisition and approval is received.

    However, it will require an additional INR30bn

    for projects in the pipeline. Funding will be an

    issue for these projects (2.8GW) which are at an

    initial stage of development e.g., Dhenkanal and

    others. We havent considered any of these

    projects into our valuation, given uncertainty

    attached to these projects.

    Current market cap vs regulatedequity base attractive valuation

    The current market cap of INR29.3bn is at only

    36% premium to the approved regulated equity

    base of INR21.5bn for FY10e after incorporating

    the Budge Budge capacity expansion, of 250 MW.

    Based on regulated return of 14% RoE, and an

    allowed depreciation charge of INR1.68bn and

    INR2.04bn for FY09 and FY10 respectively, we

    expect that the company generates minimum cashprofits of INR4bn and INR4.8bn in the next two

    years. This profit does not assume any incentives

    and rental income that CESC has been historically

    receiving due to its efficient operation. Hence,

    even considering minimum cash profit level, it is

    trading at only 6x FY10e cash profit.

    Efficient operations achieved by its operating

    plants help CESC generate higher RoE over the

    assured 14%. As CESC exports power at a higher

    rate and is allowed to keep 40% of profit from

    export sales, it adds to the profitability over and

    above the prescribed return.

    All of the above indicates that the market is ascribing

    little value to the companys capacities under

    construction, and its retail and real estate businesses.

    Key triggers

    Financial closure of power projects

    600MW Haldia power project. This is at an

    advanced stage; CESC expects it to be completed

    soon, and has acquired c75% of the land and

  • 8/1/2019 HSBC Power Utilities

    14/37

    14

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    obtained coal linkage. It has received

    environmental and water consumption clearance.

    1000 MW Dhenkanal Power Project. CESC

    expects to achieve financial closure for this

    project by the end of this year. However, we have

    not considered this in our projection.

    Turnaround of the retail business

    CESC has moderated its retail business rollout plan

    with 1.7msq ft of retail space by FY09e. This

    amounts to only a 0.55m sq ft addition, down from

    1m sq ft planned previously. It is focusing on large

    formats for growth, as well as closing unviable and

    unprofitable outlets. Management expects the

    business to see turnaround by FY10-11.

    Value unlocking in the Spencers

    Retail business

    Spencers Retail, 95% owned by CESC, is using

    cash generated from the CESC power business.

    However, if CESC is able to unlock value from

    Spencers by getting a strategic investor, this

    would add a valuation benchmark. We assign no

    value to Spencers Retail.

    HSBC vs consensus

    HSBC vs consensus (INRbn)

    ____Sales___ ____ PAT ___ EPS ( INR/share) _INRbn FY09e FY10e FY09e FY10e FY09e FY10e

    HSBCestimates

    30.50 32.39 3.53 3.77 28.1 30.0

    Consensusestimates

    30.46 33.43 3.63 4.08 29.0 32.5

    % difference 0% -3% -3% -7% -3% -8%

    Source: HSBC, Reuters

    Valuation

    We maintain our CESC estimates and our 12-

    month target price to INR345, an average of the

    following three methods.

    Discounted cash flow

    Discounting the future cash flows of the company

    assuming WACC at 12.8% and a terminal growth

    of 3%, we value the company at INR234 per

    share.

    Sum of the parts

    We value the present capacity installed at the

    replacement cost multiple of 46.5x and value the

    investments of the company to its book value. We

    assign no value to the retail business because it is

    unprofitable, and there has been significant

    correction in the retail peer valuation. We value it

    at INR375 per share on SOTP basis.

    Price to book

    We have valued CESC at INR426.5, using a

    multiple of 0.97x book value for FY10e.

    Based on the average of all the three methods, we

    derive a target price of INR345, and retain our

    estimates.

    Target price derivation

    INR per shareSOTP 375DCF 234PB 426.5Target price 345

    Source: HSBC estimates

    Under our research model, for stocks with a

    volatility indicator, the Neutral band is 10

    percentage points above and below the hurdle rate

    for Indian stocks of 11%. For CESC, this

    translates into a Neutral band of 1-21% around the

    current share price. Our target price of INR345 for

    CESC shares implies a total return (including

    dividend yield) of 44.7%, which is above the

    Neutral band; thus, we have an Overweight (V)

    rating on CESC stock.

    Risks

    Downside risks, we believe, include deeper-than-

    expected losses in the retail business and cost

    overruns from delayed execution.

  • 8/1/2019 HSBC Power Utilities

    15/37

    15

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Financials & valuation: CESC Ltd Overweight (V)Financial statements

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Profit & loss summary (INRm)

    Revenue 35,428 30,498 32,392 34,383EBITDA 3,977 7,028 7,780 8,489Depreciation & amortisation -1,962 -2,913 -3,141 -3,688Operating profit/EBIT 2,015 4,114 4,639 4,801Net interest -1,480 -2,068 -2,315 -2,539PBT 2,496 4,008 4,287 4,224HSBC PBT 2,496 4,008 4,287 4,224Taxation 131 -481 -514 -507Net profit 2,674 3,527 3,772 3,717HSBC net profit 2,674 3,527 3,772 3,717

    Cash flow summary (INRm)

    Cash flow from operations 6,356 4,328 7,105 7,777Capex -8,937 -16,218 -14,900 -12,300Cash flow from investment -8,937 -16,218 -14,900 -12,300Dividends -343 -743 -794 -783Change in net debt -155 12,633 8,590 5,306FCF equity -4,544 -13,852 -9,757 -6,485

    Balance sheet summary (INRm)

    Intangible fixed assets 0 0 0 0Tangible fixed assets 62,371 75,676 87,435 96,047Current assets 21,168 19,704 20,024 20,227Cash & others 10,170 10,170 10,170 10,170

    Total assets 89,546 101,386 113,466 122,280Operating liabilities 23,490 19,914 20,425 21,000Gross debt 20,683 33,316 41,906 47,211Net debt 10,513 23,146 31,736 37,041Shareholders funds 45,362 52,204 55,182 58,117Invested capital 49,879 65,296 76,864 85,104

    Ratio, growth and per share analysis

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Y-o-y % change

    Revenue 42.6 -13.9 6.2 6.1EBITDA -31.2 76.7 10.7 9.1Operating profit -52.0 104.2 12.8 3.5

    PBT -26.7 60.5 7.0 -1.5HSBC EPS -37.5 24.2 7.0 -1.5

    Ratios (%)

    Revenue/IC (x) 0.7 0.5 0.5 0.4ROIC 4.4 6.3 5.7 5.2ROE 6.4 7.2 7.0 6.6ROA 5.1 5.6 5.4 5.0EBITDA margin 11.2 23.0 24.0 24.7Operating profit margin 5.7 13.5 14.3 14.0EBITDA/net interest (x) 2.7 3.4 3.4 3.3Net debt/equity 23.2 44.3 57.5 63.7Net debt/EBITDA (x) 2.6 3.3 4.1 4.4CF from operations/net debt 60.5 18.7 22.4 21.0

    Per share data (INR)

    EPS Rep (diluted) 22.62 28.08 30.04 29.60HSBC EPS (diluted) 22.62 28.08 30.04 29.60DPS 4.00 5.05 5.41 5.33Book value 383.62 415.67 439.38 462.74

    Valuation data

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    EV/sales 1.0 1.6 1.7 1.8EV/EBITDA 8.9 6.8 7.3 7.3EV/IC 0.7 0.7 0.7 0.7PE* 10.7 8.6 8.1 8.2Price to book value 0.6 0.6 0.6 0.5FCF yield (%) -18.2 -55.5 -39.1 -26.0Dividend yield (%) 1.7 2.1 2.2 2.2

    Note: * = B ased on HSBC EPS (diluted)

    Issuer information

    Share price (INR) 242.00 Target price (INR) 345.00 Potentl tot rtn (%) 44.7

    Reuters (Equity) CESC.BO Bloomberg (Equity) CESC INMarket cap (USDm) 619 Market cap (INRm) 30,243Free float (%) 84 Enterprise value (INRm) 48,090Country India Sector Electric UtilitiesAnalyst Sumeet Agrawal Contact 91 22 2268 1243

    Price relative

    108

    208

    308

    408

    508

    608

    708

    2007 2008 2009 2010

    108

    208

    308

    408

    508

    608

    708

    Cesc Ltd Rel to BOMBAY SE SENSITIVE INDEX

    Source: HSBC

    Note: price at close of 12 Jan 2009

  • 8/1/2019 HSBC Power Utilities

    16/37

  • 8/1/2019 HSBC Power Utilities

    17/37

    17

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    3.9GW of projects in advancedstages of execution

    Lancos aggressive capacity expansion is

    supported by the financial closure of c3.9GW of

    projects. The projects are to be funded through a

    mix of debt and equity. The financial closure of

    some of these projects provides us with comfort in

    terms of their execution.

    These projects are in advanced stages of execution

    with the first 300MW of Amarkantak to be

    operational by end-FY09. The other 300MW of

    Amarkantak II is likely to be commissioned by

    September 2009. Other projects are in advanced

    stages of execution. We expect c620GW of

    capacity to be operational by FY10e, almost 2x

    the current installed base.

    Lanco has already spent cINR50.5bn in the above

    projects and requires an additional cINR124bn.

    We believe the capacity addition of 3.9GW over

    the next five years is not at risk.

    However, we believe the equity contribution

    should be a big challenge on the existing balance

    sheet. Lanco is already leveraged at 2.7x with net

    debt of cINR11bn. The equity contribution of

    INR61bn, including INR35bn of equity

    investment for projects in its pipeline, is an issue.

    However, we do not expect any significant issue

    in terms of equity investment of INR26.4bn for

    projects under execution. Internal accruals over

    the next five years should address the shortfall.

    We have not factored in any capacity addition

    from project under development (Babanth and

    Amarkantak III and IV).

    Fuel supply for projects

    Lanco has already met most of its coal requirements

    through coal linkages, which reduces fuel risk. For

    the Nagarjuna Power project, though, it has entered

    into a long-term (12-year) fuel supply agreement.

    As the project is based on a regulatory model, the

    fuel cost is passed through to the end user, so Lanco

    is not exposed to the fuel cost risk.

    Status of Lancos projects under execution

    Projects Location Fuel Capacity(MW)

    Est. projectcost

    (INRm)

    Holding(%)

    Capexspentso far

    (INRm)

    HSBCest.

    COD

    Status

    Amarkantak I Chhattisgarh Coal 300 12,900 76% 20,118 Feb-09 Boiler hydro test completed in Dec 07, switchyard charged, switchyard

    connected to gridAmarkantak II Chhattisgarh Coal 300 13,400 76% Sep-09 Boiler drum lifting completed in Dec07, hydro testing completed, turbine

    generator erected

    Vamshi Hydro HimachalPradesh

    Hydro 10 1,490 91% 1,234 Dec-09 Under commissioning

    VamshiIndustrial

    HimachalPradesh

    Hydro 10 91% Dec-09

    Lanco Green HimachalPradesh

    Hydro 70 4,200 90% 1,992 Apr-11 River diversion completed in Oct 07, River bed excavation of dam completed.commissioning expected in Dec 09 by company

    Kondpalli-II AndhraPradesh

    Gas 400 11,880 59% 904 Apr-10 Piling completed, erection of columns in ECB started

    Udupi(Nagarjuna)

    Karnataka ImportedCoal

    1,015 43,400 74% 14,534 Apr-12 Boiler drum lifting and TG casting done; TG erection to start soon. For U 2,boiler erection completed

    Lanco Energy Sikkim Hydro 500 30,000 74% 5,704 Jul-12 Civil work for tunnel in progressLancoUttaranchal

    Uttarakhand Hydro 152 9,500 90% 577 Apr-12 Techno-economic clearance received, infrastructure development under way

    Anpara C Uttar Pradesh Coal 1,200 48,000 100% 5,411 Jan-12 U 1: boiler foundation done, boiler erection to get started; U 2 : construction ofboiler foundation in progress

    Total 3,957 74,770 50,474

    Source: Company, HSBC

  • 8/1/2019 HSBC Power Utilities

    18/37

    18

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Taking care of fuel requirement

    Project Fuel type Status of fuel source

    Under constructionKondapalli II AP Gas From KG BasinAmarkantak I Chattisgarh Domestic Coal Coal linkages (SECL)Amarkantak II Chattisgarh Domestic Coal Coal linkages(SECL)Nagarjuna Karnataka Imported Coal Long term FSA from

    Indonesia (12 years)Anpara C UP Domestic Coal Coal linkages (NCL)Lanco Green HP Hydro HydroVamshi Industrial HP Hydro HydroVamshi Hydro HP Hydro HydroLanco Energy TeestaSikkim

    Hydro Hydro

    Lanco Hydro Uttarakhand Hydro HydroUnder pipelineBabanth I Orissa Domestic Coal 1000 MW Captive

    balance from Coallinkages

    Babanth II Orissa Domestic Coal Coal linkagesAmarkantak III & IV Chattisgarh

    Domestic Coal In process

    *SECL: South Eastern Coalfields Limited, 100% subsidiary of Coal India LtdSource: Company, HSBC

    Change in forecasts

    We have factored in delays in few of its project

    under construction. We now expect Amarkantak I

    to be operational in 4QFY09e and Amarkantak II

    in 2QFY10e, as against earlier target of 3QFY09e

    and company guidance of FY09e. We have also

    extended project completion for Anpara C to

    4QFY12e vs company guidance of FY11e.

    Apart from power execution delays, we have also

    changed our estimates for the EPC business by

    forecasting a 10% and 4% decline for FY09 and

    FY10 respectively. We have also reduced EBITDA

    margin estimates to 18% from 20% for FY09e.

    Summary of forecast changes

    ____New____ ____ Old______ __Change (%) __INRbnFY09e FY10e FY09e FY10e FY09e FY10e

    Sales 34.01 50.27 37.50 52.00 -9% -3%PAT 4.09 6.73 5.00 7.20 -18% -6%EPS (INR) 18.38 30.29 22.44 32.46 -18% -7%

    Source: HSBC estimates

    HSBC vs consensusHSBC vs consensus (INRbn)

    ___ Sales __ ___ PAT ___ _ EPS (INR/share) _INRbn FY09e FY10e FY09e FY10e FY09e FY10e

    HSBCestimates

    34.01 50.27 4.09 6.73 18.4 30.3

    Consensusestimates

    56.97 81.76 4.32 6.13 19.5 27.7

    % difference -40% -39% -5% 10% -6% 10%

    Source: HSBC, Reuters

    Valuation

    Based on this, we have reduced our FY09e profit

    estimates by 6%, driven by 3% decline in revenue

    and lower EPC margin. We have also extended

    execution time frame for EPC business, given the

    delays in power projects.

    Real estate valuation

    We have value the real estate separately and used

    a discount rate of 15%. We have assumed the

    entire Hyderabad real estate to be developed in

    the next eight years. Based on this, we derive an

    NAV of INR10.3bn. However, we have also

    removed the value of real estate (INR37 per share

    earlier) from our valuation, given the current

    slowdown in the real estate sector. We expect that

    any upturn in the real estate business to provide an

    upside to the stock.

    Discounted cash flow

    We have used the discounted cash flow method to

    value generation, and other businesses. We haveused a discount rate of 13.1% (12.8% earlier) to

    incorporate higher cost of debt (14% vs 12%

    earlier). Based on this, we derive a fair value of

    INR140 per share (INR297 per share earlier).

    Price to book value

    We have used a price-to-book multiple of 1.2x (2x

    earlier), a 33% discount to NTPCs target PB.

    Based on this, we derive a fair value of INR149

    per share (INR312 earlier).

  • 8/1/2019 HSBC Power Utilities

    19/37

  • 8/1/2019 HSBC Power Utilities

    20/37

    20

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Financials & valuation: Lanco Infratech Neutral (V)Financial statements

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Profit & loss summary (INRm)

    Revenue 32,413 34,015 50,274 77,368EBITDA 6,905 7,538 12,600 20,128Depreciation & amortisation -776 -1,235 -2,361 -3,715Operating profit/EBIT 6,129 6,302 10,238 16,413Net interest -832 -1,160 -1,578 -2,064PBT 6,175 6,191 9,813 15,617HSBC PBT 6,175 6,191 9,813 15,617Taxation -1,405 -1,391 -2,205 -3,509Net profit 3,542 4,088 6,735 10,989HSBC net profit 3,542 4,088 6,735 10,989

    Cash flow summary (INRm)

    Cash flow from operations 9,419 6,407 13,745 22,113Capex -8,520 -16,589 -15,391 -38,731Cash flow from investment -8,520 -16,589 -15,391 -38,731Dividends 0 0 0 0Change in net debt -899 9,264 462 15,236FCF equity -54 -11,230 -2,800 -17,886

    Balance sheet summary (INRm)

    Intangible fixed assets 0 0 0 0Tangible fixed assets 32,134 47,487 60,517 95,533Current assets 24,807 25,566 33,263 46,090Cash & others 5,050 5,050 5,050 5,050

    Total assets 62,970 79,082 99,810 147,652Operating liabilities 22,870 24,001 35,473 54,591Gross debt 16,200 25,464 25,926 41,162Net debt 11,150 20,413 20,875 36,112Shareholders funds 18,722 22,809 29,544 40,533Invested capital 29,021 44,002 53,257 81,982

    Ratio, growth and per share analysis

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Y-o-y % change

    Revenue 101.9 4.9 47.8 53.9EBITDA 64.5 9.2 67.2 59.7Operating profit 73.0 2.8 62.5 60.3

    PBT 96.7 0.3 58.5 59.1HSBC EPS 61.6 15.4 64.7 63.2

    Ratios (%)

    Revenue/IC (x) 1.2 0.9 1.0 1.1ROIC 17.5 13.4 16.3 18.8ROE 20.9 19.7 25.7 31.4ROA 9.8 8.0 9.9 11.1EBITDA margin 21.3 22.2 25.1 26.0Operating profit margin 18.9 18.5 20.4 21.2EBITDA/net interest (x) 8.3 6.5 8.0 9.8Net debt/equity 47.0 69.4 54.6 69.8Net debt/EBITDA (x) 1.6 2.7 1.7 1.8CF from operations/net debt 84.5 31.4 65.8 61.2

    Per share data (INR)

    EPS Rep (diluted) 15.93 18.38 30.29 49.42HSBC EPS (diluted) 15.93 18.38 30.29 49.42DPS 0.00 0.00 0.00 0.00Book value 84.20 102.58 132.87 182.30

    Valuation data

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    EV/sales 1.1 1.3 1.0 0.9EV/EBITDA 5.0 6.1 3.8 3.3EV/IC 1.2 1.0 0.9 0.8PE* 7.0 6.0 3.7 2.2Price to book value 1.3 1.1 0.8 0.6FCF yield (%) -0.2 -44.5 -10.3 -60.0Dividend yield (%) 0.0 0.0 0.0 0.0

    Note: * = Based on HSBC EPS (diluted)

    Issuer information

    Share price (INR) 110.85 Target price (INR) 132.00 Potentl tot rtn (%) 19.1

    Reuters (Equity) LAIN.BO Bloomberg (Equity) LANCI INMarket cap (USDm) 505 Market cap (INRm) 24,649Free float (%) 21 Enterprise value (INRm) 45,654Country India Sector Electric UtilitiesAnalyst Sumeet Agrawal Contact 91 22 2268 1243

    Price relative

    0

    100

    200

    300

    400500

    600

    700

    800

    900

    2007 2008 2009 2010

    0

    100

    200

    300

    400500

    600

    700

    800

    900

    Lanco Infratech Rel to BOMBAY SE SENSITIVE INDEX

    Source: HSBC

    Note: price at close of 12 Jan 2009

  • 8/1/2019 HSBC Power Utilities

    21/37

    21

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Strong project pipeline, butpoor execution

    NTPC has a strong project pipeline with capacity

    addition target of 22GW by 2012e to increase itsinstalled base to 50GW.

    We expect NTPC to miss its capacity addition

    target despite strong project execution capabilities

    and fund availability. NTPC saw execution delays

    due in the past too, from delay in land acquisition,

    regulatory approvals, and by equipment vendors.

    The Central Electricity Authority has also taken

    cognisance of delays in execution, and expects

    NTPC to commission only 15.4GW in the 11thPlan. We are more conservative, and expect it to

    commission 11.9GW of capacity by 2012.

    Capacity addition plan

    NTPC plans to add 20GW by FY12 to its current

    installed base of 29GW. We expect the projects

    under tendering (3.8GW) will not come on stream

    by FY12, leading to an overall shortfall of 10GW

    against planned capacity by the end of the 11th

    Plan period.

    Delay in coal mining a concern

    NTPC has huge coal requirement annually. In

    2008, it consumed c124mt, 2.6mt of which was

    imported. Globally, there is a shortage of coal,

    and coal prices are on the rise. Coal India Limited

    is the principal supplier of coal to NTPC.

    To meet its coal requirements on an ongoing basis,

    NTPC is developing seven coal mines, which have

    total reserves of 3.6bn tonnes, with an annual

    estimated capacity of 56m tonnes per annum

    (mtpa). Of the total approved advance expenditure

    of INR5.4bn to develop these mines, INR0.8bn was

    already spent as at end of the last financial year.

    NTPCs coal reserves

    Project Est.reserves

    (m tonnes)

    Mine life(in years)

    Est.capacity

    (mtpa)

    Projectdevmt

    yearexpected

    Pakri Barwadih 1,436 50 15 FY10Chatti Bariatu 243 30 7 FY11Chatti Bariatu II 354 30 5 FY11Kerandari 229 25 6 FY12Dulanga 260 30 5 FY11Talaipalli 965 30 15 FY13Chhatrasal 150 30 3Total Own 3,637 56JV with Coal India Limited

    Brahminni 1,900 25 25Chichro Patsimal 356 NA 5Total 5,893 86

    Source: Company, HSBC

    NTPC Ltd (NATP)

    NTPC enjoys the best positioning in terms of access to funds and

    fuel, but market ignoring delays in project execution

    NTPC continues to trade at a premium valuation, defying risk of

    delays and reduction in RoE in FY09e

    Downgrade to Underweight (V) from Neutral (V) on valuation

    trading (1.78x FY10e PB); retain our target of INR142

  • 8/1/2019 HSBC Power Utilities

    22/37

  • 8/1/2019 HSBC Power Utilities

    23/37

    23

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Discounted cash flowBased on our DCF approach, we derive a value of

    INR123.

    Sum of the parts

    We have valued NTPC on SOTP value of

    INR165. We have valued the existing generation

    business at an EV/MW of INR46.5m, based on

    expected replacement cost and a premium for the

    existing business. We have not valued the captive

    coal mining business, as the mine development

    operator has yet to be appointed and there is not

    much clarity on the transfer pricing between the

    mine and the generating station. In addition, we

    have valued NTPCs investment in various JVs

    (other than power generating JVs) at 1.5x the

    book value of the investments, since they are at

    very early stages of development.

    Price to book

    We have valued NTPC using a multiple of 1.8xFY10e book value. Based on this, we derive a fair

    value of INR138 per share.

    NTPCs SOTP

    Business Unit Capacity Multiple Value INR pershare

    Generation MW 30,807 46.50x 1,432,523 174Investments Premium to

    book101,883 50.0% 152,825 19

    Total 1,585,347 192Less Net debt 221,950 27Equity value 1,363,397 165

    Source: HSBC

    Based on the average of these three values, we

    derive a target price of INR142, suggesting

    17% downside.

    Target price derivation

    INR per share

    SOTP 165DCF 123PB 138Target price 142

    Source: HSBC estimates

    Under our research model, for stocks with a

    volatility indicator, the Neutral band is 10

    percentage points above and below the hurdle rate

    for Indian stocks of 11%. For NTPC, this

    translates into a Neutral band of 1-21% around the

    current share price. Our target price of INR142 for

    NTPC shares implies a total return (including

    dividend yield) of -14.6%, which is below the

    Neutral band; thus, we have an Underweight (V)

    rating on the NTPC stock.

    Risks

    Business risks includes fuel supply concerns,

    delays in project execution, and an impact from

    higher costs on merchant power. Also, regulatory

    risks include a reduction in RoE due to higher

    efficiency norms to be set by the regulator. Upside

    risks to our rating include faster execution, higher

    efficiency norms, and the ability to raise funds at

    lower cost and to address the fuel issue.

  • 8/1/2019 HSBC Power Utilities

    24/37

    24

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Financials & valuation: NTPC Underweight (V)Financial statements

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Profit & loss summary (INRm)

    Revenue 386,823 418,192 467,204 518,285EBITDA 117,352 131,412 144,773 156,979Depreciation & amortisation -22,060 -21,213 -23,306 -25,735Operating profit/EBIT 95,292 110,199 121,468 131,244Net interest -18,581 -20,910 -23,998 -26,860PBT 103,510 112,502 119,941 126,154HSBC PBT 103,510 112,502 119,941 126,154Taxation -28,811 -30,404 -33,057 -35,342Net profit 74,699 82,098 86,884 90,812HSBC net profit 74,699 82,098 86,884 90,812

    Cash flow summary (INRm)

    Cash flow from operations 97,822 99,202 119,943 137,619Capex -99,442 -82,556 -127,945 -206,790Cash flow from investment -82,505 -66,041 -111,430 -190,275Dividends -28,932 -29,605 -33,581 -35,221Change in net debt 16,328 1,027 30,105 93,161FCF equity -46,404 -8,414 -31,898 -92,411

    Balance sheet summary (INRm)

    Intangible fixed assets 6 6 6 6Tangible fixed assets 537,900 599,243 703,882 884,937Current assets 263,157 304,766 313,315 280,150Cash & others 153,605 190,961 186,356 139,688

    Total assets 935,533 1,021,970 1,118,644 1,250,018Operating liabilities 77,030 85,788 107,959 141,737Gross debt 303,147 341,530 367,031 413,523Net debt 149,542 150,569 180,674 273,836Shareholders funds 528,629 573,647 621,290 671,087Invested capital 570,428 627,266 722,888 883,668

    Ratio, growth and per share analysis

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Y-o-y % change

    Revenue 14.2 8.1 11.7 10.9EBITDA 15.4 12.0 10.2 8.4Operating profit 18.1 15.6 10.2 8.0

    PBT 15.5 8.7 6.6 5.2HSBC EPS 8.3 9.9 5.8 4.5

    Ratios (%)

    Revenue/IC (x) 0.7 0.7 0.7 0.6ROIC 13.0 13.4 13.0 11.8ROE 14.7 14.9 14.5 14.1ROA 9.9 9.9 9.7 9.3EBITDA margin 30.3 31.4 31.0 30.3Operating profit margin 24.6 26.4 26.0 25.3EBITDA/net interest (x) 6.3 6.3 6.0 5.8Net debt/equity 28.2 26.2 29.0 40.7Net debt/EBITDA (x) 1.3 1.1 1.2 1.7CF from operations/net debt 65.4 65.9 66.4 50.3

    Per share data (INR)

    EPS Rep (diluted) 9.06 9.96 10.54 11.01HSBC EPS (diluted) 9.06 9.96 10.54 11.01DPS 3.51 3.91 4.14 4.33Book value 64.11 69.57 75.35 81.39

    Valuation data

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    EV/sales 3.7 3.4 3.2 3.1EV/EBITDA 12.1 11.0 10.3 10.2EV/IC 2.5 2.3 2.1 1.8PE* 18.9 17.2 16.2 15.5Price to book value 2.7 2.5 2.3 2.1FCF yield (%) -3.6 -0.7 -2.4 -7.0Dividend yield (%) 2.1 2.3 2.4 2.5

    Note: * = Based on HSBC EPS (diluted)

    Issuer information

    Share price (INR) 170.90 Target price (INR) 142.00 Potentl tot rtn (%) -14.6

    Reuters (Equity) NTPC.BO Bloomberg (Equity) NATP INMarket cap (USDm) 28,849 Market cap (INRm) 1,409,150Free float (%) 11 Enterprise value (INRm) 1,441,764Country India Sector Electric UtilitiesAnalyst Sumeet Agrawal Contact 91 22 2268 1243

    Price relative

    105125145165185205

    225245265285305

    2007 2008 2009 2010

    105125145165185205

    225245265285305

    NTPC Rel to BOMBAY SE SENSITIVE INDEX

    Source: HSBC

    Note: price at close of 12 Jan 2009

  • 8/1/2019 HSBC Power Utilities

    25/37

    25

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Best-placed Indian utility

    Building on existing experience and

    presence

    Tata Power has established itself as a credible

    player in the Indian power sector by leveraging its

    experience of operating the largest installed base

    within the private sector and operating

    distribution circles in Mumbai and Delhi. It is the

    first private player to set up and operate a high-

    voltage transmission line in a JV with PGCIL,

    which completed its first year of operations in

    March 2008. It is now expanding its fleet of

    power plants across India; these are at various

    stages of construction and development. The

    success of the company is shown by its ability to

    achieve financial closure and source fuel linkages

    for most of its projects both through captive mine

    allocation and acquiring coal mines in Indonesia.

    Well-diversified generating portfolio

    Tata Power has a well-diversified generating

    portfolio in terms of both fuel mix and selling

    arrangements i.e., regulated versus tariff based,

    captive and merchant based power plant. It has a

    well-defined capacity addition plan, with

    2,400MW already under operation, 5,660MW

    under construction, and c5,670MW in the

    pipeline. Its generation portfolio consists of a

    diverse fuel mix, with thermal, hydro and

    alternative fuels accounting for 75%, 20%, and

    3% respectively.

    Tata Power (TPWR)

    Building a well-diversified generation portfolio supported by fuel

    sourcing and funding strategy

    Acquisition of overseas coal blocks proving to be a well-crafted

    strategy for security fuel; lower FY10 profit estimates 21% to

    incorporate lower coal realisation

    Reiterate Overweight (V), lower target to INR1,000 from INR1,244

    Tata Power generation portfolio

    Regulated Tariff based Captive power / IPP Merchant Renewable

    Developed1330MW Trombay thermal 428MW Jojobera 79MW Wind447MW Hydro power Station 81MW BelgaumUnder construction250MW Trombay extension 4000MW Mundra UMPP 120MW Jamshedpur 124MW Wind Power1050MW Maithon thermal 120MW Jojobera thermal 3MW Solar PV120MW Haldia thermalUnder pipeline

    1000MW Naraj Marthapur IPP 2400MW Coastal Maharashtra1270MW Naraj Marthapur CPP500MW Tubed IPP

    500MW Jharkhand (Tata Steel)

    Source: Company, HSBC

  • 8/1/2019 HSBC Power Utilities

    26/37

    26

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Within alternative energy sources, Tata Power

    plans to expand its wind capacity from 78MW

    now to 200MW over the next year. It has plans to

    further explore opportunities in the wind energy

    space, which we believe will help the company to

    manage its obligation under the renewable energy

    target imposed on distributors in Maharashtra.

    We believe Tata Powers ability to create a well-

    diversified power plant portfolio, i.e., selling in

    both the regulated and the free markets will

    enable it to mitigate fuel and offtake risks.

    Fuel and funds well tied up

    Visible success in acquiring fuel to

    power its plants

    Tata Power is well positioned to meet its fuel

    obligations, in our view, as it has made significantarrangements for most of its plants under

    construction either by way of captive mine

    allocation or through fuel offtake agreement for

    coal supply from Indonesia. For example, it has

    been allocated two coal mines for its projects. It

    received allocation of the 189mt coal block in

    Jharkhand in JV with Hindalco and the 290mt

    Mandakini coal block in Orissa along with Jindal

    Photo and Monnet Ispat. It has picked up a 30%

    stake in KPC and Arutmin from PT BumiResources in Indonesia, which allows it to draw

    10mt of coal supplies over the long term, which is

    capable of fuelling almost the entire Mundra

    plant. For Maithon projects, Tata Power has tied

    up fuel from Bharat Coking Coal mines, which

    reflects its ability to obtain fuel linkages for large

    projects.

    Successful in achieving financial

    closure for large projects

    Tata Power has completed financing for two of its

    largest power plants under construction i.e., the

    Tata Powers generation capacity addition plans

    Project Capacity(MW)

    Projectcost

    (INRbn)

    Debtto

    equity

    Debt(INRbn)

    Equity(INRbn)

    Developerstake (%)

    Developerequity

    (INRbn)

    Status of fundingclosure

    Fuel type Fuel source

    UnderconstructionMundra 4,000 170.00 75:25 127.5 42.5 100% 42.5 Done, with USD1.8bn

    forex loan and USD1.4bnrupee loan

    Imported coal 10mtpa offtake agreement withKPC*/Arutmin, pricing part fixedand part linked to CERC Index

    Maithon (74%stake)

    1,050 44.50 70:30 31.2 13.4 74% 9.9 Done; funded by StateBank of India

    Domestic coal Fuel linkage from Bharat CokingCoal mines

    Jamshedpur andJojobera

    240 11.10 70:30 7.8 3.3 74% 2.5 In advanced stage ofcompletion

    Tollingarrangement

    Coke oven gases of Tata Steel,and linkage from West Bokaroand Mahanadi coal fields

    Trombay Expansion 250 10.66 70:30 7.5 3.2 100% 3.2 In advanced s tage ofcompletion

    Imported coal Imported coal, cost pass-through

    Haldia 120 6.05 70:30 4.2 1.8 100% 1.8 In advanced stage ofcompletion

    Tollingarrangement

    Hot flue gases from HooglyMetcoke

    Sub-total 5,660 242 178 64 60

    In the pipelineCoastalMaharashtra

    2,400 101 70:30 75.6 25.2 100% 25.2 Imported Coal Coal f rom Bumi Resourcesofftake

    Naraj MarthapurIPP

    1,000 42.0 70:30 29.4 12.6 100% 12.6 Domestic coal Mandakin i Coal Block

    Naraj MarthapurCPP

    1,270 53.3 70:30 37.3 16.0 74% 11.8 Tollingarrangement

    Supply by procurers

    Tubed IPP 500 21.0 70:30 14.7 6.3 100% 6.3 Domest ic coal Capt ive coal blockJharkhand CPP 500 21.0 70:30 14.7 6.3 74% 4.7 Tolling

    arrangementSupply by Tata Steel

    Sub-total 5,670 238 172 66.4 60.6Total 11,330 480 350 131 120

    * KPC=Kaltim Prima CoalSource: Company, HSBC estimates

  • 8/1/2019 HSBC Power Utilities

    27/37

    27

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    1050MW Maithon project, for which the debt

    component of cINR30bn is being funded by a

    consortium led by State Bank of India. For its

    Mundra project, the company has tied up to raise

    USD1.8bn in foreign exchange loans and

    USD1.4bn in INR loans with several multilateral

    and domestic financial institutions. With these

    two big projects, most of the groups funding for

    plants under construction has been tied up.

    Funding for remaining smaller projects, such as

    captive projects at Jojobera and Jamshedpur, are

    at advanced stages of reaching financial closure.

    Tata Power proposes to raise the total funding

    requirement of INR240bn during the next four

    years through its own contribution (INR60bn) and

    through debt (INR180bn), a large portion of

    which is already tied up.

    Change in forecasts

    We have reduced our contribution from the coal

    mine business, given the declining coal prices. Weexpect average realisation of coal to fall to

    cUSD48 per tonne, a decrease of 30% from the

    previous year in contrast to our earlier estimate of

    10% decline. Also we have decreased the coal

    production forecast now to 4% annual increase

    from earlier estimates of 7% for FY09 and 5%

    thereafter. Also in our estimates, we now provide

    for 20% provision for taxation from earlier

    estimates of 12.4%.

    Summary of changes in forecasts

    _____ New ___ ____ Old______ __Change (%)__(INRbn)FY09e FY10e FY09e FY10e FY09e FY10e

    Sales 146.19 142.82 149.11 151.99 -2% -6%PAT 20.97 24.11 21.29 30.42 -1% -21%EPS (INR) 95.05 109.26 96.49 137.82 -1% -21%

    Source: HSBC estimates

    HSBC vs consensusHSBC vs consensus (INRbn)

    ___ Sales _ ___ ___ PAT ____ _ EPS (INR) __INRbn FY09e FY10e FY09e FY10e FY09e FY10e

    HSBCestimates

    146.2 142.8 20.9 24.1 95.0 109.3

    Consensusestimates

    150.4 169.7 18.9 26.7 84.4 116.1

    % difference -3% -16% 11% -10% 13% -6%

    Source: HSBC, DataStream

    Valuation

    Combination of valuation approaches

    We value Tata Power using the methods below

    and derive a target price of INR1,000.

    Discounted cash flow

    We use the discounted cash flow method to value

    the entire generation as well as other business. We

    used a discount rate of 12% (13.5% cost of equity

    and 6.6% cost of debt). Based on this, we derive a

    fair value of INR1,243 per share.

    Price to book value

    We value Tata Power at PB multiple of 2.0x (a

    slight premium of 15% to global utilities),

    deriving a value of INR986 per share.

    Sum of the parts

    We value the existing generation business at an

    EV/MW of INR46.5m, based on expected

    replacement cost. We value NDPL based on 2x

    price-to-book, given that it is able to generate a

    16% ROE and is growing at c15% CAGR over

    FY08-10e. We have not considered the value

    derived from projects under development. Based

    on the SOTP approach, we value the company at

    INR770 per share.

  • 8/1/2019 HSBC Power Utilities

    28/37

    28

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Target price derivation

    INR per share

    SOTP 770DCF 1243PB 986Target price 1,000

    Source: HSBC estimates

    Under our research model, for stocks with avolatility indicator, the Neutral band is 10

    percentage points above and below the hurdle rate

    for Indian stocks of 11%. For Tata Power, this

    translates into a Neutral band of 1-21% around the

    current share price. Our target price of INR1,000

    for Tata Power shares implies a total return

    (including dividend yield) of 40.7%, which is

    above the Neutral band; thus, we have an

    Overweight (V) rating on the Tata Power stock.

    RisksBusiness risks include equity funding for the

    5.6GW under pipeline, delays in project

    execution, interest rate risk, and regulatory risk.

    Tata Powers SOTP

    Business Unit Particulars Multiple Value (INRm) INR per share

    Generation MW 3,019 46.50x 140,373 636.1NDPL Equity investment 2,009 2.00x 4,019 18.2Transmission lines Book Value 2,380 2.00x 2,428 11.0License area distribution assets Book Value 5,033 2.00x 10,067 45.6Tata BP Solar 8xFY08 EV/Sales 8,500 1.76x 14,946 67.7Mundra Power Project NPV to Equity 7,802 35.430% stake in Bumi Resources NPV to Equity 38,768 175.7Value of projects under construction NPV to Equity 9,492 1.00x 9,492 43.0Investments Premium to book 26,398 50% 39,597 179.4Value of projects in pipeline 0% 0 0.0Total 267,490 1212Less Net debt -97,488 -442Equity value 170,002 770No. of shares 220.68

    Source: HSBC

  • 8/1/2019 HSBC Power Utilities

    29/37

    29

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Financials & valuation: Tata Power Overweight (V)Financial statements

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Profit & loss summary (INRm)

    Revenue 108,891 146,189 142,816 178,753EBITDA 21,203 38,517 43,359 46,493Depreciation & amortisation -5,593 -7,109 -8,230 -9,085Operating profit/EBIT 15,611 31,407 35,129 37,408Net interest -4,881 -6,841 -6,937 -7,735PBT 15,485 29,611 33,489 35,234HSBC PBT 15,485 29,611 33,489 35,234Taxation -3,765 -8,302 -8,835 -8,898Net profit 9,965 20,975 24,112 24,848HSBC net profit 9,965 20,975 24,112 24,848

    Cash flow summary (INRm)

    Cash flow from operations 13,152 23,268 23,688 42,559Capex -25,527 -17,827 -25,447 -36,717Cash flow from investment -69,956 -17,827 -25,447 -36,717Dividends -2,365 -5,944 -6,833 -7,042Change in net debt 47,753 1,198 9,981 2,241FCF equity -17,073 397 -7,056 281

    Balance sheet summary (INRm)

    Intangible fixed assets 0 0 0 0Tangible fixed assets 140,901 151,619 168,835 196,466Current assets 50,049 59,796 60,671 57,468Cash & others 5,623 5,623 5,623 5,623

    Total assets 222,228 242,693 260,784 285,212Operating liabilities 33,151 37,749 29,427 33,362Gross debt 91,136 92,334 102,315 104,556Net debt 85,513 86,711 96,692 98,933Shareholders funds 75,920 90,950 108,229 126,035Invested capital 152,176 168,044 194,456 214,949

    Ratio, growth and per share analysis

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    Y-o-y % change

    Revenue 68.1 34.3 -2.3 25.2EBITDA 94.3 81.7 12.6 7.2Operating profit 130.8 101.2 11.8 6.5

    PBT 127.9 91.2 13.1 5.2HSBC EPS 21.3 110.5 15.0 3.1

    Ratios (%)

    Revenue/IC (x) 1.0 0.9 0.8 0.9ROIC 10.6 14.1 14.3 13.7ROE 15.3 25.1 24.2 21.2ROA 8.6 11.3 11.8 11.8EBITDA margin 19.5 26.3 30.4 26.0Operating profit margin 14.3 21.5 24.6 20.9EBITDA/net interest (x) 4.3 5.6 6.3 6.0Net debt/equity 101.8 87.9 84.0 74.2Net debt/EBITDA (x) 4.0 2.3 2.2 2.1CF from operations/net debt 15.4 26.8 24.5 43.0

    Per share data (INR)

    EPS Rep (diluted) 45.15 95.05 109.26 112.60HSBC EPS (diluted) 45.15 95.05 109.26 112.60DPS 10.94 23.02 26.47 27.27Book value 344.03 412.14 490.43 571.12

    Valuation data

    Year to 03/2008a 03/2009e 03/2010e 03/2011e

    EV/sales 2.1 1.5 1.6 1.3EV/EBITDA 10.5 5.8 5.4 5.1EV/IC 1.5 1.3 1.2 1.1PE* 16.1 7.7 6.7 6.5Price to book value 2.1 1.8 1.5 1.3FCF yield (%) -12.4 0.3 -5.2 0.2Dividend yield (%) 1.5 3.2 3.6 3.8

    Note: * = Based on HSBC EPS (diluted)

    Issuer information

    Share price (INR) 727.25 Target price (INR) 1000.00 Potentl tot rtn (%) 40.7

    Reuters (Equity) TTPW.BO Bloomberg (Equity) TPWR INMarket cap (USDm) 3,296 Market cap (INRm) 161,004Free float (%) 67 Enterprise value (INRm) 224,164Country India Sector Electric UtilitiesAnalyst Sumeet Agrawal Contact 91 22 2268 1243

    Price relative

    350

    550

    750

    9501150

    1350

    1550

    1750

    2007 2008 2009 2010

    350

    550

    750

    9501150

    1350

    1550

    1750

    Tata Power Rel to BOMBAY SE SENSITIVE INDEX

    Source: HSBC

    Note: price at close of 12 Jan 2009

  • 8/1/2019 HSBC Power Utilities

    30/37

    30

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Hectic equipment ordering in2008

    2008 was a momentous year, with 15GW ordered

    for various equipment manufacturers this was

    because of the push towards achieving 78GW of

    the governments capacity addition target. The

    Ministry of Power pushed to achieve financial

    closure, and equipment ordering led to significant

    news flow in 2008.

    11th Plan: capacity addition plan (MW)

    Central State Pr ivate Total %

    Thermal 21,496 22,001 17,406 60,903 76%Hydro 8,654 3,362 3,491 15,507 19%Nuc lear 3,380 0 0 3,380 4%Total 33,530 25,363 20,897 79,790% 42% 32% 26%

    Source: CEA, HSBC estimates

    Why were targets not met?

    India has a poor record in achieving its power

    capacity addition targets. The 10th Plan achieved

    only 52% of the proposed installed base. Failure to

    achieve financial closure and delays from

    equipment vendors and regulators were key reasons

    why capacity addition targets were not met.

    Why 10th Five-Year Plan capacity addition targets were not met

    Major reasons for slippage Total

    Delay in supplies/erection by suppliers/ contractors 24%Delay in tie-up super critical technology 14%Non-availability of gas 11%Delay in award of works, mainly in state sector/NLC 9%Projects not taken up/escrow cover not given/financialclosure not achieved/funds not tied up

    19%

    Delay in clearance/investment decisions (hydro projects) 8%Hydro projects: delay in environmental clearance,geological surprises, natural calamities, relocation andrehabilitation issues, delay in signing of MoU, court cases

    11%

    Law & order problems 2%Nuclear projects included on best effort basis (otherwise

    scheduled for 11th Plan)

    4%

    Adjustments due to change of size -3%

    Source: CEA

    Capacity addition: actual vs planned over five-year plans

    -

    10,000

    20,000

    30,000

    40,000

    50,000

    I IV VII IX

    30%40%

    50%

    60%

    70%

    80%

    90%

    100%

    Capacity planned Capacity added %

    Source: CEA

    To mitigate the delays due to equipment shortage,

    developers have already placed equipment orders

    on vendors, providing sufficient time for project

    execution this time around.

    With equipment now ordered, we expect focus to

    shift towards execution, over the next three years.

    Annexure

    2008 saw hectic equipment ordering

    We analyse reasons why earlier plans were not achieved

  • 8/1/2019 HSBC Power Utilities

    31/37

    31

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    However, we still expect delays to hamper the

    capacity addition plan and expect c48GW of

    capacity addition over 2007-12e.

    Generation capacity addition analysis (MW)

    FY08 FY09e FY10e FY11e FY12e Total

    Breakdown by technologyThermal 6620 5047 7795.2 6948 11901 38311Hydro 2423 232 499 1281 2211 6646Nuclear 220 440 220 1500 1000 3380Total 9263 5719 8514.2 9729 15112 48337

    Breakdown by sectorCentra l 3240 2440 2250 4692 9051 21673State 5273 1494 3126.2 4028 3201 17122Private 750 1785 3138 1009 2860 9542Total 9263 5719 8514.2 9729 15112 48337

    Source: CEA, HSBC estimates

    We expect the major reasons for slippage in capacity

    addition will be delays from equipment vendors,

    failure to receive regulatory clearances for hydro

    projects, and the fact that most capacity addition is

    back-ended (36% capacity to be commissioned in

    FY12, as per recent CEA publications).

  • 8/1/2019 HSBC Power Utilities

    32/37

    32

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    Disclosure appendix

    Analyst certification

    The following analyst(s), who is(are) primarily responsible for this report, certifies(y) that the opinion(s) on the subject

    security(ies) or issuer(s) and any other views or forecasts expressed herein accurately reflect their personal view(s) and that no

    part of their compensation was, is or will be directly or indirectly related to the specific recommendation(s) or views contained

    in this research report: Sumeet Agrawal

    Important disclosuresStock ratings and basis for financial analysis

    HSBC believes that investors utilise various disciplines and investment horizons when making investment decisions, which

    depend largely on individual circumstances such as the investors existing holdings, risk tolerance and other considerations.

    Given these differences, HSBC has two principal aims in its equity research: (1) to identify long-term investment opportunities

    based on particular themes or ideas that may affect the future earnings or cash flows of companies on a 12 month time horizon;

    and (2) from time to time to identify short-term investment opportunities that are derived from fundamental, quantitative,

    technical or event-driven techniques on a 0-3 month time horizon and which may differ from our long-term investment rating.

    HSBC has assigned ratings for its long-term investment opportunities as described below.

    This report addresses only the long-term investment opportunities of the companies referred to in the report. As and when

    HSBC publishes a short-term trading idea the stocks to which these relate are identified on the website at

    www.hsbcnet.com/research. Details of these short-term investment opportunities can be found under the Reports section of thiswebsite.

    HSBC believes an investors decision to buy or sell a stock should depend on individual circumstances such as the investors

    existing holdings and other considerations. Different securities firms use a variety of ratings terms as well as different rating

    systems to describe their recommendations. Investors should carefully read the definitions of the ratings used in each research

    report. In addition, because research reports contain more complete information concerning the analysts views, investors

    should carefully read the entire research report and should not infer its contents from the rating. In any case, ratings should not

    be used or relied on in isolation as investment advice.

    Rating definitions for long-term investment opportunities

    Stock ratings

    HSBC assigns ratings to its stocks in this sector on the following basis:

    For each stock we set a required rate of return calculated from the risk free rate for that stocks domestic, or as appropriate,

    regional market and the relevant equity risk premium established by our strategy team. The price target for a stock represents

    the value the analyst expects the stock to reach over our performance horizon. The performance horizon is 12 months. For a

    stock to be classified as Overweight, the implied return must exceed the required return by at least 5 percentage points over the

    next 12 months (or 10 percentage points for a stock classified as Volatile*). For a stock to be classified as Underweight, the

    stock must be expected to underperform its required return by at least 5 percentage points over the next 12 months (or 10

    percentage points for a stock classified as Volatile*). Stocks between these bands are classified as Neutral.

    Our ratings are re-calibrated against these bands at the time of any material change (initiation of coverage, change of

    volatility status or change in price target). Notwithstanding this, and although ratings are subject to ongoing management

    review, expected returns will be permitted to move outside the bands as a result of normal share price fluctuations without

    necessarily triggering a rating change.

    *A stock will be classified as volatile if its historical volatility has exceeded 40%, if the stock has been listed for less than 12

    months (unless it is in an industry or sector where volatility is low) or if the analyst expects significant volatility. However,

  • 8/1/2019 HSBC Power Utilities

    33/37

    33

    Natural Resources & Energy

    Indian Utilities

    14 January 2009

    abc

    stocks which we do not consider volatile may in fact also behave in such a way. Historical volatility is defined as the pastmonths average of the daily 365-day moving average volatilities. In order to avoid misleadingly frequent changes in rating,

    however, volatility has to move 2.5 percentage points past the 40% benchmark in either direction for a stocks status to change.

    Prior to this, from 7 June 2005 HSBC applied a ratings structure which ranked the stocks according to their notional target

    price vs current market price and then categorised (approximately) the top 40% as Overweight, the next 40% as Neutral and

    the last 20% as Underweight. The performance horizon is 2 years. The notional target price was defined as the mid-point of the

    analysts valuation for a stock.

    From 15 November 2004 to 7 June 2005, HSBC carried no ratings and concentrated on long-term thematic reports which

    identified themes and trends in industries, but did not make a conclusion as to the investment action that potential investors

    should take.

    Prior to 15 November 2004, HSBCs ratings system was based upon a two-stage recommendation structure: a combination ofthe analysts view on the stock relative to its sector and the sector call relative to the market, together giving a view on the

    stock relative to the market. The sector call was the responsibility of the strategy team, set in co-operation with the analysts.

    For other companies, HSBC showed a recommendation relative to the market. The performance horizon was 6-12 months. The

    target price was the level the stock should have traded at if the market accepted the analysts view of the stock.

    Rating distribution for long-term investment opportunities

    As of 13 January 2009, the distribution of all ratings published is as follows:

    Overweight (Buy) 43% (31% of these provided with Investment Banking Services)

    Neutral (Hold) 37% (33% of these provided with Investment Banking Services)

    Underweight (Sell) 20% (21% of these provided with Investment Banking Services)

    Share price and rating changes for long-term investment opportunities

    Tata Power (TTPW.BO) share price performance INR vs HSBC rating history

    Source: HSBC

    Recommendation & price target history

    From To Date

    N/A Overweight 28 July 2006Overweight Underweight 07 November 2007Underweight Underweight (V) 17 March 2008Underweight (V) Overweight (V) 29 August 2008

    Target Price Value Date

    Price 1 679.10 28 July 2006Price 2 724.00 30 January 2007Price 3 714.00 20 April 2007Price 4 732.00 23 May 2007Price 5 843.00 26 July 2007Price 6 1198.