    24 December 2013 PMI Revision 00 1

    HP BYPASS

    SYSTEM

  • 7/25/2019 Hp Bypass System Ppt

    2/21

    24 December 2013 PMI Revision 00 2

    Presentation outline

    Introduction to HPBypass

    Components of HPBypass SystemSystem Details

  • 7/25/2019 Hp Bypass System Ppt

    3/21

    24 December 2013 PMI Revision 00 3

    Introduction

    To improve flexible operation

    Dumping of excess steam to

    Bypass steam from boiler when turbine isnot in service.

    To quickly match steam parameters with that

    of turbine metal.

    To protect reheat tubes

    Minimize water loss(Sh vent to be open

  • 7/25/2019 Hp Bypass System Ppt

    4/21

    24 December 2013 PMI Revision 00 4

    H.P. BYPASS SYSTEM

    H.P. Bypass system bypassed steam from MS line to CRH linebypassing HPT.

    Function of HP Bypass:-

    1. Raising boiler parameter during start up.

    2. To warm up steam pipe lines.3. To match live steam pressure & temp before entering into turbine.

    4. Quick

    5. start up of turbine.

    6. Bypasses the steam to HPT & during sudden unloading of

    machine, tripping of machine.7. Avoid starvation of boiler.

    8. Reduce losses of steam to atmosphere.

  • 7/25/2019 Hp Bypass System Ppt

    5/21

    24 December 2013 PMI Revision 00 5

    Over view of HP bypass

    system Working of By pass system (Explain Fig)

    Maintains pressure before Turbine i/L

    2 BP1,BP2 Upstream ,Down stream CRH

    Dump excess steam to cold RH

  • 7/25/2019 Hp Bypass System Ppt

    6/21

    24 December 2013 PMI Revision 00 6

  • 7/25/2019 Hp Bypass System Ppt

    7/21

    24 December 2013 PMI Revision 00 7

  • 7/25/2019 Hp Bypass System Ppt

    8/21

    24 December 2013 PMI Revision 00 8

  • 7/25/2019 Hp Bypass System Ppt

    9/21

    24 December 2013 PMI Revision 00 9

    System details and lay out

    Capacity to bypass 70% HP steam at rated flow

    HP ,BPE (spray ) are hydraulic actuator

    Pressurized oil is supplied from separate oil Unit

    Fast opening ( Bulk load ,generator Trip, Turbine

    trip )

    During normal operation (sliding pressure set point)

  • 7/25/2019 Hp Bypass System Ppt

    10/21

    24 December 2013 PMI Revision 00 10

    InterlocksOpening-

    Generator circuit breaker open. Turbine trip out.

    Manual command for fast opening.

    Protection- Condenser vacuum too low.

    Temp. to high at down stream of H.P. Bypass.

  • 7/25/2019 Hp Bypass System Ppt

    11/21

    24 December 2013 PMI Revision 00 11

    HP BYPASS SYSTEM and

    Components

    Oil supply unit

    Two oil pumps.

    Two tanks.

    Signal alarm PRESSURE TO HIGH orPRESSURE TO LOW if pressure is not in order.

    02 nos. of pressure control valves

    02 nos. temperature control valves

    01 no. of spray water pressure control valve

    01 no. of spray water pressure isolating valve

  • 7/25/2019 Hp Bypass System Ppt

    12/21

    24 December 2013 PMI Revision 00 12

    Hp bypass control

    Hydraulically operated

    Steam pressure control

    Down steam temperature control

    Spray water pressure control.

    On -off control

  • 7/25/2019 Hp Bypass System Ppt

    13/21

    24 December 2013 PMI Revision 00 13

    C I componenets

    Oil supply units

    Servo valves

    Blocking units

    Trip close/trip open units

    Filters

    Regulators.

  • 7/25/2019 Hp Bypass System Ppt

    14/21

  • 7/25/2019 Hp Bypass System Ppt

    15/21

    24 December 2013 PMI Revision 00 15

    Interlocks of hp bypass

    Spray water pressure auto switching

    Auto opening of spray isolation valve

    Trip closing of bypass valves

    Trip opening of bypass valves.

  • 7/25/2019 Hp Bypass System Ppt

    16/21

    24 December 2013 PMI Revision 00 16

    Stage-2 systems

    Hp bypass system

    02 nos of control valves

    02 nos of temperature control valves

    01 no. of spray water isolation valve

    Trip closes on

    -down steam temperature very high

    -vacuum is low

  • 7/25/2019 Hp Bypass System Ppt

    17/21

    24 December 2013 PMI Revision 00 17

  • 7/25/2019 Hp Bypass System Ppt

    18/21

  • 7/25/2019 Hp Bypass System Ppt

    19/21

    24 December 2013 PMI Revision 00 19

  • 7/25/2019 Hp Bypass System Ppt

    20/21

    24 December 2013 PMI Revision 00 20

  • 7/25/2019 Hp Bypass System Ppt

    21/21

    24 December 2013 PMI Revision 00 21

    THANK YOU