ZTE Pakistan (Pvt.) Ltd. Policy Manual
ZTE Telecom Pakistan Ltd. Policy Manual
Employee Training management Policy
Revised April 20, 2006 Implemented May 1st, 2006 Ver 2.0
Page 1 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
Human Resource Department
1. Purpose
To standardize employee training management , improve employee’s quality ,
organizational performance and establish learning organization.
2. Scope of application
The policy apply to Zhongxing Telecom Pakistan (Pvt.) Ltd (ZTE Pak hereafter).
3. Principle
Employee training (training hereafter) management operates with the principle of
“centralized management and hierarchical implementation”. The Training section
of HR Department ( HR Dept hereafter) is responsible for Employee training
management of ZTEPAK, make employee training regulations and policy as well
as supervising the implementation of them, and provide coaching for the training
coordinators of all divisions and departments of ZTEPAK, who are responsible for
planning, organization, implementation, evaluation and improvement of various
training projects in their own unit.
4. Definition
4.1 Training program means teaching & learning activities with some
scale involving planning, organization and evaluation, which aims
at improving trainees’ knowledge, skills, work attitudes and
behavior to inspire greater potential of the trainees for better
work quality and organizational performance.
4.2 There are four categories of training program based on priority :
systematic training, out-sourcing training, foreign training and
internal training seminar .
Page 2 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
4.2.1 Systematic training means the duration of full time training is
more than one day per month or the accumulative training
duration total is more than 8 hours per month.
4.2.2 Out-sourcing training is the training in which the courses are
provided by the experts outside of the company.
4.2.3 Internal seminar means the internal exchange within the
divisions or departments.
5. Organization structure
5.1 HR department is responsible for employee training.
5.2 HOD is the first responsible person for the training in their unit.
5.3 Full time training manager should be appointed in HR department
and part-time training coordinators should be appointed in
various divisions/departments, who will be responsible for
planning, organization, implementation the training program in
their respective unit with the guidance of training manager in HR.
6. Duties
6.1 HR department
6.1.1 To be responsible for the whole training effect of the company
level training, to supervise and to guide the training
implementation in the company.
6.1.2 To establish employee training management system,
formulate training policies and monitor to implement it.
6.1.3 To make employee annual training plan .
6.1.4 Centralized management of training fees.
6.1.5 To file and to maintain the training records .
6.1.6 To be responsible for organizing orientation training,
management training and technical training for employees.
6.2 Training coordinator of respective department
6.2.1 To be responsible for department training and assist HOD to
Page 3 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
plan, organize and implement department training program.
6.2.2 To assist HOD to collect training needs , implement
department training regularly and maintain the department
training records.
6.2.3 To be responsible for submitting training application and
training plan to HR department monthly basis.
7. Content
7.1 Training plan
7.1.1 HR department makes annual training plan based on company
strategies and HR policies, which is subjected to be adjusted
every six month .
7.1.2 HR department makes the monthly training plan and publish
the next month’s training plan in the public bulletin on 25th of
every month.
7.2 Training implementation
7.2.1 HR department is responsible for implementing the company
level training according to the scheduled training plan timely.
7.2.2 HR department is responsible for outsourcing training program
and investigating or verifying qualifications of instructors from
local universities or training/consultive agencies . HR will
submit all concerned documents to CEO for final approval.
7.2.3 HR department shall keep completed training archive for each
employee of ZTEPAK, and keep the information updated
timely.
7.3 Training fees
7.3.1 HR department is responsible for the training fees
management of ZTEPAK.
7.3.2 Training fees refer to all the expenditure on execution of
training programs, including expenses on traveling,
Page 4 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
accommodation, meals, course tutor, training manuals and
materials, rent, certificate making and activities.
7.3.3 At the end of every year, HR department shall submit annual
training budget for next year to CEO for approval.
7.4 Training expense standard
7.4.1 Local training
7.4.1.1 The expense occurred in the local training, such as
transportation, accommodation and meal etc, shall comply
with relevant financial policies of the company.
7.4.2 Foreign training
7.4.2.1 Long-distance transportation including the air-tickets,
airport construction fee and bus fee from the airport to
hotel is the real expense by the invoice incurred .
7.4.2.2 If the trainees have a training in
Shenzhen ,Beijing ,Shanghai or Guangzhou , the
accommodation expense is not more than RMB 250.00 for
one room living by the two trainees necessarily. If in other
cities , the maximum's expense is not more than RMB
150.00 for one room living in by two trainees. If the trainee
amount is odd , the left one can live in one room alone,
which will be arranged by the trainees or the training
coordinator.
7.4.2.3 The trainees are entitled to 100rmb living allowances per
day during the training session, covering urban
transportation, food and laundry service. Training organizer
may decide whether to arrange group meals according to
the situation while trainees may decide whether join the
arranged meals or not. If they do, the food expenses for
arranged meals shall be deducted from their allowances,
Page 5 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
otherwise, the allowances shall be given to them.
7.4.2.4 The communication allowances are 400rmb per month and
200rmb per half a month (including the training session
less than a month ) , which shall be given to trainees
directly.
7.4.2.5 For more details, please refer to finance police #007
Expense Standard for Training in China
7.4.3 Part-time trainer
7.4.3.1 Part-time trainers entitle training fees of 300 Rs/hour, which
will be distributed according to the result of training
evaluation score. according to the training evaluation
result: above 85 marks (contain 85) get 100% of the trainer
fee ;60-85 marks get 60% of the trainer fee ;Below 60 marks
get 20% of the trainer fee.
7.4.4 Outsourcing training
7.4.4.1 Any invited lecturer as professionals , or government public
official, University teacher , researcher of national R&D
institute, whose trainer fee standard shall be handled
according to their academic level ,course quality ,social
popularity etc. Factors , the trainer fee can not be more
than $80 Usd/per hour/per person.(tax included)
7.4.4.2 The payment for outside trainer have to link with the
training effect, paying expenses according to the training
evaluation result: Above 85 marks (contain 85) pay 100%
of the training expenses ;70-85 marks pay 60% of the
training expenses ;Below 70 marks pay 20% of the training
expenses .
7.4.5Training materials
Page 6 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
7.4.5.1 For the systematic training of more than 5 days( include 5
days), if stationeries or other necessities are needed, the
training materials expense standard is 100Rs for one
person.
7.4.5.2 For the systematic training of more than 5 days( include 5
days), the activity fee doesn’t exceed 300 Rs/per person.
7.4.5.3 Refreshment during the training, if necessary, shall be not
more than 50Rs/per day/per person.
7.4.5.4 All the training organized by the company for employees
will not issue gifts.
7.4.6 In the above-mentioned training fee expenditure standard,
except for the personal subsidy and part-time trainer fee ,
others such as accommodation fee ,meal expenses and
activity fee etc. can not be distributed to person directly.
7.4.7For special expenses occurred in the training program but not
listed in this policy, after getting approval from HR, can be
included in the training fee.
7.4.8Actual expenses exceed the standard, the expenditure which
more than the standard shall be borne by the concerned
division or person.
7.5 Surety bond
7.5.1 If the training expense is more than $500USD/per person in
local outsourcing training, the trainees shall sign the surety
bond with ZTEPAK before they attend the training.
7.5.2 For all the foreign training, surety bond is must for every
trainees.
7.5.3 Employee Surety Period and Cost
7.5.3.1 For local outsourcing training :
Training fee/ per person Duration of Surety Cost to be recovered
Page 7 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
$500Usd – $1000Usd 1 Year Real expense - Prorated after One month
$1000USD-$5000USD 2 years Real expense - Prorated after One year
More than $5000USD 3 years Real expense - Prorated after One year
7.5.3.2 For foreign training :
Number of Days of Overseas
Training
Duration of Surety Cost to be recovered
15 Days- 30 days 1Year Pak Rupee 200,000/- Prorated after One month
30 days – 180days 2 years Pak Rupee 400,000/- Prorated after One year
More than 180 days 3 years Pak Rupee 500,000/- Prorated after One year
7.5.4 In the event of an employee wishing to leave the employment
of the Company , he/she will reimburse the Company the
expenses incurred on providing the training. ZTE Pakistan will
make appropriate deductions from the employee final
settlement including Provident fund. And remaining amount
will be deposited by the employee in the Company account.
7.5.5 The employees are required to submit a Surety bond on Stamp Paper (Legal
Paper) having minimum denomination of Rs.200/- to the HR department
before the training start.
7.5.6Any breach of surety bond clauses will result in a legal action.
8. HR Department of ZTE Pak is responsible for interpretation of the
regulations.
9. Appendix :
I Training Evaluation Form
I I Training Agreement ( Local & Foreign)
Page 8 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
Appendix I
I. Training Evaluation Form
1. Evaluation for trainers
Name
Level
Items
Trainer 1 Trainer
1
Familiarity with the subject
Class operation
Manners
Clear explanation & communication
Devotion & responsibility
Specification Level A. Excellent, B. Good, C. Fair, D. Below Average E. Poor
Date: Venue:
Training Coordinator:
2、Evaluation for training arrangement
Items to be evaluated
A B C D E
Arrangement of courses
In-time& accurate information flow
Page 9 of 13
Total score
ZTE Pakistan (Pvt.) Ltd. Policy Manual
Preparation of training materials
Preparation of training site
Administration work
Criteria Level A. Excellent, B. Good, C. Fair, D. Below Average E. Poor
Your suggestions:
____________________________________________________________________________________________
____________________________________________________________________________________________
____________________________________________________________________________________________
_____________________________________________________________________________________
Appendix II SURETY BOND (FOREIGN TRAINING)
THIS SURETY BOND is made at Islamabad this ______ day of __________ , 2006 by and
BETWEEN:
___________________________________ son/daughter of ____________________________________, resident
of _______________________________________________________________, (hereinafter referred to as the
"Employee", which expression shall, where the context may admit, include his heirs, successors-in-interest and
assigns); and
___________________________________ son/daughter of ____________________________________, resident
of _________________________________________________________________________, (hereinafter
referred to as the "Surety", which expression shall, where the context may admit, include his heirs, successors-in-
interest and assigns); and
ZHONGXING TELECOM PAKISTAN (PRIVATE) LIMITED, with its registered office located at
House No. 30, Street No. 48, Sector F-8/4, Islamabad (hereinafter referred to as the "Company", which expression
shall, where the context may admit, include its successors-in-interest and assigns); WHEREAS:
1. The Company has selected the Employee to undergo a course of training and is required to serve at a location of
the Company's choice for a minimum period of two years with and under the supervision or Zhongxing Telecom
Corporation at the Company's expenses.
2. As a pre-condition to the Company selecting the Employee to undergo the Training, the Company requires the
Employee and the Surety to irrevocably and unconditionally agree and bind themselves, their heirs, executors and
assigns jointly and severally to guarantee to the Company to serve for two years and if employee fails to do so the
sum of Rs. 400,000 (Rupees Four Hundred Thousand Only) shall be payable on first demand to company. (the
"Secured Amount"); and
3. The Employee and the Surety have accepted the Employee's selection by the Company to undergo the Training
Page 10 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
and they desire and hereby jointly and severally unconditionally and irrevocably agree and guarantee to the
Company the payment of the Secured Amount.
NOW, THEREFORE, in consideration of the promises and mutual covenants and agreements hereinafter set forth,
the Parties hereby through this Bond agree and declare as follows:
4. Upon instructions by the Company, the Employee shall immediately proceed to Peoples Republic of China for
advance training with Zhongxing Telecom Corporation in the Peoples Republic of China, and serve if required
with ZTE Corporation .
5. The Employee shall devote his full time, attention and energies to gain and achieve the optimum benefits from
the Training to the best of his abilities. During Training, the Employee shall carry out all lawful instruction of the
Company, its agent and those of Zhongxing Telecom Corporation relating to the training, including manual work,
in full and without any demur. The Employee shall, at all time Training and service, be subject to the discipline as
enforced Zhongxing Telecom Corporation.
6. If during the Training and service, the Company determine in its sole and absolute discretion, that the conduct or
the progress of the Employee's Training is, for reasons wholly attributable to the Employee, unsatisfactory then the
Company shall be at liberty to terminate the Training and the Employee and the Surety shall, on the demand by the
Company, refund to the Company all moneys and expenses spent and incurred by the Company in respect of
Employees traveling expenses, training expenses, tuition fees and boarding/lodging abroad, salary and otherwise.
7. Upon successful completion of the training the Employee shall serve the Company or any of its offices in any
country or any other organization if and so directed by the Company for a period of two years .
(Continued Page # 2)
8. In the event of the Employee's premature leaving of the ZTE Corporation after successful completion of the
Training or during the service with the Company for a period of at least two (2) Years, the Employee and the
Surety shall jointly and severally be liable to pay to the Company the Secured Amount upon first demand without
demur i.e. if the employee fails to serve for two years he shall pay Rs.400,000 (Rupees Four Hundred Thousand
Only) as surety money.
9. This Bond shall remain in force until the Employee and/ or the Surety have paid to the Company the Secured
Amount, or until the Employee has served the Company for a period of at least two (2) year .
IN WITNESS WHEREOF, the Parties have duly executed this Agreement as of the date set forth
above:
1. For & on behalf of
ZHONGXING TELECOM PAKISTAN
SURETY BOND (LOCAL TRAINING)
Page 11 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
THIS SURETY BOND is made at Islamabad this ______ day of __________ , 2006 by and
BETWEEN:
___________________________________ son/daughter of ____________________________________, resident
of _______________________________________________________________, (hereinafter referred to as the
"Employee", which expression shall, where the context may admit, include his heirs, successors-in-interest and
assigns); and
___________________________________ son/daughter of ____________________________________, resident
of _________________________________________________________________________, (hereinafter
referred to as the "Surety", which expression shall, where the context may admit, include his heirs, successors-in-
interest and assigns); and
ZHONGXING TELECOM PAKISTAN (PRIVATE) LIMITED, with its registered office located at House No. 30,
Street No. 48, Sector F-8/4, Islamabad (hereinafter referred to as the "Company", which expression shall, where
the context may admit, include its successors-in-interest and assigns); WHEREAS:
The Company has selected the Employee to undergo a course of training and is required to serve in the Company
afterwards. The effective date of the bond will start from the first day of the training (i-e) April 17, 2006.
NOW, THEREFORE, in consideration of the promises and mutual covenants and agreements hereinafter set forth,
the Parties hereby through this Bond agree contained on two pages and declare as follows:
1. As a pre-condition to the Company selecting the Employee to undergo the Training, the Company requires the
Employee and the Surety to irrevocably and unconditionally agree and bind themselves, their heirs, executors and
assigns jointly and severally to guarantee to the Company to serve for ...........and till the completion of ...........
Project and if employee fails to do so the sum of Rs...........shall be payable on first demand to company. (the
"Secured Amount")
2. The Employee and the Surety have accepted the Employee's selection by the Company to undergo the Training
and they desire and hereby jointly and severally unconditionally and irrevocably agree and guarantee to the
Company the payment of the Secured Amount.
3. If during the Training and service, the Company determine in its sole and absolute discretion, that the conduct or
the progress of the Employee's Training is, for reasons wholly attributable to the Employee, unsatisfactory then the
Company shall be at liberty to terminate the Training and the Employee will be treated according to the ZTE
disengagement policy.
4. In the event of the Employee's premature leaving of the ZTE Corporation after successful completion of the
Training or during the service with the Company for a period of at least ………. Year and till the completion
of ..........., the Employee and the Surety shall jointly and severally be liable to pay to the Company the Secured
Amount upon first demand without demur i.e. if the employee fails to serve for one year he shall pay
Rs…………….. as surety money.
Page 12 of 13
ZTE Pakistan (Pvt.) Ltd. Policy Manual
5. This Bond shall remain in force until the Employee and/ or the Surety have paid to the Company the Secured
Amount, or until the Employee has served the Company for a period of at least ………….. and till the completion
of ............Project.
(Page-1)
IN WITNESS WHEREOF, the Parties have duly executed this Agreement as of the date set forth above:
1. For & on behalf of
ZHONGXING TELECOM PAKISTAN WITNESSES:
(PRIVATE) LIMITED
_
Page 13 of 13